Professional Documents
Culture Documents
A Training Report: Submitted in Partial Fulfillment of The Requirements For The Award of Degree of
A Training Report: Submitted in Partial Fulfillment of The Requirements For The Award of Degree of
SUBMITTED BY
NARENDRA NAGAR
UNIVERSITY ROLL NO-13ESKCE072
COLLEGE ID-21309
E-MAIL ID-narendranagar1995@gmail.com
SUBMITTED TO SUBMITTED BY
AJAY MANDARWALIA NARENDRA NAGAR
13ESKCE072
1
ABSTRACT
3
CONTENT
5. GEOMETRY OF ROAD
15-24
25-30
6. PROCEDURE OF PAVMENET CONSTRUCTION
31-39
7. TEST DURING ROAD CONSTRUCTION
40
8. REFRENCE
4
FIGURE CONTENT
FIG 1 13
FIG 2 13
FIG 3 15
FIG 4 16
FIG 5 16
FIG 6 17
FIG 7 19
FIG 8 19
FIG 9 20
FIG 10 20
FIG 11 21
FIG 12 23
FIG 13 24
FIG 14 26
FIG 15 26
FIG 16 27
FIG 17 28
FIG 18 29
FIG 19 32
FIG 20 34
FIG 21 34
FIG 22 35
6
CHAPTER 1
INTRODUCTION
About organization :
The Rajasthan Housing Board was established on 24th Feb, 1970 by
promulgation of an RHB Act No. 4, of 1970 (received the assent of The
Governor on the 18th day of April, 1970) by the Government of Rajasthan
as an autonomous body to provide for measures to be taken to deal with &
satisfy the need of Housing accommodation in State of Rajasthan. The
Board consist of a chairman, appointed by The State Government and of six
non official members, nominated by The Government and official Members-
Principal Secretary to Government (UDH), Secretary to Government
(Finance), Chief Town Planner, Rajasthan and the Housing Commissioner of
the Board.
Now it take the tender of road in front of housing board house to provide
flexible road facilities to the customers or people of residential of housing
board’s house
About the location of site :
7
Site location is Haldighati Marg from haldighati gate to Mahal road junction
. it is divided in three zone
I. Zone - 1 (from pratap circle to mahal road junction )
II. Zone - 2 (from panadhay circle to pratap circle )
III. Zone - 3 (from haldighati main gate to panadhay circle )
8
CHAPTER 2
ROAD
9
This is only possible when provided a well planned network of all weather
roads in the rural areas which are maintained in good condition.
Developing countries have to upgrade the road transportation to higher level,
both in terms of length and quality as to meet the demand which is being
generated by development plans.
10
CHAPTER 3
SPECIFICATION OF ROADS
In the year 2000, around 40 per cent of the 825,000 villages in India lacked
all-weather access roads. This constrained economic activities and access to
essential services. Nearly 74 per cent of India’s rural population, constituting
the majority of India’s poor, were not fully integrated into the national
economy.
The rural roads sector, which is a State subject, also lacked adequate
planning and management due to poor coordination between multiple
funding streams and agencies. Investing in rural roads was given low
priority and viewed in isolation from the need for State and National
Highways.
ROAD NETWORK : -
India has a road network of over 4,236,000 kilometers (2,632,000 mi) in
2011, the third largest road network in the world. At 0.66 km of roads per
square kilometers of land, the quantitative density of India's road network is
similar to that of the United States (0.65) and far higher than that of China
(0.16) or Brazil (0.20). However, qualitatively India's roads are a mix of
modern highways and narrow, unpaved roads, and are undergoing drastic
improvement. As of 2008, 49 percent about 2.1 million kilometers.
India in its past did not allocate enough resources to build or maintain its
road network. This has changed since 1995, with major efforts currently
underway to modernize the country's road infrastructure.
The oldest mode of travel obviously was on foot track. Animal were also
used to transport men and materials. Later simple animal drawn vehicles
were developed and this become common and popular mode of
transportation for a very long period.
Roman road
During the roman road civilization many road were built of stone
blocks of considerable thickness.
The main feature of roman roads are :
1. They are built straight regardless of gradients.
2. The soft soil was excavated and removed till hard stratum reached.
3. Total thickness of the construction was high as 0.78 meter to 1.2
meter
MATCALF METHOD :
John Metcalf was engaged on road construction work in England
during the period when Tresaguet was working in France . Metcalf
was responsible for the construction of 290 km. road in the northern
England.
TELFORD METHOD :
Thomas Telford began his work in early 19th century. He insisted on
providing the definite slope on top surface of pavement by varying the
foundation thickness of stones.
12
Figure : 1 pattern of Telford method
A level sub grade was prepared to a width of about 9 m. large foundation
stone thickness up to 17cm to 22 cm. The central portion of about 5.5 meter
width was covered with two layer of angular broken stones to compacted
thickness of 10 cm . A 4 cm. thick gravel surfacing was laid on the top with
a cross slope about 1 in 45 .
13
TYPES OF ROADS :
We construct the drainage for the rain water at side of the road
Thickness of wall – 20 cm
Thickness of cover – 25 mm
Shape of drainage – U
18
Figure : 7 cross section of drainage
19
Figure : 9 pouring of concrete in wall
20
Figure : 11 curing after construction
5. SHOULDER : -
Shoulders are provided along the road edge and is intended for
accommodation of stopped vehicles, serve as an emergency lane for vehicles
and provide lateral support for base and surface courses. The shoulder
should be strong enough to bear the weight of a fully loaded truck even in
wet conditions. The shoulder width should be adequate for giving working
space around a stopped vehicle. It is desirable to have a width of 4.6 m for
the shoulders. A minimum width of 2.5 m is recommended for 2-lane rural
highways in India.
6. ROAD MARGIN : -
The portion of the road beyond the carriageway and on the roadway can be
generally called road margin. Various elements that form the road margins
are given below.
7. SERVICE ROAD : -
Service roads or frontage roads give access to access controlled highways
like freeways and expressways. They run parallel to the highway and will be
21
usually isolated by a separator and access to the highway will be provided
only at selected points. These roads are provided to avoid congestion in the
expressways and also the speed of the traffic in those lanes is not reduced.
Here according to plan service lane will be construct both side of 3 meter
8. FOOT PATH : -
Footpaths are exclusive right of way to pedestrians, especially in urban
areas. They are provided for the safety of the pedestrians when both the
pedestrian traffic and vehicular traffic is high. Minimum width is 1.5 meter .
Here drainage top can be use as footpath by pedestrian and width of foot
path is 2 meter
23
9. TRAFFIC LANE : -
Traffic lane are the surface of road on which vehicle move from one place to
other place
Here the three lane road and width of total lane is 11 meter .
Right of way (ROW) or land width is the width of land acquired for the
road, along its alignment. It should be adequate to accommodate all the
cross-sectional elements of the highway and may reasonably provide for
future development. To prevent ribbon development along highways, control
lines and building lines may be provided. Control line is a line which
represents the nearest limits of future uncontrolled building activity in
relation to a road. Building line represents a line on either side of the road,
between which and the road no building activity is permitted at all.
24
CHAPTER 6
PROCEDURE OF PAVEMENT CONSTRUCTION
Based on the structural behaviour, road pavement are classified into two
categories :
1. Flexible pavement
2. Rigid pavement
FLEXIBLE PAVEMENT :
Flexible pavement are those , which on the whole have low or negligible
flexural strength and are rather flexible in their structural action under the
load.
The flexible pavement layer may reflect the non recoverable as well as
recoverable deformation of the lower layer including the sub grade on the
upper layer and also to the pavement surface .
The vertical component stress is maximum on the pavement surface directly
under the wheel load and is equal to the contact pressure under the wheel.
Due to the ability of flexible pavement layers distributes the compressive
stress to a larger area in the shape of truncated cone ,the compressive stress
decrease at the lower layers.
Therefore by taking advantage of distribution of stress of characteristics of
the flexible pavement layer , the ‘pavement layer system concept’ was
developed
The pavement layers are following :
I. Sub grade
II. River sand
III. Sub base (G.S.B.)
IV. Base course (W.M.M.)
V. Bituminous layer
25
Figure : 14 cross section of pavement layer
26
There was a old road but bed soil of road was black cotton soil , so there was
water logging problem .
Road was excavated till the natural soil bed and then change the soil.
We use yellow soil to the natural bed soil.
I. Natural soil : we remove the black cotton soil and use the yellow
soil which is import from other location and laid the soil layer of
thickness of 300 cm. Then we compact the layer with the vibrator
roller till the effective density which we want to gain. Level the
surface and do proper leveling according to plan .
Now we do the soil test on the soil –
CBR TEST
SOIL DENSITY TEST
MOISTURE TEST
27
II. SAND LAYER :
We laid the layer of sand on the natural soil layer of the thickness 150
cm and the sand bed is level by the grader. Sand is taken from the
BANAS river which is near the tonk.
III. G.S.B. :
The granular base course is considered as the most imp component of
flexible pavement layer which sustain the wheel load stress and
disperse through larger area on the GSB layer below
Good quality coarse aggregates are used in the GSB layer of flexible
pavement
As per the ministry of Road Transport & Highway , Gov. of India ,
the aggregates used in the base course should have low aggregates
Impact value (less than 30 % ) and low Los Angles abrasion
value(less than 40%).
On site we laid the GSB layer and compact the layer with vibrator
with proper leveling and slope.
Then cone the field test density test by sand replacement
28
IV. BASE COURSE :
Aggregates used are of the smaller sizes, varies between the 4.75 mm to 20
mm sizes and the binders(stone dust or quarry dust having PI(Plasticity
Index) not less than 6%) are premixed in a batching plant or in a mixing
machine. Then they are brought to the site for overlaying and compaction.
The PI(plasticity Index) of the binding material is kept low because it should
be a sound and non plastic material. If the plasticity index is more then there
are the chances of the swelling and more water retention properties. So this
value should be kept in mind.
We use the grader and spread the WMM on the GSB layer and then do
leveling and compact the WMM with vibrator. Thickness of the layer was
150cm
29
V. BITUMINOUS LAYER :
The binder course surface prevent the entry of surface water into the
pavement layer during the rain and thus protects the base course and
other layer below. The bituminous surfacing serves as a binder course
for the traffic and provide the strength to the pavement and prevent
from the rain water .
30
CHAPTER 7
TEST DURING ROAD CONSTRUCTION
1. Testing of soil - testing of soil is compulsory for measuring the bearing capacity
of soil . these are the test of soil
C.B.R { California bearing ratio }
O.M.C { optimum moisture content }
M.D.D { moisture dry density }
1. Cylindrical mould with inside diameter 150 mm and height 175 mm,
provided with a detachable extension collar 50 mm height and a detachable
perforated base plate 10 mm thick.
3. Metal rammers : Weight 2.6 kg with a drop of 310 mm (or) weight 4.89
kg a drop 450 mm.
4. Weights : One annular metal weight and several slotted weights weighing
2.5 kg each, 147 mm in diameter, with a central hole 53 mm in diameter.
32
8. Sieves : 4.75 mm and 20 mm I.S. Sieves.
33
Figure : 20 moisture test content meter
35
Test Procedure:
Depending on the type of mold you are using obtain a sufficient
quantity of air-dried soil in large mixing pan. For the 4-inch mold
take approximately 10 lbs, and for the 6-inch mold take roughly 15
lbs. Pulverize the soil and run it through the # 4 sieve.
Determine the weight of the soil sample as well as the weight of the
compaction mold with its base (without the collar) by using the
balance and record the weights.
Compute the amount of initial water to add by the following method:
(a) Assume water content for the first test to be 8 percent.
(b) Compute water to add from the following equation:
Measure out the water, add it to the soil, and then mix it thoroughly
into the soil using the trowel until the soil gets a uniform color
Assemble the compaction mold to the base, place some soil in the
mold and compact the soil in the number of equal layers specified by
the type of compaction method employed
The soil should completely fill the cylinder and the last compacted
layer must extend slightly above the collar joint. If the soil is below
the collar joint at the completion of the drops, the test point must be
repeated.
Carefully remove the collar and trim off the compacted soil so that it
is completely even with the top of the mold using the trowel. Replace
small bits of soil that may fall out during the trimming process
Weigh the compacted soil while it’s in the mold and to the base, and
record the mass determine the wet mass of the soil by subtracting the
weight of the mold and base.
Remove the soil from the mold using a mechanical extruder and take
soil moisture content samples from the top and bottom of the
specimen .Fill the moisture cans with soil and determine the water
content.
37
Place the soil specimen in the large tray and break up the soil until it
appears visually as if it will pass through the # 4 sieve, add 2 percent
more water based on the original sample mass, and re-mix as it.
38
CHAPTER 8
REFRENCE
40