JOB NO.

CUSTOMER JOB DESCRIPTION LOCATION/SECTION


TAKREER Scaffolding Service for maintenance RUWAIS Refinery

QP NO. DESCRIPTION CONTROLLING HOLD POINT


SPECIFICATION/ NPC VERIFYING DOCUMENTATION NPC VERIFIER CUST
PROCEDURE NAME/SIGNATURE
1 Receive work request from specific department.

2 Coordinate with requestor on type of scaffold


required and purpose Assess, Tower, Mobile,
Lifting Fram etc)
3 Identify the specific location. And identify
Hazards and assess potential for risk
4 Proceed for work and vehicle permit Permit to work system of Permit to work signed By Takreer
TAKREER representative, Issuing authority
and performer Ensure permit
controls are adhered to
throughout operation

5 Estimate and prepare scaffold material for the BS 5973, 5974, 1139, 2482
work in hand. Material provided NPC. (Tube, TAKREER Guidelines
Fittings, board or relevant propriety.
6 Competent person to inspect scaffold material BS 5973, 5974, 1139, 2482 NPC - Scaffolding procedure for
before use. Any material that does not conform TAKREER Guidelines UAE scaffolding
to be quarantined at designated area and Ministerial Order
scrapped or serviced as appropriate.
7 Tool box talk by scaffolding supervisor, Place the NPC - Scaffolding procedure for
permit near to work area, barrier and safety scaffolding
signage placed to prevent persons entering the
work area.
8 Erection of scaffolding All NPC scaffolds to be BS 5973, 5974 NPC - Scaffolding procedure for
erected by competent person. scaffolding
9 Scafftaq system. On completion of scaffold BS 5973, 5974 NPC - Scaffolding procedure for
scaffolding
10 Notify department that will carry out work agree NPC - Scaffolding procedure for
scaffold is fit for purpose inspector to place scaffolding
scafftag and endorse, with signature, that the
scaffold is safe to use in compliance with the
conditions on the scafftag.
JOB NO. CUSTOMER JOB DESCRIPTION LOCATION/SECTION
TAKREER Scaffolding Service for maintenance RUWAIS Refinery

QP NO. DESCRIPTION CONTROLLING HOLD POINT


SPECIFICATION/ NPC VERIFYING DOCUMENTATION NPC VERIFIER CUST
PROCEDURE NAME/SIGNATURE
11 Modification, damage incurred, inclement When carrying our remedial
weather work scafftag to be removed
whilst work is undertaken.
Damage incurred by vehicle,
weather, undermining-
sacfftag removed, remedial
works undertaken, once
satisfied inspector to replace
sacfftag

12 Inspection Every 7 Days. Other NPC- Scafftag to be signed and


damage, inclement weather, dated on the reverse side
remedial works
13 Dismantling, Notice given by person in charge, Scafftag system Removed
supervisory level. Reinstate Permit to Work sacfftag displaying 'DO NOT
system. Place barrier, warning signs. All material USE'
removed to store- housekeeping