Professional Documents
Culture Documents
Session 10 : 1
NEED FOR BUS PROTECTION
I2 I2
I3 I3
I4 I4
I5 I5
I6 I6
IF
IF=I6=I1+I2+I3+I4+I5 IF=I1+I2+I3+I4+I5+I6
Kirchoff’s current law states that the sum of the current entering
A given node must be equal to the currents leaving that node.
ABB India, Bangalore
Session 10 : 3
CT Saturation
Rct Is RL
Ip
Ie Xm Rb
RL
The most suitable protection scheme for Double and multiple busbar
Systems (with or without transfer bus) with feeders being switched
Between sections of the busbar, which operates with full selectivity
For all possible busbar configurations.
And 1 ½ breaker systems. The system has limits when used in complex
Busbar configurations.
Where:
ir1 = Current setting of the diff. relay
ik ir is
i3 i2
Ur1 = Voltage setting of relay ckt.
Rr Rs
I3 I2 Ik=I2+I3 Xm=0
ik1 = Maximum secondary fault
Ur current on external faults
87
R2 R2 R2
ik
im = CT secondary magnetising
ir
current at Ur1 volts.
Check-Zone Feature
For a double busbar arrangement, two different high impedance units are required.
In this case, the current must be switched between the two different measuring units
By connecting auxiliary switches to the busbar isolator contacts.
In some cases the auxiliary switches did not operate correctly. This caused the busbar
Protection to trip the busbar. For this reason, a safety precaution was introduced:
An overall Check-Zone unit, fed from individual CT cores. This overall scheme does not
Include any switching of CT and therefore is more secure.
The TRIP command is only given when both a discriminating and check-zone system
Operates.
C. SLOW RESPONSE
• BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 - 20 ms.
• INSENSITIVE TO CT SATURATION.
IR1
T MD
n MD
Ud3
dR
D2 D1
US
RL > S
1-S
FOR S = 0.8, RL = 1024 Ohms
• SENSITIVITY IS ADJUSTABLE.
• In Percent biased relay (RADSS), the required voltage to operate, increases a the
Restraint voltage increases in proportion to the severity of external fault. In addition
Percent bias relay (RADSS) has following advantages.
• Basic operating time of RADSS is 1-2m secs, and total time including trip relays
Is 5-7m secs.
• RADSS is stable against through fault currents even for infinite fault MVA. The
Growing fault MVA levels does not affect the stability of the relay and only CTs
With moderate knee-point voltage (500V) need to be connected.
BUS
Buss Diff
Relay
BUS-A BUS-B
When both the buses are coupled through isolators I.e. when both the
Bus isolators of any feeder is closed during bus change over, both the
Bus bars will act as single bus bar and bus coupler gets bypassed. In
The event of fault on any one of the buses during this condition, feeders
Connected to both the buses will be tripped. In the case of bus bar
Protection type RADSS, this logic is achieved through a separate bus
Interconnection unit or Single zone reconnection unit.
BUS-A BUS-B
BUS-A BUS-B
# CT DISCONNECTION UNIT
ABB India, Bangalore
Session 10 : 26
# CT DISCONNECTION UNIT
Where there is only one CT in the bus coupler bay, there will be a blind
Zone or dead zone between the breaker and the CT, and for a fault in
This zone the selectivity of the busbar protection is lost resulting in
Mal-operation and unwanted operation of wrong bus bar protection and
Non-operation of the required busbar protection. If this is allowed to
Persist, it will result in tripping of remote end feeders in Zone-II.
Further, when both the buses are coupled through bus coupler and if
The bus coupler breaker fails to trip for a fault on any of the buses, the
Other bus continue to feed the fault till all the feeders connected to that
Bus trip at remote end in Zone-II or by LBB of bus coupler breaker.
To take care of this type of faults, the bus bar protection is provided with
A feature called bus coupler CT disconnection , which shorts the bus
Coupler CT after a preset time after the operation any of the bus bar
Protections irrespective of the status of bus coupler breaker.
DIR.
RELAY
AUX. BUS
RS/2
RS/2 Rd
BUS - B
AUX. BUS
RADSS - A
L1 L3 L5
BUS - A
BUS - B
L2 L4 L6
RADSS - B
0% 100%
Main
contact
Aux.
Contact
a
Aux.
Contact
b
ABB India, Bangalore
Session 10 : 31
ABB India, Bangalore
Session 10 : 32
Local Breaker Back-up Protection
G G
• In modern networks the critical fault clearing time may be less than 200 ms.
Hence, if the fault is not cleared due to failure of the primary protective
relays or their associated circuit breaker, a fast-acting back-up protective
relay must clear the fault
ZL1
I1
Z <
1. Relay back - up
2. Breaker back - up
RELAY
Duplicate primary protection, SYSTEM CHANNEL
e.g. one non-switched and
one switched distance protn.
-
To increase the security, the 52
circuit-breaker has two trip 52a
coils, one connected to the
non-switched relay, the other 52 52a
connected to the switched -
50
relay.
RELAY CHANNEL
SYSTEM
+
ABB India, Bangalore
Session 10 : 37
BREAKER BACK - UP
5 1 2 6
Z<
7 3 4 8
RESET
MAIN YES TRIP YES
FAULT BREAKER
PROTECTION MAIN
CLEARED FAILURE
OPERATED BREAKER
SCHEME
NO
TRIP
BACK - UP
BREAKERS
t
Sec. Current when the
primary current is
zero=0
• In the current detector RXIB 2 the influence of the dc component is
suppressed by the air gap in the input current transformer of the relay
E2= -N2 . dø / dt
E2
ABB India, Bangalore
Session 10 : 42
REQUIREMENT ON BREAKER- FAILURE RELAYING