DATA REQUIREMENT
The following are essential inputs required to perform the studies but not limited to
1. Single line diagram of whole network
2. Transmission line data
a. Length in km
b. Conductor type
c. Tower data
Altitude of first tower in meter
Height of all conductors in meter
Horizontal spacing between phases in meter
Shunt conductance in mho / m
Number of ground wires
Distance between towers
d. Ground wire
Radius in meter
DC resistance in ohm / m
Sag in meter
Height of ground wire above lowest conductor in meter
e. Gantry for incoming lines
Altitude of gantry in meter above sea level
Horizontal spacing of phase lines in meter
3. Connection Data
a. Droppers (inductor) in uH/m
b. Line section between Busbar system (inductor) in uH/m
4. Surge arrestors
a. Connecting leads (Cable between Line and Surge Arrester) in meter
b. Arrester type
c. Lightning Impulse protective level
5. Tower Data
a. Tower footing resistance in ohm
b. Tower model
c. Tower configuration
6. Switching impulse voltage
7. Lightning impulse voltage
8. Fault current with standard clearing time