M4 and M5 Template (Resource Estimates)

Instructions: Follow the steps below to complete the table of resource estimates for the project.
Delete all red text in the template and insert your own text in black. See the example at the very
bottom of this page for a model of how to complete this template.

Steps

1. After the words Project Manager, list your name.


2. In the WBS Number column, list the WBS number.
3. In the WBS Element Name column, list the name of the WBS element using an active verb.
4. In the Duration column, list an estimate for how many calendar days it will take to complete
each element.
5. In the Effort column, list the number of staff days you will need to complete each element.
6. In the Non-Labor Budget column, list the non-labor budget you have allotted for each
element.

Project Manager: Sonya Kobe

WBS WBS Element Duration Effort (Staff- Non-Labor Budget ($)


Number Name (Calendar Days)
Days)
1.a.i Operating 2 days 2 days $10,000
System
Research:
Android
1.a.ii Operating 2 days 2 days $10,000
System
Research: IOS
1.a.iii Operating 2 days 2 days $10,000
System
Research:
Windows
1.a.iv Operating 2 days 2 days $10,000
System
Research:
Blackberry
1.b Operating 2 days 2 days None
System
Research Report
1.c Operating 3 days 3 days None
Last updated on 23 September 2018 Page 2 of 3

System Decision
Memo
2.a Hardware 20 days 10 days None
Brainstorm
Session Phase 1
2.b Hardware 20 days 10 days None
Brainstorm
Session Phase 2
2.c Preliminary 10 days 3 days None
Hardware
Options Report
3. a Hardware Final 20 days 15 days None
Decision
3.b Final Hardware 5 days 5 days None
Features
Document
4.a Market Feedback 30 days 30 days $50,000
(Software and
hardware)
4.b Market Feedback 10 days 10 days
Report
5.a Final Design 20 days 20 days $20,000
Delivery
Document Draft
5.b Final Design 10 days 10 days
Delivery
Document Final

TOTAL Total staff- Total of Non-Labor Budget


days allocated: $110,000
allocated:
123

Example of Resource Estimates


Remember that you estimate duration and effort only for the work packages (leaves of the tree).
Following is an example.
Last updated on 23 September 2018 Page 3 of 3

WBS WBS Element Duration Effort Non-Labor Budget ($)


Numbe (Calenda (Staff-
r r Days) Days)
1.0 Describe problem background
1.1 Conduct literature Review
1.1.1 Conduct review of journals 5 9
1.1.2 Review relevant conference 7 4
proceedings
1.2 Draft summary of research on 10 16 $15,000
problem
2.0 Generate hypothesis
2.1 Develop preliminary hypotheses 15 37
2.2 Review hypotheses with PI 8 12 $35,000
Etc. Etc.
… … … … …
TOTAL Total Total non-labor budget
staff- allocated
days
allocate
d