Work of Tramission (O&M) Cell
Work of Tramission (O&M) Cell
1. Preparation of Weekly & Monthly tripping report of 220KV & 132KV transmission system and their
monthly availability for each zone & overall (TAFM).
First overhauling work of 20MVA transformer at Sultanganj G/S/S started from 25-03-
14 and it was charged on 08-07-14 but it tripped on 09-07-14 and was declared defective.
Second overhauling work of 20MVA transformer at Katihar G/S/S was taken up &
charged successfully on 27-08-14. Filtration work of another 20MVA transformer at Katihar
G/S/S is to be taken up by the Agency in a couple of days.
Order placed on M/S Emco Ltd; Jalgaon vide w.o. no-11, dt-10-03-14 for repair of
followings transformers-:
4. Planning of winter and annual maintenance of transmission lines, grids & associated equipments:
5. Working out requirement of spare equipment of transmission system at G/S/S for procurement
by Chief Engineer Trans. (P&P).
Requirement of critical spares & T&P has been sent to C.E., Trans (P&P) on 13-06-14
for procurement.
6. Official correspondence on behalf of C.E., Trans (O&M) received from field office regarding
training, outage of transmission system, equipment availability, diversion of spares etc.