RETURNED
RETURNED
RETURNED
RETURNED
GF 06, GF 14 & GF IDF & T/E Room 1&2, Pump Room, Transformer, Genset Room
Epoxy Floor Coating 15 *changed to smooth straight to finish refer to PMI13 DB002
3RD FLOOR
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY
NO.
2BE01-02-03-04 KITCHEN/DINING, LIVING. MBR, BR, T&B (UNIT 15)
3BA01-02-03-04- KITCHEN/DINING, LIVING, T&B, BR, BR, MBR, T&B, UTILITY
300X300 Ceramic Tiles (FF1) 05-06-07 (UNIT 4)
3BA01-02-03-04- KITCHEN/DINING, LIVING, T&B, BR, BR, MBR, T&B, UTILITY
05-06-07 (UNIT 5)
ROOFDECK
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY
NO.
Poured Concrete RD01 ROOFDECK
Dust Proof Concrete Finish FE 01, FE 02 FE Stair 1 & FE Stair 2
Epoxy Floor Coating MR01, UR01 MACHINE ROOM, UNASSIGNED ROOM
REMARKS
REMARKS
*02=T&B
*04-T&B
*04-T&B
*04-T&B
*04-T&B
*05-T&B
*02&07-T&B
*02&07-T&B
*02&07-T&B
COMMON
AREAS
REMARKS
*04-T&B
*02&07-T&B
*02&07-T&B
REMARKS
*NO FINISH
CEILING SCHEDULE AND MONITORING (Summary)
GROUND FLOOR
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY NOTES
NO.
GF 06, GF 07, GF IDF, T/E Room, FE Stair 1&2, Pump Room, Genset Room,
Rubbed Finish/ Skimcoat/ Exposed Concrete 08, GF 09, GF 15, Driveway/ Parking
(EC) GF 11
9mm THK Ficemboard GF 12, GF 13 Patio, Metering Area
GF 01, 02, 03, 04, Lobby, Elev. Lobby, Mail Box, T&B, JC, Drop Of, Driveway/
12.5mm Gympsum Board MR 05, 10, 11 Parking
FE 02 STAIR 2
1BA03 BR (UNIT 1)
1BBB03 BR (UNIT 6)
FE 02 STAIR 2
1BBB03 BR (UNIT 6)
HW-01 HALLWAY
COMMON AREAS
3RD FLOOR
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY
NO.
2BE02-03 MBR, BR (UNIT 15)
Rubbed Finish/ Skimcoat/ Exposed Concrete
(EC) 3BA03-04-05 BR, BR, MBR (UNIT 4)
3BB03-04-05 BR, BR, MBR (UNIT 5)
9mm THK Ficemboard 2BE02 MBR (UNIT 15)
ROOF DECK
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY
NO.
MR-01 MACHINE ROOM
Rubbed Finish/ Skimcoat/ Exposed Concrete
(EC) UR-01 UNASSIGNED ROOM
REMARKS
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
REMARKS
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
*CONFLICT W/
SCHEDULE
REMARKS
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
*CONFLICT W/
DRAWING
REMARKS
WALL FINISHES SCHEDULE AND MONITORING (Summary)
GROUND FLOOR
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY NOTES
NO.
JANITOR'S CLOSET
GF 01-02-03-07- LOBBY, ELEVATOR LOBBY, MAILBOX, FE STAIR 1, FE STAIR 2,
PAINTED FINISH, GLASS 08-10-12 DROP-OFF, PATIO
PAINTED PLASTER GF 06-13-14-15 IDF & T/E ROOM, METERING AREA, TRANSFORMER, GENSET
* TO BE VERIFIED COLUMNS
* TO BE VERIFIED DRIVEWAY AND PARKING COLUMNS AND DROPWALLS
* TO BE VERIFIED INTERIOR OF PIPE CHASE
HW-01 HALLWAY
PAINTED PLASTER, GLASS FE 01 STAIR 1 COMMON AREAS
FE 02 STAIR 2
EL-01 ELEVATOR LOBBY
PAINTED PLASTER
TE-01 T/E ROOM
DRIVEWAY AND PARKING COLUMNS AND DROPWALLS,
* TO BE VERIFIED PARAPET WALLS
* TO BE VERIFIED INTERIOR OF PIPE CHASE
17TH FLOOR
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY
NO.
1BA03 BR (UNIT 1)
1BB03 BR (UNIT 7,9,12)
1BBB03 BR (UNIT 6)
2BA02-03 MBR, BR (UNIT 2)
2BAB02-03 MBR, BR (UNIT 8,13)
2BB02-03 MBR, BR (UNIT 3)
PAINTED PLASTER, GLASS 2BBB02-03 MBR, BR (UNIT 16)
2BC02-03 MBR, BR (UNIT 10)
2BD02-03 MBR, BR (UNIT 11)
2BE02-03 MBR, BR (UNIT 16)
3BA03-05-06 MBR, BR, BR (UNIT 4)
3BB03-05-06 MBR, BR, BR (UNIT 5)
3BBB03-05-06 MBR, BR, BR (UNIT 14)
1BA03 BR (UNIT 1) BULKHEADS
HW-01 HALLWAY
PAINTED PLASTER, GLASS FE 01 STAIR 1
COMMON AREAS
FE 02 STAIR 2
ROOF DECK
ITEM ITEM DESCRIPTION SCHEDULE LOCATION STATUS QUANTITY
NO.
MR-01 MACHINE ROOM
PAINTED PLASTER UR-01 UNASSIGNED ROOM
RD-01 ROOFDECK
PAINTED PLASTER FE-01 STAIR 1
PAINTED PLASTER FE-02 STAIR 2
HW-01 HALLWAY
PAINTED PLASTER, GLASS FE 01 STAIR 1 COMMON AREAS
FE 02 STAIR 2
DRIVEWAY AND PARKING COLUMNS AND DROPWALLS,
* TO BE VERIFIED PARAPET WALLS
REMARKS
*VERIFY FINISH OF
CERAMIC TILES
*VERIFY FINISH OF
CERAMIC TILES
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
REMARKS
* VERIFY TYPE OF TILES
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
*PAINT TO BE VERIFIED
REMARKS
* VERIFY TYPE OF TILES
REMARKS
*PAINT TO BE VERIFIED
WATERPROOFING SCHEDULE AN
Item Material Additional Materials Approved Equal
No.
A. CAPILLARY WATERPROOFING (Surface-Applied)
Specserv/Hitchins Formdex Plus
Bostic Boscocem Slurry
Tremco Permaquik 200
Specserv/Hitchins Formdex
Admix
1
Pioneer ETL (Epoxy Tank
Lining
Bentonite Waterproofing,
Volclay Voltex Ds/Cetco
(EEI) or Nuraprufe 415
(Specserv/Hitchins)
Specserv/Hitchins Formdex Plus
Bostic Boscocem Slurry
Tremco Permaquik 200
Specserv/Hitchins Formdex
2 Admix
Bentonite Waterproofing,
Volclay Voltex Ds/Cetco
(EEI) or Nuraprufe 415
(Specserv/Hitchins)
3
Specserv/Hitchins Formdex Plus
Specserv/Hitchins Formdex Plus
Bostic Boscocem Slurry
4
Bentonite Waterproofing,
5 Volclay Voltex Ds/Cetco
(EEI) or Nuraprufe 415
Specserv/Hitchins Formdex Uniflex (Specserv/Hitchins)
6
Specserv/Hitchins Formdex Uniflex
7 Specserv/Hitchins Formdex Plus
B. CRYSTALLINE CONCRETE WATERPROOFING (Surface-Applied)
1
Bentonite Waterproofing,
Volclay Voltex Ds/Cetco
(EEI) or Nuraprufe 415
1 (Specserv/Hitchins)
Bentonite Waterproofing,
Volclay Voltex Ds/Cetco
(EEI) or Nuraprufe 415
2 (Specserv/Hitchins)
Specserv/Hitchins Formdex Plus
Specserv/Hitchins Formdex
Admix
Bentonite Waterproofing,
Volclay Voltex Ds/Cetco
(EEI) or Nuraprufe 415
3 (Specserv/Hitchins)
C. BENTONITE WATERPROOFING
Specserv/Hitchins Formdex
Admix
2
3
w/ fabric reinf. And silica
Formak 629 (Hitchkins/Specserv) sand elastomeric waterproofing
Nuraplan SF-12 (Hitchins/Specserv)
4
Specserv/Hitchins Formdex Plus Capillary/Cementitious WP
negative application
25mm thick
c. Centralized Grease
Trap/Trench Drain
d. MEC/Genset Room/
Transformer Room/ Genset/Transformer/Pum
Exposed or With Areas p Room/Mechanical
Above Room
a. RC Domestic
Water/Gray Water &
Fire Water Tanks
(underground &
overhead)
Cistern Tank
negative application
25mm thick
negative application
25mm thick
negative application
25mm thick
a. Lower Ground
Earthside Walls
(exterior or positive
application)
b. Underground
Cistern Tanks, STP,
(exterior or positive
application)
Cistern Tanks
Blanket Layout before
pouring Lower Ground
Slab
Lower Ground Slab
Elevator Pits
Elevator Pits
Balconies, Toilets,
Washer/Dryer, Decks, Top
slab of domestic water
and fire reserve tank,
a. Balconies Balconies Other Wet areas
Roof Decks
Roof Decks, Amenity
Level
d. Daytanks Daytanks
If more than
50mm use
welded wire
fabric
If more than
50mm use
welded wire
fabric
W/ 50mm
Thermal
Insulation
see for
residential
07200
see
specifications
for additional
procedure
see
specifications
for additional
procedure
negative
application
see
specifications
for additional
procedure
T
Item Original Material Legend Revised Material Size & Type as per ID 001
No.
LAM
BLACK SILVER GM9209 (w/ Chiseled Wood Reception Counter, Elevator Wall
Green Laminates
3332) Opening
Ground Floor
Ground Floor
Ground Floor
Ground Floor
Ground Floor
Ground Floor
PDATED)
2nd to 17th
Ground to 17th
ATED)
Ground, 2nd-17th
Ground, 2nd-17th
Ground, 2nd-17th
Ground
References
ID.GF.503/504
ID.GF.503
GLASS SCHEDULE AND MONITORING (
1 SS1
1 CF-01
Acoustic Ceiling Board in T-runner 600x600mm
2 CF-02
Acoustic Ceiling Board in T-runner 10mm thk
GLASS SCHEDULE AND MONITORING (Summary) as of June 04, 2018 (UPDATED)
Elevator Car
Pacific Glass Corp Interior Elevator Car
Finish
ONE FINISH SCHEDULE AND MONITORING (Summary) as of June 04, 2018 (UPDATED)
NLESS STEEL SCHEDULE AND MONITORING (Summary) as of June 04, 2018 (UPDATED)
Gyroproc or Skycon
Status Other Notes References
w/ 20mm thk
Marine Plywood
substrate
w/ 20mm thk
Marine Plywood ID.GF.502/503
substrate
TABULATION OF PILE CAP
Sparkmix Epoxy-
7 118 CBE All purpose bonding epoxy Tower C & MRF
8 153 Philmetal Rib Type Long Span Roofing Tower C & MRF
MATERIAL SUBMITTAL TABULATION
SUBMITTED
LOCATION Technical
DateSubmitted by Date Received by Physical Sample/ Specifications/
BSPCI EELHI Sample Board Description
Soil Reticulation 28-May-18 28-May-18 ●
Concrete Masonry 8-May-18 9-May-18
● ●
● ●
● ●
● ●
●
APPROVED DATE REMARKS
Letter for Alternative
Brand
● - Pending
21-May-18 Approved
Disapprove (for
18-May-18 resubmission)
18-May-18 Approved
18-May-18 Approved
1-Jun-18 Approved
21-May-18 Approved
- Pending