Scope of Work
Supply of labor and tools necessary for the installation of Enerzone metering for Alpha facilities
as specified and shown in Drawing No. PRJ-20MW-004-7 .
1. Installation of 2 units back to back secondary racks with 4 spool insulators each
2. Installation of meter base and associated instrumentation box, main circuit breaker and
grounding rod
3. Installation of required RSC conduits and service entrance caps with corresponding RSC
clamps
4. Providing locknuts and bushing to box and conduit connection
5. Wiring of meter, circuit breaker and conduit
6. Provision for grounding of main circuit breaker connected to grounding rod
7. Testing and commissioning