RINCIAN BIAYA

NO DESCRIPTION QNTY PCS Rp/MONTH REMARK


SALARY A. OFFICE & UMUM 42,000,000
B. PRODUKSI/PENGAWAS 43,644,612
C. PRODUKSI/OPR/DRIVER 135,000,000 RENT
D.Engineering 8,322,306
D. WORKSHOP 64,672,157
SUB TOTAL 293,639,075

EQUIPMENT E. COST RENT (EKSLUDE OPR & DRIVER ) 19.00 UNIT 1,320,327,843.19 RENT
F.FUEL EQUIPMENT 19.00 UNIT 797,760,000.00
TOTAL BEBAN OERASIONAL/ BULAN 2,411,726,918

COST COAL GETT 173,360,000.00 TARGET OB/MONTH 144,000.00 BCM


COST OB 2,238,366,918.00 COST OB 15,544.21 BCM