You are on page 1of 3

Overall Breakup of manpower - 04 Nov 2020

Area Total Manpower MFS - Internal MFS -External SFS Infra Laydown / HSE /
Common
Mason 29 15 2 9 2 1
Carpenter 18 11 2 5
Steel Fixer 37 12 8 12 3 2
Helper 6 2 1 1 2
welder 2 2
Scaffolder 7 4 2 1
Painter 1 1
Electrician 2 2 0
Store keeper 1 0 1
Safety Inspector 1 1
Rigger 5 5
Office Boy 2 0 2
operator 11 8 3
chargehand 6 2 1 3
chain boy 1 1

Mason 20 14 3 1 2
Carpenter 16 4 5 4 3
Helper 8 3 2 1 2
Painter 5 2 3
scaffolder 35 19 14 2
Steel Fixer 7 0 3 4

Total - ALB 129 51 28 36 5 9


Total - supply 91 42 13 23 13 0
Grand total 220 93 41 59 18 9

Supply Manpower Work Assignment 04 Nov 2020 Required Till

Mason 14 Tiling, Fire sealant, Plinth Plastering, Concrete, Mar-21


Grinding, MEP opening, wall maintanence

Carpenter 4 Ceiling, Metal door Mar-21

Helper 3 All General Works, Curign, Materail shifting Mar-21


MFS - Internal
Painter 2 Painting works @ Zone 3, Zone 2, First floor @ Zone 1 Mar-21

scaffolder 19 Appliance way - High level Scaffolding for Intumascent Mar-21


painting and MEP works, External Painting

Steel Fixer 0 Mar-21

Mason 3 Excavation for Gully pipe, Manhole works Mar-21


Shutterign for Manhole, Kerb, MEP pipe protection,
Carpenter 5 Light pole Mar-21

Helper 2 Water proofing, materail shifting, hilti works Mar-21


MFS -External
Painter 0 Mar-21

scaffolder 0 Mar-21
reinforcement for Light pole, fire chamber, Silt
Steel Fixer 3 Mar-21
chamber,
Mason 1 Tiling work Mar-21
Manhole shuttering, Beam Shuttering, Upstand, Kerb
Carpenter 4 Mar-21
etc
Helper 1 Backfilling, compaction, Grinding Mar-21
SFS
Painter 3 substation Painting Mar-21
Backfilling, Material handling, Scaffolding, backfilling
scaffolder 14 Mar-21
compaction
Steel Fixer 0 Mar-21

Mason 2 Mar-21

Carpenter 3 Mar-21
Excavation & Related Trial trench Work, Back filling,
Helper 2 Protection of servises Mar-21
Infrastructure
Painter 0 For HV cable pulling and Existign pipe protection Mar-21

scaffolder 2 Mar-21
Steel Fixer 4 Mar-21
Manpower Strength - Staff and Workers Coming in Bus from Camp @ Industrial Area

Camp Present Strength 6 am to 5 pm 3 pm to 2 am

Street - 15 2 2 0

Street - 30 64 48 16

Street - 37 3 3 0

Street - 38 44 39 5

Street - 46 39 32 7

Total 152 124 28

Mathai Mathai Sumesh


Jaspal Jaspal 1 bus, 1 trip only
Sumesh
Bus Driver 2 Bus - 2 trip Each
3 Bus, Total 5 Trip

Jasbeer Jasbeer
Tika Tika
Staff Driver to pick staff from Doha New Driver required
Tika - 2 trip - Abuhamur, Tika - 2 trip - Abuhamur,
Wukair Wukair
Overall Breakup of supply manpower - 04 Nov 2020
Laydown / HSE /
Area Total Manpower MFS - Internal MFS -External SFS Infra
Common
Mason 23 15 5 1 2
Carpenter 18 4 6 4 4
Helper 8 3 2 1 2
Painter 6 2 4
scaffolder 36 20 14 2
Steel Fixer 7 0 3 4

Total - supply 98 44 16 24 14 0

Supply Manpower Work Assignment 04 Nov 2020 Required Till

Tiling, Fire sealant, Plinth Plastering, Concrete,


Mason 15 Mar-21
Grinding, MEP opening, wall maintanence

Carpenter 4 Ceiling, Metal door Mar-21

Helper 3 All General Works, Curign, Materail shifting Mar-21


MFS - Internal
Painter 2 Painting works @ Zone 3, Zone 2, First floor @ Zone 1 Mar-21

scaffolder 20 Appliance way - High level Scaffolding for Intumascent Mar-21


painting and MEP works, External Painting

Steel Fixer 0 Mar-21

Mason 5 Excavation for Gully pipe, Manhole works Mar-21


Shutterign for Manhole, Kerb, MEP pipe protection,
Carpenter 6 Light pole Mar-21

Helper 2 Water proofing, materail shifting, hilti works Mar-21


MFS -External
Painter 0 Mar-21

scaffolder 0 Mar-21
reinforcement for Light pole, fire chamber, Silt
Steel Fixer 3 Mar-21
chamber,
Mason 1 Tiling work Mar-21
Manhole shuttering, Beam Shuttering, Upstand, Kerb
Carpenter 4 Mar-21
etc
Helper 1 Backfilling, compaction, Grinding Mar-21
SFS
Painter 4 substation Painting Mar-21
Backfilling, Material handling, Scaffolding, backfilling
scaffolder 14 Mar-21
compaction
Steel Fixer 0 Mar-21

Mason 2 Mar-21

Carpenter 4 Mar-21
Excavation & Related Trial trench Work, Back filling,
Helper 2 Protection of servises Mar-21
Infrastructure
Painter 0 For HV cable pulling and Existign pipe protection Mar-21

scaffolder 2 Mar-21
Steel Fixer 4 Mar-21