You are on page 1of 38

Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane

with paved shoulder configuration from existing Km. 268.000(Design Km.


266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of
Uttarakhand through an Engineering, Procurement and Construction (EPC)
Contract

Stage Payment Statement-


1.3.1 A.-Widening and Strengthening of Existing Road
1. Earthwork upto the top of the Subgrade
Chainage Length
Sl No Unit Side IPC No. Remarks
From To

1 266+100 266+265 Km 0.165 IPC-1


2 266+265 266+780 Km 0.515 IPC-4
3 266+345 266+630 Km 0.285 IPC-1

4 266+720 266+800 Km 0.080 IPC-1

5 266+840 267+080 Km 0.240 IPC-4


6 267+030 267+150 Km 0.120 IPC-1
7 268+010 268+190 Km 0.180 IPC-4
8 268+020 268+100 Km 0.080 IPC-1
9 268+190 268+495 Km 0.305 IPC-1
10 268+550 268+740 Km 0.190 IPC-1
11 270+880 270+940 Km 0.060 IPC-1
12 270+940 271+000 Km 0.060 IPC-3
13 271+000 271+120 Km 0.120 IPC-1
14 271+120 271+180 Km 0.060 IPC3
15 271+190 271+290 Km 0.100 IPC-1
16 271+290 271+420 Km 0.130 IPC-3
17 271+520 271+750 Km 0.230 IPC-3
18 271+880 271+970 Km 0.090 IPC-4
19 272+540 272+700 Km 0.160 IPC-1
20 273+350 273+450 Km 0.100 IPC-1
21 273+460 273+820 Km 0.360 IPC-1
22 273+830 273+890 Km 0.060 IPC-1
23 273+890 273+930 Km 0.040 IPC-3
24 273+930 274+000 Km 0.070 IPC-1
25 274+000 274+150 Km 0.150 IPC-3
26 274+350 274+510 Km 0.160 IPC-1
27 274+610 274+850 Km 0.240 IPC-1
28 274+850 275+000 Km 0.150 IPC-3
29 275+600 275+750 Km 0.150 IPC-1
30 276+040 276+170 Km 0.130 IPC-1
31 276+370 276+700 Km 0.330 IPC-1
32 276+740 276+860 Km 0.120 IPC-1
33 276+900 276+950 Km 0.050 IPC-3
34 276+950 276+990 Km 0.040 IPC-1
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design Km.
266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of
Uttarakhand through an Engineering, Procurement and Construction (EPC)
Contract

Stage Payment Statement-


1.3.1 A.-Widening and Strengthening of Existing Road
1. Earthwork upto the top of the Subgrade
Chainage Length
Sl No Unit Side IPC No. Remarks
From To
35 277+500 277+770 Km 0.270 IPC-3
36 277+770 277+860 Km 0.090 IPC-1
37 277+860 277+930 Km 0.070 IPC-1
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design Km.
266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of
Uttarakhand through an Engineering, Procurement and Construction (EPC)
Contract

Stage Payment Statement-


1.3.1 A.-Widening and Strengthening of Existing Road
1. Earthwork upto the top of the Subgrade
Chainage Length
Sl No Unit Side IPC No. Remarks
From To
38 277+930 277+990 Km 0.060 IPC-3
39 277+990 278+000 Km 0.010 IPC-1
40 278+000 278+140 Km 0.140 IPC-3
41 278+140 278+530 Km 0.390 IPC-1
42 278+600 278+780 Km 0.180 IPC-1
43 278+800 278+840 Km 0.040 IPC-1
44 278+980 279+150 Km 0.170 IPC-4
45 279+060 279+480 Km 0.420 IPC3

46 279+190 279+300 Km 0.110 IPC-4

47 279+300 279+450 Km 0.150 IPC-4

48 279+635 279+705 Km 0.070 IPC-1

49 280+185 280+265 Km 0.080 IPC-3

50 280+250 280+690 Km 0.440 IPC-4

51 280+460 280+640 Km 0.180 IPC-3

52 280+650 280+750 Km 0.100 IPC-4

53 280+780 280+960 Km 0.180 IPC-4

54 281+900 282+150 Km 0.250 IPC-1

55 282+220 282+265 Km 0.045 IPC-3

56 282+265 282+360 Km 0.095 IPC-3

57 282+360 282+370 Km 0.010 IPC-3

58 282+370 282+620 Km 0.250 IPC-1

59 282+650 282+670 Km 0.020 IPC-3


Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design Km.
266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of
Uttarakhand through an Engineering, Procurement and Construction (EPC)
Contract

Stage Payment Statement-


1.3.1 A.-Widening and Strengthening of Existing Road
1. Earthwork upto the top of the Subgrade
Chainage Length
Sl No Unit Side IPC No. Remarks
From To

60 282+670 282+880 Km 0.210 IPC-1

61 282+880 282+930 Km 0.050 IPC-3

62 282+930 283+220 Km 0.290 IPC-1

63 283+220 283+680 Km 0.460 IPC-3

64 283+230 283+500 Km 0.270 IPC-4

65 283+680 283+850 Km 0.170 IPC-1

66 284+050 284+090 Km 0.040 IPC-1

67 284+100 284+300 Km 0.200 IPC-4

68 284+170 284+400 Km 0.230 IPC-3


69 285+000 285+300 Km 0.300 IPC-3
70 285+310 285+390 Km 0.080 IPC-4
71 285+580 285+650 Km 0.070 IPC-4
72 285+650 285+850 Km 0.200 IPC-1
73 285+650 285+920 Km 0.270 IPC-4
74 286+200 286+300 Km 0.100 IPC-3
75 286+300 286+530 Km 0.230 IPC-3
76 286+590 286+750 Km 0.160 IPC-3
77 286+750 286+900 Km 0.150 IPC-3
78 287+930 288+070 Km 0.140 IPC-1
79 288+320 288+600 Km 0.280 IPC-1
80 288+880 289+120 Km 0.240 IPC-1
81 289+600 290+000 Km 0.400 IPC-1
82 290+200 290+350 Km 0.150 IPC-1
83
Stage Complete(Jan-2019) 4
Up to date executed Lengh in Km #REF!
Up to Previous Executed Length in Km 8
This bill executed Lengh in KM #REF!
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuration fro
Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 277.650 to 277.9
297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procurement and Constructi
Contract

INTERIM PAYMENT CERTIFICATE - 01


1.3.1. B. -New 2 lane Realignment/bypass
Earthwork upto the top of the Sub-grade
Chainage Length
Sl No RFI No. Date Unit Side
From To

1 CDS/KD/HWY/49 24.06.2018 266+265 266+345 Km 0.080

5 CDS/KD/HWY/54 25.06.2018 270+940 271+000 Km 0.060

6 CDS/KD/HWY/59 28.06.2018 271+120 271+160 Km 0.040

7 CDS/KD/HWY/42 21.06.2018 274+510 274+610 Km 0.100

10 CDS/KD/HWY/9 08.06.2018 276+860 276+950 Km 0.090

11 CDS/KD/HWY/18 12.06.2018 277+930 277+990 Km 0.060

12 CDS/KD/HWY/24 15.06.2018 278+530 278+600 Km 0.070

13 CDS/KD/HWY/20 13.06.2018 282+150 282+265 Km 0.115

Total Quantity Executed in Month Jun-18 0.615

2 CDS/KD/HWY/94 16.07.2018 266+630 266+720 Km 0.090

3 CDS/KD/HWY/100 17.07.2018 266+830 266+920 Km 0.090

4 CDS/KD/HWY/106 21.07.2018 268+495 268+550 Km 0.055

8 CDS/KD/HWY/92 15.07.2018 275+550 275+600 Km 0.050

9 CDS/KD/HWY/102 18.07.2018 275+940 276+010 Km 0.070

Total Quantity Executed in Month July-18 0.355


Up to date executed Lengh in Km 0.970
Up to Previous Executed Length in Km 0
This bill executed Lengh in KM 0.970
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuration fro
Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 277.650 to 277.9
297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procurement and Constructi
Contract

INTERIM PAYMENT CERTIFICATE - 01


1.3.1. B. -New 2 lane Realignment/bypass
Earthwork upto the top of the Sub-grade
Chainage Length
Sl No RFI No. Date Unit Side
From To
Submitted By Checked By Team Lead
Contractor: Authority Engineer:
nfiguration from existing
277.650 to 277.900 & Km.
and Construction (EPC)

IPC No. Remarks

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1

IPC-1
nfiguration from existing
277.650 to 277.900 & Km.
and Construction (EPC)

IPC No. Remarks

Team Leader
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design
Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of
Uttarakhand through an Engineering, Procurement and Construction
(EPC) Contract

Stage Payment Statement-


1.3.1 A.-Widening and Strengthening of Existing Road
2. Granular SubBase
GSB
Chainage Length
Sl No Unit Side IPC No. Remarks
From To

1 273+400 274+150 Km BHS 750 IPC-2


2 266+100 266+280 Km BHS 180 IPC-3
3 266+350 266+660 Km BHS 310 IPC-3
4 266+740 266+870 Km BHS 130 IPC-3
5 266+940 266+950 Km BHS 10 IPC-3
6 268+350 268+530 Km BHS 180 IPC-3
7 268+580 268+630 Km BHS 50 IPC-3
8 270+900 271+420 Km BHS 520 IPC-3
9 271+520 271+750 Km BHS 230 IPC-3
10 274+400 274+530 Km BHS 130 IPC-2
11 274+620 274+920 Km BHS 300 IPC-2
12 274+920 275+000 Km BHS 80 IPC-3
13 276+400 276+830 Km BHS 430 IPC-2
13 277+400 277+700 Km BHS 300 IPC-3
14 277+700 277+950 Km BHS 250 IPC-2
15 277+950 278+200 Km BHS 250 IPC-3
15 278+200 278+650 Km BHS 450 IPC-2
16 278+650 278+700 Km BHS 50 IPC-3
16 279+200 279+230 Km BHS 30 IPC-3
17 279+230 279+450 Km BHS 220 IPC-2
18 281+900 281+950 Km BHS 50 IPC-3
18 281+950 282+120 Km BHS 170 IPC-2
18 282+220 282+550 Km BHS 330 IPC-2
18 282+640 283+050 Km BHS 410 IPC-2
19 283+950 284+080 Km BHS 130 IPC-3
20 284+170 284+500 Km BHS 330 IPC-3
21 285+000 285+200 Km BHS 200 IPC-3
19 286+200 286+300 Km BHS 100 IPC-3
19 286+300 286+530 Km BHS 230 IPC-3
19 286+590 286+750 Km BHS 160 IPC-3
19 286+750 286+900 Km BHS 150 IPC-3
22 286+900 287+060 Km BHS 160 IPC-3
Up to date executed Lengh in Km ###
Up to Previous Executed Length in Km 3.440
This bill executed Lengh in KM ###
Widening and Reconstruction of existing intermediate/2 Lane to 2
Lane with paved shoulder configuration from existing Km.
268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500)
excluding existing Km. 277.650 to 277.900 & Km. 297.080 to 297.315
of NH-58 in the state of Uttarakhand through an Engineering,
Procurement and Construction (EPC) Contract

Stage Payment Statement-


1.3.1 A.-Widening and Strengthening of Existing Road
2. Granular SubBase
CT BASE
Sl Chainage Length
Unit Side IPC No. Remarks
No From To

1 266+100 266+280 Km BHS 0.180 IPC-3


2 266+265 266+780 Km BHS 0.515 IPC-4
3 266+350 266+660 Km BHS 0.310 IPC-3
4 266+740 266+850 Km BHS 0.110 IPC-3
5 266+840 267+080 Km BHS 0.240 IPC-4
6 268+010 268+190 Km BHS 0.180 IPC-4
7 268+350 268+530 Km BHS 0.180 IPC-3
8 268+580 268+630 Km BHS 0.050 IPC-3
9 270+900 271+420 Km BHS 0.520 IPC-3
10 271+520 271+750 Km BHS 0.230 IPC-3
3 271+880 271+970 Km BHS 0.090 IPC-4
3 273+400 274+150 Km BHS 0.750 IPC-2
3 274+400 274+530 Km BHS 0.130 IPC-2
4 274+620 274+900 Km BHS 0.280 IPC-2
6 274+900 275+000 Km BHS 0.100 IPC-3
6 276+460 276+830 Km BHS 0.370 IPC-2
6 277+600 277+700 Km BHS 0.100 IPC-3
7 277+700 277+850 Km BHS 0.150 IPC-2
8 277+850 278+200 Km BHS 0.350 IPC-3
8 278+200 278+620 Km BHS 0.420 IPC-2
8 278+620 278+700 Km BHS 0.080 IPC-3
8 278+980 279+150 Km BHS 0.170 IPC-4
9 279+190 279+300 Km BHS 0.110 IPC-4
10 279+230 279+350 Km BHS 0.120 IPC-2
11 279+300 279+450 Km BHS 0.150 IPC-4
5 279+350 279+400 Km BHS 0.050 IPC-3
5 280+250 280+690 Km BHS 0.440 IPC-4
5 280+650 280+750 Km BHS 0.100 IPC-4
280+780 280+960 Km BHS 0.180 IPC-4
282+000 282+120 Km BHS 0.120 IPC-2
282+220 282+550 Km BHS 0.330 IPC-2
282+650 283+020 Km BHS 0.370 IPC-2
283+040 283+150 Km BHS 0.110 IPC-3
283+230 283+500 Km BHS 0.270 IPC-4
284+100 284+300 Km BHS 0.200 IPC-4
285+000 285+200 Km BHS 0.200 IPC-3
285+310 285+390 Km BHS 0.080 IPC-4
285+580 285+650 Km BHS 0.070 IPC-4
285+650 285+920 Km BHS 0.270 IPC-4
286+200 286+300 Km BHS 0.100 IPC-3
286+300 286+530 Km BHS 0.230 IPC-3
286+590 286+650 Km BHS 0.060 IPC-3
286+755 286+850 Km BHS 0.095 IPC-3

Stage Complete(March-2019) 3.960


Up to date executed Lengh in Km #REF!
Up to Previous Executed Length in Km 3.040
This bill executed Lengh in KM #REF!
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design
Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing
Km. 277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state
of Uttarakhand through an Engineering, Procurement and Construction
(EPC) Contract

Stage Payment Statement-


1.3.1 (C) New Culverts, Minor Bridges, Underpasses, Overpasses:
(1) Culverts
Sr. No. Chainage Unit Size Nos IPC No. Remarks

1 266+450 No 1x1.5 1 IPC2


2 270+995 No 1x1.5 1 IPC-1
3 271+130 No 1x1.5 1 IPC2
4 271+290 No 1x1.5 1 IPC2
5 272+525 No 1x1.5 1 IPC-3
6 273+770 No 1x1.5 1 IPC2
7 273+925 No 1x1.5 1 IPC2
8 274+100 No 1x1.5 1 IPC2
9 274+475 No 1x1.5 1 IPC-1
10 274+620 No 1x1.5 1 IPC2
11 274+780 No 1x1.5 1 IPC2
12 276+515 No 1x1.5 1 IPC-1
13 276+830 No 1x1.5 1 IPC-1
14 276+960 No 1x1.5 1.0 IPC-1
15 277+605 No 1x1.5 1.0 IPC-3
16 277+860 No 1x1.5 1.0 IPC-3
17 278+175 No 1x1.5 1.0 IPC-1
18 278+255 No 1x1.5 1.0 IPC-1
19 278+450 No 1x1.5 1.0 IPC-1
20 278+590 No 1x1.5 1.0 IPC-1
21 278+690 No 1x1.5 1.0 IPC-1
22 278+780 No 1x1.5 1.0 IPC-1
23 279+695 No 1x1.5 1.0 IPC-1
24 281+250 No 1x1.5 1.0 IPC-3
25 281+900 No 1x1.5 1.0 IPC-3
26 282+015 No 1x1.5 1.0 IPC-1
27 282+200 No 1x1.5 1.0 IPC-3
28 282+330 No 1x1.5 1.0 IPC2
29 282+640 No 1x1.5 1.0 IPC2
30 282+780 No 1x1.5 1.0 IPC2
31 282+905 No 1x1.5 1.0 IPC-3
32 282+950 No 1x1.5 1.0 IPC2
33 283+050 No 1x1.5 1.0 IPC2
34 285+010 No 1x1.5 1.0 IPC-3
35 285+730 No 1x1.5 1.0 IPC-3
36 286+185 No 1x1.5 1.0 IPC-3
37 286+335 No 1x1.5 1.0 IPC-3
38 286+460 No 1x1.5 1.0 IPC-3
39 286+755 No 1x1.5 1.0 IPC-3
40 289+910 No 1x1.5 1.0 IPC2
41 290+230 No 1x1.5 1.0 IPC2
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design
Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing
Km. 277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state
of Uttarakhand through an Engineering, Procurement and Construction
(EPC) Contract

Stage Payment Statement-


1.3.1 (C) New Culverts, Minor Bridges, Underpasses, Overpasses:
(1) Culverts
Sr. No. Chainage Unit Size Nos IPC No. Remarks
42 266+130 No 1x1.5 1.0 IPC-4
43 266+920 No 1x1.5 1.0 IPC-4
44 268+050 No 1x1.5 1.0 IPC-4
45 280+825 No 1x1.5 1.0 IPC-4
46 280+902 No 1x1.5 1.0 IPC-4
47 283+160 No 1x1.5 1.0 IPC-4
48 283+405 No 1x1.5 1.0 IPC-4
49 285+570 No 1x1.5 1.0 IPC-4

Stage Complete(Feb-2019) 9
Upto Date #REF!
Total Paid till Previous Bill = 28.00
Total This Bill #REF!
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane
with paved shoulder configuration from existing Km. 268.000(Design Km.
266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of
Uttarakhand through an Engineering, Procurement and Construction
(EPC) Contract
Stage Payment Statement-
1.3.4 (iii) Road side Drain

Chainage Length
Sl No Unit Side IPC No. Remarks
From To

1 268+350 268+600 Km LHS 0.250 IPC-3


2 271+050 271+300 Km LHS 0.250 IPC-3
3 273+400 274+150 Km LHS 0.750 IPC-3
4 274+400 274+700 Km LHS 0.300 IPC-3
5 276+470 276+800 Km LHS 0.330 IPC-3
6 278+230 278+600 Km LHS 0.370 IPC-3
7 282+050 282+550 Km LHS 0.500 IPC-3
8 282+650 283+100 Km LHS 0.450 IPC-3
Stage Complete(March-2019) 3.200
Up to date executed Lengh in Km 3.200
Up to Previous Executed Length in Km 0.000
This bill executed Lengh in KM 3.200
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with
paved shoulder configuration from existing Km. 268.000(Design Km. 266.100) to
Km. 300.00 (Design Km. 296.500) excluding existing Km. 277.650 to 277.900 &
Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an
Engineering, Procurement and Construction (EPC) Contract

Stage Payment Statement-


1.3.4 Other Works
(V) Project Facilities
(c) Utility Duct
Chainage Length
Sl No Unit Side IPC No. Remarks
From To

1 266+100 266+340 Km LHS 0.240 IPC-1

2 266+340 266+640 Km LHS 0.300 IPC-1

3 266+640 266+815 Km LHS 0.175 IPC-1

4 266+830 266+950 Km LHS 0.120 IPC-1


5 266+840 267+080 Km LHS 0.240 IPC-4

6 267+030 267+165 Km LHS 0.135 IPC-1

7 268+020 268+100 Km LHS 0.080 IPC-1


8 268+100 268+190 Km LHS 0.090 IPC-4
9 268+190 268+490 Km LHS 0.300 IPC-1

10 268+490 268+775 Km LHS 0.285 IPC-1

11 270+850 271+150 Km LHS 0.300 IPC-1

12 271+180 271+290 Km LHS 0.110 IPC-1

13 271+880 271+970 Km LHS 0.090 IPC-4

14 272+525 272+720 Km LHS 0.195 IPC-1


15 273+345 273+465 Km LHS 0.120 IPC-1
16 273+465 273+820 Km LHS 0.355 IPC-1
17 273+820 274+030 Km LHS 0.210 IPC-1
18 274+080 274+110 Km LHS 0.030 IPC-1
19 274+350 274+630 Km LHS 0.280 IPC-1
20 275+540 275+580 Km LHS 0.040 IPC-1

21 275+600 275+760 Km LHS 0.160 IPC-1

22 275+930 276+010 Km LHS 0.080 IPC-1


23 276+030 276+170 Km LHS 0.140 IPC-1
24 276+370 276+700 Km LHS 0.330 IPC-1
25 276+740 276+990 Km LHS 0.250 IPC-1
26 277+770 278+020 Km LHS 0.250 IPC-1
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with
paved shoulder configuration from existing Km. 268.000(Design Km. 266.100) to
Km. 300.00 (Design Km. 296.500) excluding existing Km. 277.650 to 277.900 &
Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an
Engineering, Procurement and Construction (EPC) Contract

Stage Payment Statement-


1.3.4 Other Works
(V) Project Facilities
(c) Utility Duct
27 278+140 278+540 Km LHS 0.400 IPC-1

28 278+540 278+790 Km LHS 0.250 IPC-1


29 278+790 278+840 Km LHS 0.050 IPC-1
30 278+840 279+060 Km LHS 0.220 IPC-4
31 278+980 279+150 Km LHS 0.170 IPC-4
32 279+060 279+480 Km LHS 0.420 IPC-1
33 279+635 279+715 Km LHS 0.080 IPC-1
34 280+185 280+270 Km LHS 0.085 IPC-1

35 280+270 280+460 Km LHS 0.190 IPC-4

36 280+460 280+650 Km LHS 0.190 IPC-1


37 280+650 280+750 Km LHS 0.100 IPC-4
38 280+650 280+780 Km LHS 0.130 IPC-4
39 280+780 280+960 Km LHS 0.180 IPC-4
40 280+780 280+960 Km LHS 0.180 IPC-4
41 281+150 281+300 Km LHS 0.150 IPC-4

42 281+340 281+430 Km LHS 0.090 IPC-4

43 281+900 282+260 Km LHS 0.360 IPC-1


44 282+260 282+385 Km LHS 0.125 IPC-1
45 282+385 282+620 Km LHS 0.235 IPC-1
46 282+670 282+880 Km LHS 0.210 IPC-1
47 282+910 283+235 Km LHS 0.325 IPC-1
48 283+230 283+500 Km LHS 0.270 IPC-4
49 283+230 283+500 Km LHS 0.270 IPC-4
50 283+680 283+860 Km LHS 0.180 IPC-1
51 284+050 284+090 Km LHS 0.040 IPC-1
52 284+100 284+300 Km LHS 0.200 IPC-4
53 284+100 284+400 Km LHS 0.300 IPC-4
54 285+310 285+390 Km LHS 0.080 IPC-4
55 285+580 285+650 Km LHS 0.070 IPC-4
56 285+650 285+850 Km LHS 0.200 IPC-1
57 287+930 288+070 Km LHS 0.140 IPC-1
58 288+320 288+600 Km LHS 0.280 IPC-1
59 288+880 289+120 Km LHS 0.240 IPC-1
60 289+600 290+000 Km LHS 0.400 IPC-1
61 290+200 290+350 Km LHS 0.150 IPC-1
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with
paved shoulder configuration from existing Km. 268.000(Design Km. 266.100) to
Km. 300.00 (Design Km. 296.500) excluding existing Km. 277.650 to 277.900 &
Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an
Engineering, Procurement and Construction (EPC) Contract

Stage Payment Statement-


1.3.4 Other Works
(V) Project Facilities
(c) Utility Duct

Stage Complete(July-18) 4.295


Up to date executed Lengh in Km #REF!
Up to Previous Executed Length in Km 8.845
This bill executed Lengh in KM #REF!
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuratio
existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 27
277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procure
Construction (EPC) Contract
Stage Payment Statement-
1.3.4 Other Works
(VIII) Protection Works
(a) Retaining Wall

Chainage
Sl No RFI No. Date Unit Side Unit
From To

CDS/KD/PROT/39A & 10/6/2018 &


1 55A 12/6/2018 266+120 266+131 Mtr RHS 0.011

10/6/2018,
16/6/2018,
CDS/KD/PROT/44, 103, 21/6/2018,
2 164, 222, 258, 324 & 24/6/2018, 266+130 266+137 Mtr RHS 0.007
335 27/6/2018/
10/7/2018 &
11/6/2018,
13/7/2018
12/6/2018,
CDS/KD/PROT/47A, 62A, 13/6/2018,
3 64A, 81, 96, 153, 262 & 15/6/2018, 266+137 266+142 Mtr RHS 0.005
16/6/2018,
276A 20/6/2018,
28/6/2018
11/6/2018,&
CDS/KD/PROT/49, 54, 30/6/2018
12/6/2018,
4 112 & 150 17/6/2018 266+200 266+260 Mtr RHS 0.060
11/6/2018,&
20/6/2018
6/7/2018,
8/7/2018,
CDS/KD/PROT/50, 314A, 11/7/2018,
5 319, 332, 337, 345, 350 14/7/2018, 266+420 266+425 Mtr RHS 0.005
& 351 21/7/2018
25/7/2018
12/6/2018,&
CDS/KD/PROT/62, 118, 24/7/2018
18/6/2018,
6 223 & 331 24/6/2018 & 266+427 266+444 Mtr RHS 0.017
11/7/2018

CDS/KD/PROT/333A & 12/7/2018 &


7 336 B 13/07/2018 266+444 266+452 Mtr RHS 0.008

13/6/2018,
CDS/KD/PROT/69,221 &
8 272 24/6/2018 & 266+460 266+460 Mtr RHS 0.000
29/06/2018

13/7/2018,
CDS/KD/PROT/334B, 13/7/2018,
9 331B, 342B & 343B 16/7/2018 & 266+468 266+473 Mtr RHS 0.005
20/7/2018

14/6/2018,
CDS/KD/PROT/72, 81A, 15/6/2018,
10 151A & 274A 20/6/2018 & 266+550 266+585 Mtr RHS 0.035
29/6/2018

15/6/2018 &
11 CDS/KD/PROT/93 & 148 20/6/2018 266+615 266+655 Mtr RHS 0.040

15/6/2018 &
12 CDS/KD/PROT/92 & 149 20/6/2018 266+780 266+810 Mtr RHS 0.030
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuratio
existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 27
277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procure
Construction (EPC) Contract
Stage Payment Statement-
1.3.4 Other Works
(VIII) Protection Works
(a) Retaining Wall

Chainage
Sl No RFI No. Date Unit Side Unit
13 CDS/KD/PROT/341A 16/7/2018 266+810 266+860 Mtr RHS 0.050
17/6/2018,
CDS/KD/PROT/105, 151
14 & 203 20/6/2018 & 266+870 266+890 Mtr RHS 0.020
23/6/2018

18/6/2018,
21/6/2018,
CDS/KD/PROT/119, 165,
15 213, 304 & 314B 24/6/2018, 268+050 268+085 Mtr RHS 0.035
3/7/2018 &
6/7/2018

16 CDS/KD/PROT/136 20/6/2018 268+150 268+170 Mtr RHS 0.020


22/6/2018,
CDS/KD/PROT/174, 202
17 & 303 23/6/2018 & 268+190 268+200 Mtr RHS 0.010
3/7/2018

22/6/2018,
CDS/KD/PROT/175A, 24/6/2018,
18 209, 263 & 306 28/6/2018 & 268+230 268+250 Mtr RHS 0.020
3/7/2018

22/6/2018,
CDS/KD/PROT/173A,
19 250, 251 & 336A 26/6/2018 & 268+480 268+500 Mtr RHS 0.020
13/7/2018

20 CDS/KD/PROT/200 & 23/6/2018 & 268+700 268+727 Mtr RHS 0.027


253 27/6/2018

23/6/2018,01/
CDS/KD/PROT/201,285,3 07/2018,
21 269+600 269+623 Mtr RHS 0.023
31A &344 12/07/2018 &
21/07/2018

25/6/2018,
CDS/KD/PROT/240,273
22 29/6/2018 & 270+705 270+725 Mtr RHS 0.020
& 323 10/07/2018

25/6/2018,5/0
CDS/KD/PROT/239,313,3 7/2018 ,
23 270+740 270+755 Mtr RHS 0.015
32A & 340 12/07/2018 &
16/07/2018

CDS/KD/PROT/251A & 26/6/18 &


24 270+910 270+938 Mtr RHS 0.028
271 29/6/2018

26/6/2018,
29/6/2018,
CDS/KD/PROT/249,
25 29/6/2018, 271+010 271+053 Mtr RHS 0.043
273A, 274, 288 & 318 1/7/2018 &
8/7/2018
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuratio
existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 27
277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procure
Construction (EPC) Contract
Stage Payment Statement-
1.3.4 Other Works
(VIII) Protection Works
(a) Retaining Wall

Chainage
Sl No RFI No. Date Unit Side Unit
26/6/2018,
CDS/KD/PROT/252, 278,
26 279 & 337 30/6/2018, 271+190 271+220 Mtr RHS 0.030
14/7/2018
9/6/2018 &
27 CDS/KD/PROT/36 & 70 13/6/2018 271+460 271+485 Mtr RHS 0.025

9/6/2018 &
28 CDS/KD/PROT/26 & 27 9/6/2018 271+555 271+600 Mtr RHS 0.045

9/6/2018,
10/6/2018,
CDS/KD/PROT/35,43,102 16/6/2018,
29 ,314 & 341 271+760 271+780 Mtr RHS 0.020
5/07/2018 &
16/07/2018

9/7/2018,
CDS/KD/PROT/321A, 12/07/2018,
30 271+840 271+864 Mtr RHS 0.024
335B, 344A &346 21/07/2018 &
23/07/2018
31 CDS/KD/PROT/421 8/7/2018 271+864 271+875 Mtr RHS 0.011

32 CDS/KD/PROT/439 8/11/2018 271+880 271+950 Mtr RHS 0.070

33 CDS/KD/PROT/474 8/14/2018 271+960 271+975 Mtr RHS 0.015


34 CDS/KD/PROT/475 8/14/2018 272+500 272+530 Mtr RHS 0.030
35 CDS/KD/PROT/482 8/16/2018 272+810 272+820 Mtr RHS 0.010
36 CDS/KD/PROT/490 8/17/2018 272+820 272+824 Mtr RHS 0.004

37 CDS/KD/PROT/504 8/19/2018 272+860 272+875 Mtr RHS 0.015


Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuratio
existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 27
277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procure
Construction (EPC) Contract
Stage Payment Statement-
1.3.4 Other Works
(VIII) Protection Works
(a) Retaining Wall

Chainage
Sl No RFI No. Date Unit Side Unit
38 CDS/KD/PROT/505 8/19/2018 273+280 273+292 Mtr RHS 0.012
39 CDS/KD/PROT/843 8/20/2018 273+500 273+535 Mtr RHS 0.035
40 CDS/KD/PROT/513 8/20/2018 273+900 273+941 Mtr RHS 0.041
41 CDS/KD/PROT/517 8/24/2018 273+955 274+050 Mtr RHS 0.095
1 CDS/KD/PROT/536 9/3/2018 274+050 274+060 Mtr RHS 0.010
2 CDS/KD/PROT/543 9/8/2018 274+060 274+110 Mtr RHS 0.050
3 CDS/KD//PROT/583 9/15/2018 274+110 274+132 Mtr RHS 0.022
4 CDS/KD/PROT/595 9/18/2018 274+540 274+580 Mtr RHS 0.040
5 CDS/KD/PROT/598 9/18/2018 274+740 274+765 Mtr RHS 0.025
6 CDS/KD/PROT/609 9/21/2018 274+765 274+787 Mtr RHS 0.022
7 CDS/KD/PROT/611 9/22/2018 274+900 274+945 Mtr RHS 0.045
8 CDS/KD/PROT/614 9/22/2018 274+945 275+005 Mtr RHS 0.060
9 CDS/KD/PROT/624 9/25/2018 276+100 276+140 Mtr RHS 0.040
10 CDS/KD/PROT/631 9/29/2018 276+555 276+585 Mtr RHS 0.030
11 CDS/NH/58/2/PW/88 10/22/2018 276+640 276+680 Mtr RHS 0.040
12 CDS/NH/58/2/PW/149 11/2/2018 276+800 276+828 Mtr RHS 0.028
13 CDS/NH58/2/PW/151 11/2/2018 277+510 277+535 Mtr RHS 0.025
14 CDS/NH58/2/PW/152 11/2/2018 277+535 277+551 Mtr RHS 0.016
15 CDS/NH58/2/PW/150 11/2/2018 277+580 277+590 Mtr RHS 0.010
16 CDS/NH/58/2/PW/163 11/4/2018 277+620 277+680 Mtr RHS 0.060
17 CDS/NH/58/2/PW/159 11/5/2018 277+750 277+816 Mtr RHS 0.066
18 CDS/NH/58/2/PW/580 11/15/2018 278+300 278+322 Mtr RHS 0.022
19 CDS/KD/PROT/724 11/28/2018 278+322 278+323 Mtr RHS 0.001
20 CDS/NH/58/2/PW/273 12/1/2018 278+930 278+956 Mtr RHS 0.026
21 CDS/NH/58/2/PW/272 12/1/2018 278+980 279+004 Mtr RHS 0.024
22 CDS/KD/PROT/755 12/2/2018 279+004 279+021 Mtr RHS 0.017
23 CDS/KD/PROT/794 12/7/2018 279+100 279+109 Mtr RHS 0.009
24 CDS/KD/PROT/795 12/7/2018 279+668 279+723 Mtr RHS 0.055
25 CDS/NH/58/2/PW/335 12/7/2018 280+170 280+244 Mtr RHS 0.074
26 CDS/KD/PROT/480 12/12/2018 280+660 280+699 Mtr RHS 0.039
27 CDS/NH/58/2/PW/404 12/14/2018 281+250 281+290 Mtr RHS 0.040
28 CDS/NH/58/2/PW/386 12/14/2018 281+290 281+302 Mtr RHS 0.012
29 CDS/NH/58/2/PW/387 12/15/2018 281+350 281+390 Mtr RHS 0.040
30 CDS/KD/PROT/834 12/16/2018 281+660 281+694 Mtr RHS 0.034
31 CDS/KD/PROT/843 12/17/2018 281+750 281+785 Mtr RHS 0.035
32 CDS/KD/PROT/852 12/18/2018 281+930 282+020 Mtr RHS 0.090
33 CDS/KD/PROT/850 12/18/2018 282+030 282+070 Mtr RHS 0.040
34 CDS/KD/PROT/856 12/18/2018 282+100 282+148 Mtr RHS 0.048
35 CDS/KD/PROT/857 12/18/2018 282+250 282+273 Mtr RHS 0.023
36 CDS/NH/58/2/PW/442 12/20/2018 282+290 282+340 Mtr RHS 0.050
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuratio
existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 27
277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procure
Construction (EPC) Contract
Stage Payment Statement-
1.3.4 Other Works
(VIII) Protection Works
(a) Retaining Wall

Chainage
Sl No RFI No. Date Unit Side Unit
37 CDS/KD/PROT/906 12/24/2018 282+355 282+362 Mtr RHS 0.007
38 CDS/KD/PROT/909 12/25/2018 282+450 282+466 Mtr RHS 0.016
39 CDS/KD/PROT/942 12/29/2018 282+800 282+829 Mtr RHS 0.029
40 CDS/KD/PROT/946 12/29/2018 282+850 282+905 Mtr RHS 0.055
41 CDS/KD/PROT/950 12/30/2018 282+924 282+930 Mtr RHS 0.006
282+930 282+950 Mtr RHS 0.020
282+955 282+963 Mtr RHS 0.008
283+000 283+025 Mtr RHS 0.025
283+037 283+048 Mtr RHS 0.011
283+053 283+063 Mtr RHS 0.010
283+200 283+550 Mtr RHS 0.350
284+239 284+280 Mtr RHS 0.041
285+170 285+185 Mtr RHS 0.015
285+560 285+566 Mtr RHS 0.006
285+571 285+596 Mtr RHS 0.025
285+640 285+681 Mtr RHS 0.041
285+750 285+757 Mtr RHS 0.007
285+762 285+770 Mtr RHS 0.008
286+200 286+220 Mtr RHS 0.020
286+240 286+280 Mtr RHS 0.040
286+700 286+750 Mtr RHS 0.050
286+800 286+831 Mtr RHS 0.031
286+870 286+893 Mtr RHS 0.023
287+010 287+042 Mtr RHS 0.032
287+050 287+086 Mtr RHS 0.036
287+100 287+126 Mtr RHS 0.026
287+150 287+167 Mtr RHS 0.017
287+300 287+333 Mtr RHS 0.033
287+990 288+054 Mtr RHS 0.064
288+725 288+820 Mtr RHS 0.095
288+825 288+835 Mtr RHS 0.010
289+910 289+925 Mtr RHS 0.015
289+930 289+932 Mtr RHS 0.002
290+217 290+230 Mtr RHS 0.013
290+235 290+246 Mtr RHS 0.011
291+350 291+391 Mtr RHS 0.041
291+455 291+480 Mtr RHS 0.025
291+560 291+730 Mtr RHS 0.170
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuratio
existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km. 27
277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering, Procure
Construction (EPC) Contract
Stage Payment Statement-
1.3.4 Other Works
(VIII) Protection Works
(a) Retaining Wall

Chainage
Sl No RFI No. Date Unit Side Unit

Stage Complete(Dec-18) 1.378


Up to date executed Lengh in mtr #REF!
Up to Previous Executed Length in mtr 2540.30
This bill executed Lengh in mtr #REF!
houlder configuration from
ding existing Km. 277.650 to
ngineering, Procurement and

IPC No. Remarks

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4
houlder configuration from
ding existing Km. 277.650 to
ngineering, Procurement and

IPC No. Remarks


IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-4

IPC-1

IPC-1

IPC-2

IPC-2

IPC-2

IPC-2
houlder configuration from
ding existing Km. 277.650 to
ngineering, Procurement and

IPC No. Remarks


IPC-4

IPC-4

IPC-4

IPC-4

IPC-1

IPC-2

IPC-2

IPC-2
IPC-2
IPC-2
IPC-2

IPC-2
houlder configuration from
ding existing Km. 277.650 to
ngineering, Procurement and

IPC No. Remarks


IPC-4
IPC-1
IPC-1
IPC-4
IPC-2
IPC-1
IPC-2
IPC-2
IPC-1
IPC-2
IPC-1
IPC-2
IPC-1
IPC-1
IPC-1
IPC-2
IPC-1
IPC-2
IPC-4
IPC-1
IPC-1
IPC-1
IPC-2
IPC-2
IPC-1
IPC-2
IPC-2
IPC-2
IPC-1
IPC-1
IPC-1
IPC-2
IPC-1
IPC-1
IPC-1
IPC-1
IPC-1
IPC-1
IPC-2
IPC-1
houlder configuration from
ding existing Km. 277.650 to
ngineering, Procurement and

IPC No. Remarks


IPC-2
IPC-1
IPC-2
IPC-1
IPC-2
IPC-1
IPC-2
IPC-1
IPC-2
IPC-2
IPC-4
IPC-2
IPC-4
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-4
IPC-4
IPC-4
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
IPC-2
houlder configuration from
ding existing Km. 277.650 to
ngineering, Procurement and

IPC No. Remarks


Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder configuration
from existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500) excluding existing Km.
277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand through an Engineering,
Procurement and Construction (EPC) Contract

Stage Payment Statement-


1.3.4 Other Works
(VIII) Protection Works

(b) Breast Wall


Chainage Length
Sl No RFI No. Date Unit Side IPC No.
From To
1 CDS/KD/PROT/193 23/06/2018 266+100 266+133 Mtr LHS 33 IPC-1
19 CDS/KD/PROT/195 23/6/2018 282+000 282+030 Mtr LHS 30 IPC-1
20 CDS/KD/PROT/257 27/6/2018 282+150 282+270 Mtr LHS 120 IPC-1
21 CDS/KD/PROT/127 19/6/2018 282+660 282+696 Mtr LHS 36 IPC-1
22 CDS/KD/PROT/246 26/6/2018 282+696 282+723 Mtr LHS 27 IPC-1
24 CDS/KD/PROT/108 17/6/2018 282+990 283+002 Mtr LHS 12 IPC-1
26 CDS/KD/PROT/142 20/6/2018 283+030 283+063 Mtr LHS 33 IPC-1
27 CDS/KD/PROT/196 23/6/2018 283+070 283+112 Mtr LHS 42 IPC-1
28 CDS/KD/PROT/141 20/6/2018 283+700 283+736 Mtr LHS 36 IPC-1
3 CDS/KD/PROT/234 25/6/2018 266+530 266+602 Mtr LHS 72 IPC-1
4 CDS/KD/PROT/255 27/6/2018 266+600 266+681 Mtr LHS 81 IPC-1
6 CDS/KD/PROT/265 28/6/2018 266+970 267+042 Mtr LHS 72 IPC-1
7 CDS/KD/PROT/176 22/6/2018 268+370 268+470 Mtr LHS 100 IPC-1
13 CDS/KD/PROT/256 27/6/2018 276+500 276+560 Mtr LHS 60 IPC-1
14 CDS/KD/PROT/111A 17/6/2018 276+700 276+760 Mtr LHS 60 IPC-1
16 CDS/KD/PROT/216 24/6/2018 277+740 277+776 Mtr LHS 36 IPC-1
17 CDS/KD/PROT/82 15/6/2018 278+310 278+350 Mtr LHS 40 IPC-1
Stage Complete(Jun-18) 890.000
2 CDS/KD/PROT/310 05.07-2018 266+140 266+269 Mtr LHS 129 IPC-1
8 CDS/KD/PROT/322 09.07-2018 271+350 271+392 Mtr LHS 42 IPC-1
10 CDS/KD/PROT/307 04.07.2018 273+800 273+890 Mtr LHS 90 IPC-1
11 CDS/KD/PROT/284 01.07-2018 273+940 274+050 Mtr LHS 110 IPC-1
12 CDS/KD/PROT/287 01.07-2018 276+100 276+174 Mtr LHS 74 IPC-1
15 CDS/KD/PROT/325 10.07-2018 276+820 276+883 Mtr LHS 63 IPC-1
18 CDS/KD/PROT/343A 20/7/2018 281+350 281+470 Mtr LHS 120 IPC-1
Stage Complete(July-18) 628.000
Up to date executed Lengh in mtr 1518
Up to Previous Executed Length in mtr 1518
This bill executed Lengh in mtr 0.000
houlder configuration
excluding existing Km.
hrough an Engineering,

Remarks
Widening and Reconstruction of existing intermediate/2 Lane to 2 Lane with paved shoulder
configuration from existing Km. 268.000(Design Km. 266.100) to Km. 300.00 (Design Km. 296.500)
excluding existing Km. 277.650 to 277.900 & Km. 297.080 to 297.315 of NH-58 in the state of Uttarakhand
through an Engineering, Procurement and Construction (EPC) Contract

Stage Payment Statement-

1.3.4 Other Works

(IX) Safety & Traffic Management During Construction Period


SL.
Description Chainage Duration QTY (No.) IPC No. Remarks
NO.
Safety & Traffic
266+100 to 296+500 01-Jan-2018 To
1 Management During 1 IPC-1
30-June-2018
Construction Period
Stage Complete(Jun-18) 1

Safety & Traffic


266+100 to 296+500 01-Jul-2018 To
2 Management During 1 IPC-2
31- Dec-2018
Construction Period

Stage Complete(Dec-18) 1
Up to date Quantity 2
Up to Previous Quantity 2
This bill Quantity 0
existing New
100 70
200 80
200 70
20 70
20 60
60 50
150 30
100 40
30 140
70 60
100 60
120 100
130 100
100 100
30 85
280 90
190 90
100 80
100 120
400 60
450 70
320 90
130 100
250 90
350 140
200 60
300 70
200 80
280 100
190 80
230 100
70 120
130 2655
50
230
240
50
100
30
100
50
50
200
50
250
100
30
120
70
180
120
130
50
100
200
40
360
100
650
110
100
140
50
50
120
130
40
40
150
20
70
80
100
50
130
170
80
120
100
200
100
50
100
50
100
50
50
70
50
130
100
590
160
100
250
50
70
30
350
100
50
100
900
150
350
150
500
600
50
260
60
80
120
380
50
850
340
60
50
100
400
50
200
180
220
70
170
60
250
50
50
150
100
60
40
350
50
500
130
370
250
50
120
30
50
100
40
110
190
760
50
100
20
30
100
250
170
580
50
610
490
30
380
160
280
30
120
70
220
560
450
150
230
170
340
60
100
30000
27345
85

You might also like