You are on page 1of 81

COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 1 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Rev. A3 Comments received vide Transmittal No. PE-ZR-DAS-NT-TR-02209

Contractor to discuss the comments and their


resolution before the next revision of the Noted and incorporated
1 CRS CRS
document, to ensure a code-1 in the next revision
of the document.

Noted and the document updated based on


alignment with CONTRACTOR’s
Meeting to be arranged by the Contractor with Instrumentation Team, as suited for a
CRS, Rev. A2 , Company in order to finalise the signals philosophy level document.
2 CRS
Sr. No. 8 requirements in the matrix panel, in line with the
existing philosophy The relevant details of matrix panel shall be
provided as part of Vendor details.

Noted and updated based on following


correspondences and COMPANY’s review
of ESD Cause and Effect.

 Company’s Letter PE/ZR&DAS/L-


0267/19/P7564 dated 20th March
CRS, Rev. A2 , To be identified based on agreed executive action
3 CRS 2019
Sr. No. 25 & 26 (refer to F&G design review report point. 17)
 Contractor Response Letter
E14016/CCJV-ZAD/L-0406 dated 11
April 2019
 Company Response Letter
PE/ZR&DAS/L-0336/19/P7564
dated 12th May 2019
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 2 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Noted and updated based on following


correspondences and COMPANY’s review
of ESD Cause and Effect.

 Company’s Letter PE/ZR&DAS/L-


The LP Philosophy shall be updated subsequent
0267/19/P7564 dated 20th March
Revision Control to meeting on F&G Cause and Effect and
4 Page 2 2019
Sheet Page finalization/ resolution of Instrumentation related
 Contractor Response Letter
aspects.
E14016/CCJV-ZAD/L-0406 dated 11
April 2019
 Company Response Letter
PE/ZR&DAS/L-0336/19/P7564
dated 12th May 2019

This is not in line with the FEED (as below)


- March Time or Code 3- indicates
Noted and updated for further clarity as per
hydrocarbon/toxic gas present within the fire &
5 Page 39 Section 6.6.1 P8363.
gas zone
- Steady Tone - indicates fire within the fire & gas
zone

Rev. A2 Comments received vide Transmittal No. ZRIP-NT-TR-00645

F & G philosophy shall be aligned with F & G Noted and the philosophy is updated.
1. Page 1 Cover Page
upgrade project and Findings of Site Visit
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 3 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Noted and the TQs have been raised to


formalize any changes from FEED.

 Hydrants have standard capacity.


 Monitor capacity is aligned with
existing monitor capacity of 6000
The design criteria such as capacity of Hydrants, lpm.
2. Page 1 Cover Page Monitors , Deluge, Firefighting Equipment, , Fire  Deluge capacity is based on water
Extinguishers etc. shall be verified during site Visit demand.
 Hose reels are not available at site.
 TQ has been raised for fire
extinguishers
 Mobile foam units are similar to
existing.

Existing type of Firefighting equipment and


existing plant design data shall be taken into Noted. Refer response to Item #2.
3. Page 1 Cover Page
consideration while deciding the selection of
Firefighting design of the Project.
The Instrumentation comments on previous
revision were not received. The comments
comments are neither incorporated nor addressed
4. Page 1 Cover Page received now with Rev. A2 comments are
in the CRS Comments attached again
addressed in subsequent rows accordingly.

contractor shall action the above through interface Fire and Gas Design Review has been
Revision Control
5. Page 2 agreement meeting at the earliest. Also include conducted and the report has been issued.
Sheet
the F&G console at ZCC/ZER.

The temperature class is already indicated in


6. Page 27 Section 5.4.4 Indicate Temp class also previous para.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 4 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Smoke detection for battery rooms in


Address about smoke detectors in battery room
7. Page 27 Section 5.4.4 included in Section 6.5.1.
(as applicable)

- Reset and override push buttons shall be


detailed in relevant Instrumentation
documents/drawings.
- HVAC feedback/status will be available in
HMI
Clarify and update below - Suppression agent PB will be available in
- Reset and override push buttons Inergen Status Panels provided by Inergen
8. Page 40 Section 6.7.4 Vendor
HVAC status
- Suppression agent PB and status alarms
- and status alarms in auxiliary consoles are
already updated in the philosophy.

For details refer to F&G Cause and Effect


Diagram for the Project.

Review and update the matrix panel in SS116


Noted and incorporated.
9. Page 40 Section 6.7.4 (Refer to P8363 LP philosophy, every SS shall be
provided with F&G matrix panel)

Instrumentation Comments

Noted and incorporated for Operator Cabin.

10. Page 26 Section 5.4.4 Address also Operator Cabin, Analyser shelter Analyser Shelter shall follow the Specification
for Analyser Shelter, P7564-TS-400-J-0047.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 5 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Noted and incorporated


11. Page 29 Section 6.3.1 following the existing F&G upgrade project

Instrument tubing to facilitate calibration shall be


Noted and incorporated
12. Page 29 Section 6.3.1 made, if the detectors are at inaccessible
locations
Air lock is provided for LER. The document is
clarify and update the requirement of Air lock for updated accordingly.
13. Page 31 Section 6.3.4.1 SS116 and LER. Refer to FEED Plot plan review
report (P7564-SR-400-P-0019) item 31,32 Air lock is not provided for SS116

Noted and incorporated for 30 % and 90 %


model only as per Scope of Work for F&G
14. Page 34 Section 6.3.9 at each stage based on 3D model
Mapping Study (Refer Section 6.4)

Noted. The clause has been deleted in Rev.


15. Page 34 Section 6.4.1 PROJECT specifications A2 because of other COMPANY comments.

Noted and incorporated (Refer section


16. Page 36 Section 6.4.1.4 NFPA 72 6.5.1.4)

Reinstate FEED statement: Flammable and Toxic


Noted and incorporated.
17. Page 36 Section 6.4.2 gas detectors shall be provided in HVAC air intake
of Sub-station, LER and the air locks.

Type to be clarified and updated based on F&G Noted and incorporated.


18. Page 37 Section 6.4.2.1
upgrade project meeting COMPANY requirements

To be reviewed and updated in line with F&G Noted and incorporated.


19. Page 38 Section 6.5.1
upgrade project LP philosophy
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 6 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Alarms to be defined as High and High High


(Confirmed detection) instead of Low and High Noted and incorporated.
20. Page 38 Section 6.5.2
alarms. Review to consider based on the F&G
upgrade project philosophy
The required panels etc. are updated in line
21. Page 38 Section 6.6 What about ZCC? with P8363 and Fire and Gas Design Review.

Noted and incorporated.


22. Page 40 Section 6.7.1 What about fire station? [Typical comment]

There is no F&G Matrix Panel in Fire Station.


What about ZCC and Fire station? [Typical The effects at existing matrix panel are
23. Page 40 Section 6.7.1
comment] already included in the philosophy.

In case of 2ooN in battery room, clarify the Noted and incorporated.


24. Page 41 Section 6.7.4
actions?

There is no ESD Shutdown Level for smoke


25. Page 41 Section 6.7.4 Identify the ESD shutdown level detection.

There is no ESD Shutdown Level for gas


26. Page 42 Section 6.7.7 Identify the ESD shutdown level detection at HVAC Air Intake.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 7 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

As per HVAC team 6 – 8 ACH (Air Changes


per Hour) considered for designing Battery
Room Exhaust Fan capacity and which is
sufficient to exhaust all the Air inside the
Room. In case of failure of working fan, the
Standby exhaust Fan shall start
Review to Start standby exhaust fans upon H2 automatically with the help of DPS inside the
27. Page 43 Section 6.7.8
detection
Exhaust Air Duct.

Refer SS-116 HVACP Control Description


and Sequence of Operation (Doc No-A1-
SS116-H-0004_001) for detail of HVAC
cause and effect

Alarm only for MACP actuation. Document is


updated accordingly with detailed effects for
28. Page 44 Section 6.8 Clarify and update whether alarm or any action?
MACP Activation.

The cause for stop of exhaust fans in case of


confirmed smoke detection inside battery
room before activation of inergen is updated
29. Page 45 Section 6.12 indicate the cause of this signal in the document. The commented section is
not available and is already deleted based on
other COMPANY comments.

The comment is not clear. Fire Proofing is in


30. Page 59 Section 8.4 Specify the temperature rating also terms of duration and type of fire.

Rev. A1 Comments received vide Transmittal No. ZRIP-NT-TR-00188-P7564


COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 8 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Introduction of the Project shall be standard for


the Project and that shall be approved by Project.
1. Page 10 Section 1 Updated as received from COMPANY.
This shall be used as a template for all
Deliverables

2. Page 11 Section 2.1 Emergency System Noted and reinstated as per FEED.

Definitions are deleted as per COMPANY /


Project titles and other definitions shall be Project Team instructions. These definitions
3. Page 13 Section 3.1
updated as per approved Contract documents. are already covered as part of new Project
Introduction received from COMPANY.

All equipment tags shall have 4 digits as


4. Page 13 Section 3.1, Noted.
instructed by DOP

Ambient air quality and noise level standards or


5. Page 17 Section 4.2 Noted and reinstated as per FEED.
laws numbers with year to be mentioned.

All UAE Laws and Regulations applicable shall be


6. Page 17 Section 4.2 listed. Why some laws have been deleted from Noted and reinstated as per FEED.
FEED

Section 4.3 from FEED has been deleted.


7. Page 17 Section 4.2 Reinstate and List all International Conventions Noted and reinstated as per FEED.
and Protocol

Noted and updated.


All ADNOC COPs and TGNs requirement shall be
8. Page 18 Section 4.3
implemented and complied for the Project
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 9 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Check and verify the Doc nos. e.g. HAZOP Noted and updated.
9. Page 19 Section 4.4 Procedure

Refer all the Relevant Project design documents


like relevant disciplines design basis (such as Noted and updated.
10. Page 21 Section 4.6
Process, Piping, Electrical, Instrument etc.)

a) To assist in determining the appropriate


location of combustion air inlets and
Page No. exhausts for fired equipment, engines and
11. Section 5.1
22 turbines; Noted and reinstated as per FEED.
b) To define the extent of hazardous area
from cold vents; and
Please refer the relevant section of the applicable
Noted and reinstated as per FEED.
12. Page 23 Section 5.2 Code

Many sections have been deleted from FEED.


13. Page 24 Section 5.3 Please reinstate all relevant clauses. Noted and reinstated as per FEED.

Check requirements for Battery Room as Noted and reinstated as per FEED in section
14. Page 25 Section 5.4.1 Hydrogen is expected. 5.4.4.

Hazardous Area Report and Schedule shall be


prepared and it shall be consistent with the
Hazardous Area Classification Update Project
15. Page 25 Section 5.4.1 P8658. Hazardous Area Classification Drawings Noted and reinstated as per FEED.
prepared for this project shall be made consistent
with the guidelines developed under P8658.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 10 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Refer relevant section and clause of the Code Noted and reinstated as per FEED.
16. Page 25 Section 5.4.1

Add a section on HAC requirements within Non-


17. Page 25 Section 5.4.2 Process Areas Noted and reinstated as per FEED.

This is in line with FEED HSE Philosophy.

Furthermore, during site visit, it has been

18. Page 26 Section 5.4.3


Delete “a wall mounted portable” observed that similar type of Portable Eye
wash unit is available in New Substation
installed at Zirku Island as part of Power
Upgrade Project.

Page 26
19. Section 5.4.4 Please refer the Code Noted and reinstated as per FEED.

Buildings located in a non-hazardous (safe) area


shall be pressurized to 25 Pa (0.1 inch water Noted and updated (Indicated “Pressurised to
20. Page 27 Section 5.4.4
column) if deemed necessary by QRA and FERA. 35pa” in line with HSE Philosophy.

Addressable local and remote fire and gas alarm; Noted and reinstated as per FEED.
21. Page 28 Section 6.2

Zoning ppm levels to be specified. Noted and reinstated as per FEED.


22. Page 29 Section 6.3.3.1

Page 31
23. Section 6.3.6.1 H2S toxic value to be specified (in terms of ppm). Noted and reinstated as per FEED.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 11 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

All Tables shall be Titled & numbered in the


Page No.
24. Section 6.3.6.1 document Noted and incorporated.
32

Noted and updated document reference


number of P8363 Loss Prevention
Philosophy.
The referred document in FEED was deleted
from MDR of P8363 Project and all the
Page 33 Please check and confirm COMPANY’s Fire & information is now available in Loss
25. Section 6.3.6.3
Gas Philosophy (Fire & Gas System Upgrade at Prevention Philosophy, Doc. No. P8363-PB-
Zirku) Document # P8363-TS-400-N-0011) 400-O-0004

Technical HSE Documents of P8363 are


requested vide CCEL-ZAD-TQ-0047 Rev
A3.
Add the basis / philosophy of preparing F & G
Page 34
26. Section 6.3.7 Layouts (Location of Hydrocarbon, Fire, Gas, Noted and reinstated as per FEED.
Toxic etc.) preparation also.
The most common areas suitable for smoke
Page 35 detection are the Control Rooms, Operator
27. Section 6.4.1 Noted and reinstated as per FEED.
Shelter, Local Equipment Room (LER) and Sub-
stations.

Reinstate the Clauses from FEED Philosophy Noted and reinstated as per FEED.
28. Page 35 Section 6.4.1

Fusible plugs shall be used along with flame


Page 35 detection for deluge activation and should be Noted and reinstated as per FEED.
29. Section 6.4.1.3
similar to the type which is currently being used in
Zirku facility.
Changes from the FEED shall be discussed and
agreed. if no agreement please reinstate the Noted and reinstated as per FEED.
30. Page 36 Section 6.4.1.4
FEED requirements
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 12 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Section 6.5.1 Shall be inline with the Existing Plant Philosophy


31. Page 37 and F & G philosophy of F & G Upgrade Project Noted.

Page 37
32. Section 6.5.1 Why Change from FEED Noted and reinstated as per FEED.

Shall be inline with the Existing Plant Philosophy


33. Page 38 Section 6.5.2 and F & G philosophy of F & G Upgrade Project Noted.

All F & G display, Control and Monitoring shall be


34. Page 38 Section 6.6.1 in line with Instrumentation philosophy Noted

Page 40 The Voting Logic and actions shall be in line with


35. Section 6.7 Noted
Existing and F & G Upgrade Project Philosophy

Changes from the FEED shall be discussed and


Page 40
36. Section 6.7.1 agreed. if no agreement please reinstate the Noted and reinstated as per FEED.
FEED requirements

Page 44 Shall be in-line with Existing and F & G Upgrade


37. Section 6.7.10 Noted.
Project Philosophy

The basis shall be in line with other philosophy


Page 48
38. Section 7.2.1 and FEED Documents such as FW Demand Noted and updated.
report etc.

Page 49
39. Section 7.2.3 Please Check and Confirm Noted and Confirm.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 13 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Page 49 Piping Material shall be confirmed with Piping and Noted.


40. Section 7.2.3
metallurgy

This shall be confirmed and verified as per SOW


Page 49
41. Section 7.2.4 and Site Visit. The adequacy of Fire Protection Noted and updated.
facilities available shall be demonstrated

Page 50
42. Section 7.3.1 subject to approval by Company Noted.

Page 50
43. Section 7.3.1 Are these located in Offsite? Please confirm Noted and updated.

Any change from the FEED Philosophy and other


Page 51 FEED HSE documents shall be agreed with Noted and deleted sections from FEED are
44. Section 7.3.2
Company on case by case basis and shall be reinstated.
agreed.

Page 54
45. Section 7.3.4 Why there is change from FEED Noted and reinstated as per FEED.

Page 55 Add section on Firewater Application Rates (Refer Noted and reinstated as per FEED (Refer
46. Section 7.4.1
FEED) section 7.2.2).

Page 59 Passive fire proofing height shall be 9.0 m instead


47. Section 8.4 Noted and updated.
of 7.5 m as per FEED drawing A0-400-O-0001.

Page 59
48. Section 8.4 30 Mins as per FEED Noted.
COMMENTS RESOLUTION SHEET

DOC NO: P7564-GD-400-O-0001 DOCUMENT TITLE: LOSS PREVENTION PHILOSOPHY

Ref TRL No: PE-ZR-DAS-NT-TR-02209 DATE: 19.07.2018 Page: 14 of 14

NO REF SECTION ZADCO COMMENTS CTR RESPONSE ZADCO REVIEW

Page 60 This shall be captured in details on PFP Schedule


49. Section 8.4 Noted and updated.
and layouts

a) Blast over-pressure protection for


Operator Cabin shall be included.
Page 60
50. Section 9.0 b) Building structural elements to withstand Noted and incorporated.
blast over-pressure shall be designed as
Reinforced Concrete.
The Plant Communication System (General,
Page 61
51. Section 9.0 Emergency, PABX, PA/GA shall be added in the Noted and reinstated as per FEED.
Philosophy.)
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 1 of 67

CODE-2

ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)


ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK

COMPANY PROJECT NO. P-7564


CONTRACT NO. CTBRFPZR140310

LOSS PREVENTION PHILOSOPHY

COMPANY DOCUMENT NO.: P7564-GD-400-O-0001

A4 16/09/2019 RE-ISSUED FOR APPROVAL VS MJI WM / TI / IN

A3 26/11/2018 RE-ISSUED FOR APPROVAL VS MJI WM / TI / IN

A2 27/06/2018 ISSUED FOR APPROVAL VS MJI WM / TI / IN

A1 17/04/2018 ISSUED FOR REVIEW VS MJI WM / TI / IN

Rev.
DATE DESCRIPTION
No. PREPARED BY REVIEWED BY APPROVED BY
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 2 of 67

REVISION CONTROL SHEET

Rev Rev. Revision


Description
No. Date Section

A1 17/04/2018 First Issue Issued for Review

As per attached
A2 27/06/2018 Issued for Approval
CRS

As per attached
A3 26/11/2018 Re-Issued for Approval
CRS

As per attached
A4 16/09/2019 Re-Issued for Approval
CRS

Note:

For this Project, new drawings / documents, the “Project revision”, shall start with an
alphanumeric code “A1”. The first letter “A” representing the major revision, denotes that the
drawing/document is at the First stage as defined by the project and the second letter “1”
denotes the minor revision.

1- Section 4.4, remove duplicate rows.


2- Section 4.7, add reference of ESD Philosophy
3- Section 6.3.3.2 Definition of Zone Grades for flammable gas, toxic gas and fire hazards shall be added
4- Contractor to ensure that all changes w.r.t. Vendor inputs are reflected in the Philosophy
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 3 of 67

This document is identical to FEED Loss Prevention Philosophy Document No. P7564-GD-400-O-0001 Rev B2
except as below:

Sr. No. Existing Document Reference Change / Revision

Section 1-Project Description Section 1-Title is changed to “Introduction”


1. Project Description is updated for CONTRACTOR’s scope for 5th Oil
Train

Section 2.1- Scope Section 2.1- Scope section is updated for CONTRACTOR’s scope for
2.
5th Oil Train

Section 3-Acronyms and Definition Section 3 – Title is changed to “Abbreviation and Terminology”
3. Abbreviation & Terminology is updated for CONTRACTOR’s scope
for 5th Oil Train PROJECT and shifted to Table format

Section 4.5-ZADCO Standards and Section 4.5-title changed as “ Company Procedure and Regulations”
4. Regulations

Section 4.7-Other ZADCO Section 4.7- title changed as “Other Project Documents”
5. Documents

Section 6.0 Fire and Gas Detection Section 6.0 Fire and Gas Detection updated to remove reference to
CCR.
6.
The section is aligned with philosophy of P8363, Fire and Gas
Upgrade Project.

Section 7.1-General Section 7.1- General is updated to indicate specific information


7. related to PROJECT scope like revised monitor capacity, FERA
outcomes etc.

Section 7.2-Fire Water Demand Section 7.2- title changed as “Fire Protection System Design” under
which subtitles are made to provide systematic flow of information.
The subtitles are FW demand, FW Application Rates, Fire water
8. Mains and Fire Protection for BOP Area.

Section 7.2.1-Fire Water Demand is updated to reflect applicable


clauses from latest standards.

Section 7.3-Fire Protection for Section 7.5-Fire Protection for Building updated to indicate
9.
buildings CONTRACTOR’s scope for PROJECT.

Section 7.4-Fire water Mains Section 7.2.3-Fire water Mains is updated for CONTRACTOR’s scope
10.
for PROJECT and to reflect material for FW piping.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 4 of 67

Sr. No. Existing Document Reference Change / Revision

Section 7.5-Fixed, Portable and Section 7.3-Title changed as “Fixed Fire Protection Equipment” under
11. Mobile Fire Equipment which subtitles Hydrant, Deluge System, Monitors, Fire Hose
Cabinets, Hose Reels are indicated

Section 7.6-Hydrant Section 7.3.1-Hydrant is updated slightly


12.

Section 7.7-Deluge System Section 7.3.2-Deluge System is updated to include Table of Deluge
13.
systems required as part of PROJECT scope.

Section 7.8-Monitors Section 7.3.3-Monitors is updated to reflect revised capacity of


14.
manual and elevated monitors

Section 7.9-Fire Hose Cabinets Section 7.3.4-Fire Hose Cabinets is updated slightly
15.

Section 7.10-Hose Reels Section 7.3.5-Hose Reel is updated slightly


16.

Section 7.11-Fire water Application Section 7.2.2-Water application Rates is updated to reflect applicable
17.
Rate rates to CONTRACTOR’s scope for PROJECT

Section 7.12-Clean Agent Fire Section 7.5.1- Updated Title as “Clean Agent Fire Extinguishing
Extinguishing (Gaseous) Systems System”
18.
This section updated to include PROJECT specific Building / Rooms
requiring Clean Agent Systems

New Section 7.4-Portable Fire Protection Equipment added to


19. describe Portable Fire Extinguishers and Foam units as part of
PROJECT scope

Section 10-Communication System Section 10-Communication System updated slightly as per


20. Interdisciplinary comments and Telecommunication Design Basis
(Doc No- P7564-BD-540-T-0001)
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 5 of 67

TABLE OF CONTENTS

1 INTRODUCTION .............................................................................................................8
2 GENERAL .......................................................................................................................9
2.1 SCOPE .................................................................................................................... 9
2.2 PURPOSE AND OBJECTIVE ................................................................................10
3 ABBREVIATION AND TERMINOLOGY .......................................................................11
3.1 ABBREVIATION ....................................................................................................11
3.2 TERMINOLOGY .....................................................................................................15
4 REFERENCE DOCUMENTS .........................................................................................15
4.1 GENERAL ..............................................................................................................15
4.2 UAE LAWS AND REGULATIONS .........................................................................16
4.3 INTERNATIONAL CONVENTIONS & PROTOCOL ...............................................16
4.4 ADNOC CODE OF PRACTICES ............................................................................17
4.5 COMPANY PROCEDURES AND REGULATIONS ................................................20
4.6 INTERNATIONAL CODES AND STANDARDS .....................................................21
4.7 OTHER PROJECT DOCUMENTS ..........................................................................23
4.8 ORDER OF PRECEDENCE ...................................................................................24
5 HAZARDOUS AREA CLASSIFICATION ......................................................................24
5.1 GENERAL ..............................................................................................................24
5.2 CLASSIFICATION OF HAZARDOUS AREAS .......................................................25
5.3 VENTILATION AND AIR INTAKE SYSTEMS ........................................................26
5.4 EQUIPMENT SELECTION FOR HAZARDOUS AREAS ........................................27
5.4.1 General.....................................................................................................27
5.4.2 Outdoor Non-Process Areas ..................................................................27
5.4.3 Process Areas .........................................................................................28
5.4.4 Battery Rooms.........................................................................................28
5.4.5 Indoor Installations .................................................................................29
6 FIRE AND GAS DETECTION .......................................................................................29
6.1 SCOPE AND METHODOLOGY OF F&G PHILOSOPHY .......................................29
6.1.1 Scope .......................................................................................................29
6.1.2 Methodology............................................................................................29
6.2 ROLE OF FIRE & GAS SYSTEM ...........................................................................30
6.3 FIRE AND GAS STUDY .........................................................................................31
6.3.1 General.....................................................................................................31
6.3.2 Definition and Identification of F&G Zones ...........................................32
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 6 of 67

6.3.3 Definition and Zone Categories and Zone Grades ................................32


6.3.4 Identification of F&G Hazard Scenarios ................................................33
6.3.5 Assigning Zone Category for Identified F&G Zones .............................34
6.3.6 Defining Performance Requirements for F&G Detectors .....................34
6.4 FIRE AND GAS MODELLING ................................................................................36
6.5 SELECTION OF TYPE OF F&G DETECTORS ......................................................36
6.5.1 Fire and Smoke Detection ......................................................................36
6.5.2 Gas Detection ..........................................................................................38
6.6 ALARM SYSTEM ...................................................................................................39
6.6.1 Type of Alarm ..........................................................................................39
6.6.2 Alarm Setting ...........................................................................................39
6.7 FIRE AND GAS CONTROL MONITORING ............................................................40
6.7.1 F&G Operator Station (HMI)....................................................................40
6.7.2 F&G Auxiliary Console ...........................................................................40
6.7.3 F&G Display.............................................................................................41
6.7.4 F&G Matrix Panel ....................................................................................41
6.8 ALARM, VOTING LOGIC AND ACTION ................................................................42
6.8.1 Fire Detection ..........................................................................................42
6.8.2 Flammable Gas Detection.......................................................................45
6.8.3 Toxic Gas Detection ................................................................................48
6.9 FIRE AND GAS MAPPING STUDY........................................................................49
6.10 LOCATION AND INSTALLATION REQUIREMENTS OF FIRE AND GAS
DETECTORS ................................................................................................................49
6.11 MANUAL ALARM CALL POINT........................................................................49
6.12 INTEGRATION WITH EXISTING F&G SYSTEM ...............................................50
6.13 INTERFACE WITH NEW ESD SYSTEM ............................................................50
7 ACTIVE FIRE PROTECTION ........................................................................................51
7.1 GENERAL ..............................................................................................................51
7.2 FIRE PROTECTION SYSTEM DESIGN .................................................................52
7.2.1 Firewater Demand ...................................................................................52
7.2.2 Fire Water Application Rates ..................................................................54
7.2.3 Firewater Mains .......................................................................................55
7.2.4 Existing Fire Protection in BOP Area.....................................................55
7.3 FIXED FIRE PROTECTION EQUIPMENT ..............................................................56
7.3.1 Hydrants ..................................................................................................56
7.3.2 Deluge System ........................................................................................56
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 7 of 67

7.3.3 Monitors ...................................................................................................59


7.3.4 Fire Hose Cabinets ..................................................................................59
7.3.5 Hose Reels...............................................................................................60
7.4 PORTABLE FIRE PROTECTION EQUIPMENT .....................................................61
7.4.1 Portable Fire Extinguishers ....................................................................61
7.4.2 Foam Units ..............................................................................................61
7.5 FIRE PROTECTION FOR BUILDINGS ..................................................................61
7.5.1 Clean Agent Fire Extinguishing System ................................................62
8 PASSIVE FIRE PROTECTION ......................................................................................63
8.1 GENERAL PRINCIPLES ........................................................................................63
8.2 FIRE PROOFING ...................................................................................................63
8.3 EXPOSURE PROTECTION OF BUILDINGS .........................................................64
8.4 EXTENT AND DURATION OF FIRE PROOFING...................................................64
9 BLAST OVERPRESSURE PROTECTION ....................................................................65
10 EMERGENCY COMMUNICATION SYSTEM ................................................................66
10.1 GENERAL .........................................................................................................66
10.2 EMERGENCY TELEPHONE SYSTEM ..............................................................66
10.3 PABX and Telephone System..........................................................................66
10.4 PUBLIC ADDRESS AND GENERAL ALARM SYSTEM ...................................67
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 8 of 67

1 INTRODUCTION

COMPANY operates three oil fields in the Arabian Gulf and treats the oil recovered from the fields at
their processing facilities on Zirkud Island. The processing facilities receive two types of crude: UZ
Blend crude and Satah crude; UZ blend is sweet while Satah crude is sour. COMPANY processes
the two crudes separately in dedicated facilities on the island. The reservoir fluid produced at Upper
Zakum and Umm Al Dalakh Fields (UZ Blend), after partial degassing and dewatering, flow to Zirku
island via a 42” Main Oil Line (MOL), whereas the reservoir fluid produced at Satah Field is
transported to Zirku Island via a separate 14” MOL. Common storage and export facilities receive
both the processed crudes.

COMPANY has embarked on an Upper Zakum Field Development (UZFD) Program which is aimed
at ultimately achieving a target oil production plateau rate of 1,000 MBD from the UZ field and to
sustain this production target for at least 25 years. To achieve the production target several projects,
studies and operating initiatives related to upstream facilities were carried out and in order to
accommodate this production build-up. COMPANY will develop facilities required for 1,000 MBD
production in the following stages:

1) 750 MBD (UZ-750): Includes the installation of the necessary facilities at Zirku Island required
to accommodate an upstream production of 750 MBD, along with the associated utilities and
upgrades including limited pre-investment for the facilities required for an upstream production of
1,000 MBD.

2) 1,000 MBD (UZ-1000): Includes the installation of the necessary facilities at Zirku Island required
to accommodate an upstream production of 1,000 MBD.

COMPANY awarded the PROJECT to the consortium between Chiyoda CCC Engineering (Pte) Ltd.
(CCEL) and Consolidated Contracting Engineering & Procurement S.A.L. (Offshore) (CCEP) (herein
after referred to as "CONTRACTOR") under Contract Number CTBRFPZR140310 on 17th January
2018 to carryout Engineering, Procurement, Construction and Commissioning (EPC) work.

In order to accommodate the increased upstream production of UZ-750, a 5th Oil Processing Train
will be installed and operated along with the existing four Oil Processing Trains allowing one Oil
Processing Train to be retained as a spare, thus ensuring reliability, availability and providing
excellent maintenance capabilities. The four existing Oil Processing Trains have a processing
capacity of 210 MSTBOPD each whereas the new 5th Oil Processing train will have a capacity of
260 MSTBOPD. The combination of trains in operation will be dictated by the production quota for
the period, the scheduled maintenance, and unscheduled events. In the event of unscheduled
shutdown of one of the trains the spare train can be brought on line to compensate for the loss of
processing capacity.

The new Oil Processing Trains will operate in parallel (i.e., integrated) with the existing facilities, and
as such the new facilities will be connected to the Common Facilities and Utilities of the existing
facilities. These tie-ins shall be done in such a manner as to accommodate all future envisaged
expansions so as to avoid future disruption to the existing facilities.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 9 of 67

In order to accommodate the new Oil Processing Trains, various upgrades and changes to the
Common Facilities and to the Utilities are also required, these changes are sized for a 1,000 MBD
development case , and shall also consider an overall 10% margin on oil production, ensuring future
production capacity increases can be accommodated, when required. The new Oil Processing Trains
will be supported by a new Substation SS-116 and a new LER (Local Equipment room). New LER
will be connected to existing Zirku Control Centre (ZCC) with necessary upgrades for the operation
and control of the new facilities

As part of the PROJECT, CONTRACTOR shall perform all work required for the installation to achieve
an oil processing capacity in the Upper Zakum Facilities on Zirku Island of 750 MBD. In summary,
the key objectives of this PROJECT are as listed here-under:

 Installation of a new Oil Processing Train (5th Oil Processing Train) that will enable COMPANY
to sustain/accommodate an oil processing capacity of 750 MBD.

 Upgrade the Utilities and Balance of Plant portion of the Existing Facilities to accommodate an
oil processing capacity of 1,000 MBD.

 Upgrade the existing Zirku Control Centre (ZCC) to manage operation of all the new facilities.

 Incorporate limited pre-investment for future expansion (i.e., 6th Oil Processing Train and 5th
Gas Compressor).

 Implementation of modularization strategy.

The PROJECT scope of work covers all aspects of Engineering, Procurement, Fabrication,
Transportation, Construction, Demolition, Pre-Commissioning, Commissioning, Handover,
Assistance for Start-Up and completion of Performance Test required for the completion of the
installation.

2 GENERAL

2.1 SCOPE

This Loss Prevention (LP) Philosophy is intended to be used for the Detailed Engineering phase of
the Zirku Facilities Capacity Enhancement Project (hereinafter referred as PROJECT).

The principles defined in this document will provide guidance to the detailed engineering design for
the PROJECT.

This Loss Prevention Philosophy focuses upon the requirements for:

 Active Fire Protection

 Passive Fire Protection

 Explosion Protection
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 10 of 67

 Fire & Gas Detection

 Hazardous Area Classification

 Emergency Communication System

This philosophy complements the Project HSE Philosophy (Document No: P7564-GD-400-N-0007).

The scope of this document excludes construction activities.

2.2 PURPOSE AND OBJECTIVE

The purpose of the LP Philosophy is to promote a safe design of the facilities and to minimize the
possibility of injury to personnel and damage to asset and environment. This will be achieved by
reducing the possibility of an event occurring and by providing protective measures to control or
mitigate the consequences, should an unplanned or undesired event occur.

The LP Philosophy aims to highlight how LP aspects are accounted for in the design of the facilities
taking into account the risks inherent to the PROJECT and the safety level required by the operator.

The LP Philosophy defines the safety systems that are needed to protect personnel, environment
and assets from potential harm.

The primary objective of this LP Philosophy is to ensure that all design decisions are based on sound
safety and environmental protection principles and that LP rationale for decisions and their
alternatives are demonstrated. The design decisions shall be based on the following principles:

 Identify measures to remove or reduce exposure to potential hazards;

 Minimise the potential for hazardous events to occur (reduce the frequency);

 Identify measures for detection, containment and mitigation measures for fire, explosion and loss
of containment;

 Minimise the severity of the hazardous event and prevent escalation;

 Define the response required for a hazardous event, e.g. deluge activation / depressurization;
and

 Protection of the environment by minimizing accidental releases and spills, and providing a
means to rapidly detect and isolate the source of any loss of containment.

Achieving these objectives will ensure a safe design and will provide a safe working environment for
site personnel. It will assure to stakeholders that the risk of exposure to a hazardous event is being
managed.

The safety objectives are achieved through the following approach:


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 11 of 67

 Identification of major hazardous events;

 Evaluation of the consequences;

 Definition of primary protection systems;

 Definition of secondary protection systems; and

 Definition of emergency support systems.

Primary protection systems include monitoring and detection (e.g., process control variable limits on
distributed control systems), notification (e.g., audible and visual alarms) and process control systems
with specific action to prevent hazardous events developing from the process (e.g., control loops that
activate a process shut down to manage process deviations).

Secondary protection systems are additional controls that are independent from primary protection
systems e.g., Pressure Relief Valves (PRVs) on high pressure equipment to protect against
overpressure and catastrophic vessel failure.

Emergency support systems include but are not limited to fire and gas detection, emergency
shutdown and blowdown and active fire protection (fire water and foam systems etc.) and passive
fire protection (Fire Proofing).

3 ABBREVIATION AND TERMINOLOGY

3.1 ABBREVIATION

The following abbreviations have been used in this document:

Acronyms Description

ADNOC Abu Dhabi National Oil Company

AG Above Ground

AIT Auto Ignition Temperature

API American Petroleum Institute

BD Blow Down

BEDD Basic Engineering Design Data


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 12 of 67

Acronyms Description

BOP Balance of Plant

CCEP Consolidated Contracting, Engineering and Procurement S.S.L Offshore

CCEL Chiyoda CCC Engineering Ltd

CoP Code of Practice

CFD Computational Fluid Dynamics

DCS Distributed Control System

EPC Engineering, Procurement and Construction

ESD Emergency Shutdown

ETS Emergency Telephone System

FEED Front End Engineering Design

FERA Fire & Explosion Risk Assessment

F&G Fire and Gas

FGS Fire and Gas Detection system

FW Fire water

GPM US Gallons per Minute

HAC Hazard Area Classification

HC Hydrocarbon

HMI Human Machine Interface


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 13 of 67

Acronyms Description

HSE Health, Safety and Environment

HSSD High Sensitivity Smoke Detection System

HVAC Heating, Ventilation and Air Conditioning

HO Head Office

HVO High Value Office

IDLH Immediately Dangerous to Life and Health

IR Infra-Red

LEL Lower Explosive Limit (also known as Lower Flammability Limit)

LER Local equipment Room

LP Loss Prevention

MACP Manual Alarm Call Points

MOL Main Oil Line

MOS Metal Oxide Semiconductor

MSTBOPD Thousand Stock Tank Barrel Oil per Day

NFPA National Fire Protection Association

OEL Occupational Exposure Limit

PA Public Address

PABX Private Automatic Branch Exchange


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 14 of 67

Acronyms Description

PAGA Public Address and General Alarm

PFP Passive Fire Protection

PIV Post Indicator Valve

PRV Pressure Relief Valve

QRA Quantitative Risk Assessment

RHO Radiant Heat Output

SOV Shut Off Valve

SS Substation

UPS Uninterrupted Power Supply

UG Underground

UV Ultra Violet

VESDA Very Early Smoke Detection Apparatus

ZADCO Zakum Development Company (Known as ADNOC Offshore)

ZCC Zirku Control Center

ZCR Zirku Control Room

ZER Zirku Equipment Room


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 15 of 67

3.2 TERMINOLOGY

 Emergency System - A system that controls or mitigates the consequences of accidental events.
Examples include ESD, fire protection and communication systems, etc.

 Hazard - A source or a situation with a potential to cause human injury or illness, damage to
property, material and/or the environment, production losses or any combination of these.

 Mitigation - The reduction of risk to people, equipment, material, property, process and the
environment.

 Prevention - Removal of the means of an accidental event occurring, either by design or


operational control.

 Risk - The chance of an undesired event happening that negatively impacts people, equipment,
material, property, process and/or environment. Determining the degree of risk is based on a
combination of consequence severity and probability that the event will occur.

 Safety - Safety refers to the control of accidental loss.

 Shall/will/must - “shall” or “must” or “will” represent non -negotiable terms and are used when
personnel are obligated to fulfill certain requirements.

 Should - “should” is a recommendation and describes good engineering and industry practice.

4 REFERENCE DOCUMENTS

4.1 GENERAL

The codes and standards listed below are appropriate for the application of this philosophy. These
documents (Codes & Standards) in their entirety may not be applicable to the PROJECT; hence only
the relevant sections of these documents shall be used. The list is not intended to be all-inclusive. In
all cases, the latest edition of the document in effect at the time the PROJECT contract is awarded
shall be used as guidance. The PROJECT will use international codes and standards and best
industry/engineering practices where ADNOC or COMPANY documents do not provide guidance on
specific issues.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 16 of 67

4.2 UAE LAWS AND REGULATIONS

Federal Law No. 24 of March 1999, for the Protection and Development of the Environment and
as amended, and its Executive Order issued by council of Ministers Decree No. (37) of 2001

Federal Law No. 1 of 2002, regarding Organization and Monitoring the Use of Radiation and
Protection;

Federal Law No. 8 (1980) The Labour Law (as amended 1986)

Ministerial Order 32 of 1982; Determination of Preventative Methods and Measures for the
Protection of Labour from Risks at Work.

Labour Law of 1982;

Regulations/Executive Orders made under the Federal Environment Law.

Regulation for Assessment of Environmental Effects of Installations 2001.

Regulation for handling Hazardous Materials, Hazardous Wastes and Medical Wastes 2001.

National Ambient Air Quality Standards (Draft approved by FEA, currently going through legislative
approval process - May 2003)

Abu Dhabi Law No. 16 (2005) concerning the Re-organization of the Environment Agency - Abu
Dhabi. (Replaced Law No. (4) Of 1996, as amended.

Abu Dhabi Law No. 21 (2005) for Waste Management in Abu Dhabi Emirate.

4.3 INTERNATIONAL CONVENTIONS & PROTOCOL

1979 United Nation Economic Commission for Europe (UNECE) Convention on long-range trans
boundary air pollution (LRTAP)

1991 Geneva Protocol concerning the control of emissions of VOCs or their trans boundary fluxes

1987 Montreal Protocol on Substances that Deplete the Ozone Layer and its amendments
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 17 of 67

1997 Kyoto Protocol

1994 Energy Charter Protocol on energy efficiency and related environmental aspects

The specific U.A.E. position in relation to certain of the conventions and protocols has still to be
ascertained

4.4 ADNOC CODE OF PRACTICES

All Project activities shall fully comply with and shall ensure implementation of all applicable ADNOC
COPs and TGNs. The list of ADNOC COPs and TGNs is as follows:

Doc.
Doc. No. Document Title Version
Type

ADNOC-COPV1-02 CoP HSEIA Requirements April, 2014 Version 3

ADNOC-COPV1-02 CoP HSEIA Requirements April, 2014 Version 3

Determining Reportability of
ADNOC-COPV1-03 CoP Occupational Injuries and April, 2014 Version 2
Illness
Management of Contractor
ADNOC-COPV1-04 CoP April, 2014 Version 2
HSE
HSE Definitions &
ADNOC-COPV1-05 CoP April, 2014 Version 2
Abbreviations
Self-regulation, Governance
ADNOC-COPV1-06 CoP & Assurance-Guidelines for April, 2014 Version 1
ADNOC Senior Managers
Health Safety and
ADNOC-COPV1-07 CoP Environment (HSE) April, 2014 Version 7
Performance Letter
Reporting of Serious HSE
ADNOC-COPV1-08 CoP April, 2014 Version 2
Incidents (To ADNOC)
ADNOC HSE Management
ADNOC-COPV1-09 CoP April, 2014 Version 2
System
Food & Water Safety &
ADNOC-COPV1-10 CoP April, 2014 Version 2
Welfare
Audit of HSE Management
ADNOC-COPV1-11 CoP April, 2014 Version 2
System
Reporting of Process
ADNOC-COPV1-12 CoP April, 2014 Version 1
Release Events
Preparation of Project HSE
ADNOC-COPV1-13 CoP April, 2014 Version 2
Plans
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 18 of 67

Doc.
Doc. No. Document Title Version
Type

ADNOC-COPV1-14 CoP Training & Competence April, 2014 Version 1

ADNOC Annual
ADNOC-COPV1-15 CoP April, 2014 Version 1
Sustainability Reporting
Environmental Impact
ADNOC-COPV2-01 CoP April, 2014 Version 2
Assessment
Pollution Prevention and
ADNOC-COPV2-02 CoP April, 2014 Version 2
Control

ADNOC-COPV2-03 CoP Energy Management System April, 2014 Version 1

Environmental Management
ADNOC-COPV2-04 TGN April, 2014 Version 2
System

ADNOC-COPV2-05 CoP Waste Management April, 2014 Version 2

Environment Performance
ADNOC-COPV2-06 TGN April, 2014 Version 2
Monitoring
Environmental Risk
ADNOC-COPV2-07 TGN April, 2014 Version 2
Assessment

ADNOC-COPV2-08 CoP Use of Oil Spill Dispersant April, 2014 Version 2

Occupational Health Risk


ADNOC-COPV3-01 CoP April, 2014 Version 2
Management

ADNOC-COPV3-02 CoP Physical Agents April, 2014 Version 2

ADNOC-COPV3-03 CoP Chemical Agents April, 2014 Version 1

ADNOC-COPV3-04 CoP Biological Agents April, 2014 Verion 1

ADNOC-COPV3-05 TGN Ergonomics April, 2014 Version 1

Working with Asbestos


ADNOC-COPV3-06 CoP April, 2014 Version 2
containing materials (ACM)
Indoor Air Quality& Indoor
ADNOC-COPV3-07 TGN April, 2014 Version 1
Environment
Occupation Health
ADNOC-COPV3-08 TGN Monitoring and Health April, 2014 Version 1
Surveillance
Framework for Occupational
ADNOC-COPV4-01 CoP April, 2014 Version 2
Safety Risk Management
Work Equipment Risk
ADNOC-COPV4-02 CoP April, 2014 Version 2
Assessment and Control
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 19 of 67

Doc.
Doc. No. Document Title Version
Type

ADNOC-COPV4-03 CoP Fire Risk Assessment April, 2014 Version 2

ADNOC-COPV4-04 CoP PPE April, 2014 Version 1

ADNOC-COPV4-05 CoP Non-Routing Operations April, 2014 Version 1

Essential Features of Road


ADNOC-COPV4-06 CoP Transport Operations, Risk April, 2014 Version 1
Assessment and Control
Essential Features of Air
ADNOC-COPV4-07 CoP Transport Operations, Risk April, 2014 Version 1
Assessment and Control
Essential Features of Marine
ADNOC-COPV4-08 CoP Transport Operations, Risk April, 2014 Version 1
Assessment and Control
Diving Operations-Risk
ADNOC-COPV4-09 CoP April, 2014 Version 2
Assessment and Control
Management of Hydrogen
ADNOC-COPV4-10 CoP April, 2014 Version 2
Sulfide

ADNOC-COPV4-11 CoP Road Safety April, 2014 Version 1

Lifesaving Appliances at
ADNOC-COPV4-12 CoP April, 2014 Version 2
Offshore Installation
Provision of Fire Equipment
ADNOC-COPV4-14 CoP April, 2014 Version 1
& Services
Personnel Protective
ADNOC-COPV4-13 TGN Equipment in the middle-east April, 2014 Version 1
environment
Control of Major Accident
ADNOC-COPV5-01 CoP April, 2014 Version 2
Hazards (COMAH)
Crisis and Emergency
ADNOC-COPV5-02 CoP April, 2014 Version 2
Management
Qualitative and Quantitative
ADNOC-COPV5-03 CoP G/L April, 2014 Version 2
Risk Assessment (QRA)
Outline HSE Design
CoP
ADNOC-COPV5-04 Philosophy for Major Hazard April, 2014 Version 1
Plant and Equipment

ADNOC-COPV5-05 CoP Incident Command System April, 2014 Version 1

ADNOC- COPV5-
CoP HSE Risk Management April, 2014 Version 3
06
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 20 of 67

Doc.
Doc. No. Document Title Version
Type
Identification and Integrity
ADNOC-COPV6-01 CoP Assurance of HSE Critical April, 2014 Version 2
Equipment and Systems

4.5 COMPANY PROCEDURES AND REGULATIONS

Document No. Description

ADNOC GROUP Health, Safety & Environment (HSE)


HSE Policy
Policy

Z0000-PB-GEN-N-039-043 HSE Risk Management Procedure

Health, Safety & Environmental Management System


Z0000-MS-GEN-N-002-041
(HSEMS) Manual

Z0000-PB-GEN-N-026-036 Waste Management Procedure

HSE Management of Contractors (including all


Z0000-PB-GEN-N-032-019
attachments)

Z0000-PB-GEN-N-032-019 HSE Pre-qualification Questionnaire Attachment A

Z0000-PB-GEN-N-036-064 Project HSE Reviews (PHSER)

Z0000-ST-GEN-N-006-011 Standard for Effluent & Emission Discharges

ZADCO-HSE-06.11 HSE Guide

Z0000-PB-GEN-N-027-016 HSE Training Procedure

Z0000-GL-GEN-N-006-028 Occupation Health Guidelines

Z0000-PB-GEN-N-023-017 Procedure for Health Risk Assessment

Z000-PB-GEN-N-098 HAZOP Review Procedure

Z0000-PB-GEN-N-103 PHA Procedure

Z0000-GL-GEN –N-019-020 Guide on reporting EIA and EIS

Zirku Emergency Procedure Manual & Command


HSE.03.08 a & b
Centre Manual

Z0000-GL-GEN-N-005-025 Hazardous Material Management


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 21 of 67

Document No. Description

Z000-PB-GEN-N-052-027 Management of PPE

4.6 INTERNATIONAL CODES AND STANDARDS

Standard Description

Sizing, Selection, and Installation of Pressure Relieving Devices in


API RP 520
Refineries

API STD 521 Pressure relieving and depressurizing systems

API 2001 Fire protection in Refineries

Application of Fixed Water Spray System for Fire Protection in


API 2030
Petroleum and Petrochemical Industry

Fireproofing practices in petroleum and petrochemical Processing


API 2218
Plants

NFPA 10 Standard for Portable Fire Extinguishers

NFPA 11 Standard for Low-, Medium-, and High-Expansion Foam

NFPA 12 Standard on Carbon Dioxide Extinguishing Systems

NFPA 13 Standard for Installation Sprinkler Systems

NFPA 14 Standard for Installation of Standpipe and Hose Systems

NFPA 15 Standard for Water Spray Fixed Systems for Fire Protection

Standard for Installation of Foam Water Sprinkler and Foam Water


NFPA 16
Spray System

NFPA 17 Standard for Dry Chemical Extinguishing Systems

NFPA 20 Standard for Installation of Stationary Pumps for Fire Protection

NFPA 22 Standard for Water Tanks for Private Fire Protection

NFPA 24 Standard for the Installation of Private Fire Service Mains and
Their Appurtenances
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 22 of 67

Standard Description

NFPA 25 Standard for the Inspection, Testing, and Maintenance of Water-


Based Fire Protection Systems

NFPA 30 Flammable and Combustible Liquids Code

NFPA 70 National Electric Code

NFPA 72 National Fire Alarm Code

NFPA 101 Life Safety Code

NFPA 496 Standard for Purged and Pressurised Enclosure for Electrical
Equipment

NFPA 2001 Standard on Clean Agent Fire-Extinguishing Systems

IEC 60331 Tests for Electric Cables under Fire Conditions

IEC 60079 0 to 17 Electrical apparatus for explosive gas atmosphere

IEC 60529 Degrees for protection provided by enclosures (IP code)

Functional Safety of electrical / electronic / programmable


IEC 61508
electronic safety related systems

Functional safety – Safety instrumented systems for the process


IEC 61511
industry sector

Model Code of Safe Practice Area Classification for Installations


EI 15
handling flammable fluids

BS EN 60079-14 Electrical apparatus for explosive gas atmospheres Electrical


installations in hazardous areas (other than mines)

BSI BS ISO 7010 Graphic Symbols –Safety Colours and Safety Signs –Registered
Safety Signs

BSI BS EN 54 Fire Detection and Fire Alarm Systems

BS 5839-1 Fire detection and fire alarm systems for buildings Part 1 - Code of
practice for design, installation, commissioning and maintenance
of systems in non-domestic premises

BS 5908-1 Fire and explosion precautions at premises handling flammable


gases, liquids and dusts Part 1 - Code of practice for precautions
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 23 of 67

Standard Description

against fire and explosion in chemical plants, chemical storage


and similar premises

FMG Data Sheet 3-10 Installation and Maintenance of Private Fire Service Mains and
Their Appurtenances

UL 1091 UL Standard for Safety-Butterfly Valves for Fire-Protection Service

FMG Data Sheet 5-4 Transformers

4.7 OTHER PROJECT DOCUMENTS

Document No Description

P7564-GD-400-N-0006 Project HSE Plan (Engineering & Procurement)

P7564-BD-400-G-0009 Basic Engineering Design Data

P7564-GD-400-N-0007 HSE Philosophy

P7564-SR-400-E-0021 Hazardous Area Classification Report

P7564-GD-428-O-0001 Passive Fire Protection Philosophy and Schedule

P7564-SR-400-N-0042 Fire and Explosion Risk Assessment (FERA) Report

P7564-BD-400-E-0002 Electrical Design Basis

P7564-BD-540-T-0001 Telecommunication Basis of Design

P7564-BD-400-J-0001 Instrumentation Basis of Design

P7564-BD-400-F-0033 Process Design Basis & Criteria

P7564-BD-400-P-0002 Piping Design Basis

P7564-BD-400-C-0002 Civil and Structural Design Basis


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 24 of 67

Document No Description

P7564-TS-400-E-0038 Addendum to ZADCO Specification on Electrical


Installation in Civil Building

Design Criteria and Specification for Building Heating,


P7564-BD-400-H-0010
Ventilation, and Air-conditioning (HVAC) System

P7564-TS-400-A-0001 Technical Specification of Architectural Building


Material &Construction Works

A3-401-J-0519_001 Fire and Gas Cause and Effect Diagram Train#5

Interface Projects Reference Documents

P8363-TS-400-O-0004 Loss Prevention Philosophy for Zirku Fire & Gas


System Upgrade Project, P8363

4.8 ORDER OF PRECEDENCE

In the event of conflict between any of the Codes and Standards and other requirements of this
document, the most stringent requirements shall take precedence. See Basic Engineering Design
Data (Document # P7564-BD-400-G-0009) for further details.

5 HAZARDOUS AREA CLASSIFICATION

5.1 GENERAL

The purpose of area classification is to ensure that ignition sources are eliminated or controlled by
engineering design to prevent ignition of potential flammable or combustible atmospheres.

The main reasons for classifying the project scope facilities into hazardous areas are:

 To ensure that sources of ignition are segregated and/or contained from sources of flammable
gas or vapour;

 To define the electrical system certification requirements;

 To assist in determining the appropriate location of ventilation air inlets and outlets;

 To assist in determine the appropriate location of combustion air inlets and exhaust for fired
equipment, engines and turbines, where applicable for the PROJECT;

 To define the extend of hazardous area from cold vents, where applicable for the PROJECT;
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 25 of 67

 To determine the maximum allowable surface temperature of equipment depending on type of


flammable gases present or likely to be present in the area.

The purpose of the electrical hazardous area classification is to ensure that ignition sources from
electrical equipment do not ignite potential flammable atmospheres. The overall design philosophy
will be to make the site as safe as possible by minimizing the potential sources of release of
flammable gas and ensuring efficient ventilation to disperse / dilute any gas that is released.

5.2 CLASSIFICATION OF HAZARDOUS AREAS

Process facilities will generally be designed to minimize hazardous location areas, such as Zone 0
and Zone 1; however by exception Zone 1 rating will apply where powered process/hazardous
equipment must remain in operation. Example of such exception is the exhaust fan of battery room.

The basis of area classification shall be IEC 60079-10-1 Explosive atmospheres – Part 10-1:
Classification of areas – Explosive atmospheres (This terminology is utilized in ATEX directive. The
terminology “Flammable”, “Combustible” and “explosive” have been used interchangeably within this
section and other applicable sections of document).

Hazardous Areas are those in which flammable gases or vapors are or may be present in the air in
quantities sufficient to produce explosive gas atmospheres. Hazardous Areas can be further divided
into three Zones, based on frequency of occurrence and duration of an explosive gas atmosphere,
as follows:

Zone 0

Location where ignitable concentrations of flammable gases or vapors are present continuously or
for long periods of time.

Zone 1

Location where ignitable concentrations of flammable gases or vapors are likely to exist under normal
operating conditions or may exist frequently because of repair, maintenance operations or leakage.
If equipment failure or faulty operations results in the release of ignitable concentrations of flammable
gases or vapors and causes electrical equipment nearby to fail, they could become a source of
ignition; therefore, this location would be considered Zone 1. Also, if a location is adjacent to Zone 0
and flammable gases or vapors could be communicated through from Zone 0 to this location it is
considered Zone 1 as well.

Zone 2

Location where ignitable concentrations of flammable gases or vapors are not likely to exist under
normal operating conditions and if they do occur, they will exist for a short period of time. If the
container ruptures or abnormal operation results in the release of ignitable concentrations of
flammable gases or vapors then this location is considered Zone 2. If the ventilation equipment that
prevents flammable gases or vapors from building up to ignitable concentrations by positive
mechanical feedback fails then the area around it is considered Zone 2. Also, if a location is adjacent
to Zone 1 and flammable gases or vapors could be communicated through from Zone 1 to this
location, it is considered Zone 2 as well.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 26 of 67

Non Hazardous Area

A non-hazardous area or safe area is an area in which an explosive atmosphere is not expected to
be present.

As a general note for Zones 0, 1, and 2, the greater the release rate, the larger the extent of the zone.
The release rate depends mainly on the geometry of the source of release, release velocity,
concentration, volatility of a flammable fluid and fluid temperature. The extent of the zone also
increases if the lower explosive limit decreases. The horizontal extent of the zone at ground level will
increase with increasing relative density of gas or vapour and the vertical extent above the source
will increase with decreasing relative density of gas or vapour.

To reduce the extent of the zone, physical barrier or maintaining a sufficient overpressure in the area
relative to the adjacent areas to prevent the ingress of the explosive gas atmosphere and purging the
area with sufficient flow of fresh air to ensure that the air escapes from all openings where the
flammable gas or vapour may enter or accumulate. As part of PROJECT, dikes, walls or ceilings can
be used to limit the extent of the zone.

5.3 VENTILATION AND AIR INTAKE SYSTEMS

Any building containing a fuel source and/or any contaminating agent, or in connection with a
hazardous area, shall be ventilated as follows:

 Buildings containing a continuous or primary grade release or in connection with a hazardous


area, Zone 1, shall be provided with dilution ventilation (e.g., Battery Room).

 Buildings containing a secondary source of release or in connection with a hazardous area, Zone
2, shall be either adequately ventilated if it is acceptable they remain classified Zone 2; or shall
be provided with dilution ventilation if they must be rendered non-hazardous.

 Ventilation should be used to prevent accumulation of flammable gases / vapors in an enclosed


space due to loss of containment within the enclosed space, or ingress of flammable gases /
vapors from sources originating external from the enclosed space.

 Dilution ventilation should be used to prevent accumulation of dangerous concentration of


flammable gases / vapors in an enclosed space. The method of ventilation can be either natural
or mechanical. Design of dilution ventilation systems should specify the number of air changes
per hour that is required to keep the atmosphere within the enclosed space at less than 20%
LEL.

 Pressurisation of an enclosed area containing no internal source of leakage of flammable


gas / vapors , should be used to prevent ingress of flammable gas / vapors from adjacent areas.
The air intake shall be taken from a safe, unclassified area.

 Ventilation air intakes for buildings shall be located in a safe (unclassified) area, at least 3 m
away from any hazardous area to avoid ingestion of flammable or toxic gas/vapor. The air intakes
shall be elevated.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 27 of 67

 All diesel engines, if applicable, shall be equipped with provision to shut-off the engine upon
ingestion of flammable gases / vapors in the air intake.

5.4 EQUIPMENT SELECTION FOR HAZARDOUS AREAS

5.4.1 General

Electrical equipment shall not normally be installed in Zone 0 hazardous area unless written approval
provided by COMPANY.

All electrical equipment selected for installation in Hazardous Area will be suitable for Zone 2 Gas
Group llB, Temperature Class T3, as a minimum.

All field instruments shall be suitable for installation in Zone 1, Gas Group IIB, and Temperature Class
T3 as minimum.

All safety critical items i.e. devices required to operate under the emergency conditions, such as Field
F&G/ESD devices shall be suitable for use within a Zone 1, Gas Group IIB, and Temperature Class
T3 as a minimum.

Street/outdoor lighting shall be suitable for minimum Zone 2, Gas Group IIB, and Temperature Class
T3 hazardous area, irrespective of whether they are located in Process or Non-Process area.

All mechanical equipment installed in hazardous areas will be manufactured to ensure that rotating
parts are non-sparking and adequately protected against the generation of a static charge. All
mechanical equipment will be grounded.

All electrical equipment and materials selected for installation in hazardous area shall comply with
relevant parts of IEC standards/CENELEC harmonized standards and approved by ATEX
(ATmosphere EXplosive) notified bodies.

Surface temperature of mechanical equipment installed in the hazardous areas should not exceed
200°C.

Hazardous Area Classification Report and Schedule shall be prepared and it shall be consistent with
the Hazardous Area Classification Update Project P8658. Hazardous Area Classification Drawings
prepared for this project shall be made consistent with the guidelines developed under P8658.

5.4.2 Outdoor Non-Process Areas

All electrical equipment to be installed outdoor in non-process area (safe area) shall be of standard
industrial type construction.

Any additional requirement identified during hazardous area classification for outdoor non-process
area shall be complied with.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 28 of 67

5.4.3 Process Areas

All electrical equipment to be installed outdoor within process area that are classified as non-
hazardous shall be certified for Zone 2, Gas Group IIB, and Temperature Class T3 as a minimum.
This electrical equipment include, but are not limited to, Transformers, HVAC equipment, motors,
local control panels, Distribution boards, luminaries, power & convenience outlets.

All other outdoor equipment and installations within the main plant shall also be certified for minimum
Zone 2. Any additional and specific Hazardous area requirement that may be identified in the HAC
schedule shall be complied with.

If small pockets of non-hazardous area are present within a general hazardous area, it is not
considered a good practice to denote these pockets as non-hazardous (Reference Section 2.5 of EI
15, “Area classification code for installations handling flammable fluids”).

Critical safety light fixtures and associated circuits such as PA system, F&G detectors shall be
suitable for installation in Zone 1, Gas Group IIB, Temperature Class T3, as a minimum.

5.4.4 Battery Rooms

Battery rooms are generally a part of the UPS system. With the exception of small capacity sealed
batteries, accumulator batteries are regarded as primary sources of Hydrogen gas release when they
are charged.

Gases released by batteries in charge mode can be recombined. There are two types of storage
batteries:

 Batteries for which the recombination rate is less than 95%. They are called “Open Batteries”.

 Batteries for which the recombination rate is 95% or more. They are called “Recombination
Batteries”.

Dilution ventilation shall be provided in the enclosures containing accumulator batteries.

Accumulator batteries and their chargers may be located in the same cubical only if this cubical is
provided with natural or artificial ventilation. The fan in this battery room shall be located at the highest
point and shall have type Exd protection and be suitable for operation in Zone 1 for Group IIC
(includes Hydrogen) gases and Temperature class T6. When dilution ventilation is achieved by
mechanical means, the battery charging will be automatically stopped on loss of ventilation.

The luminaries, junction boxes and convenience outlets located in battery rooms shall be suitable for
Zone 1 and Gas Group llC as a minimum.

Hydrogen gas detection shall be installed in the battery room. These detectors shall be certified for
gas group IIC.

Open batteries shall be located in a dedicated Battery Room.


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 29 of 67

For the safety of personnel handling the hazardous fluids associated with open batteries, a wall-
mounted portable eye wash station shall be provided.

5.4.5 Indoor Installations

Buildings located within a Hazardous area shall be pressurised, with air taken from safe area, by
mechanical ventilation to minimum of 35 pa (0.14 inch water column) above ambient atmospheric
pressure based on industry practice.

Flammable and toxic gas (H2S) detectors shall be provided at the fresh air intake of HVAC for
PROJECT buildings and Air Lock Room of LER for Oil Train#5 & 6.

Executive actions will be performed upon confirmed gas detection (i.e. hydrocarbon or toxic gas) at
HVAC air intake, as detailed in Section No. 6.8 of this document.

On loss of pressurization within the building, alarm shall be activated locally and in a continuously
manned location and all electrical equipment inside the building that are not suitable for outdoor
hazardous area classification shall be powered off.

Building located in a non-hazardous area shall be pressurised to 35 pa (0.14 inch water column) if
deemed necessary by QRA and FERA.

The critical/safety light fittings, F&G detectors, FGS connected devices like horns, beacons, status
panel etc. and PAGA system speakers and associated circuits shall be suitable for installation in
Zone 1, Gas Group IIB, Temperature Class T3, as a minimum.

Confirmed HC gas detection of plant area shall isolate the operator cabin electrically.

6 FIRE AND GAS DETECTION

6.1 SCOPE AND METHODOLOGY OF F&G PHILOSOPHY

6.1.1 Scope

This section on F&G detection, which is a part of the overall Loss Prevention Philosophy for
PROJECT, defines the goals for the design of the Fire & Gas Detection and Alarm system. It defines
also the strategy to be used to achieve these goals and provides guidance on the selection and
location of detectors, alarms and communication to concerned personnel.

6.1.2 Methodology

The methodology is as follows:

 Review existing Fire & Gas detection system.

 Determine/review potential sources of loss of containment, and identify impacted area

 Define detector type, location, voting logic and action upon detection
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 30 of 67

6.2 ROLE OF FIRE & GAS SYSTEM

The primary role of a Fire and Gas detection system is to detect loss of containment of flammable
and toxic material and the ignition resulting in fires to provide an early warning to operational and
emergency response team personnel so that necessary action can be initiated to control the
emergency and avoid escalation.

Considering the flammable and toxic nature of the process streams in this plant, the selection of
appropriate type of detectors, their location, voting logic and alarm is important for appropriate and
effective design of the system.

The fire & gas detection system shall perform the following three basic functions:

 Monitoring: Continuous automatic monitoring of the environment for the presence of flammable
and toxic vapour/gases and detection of fire (smoke, heat or flame)

 Alarm: Initiate alarm to alert personnel to the presence of flammable and toxic vapour/gases
and/or fire.

 Protection: Initiates control signals to ESD or Fire Suppression systems or Deluge Systems to
control the situation and prevent escalation of the event.

During FEED, an assessment of the number and locations of fire & gas detectors was carried out by
FEED Consultant by consequence analysis based 2D F&G mapping study and the devices were laid
out on the Plot Plan. During EPC, 3D F&G Mapping Study shall be conducted to confirm the
adequacy of the number and location of all F&G devices for achieving the required coverage.

Essential design features of the detection system shall include:

 Local and remote audible and visual alarms;

 Addressable, local and remote fire and gas alarm;

 Self-diagnostic capabilities to detect faults and raise an alarm at a continuously manned location
e.g. control room, fire station and or on HMI

 Signals from the fire detection system may be used to initiate operation of fire suppression
systems and facility shutdown through the Emergency Shutdown System;

 Provisions shall be made for functional tests of system components without disruption to routine
operations or interruption of protection;

 Power to FGS shall be supplied from UPS; and

 Protection of FGS against accidental damage, bypassing or deliberate tampering


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 31 of 67

6.3 FIRE AND GAS STUDY

6.3.1 General

The Fire and Gas Detection System in the 5th Oil Train will be in line with Loss Prevention Philosophy
for P8363 Fire and Gas Upgrade Project, Document No. P8363-PB-400-O-0004, “Zirku Fire & Gas
System Upgrade Project.

The scope of the study to consider fire hazards, flammable hazards, and toxic gas hazards
associated with hydrogen sulphide (H2S). Hazards associated with process areas of 5th oil train,
transformers, substation and LER will be addressed.

A Fire & Gas study shall be carried out. The study shall address:

 Definition & identification of fire & gas hazard zones for PROJECT

 Definition of zone categories & zone grades;

 Identification of the fire & gas hazard scenarios for PROJECT.

 Assigning zone category for each identified fire & gas hazard zone;

 Defining the performance requirements for fire & gas detection;

 Recommendations and findings from fire & gas study.

A Fire and Gas Detection system (FGS), totally independent from the process control systems, will
continuously monitor areas of the plant for abnormal conditions. In the event of a hazardous situation
being detected, the system shall initiate protective actions and pre-determined alarms to warn the
First Response Team, personnel in the any continuously manned location and locally where the fire
or loss of containment has occurred. The FGS initiates the appropriate visual and audible alarms by
activating beacons and horns. FGS is also used for initiating mitigating actions upon activation,
wherein such activation is not deemed to present other risks.

Fire and/or Gas detectors, appropriate to the anticipated hazard, shall be provided in sufficient
number and suitably located for effective monitoring. Detectors shall be certified for use in hazardous
areas and suitable for the area classification where installed. For operational and maintenance
reasons, the make and models of detectors shall, where reasonably practicable, be standardised
throughout the whole installation following the existing F&G Upgrade Project, inclusive of detectors
in vendor packages.

Detectors shall, as far as possible, be protected against environmental effects which may influence
their operation. Where necessary, detectors shall be protected against mechanical damage. All
cabling associated with the FGS shall be fire resistant in accordance with IEC 60331.

All detectors shall be located such that they are accessible for calibration and maintenance, as much
as possible, without the use of scaffolding. Instrument tubing to facilitate the calibration shall be
provided if the detectors are at inaccessible locations.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 32 of 67

6.3.2 Definition and Identification of F&G Zones

6.3.2.1 Definition of F&G Zones

Fire & Gas Zones are primarily segregation of process and non-process areas into discrete zones
based on common hazards and automated actions of F&G detection systems.

The following criteria shall be used to define the zones in rank order:

 Similar process equipment and hazard: Zone boundaries should be defined such that equipment
with similar process hazards are grouped together. Distinct and separate hazards shall be
classified as separate zones;

 Similar FGS system actions: Detection and alarm within an individual zone should initiate a
distinct set of defined automatic FGS response. If different FGS actions are required between
adjacent areas, even with similar equipment, then a separate zone shall be defined;

 Similar alarm type and emergency response: Alarm within an individual zone should imply a
distinct set of defined protective actions to be taken by personnel. If the required protective
actions taken by personnel differ between adjacent areas, then separate zones shall be defined;

 Segregation of gas migration hazard: An additional design objective is to detect migration of


flammable or toxic gas from one operating area to adjacent areas or buildings using gas detection
with appropriate alarms and FGS actions. Separate hazard zones shall be identified that require
segregation from adjacent operating areas to achieve this design objective.

 Areas with high toxic gas (H2S) hazard shall be segregated from areas with significantly lower or
no H2S hazard. Areas that are determined to have significantly different levels of risk from the
same hazard should be classified as separate zones.

 Unclassified Electrical Equipment: The need to protect unclassified electrical equipment within
an enclosure and segregate from classified areas requires definition of a separate zone; Areas
requiring segregation of flammable gas hazards to prevent ignition from unclassified electrical
equipment shall be segregated from adjacent areas and separate zones shall be identified.

6.3.2.2 Identification of F&G Zones

Each identified fire and gas zone, based on the above definition, shall be listed with general
characterization of flammable/toxic gas and fire hazard and shall be laid out on a plot plan to clearly
identify the zones.

6.3.3 Definition and Zone Categories and Zone Grades

6.3.3.1 Zone Categories

The fire & gas zones shall be assigned a category as defined in the table below:
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 33 of 67

Zone Examples
Area Definitions
Category
Hydrocarbon process area with general
Drums, heat exchangers,
H fire/flammable gas/toxic gas hazard under normal
pumps
or abnormal operation

N Non-hydrocarbon fire hazard.

General occupancy with no hydrocarbon fire Accommodations, Control


D
hazard rooms etc.

Non-hydrocarbon hazards with protection of Electrical room, transformer


E
special equipment. enclosures etc.

Ventilation and air intake for building, unclassified HVAC fresh air intake,
V
electrical equipment and Combustion air system. building airlocks etc.

Table 01 - Zone Category Definitions

6.3.3.2 Zone Grades

A graded area is a sub-section of a fire and gas zone to which performance targets are applied. Zone
grades shall be used to determine appropriate coverage of detectors for a specific hazard. The zone
category H defined in above section shall be graded into one of the three fire and gas grades given
in the table below. The grades define the relative risk of fire and gas hazards between different
hydrocarbon process zones. The following Table shows the definition of different zone grades:

Zone Grade Definition

A Hydrocarbon Process with high exposure/risk

B Hydrocarbon Process with moderate exposure/risk

C Hydrocarbon Process with low or very low exposure/risk

Table 02 - Zone Grade Definitions (Zone Category H)

Grading is a function of the equipment, hazards, consequences, likelihood, occupancy, and special
factors. An assessment of hazards for each zone to assign grading shall address the following;

 Assessment of hydrocarbon process equipment;

 Assessment of fire and gas consequences; and

 Assessment of release likelihood

6.3.4 Identification of F&G Hazard Scenarios

Different types of fire & gas hazards that can occur in the PROJECT facility shall be identified.

These identified fire & gas hazards shall be modelled to determine thermal radiation (due to pool, jet
and flash fire) explosion overpressure and flammable / toxic gas cloud boundaries.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 34 of 67

The consequence modelling results shall be used to determine the number and location of fire and
gas detectors.

6.3.5 Assigning Zone Category for Identified F&G Zones

The identified fire & gas zones as per Section 6.3.3 above shall be assigned a zone category based
on Section 6.3.3.1 and zone grade based on Section 6.3.3.2 above for Zones Category H.

6.3.6 Defining Performance Requirements for F&G Detectors

6.3.6.1 Performance Target for F&G Zones

The performance target defines the ability of the function to detect, alarm, and if necessary, mitigate
the consequence of a fire or gas release upon a demand condition. In concept, a higher hazard
installation should require higher levels of performance; while a lower hazard installation should allow
for lower levels of performance, so that FGS resources can be more effectively allocated.

Performance target for Fire and Gas zones is defined below in Table 03. These targets are based on
assessment of typical hazard scenarios, consequences, likelihoods and target risk reduction. As per
ADNOC Offshore Corporate risk tolerance guideline.

Fire or Gas Grade Target Fire or Gas Detection Coverage


A 90 %
B 85 %
C 60%

Table 03–Performance Target for Fire and Gas Detection

6.3.6.2 Performance Target for Toxic Gas Detectors

Design of toxic gas detection to achieve general coverage in process areas requires H2S detection
at an incipient stage where action can be taken to prevent personnel exposure. The primary concern
is to alert workers of a hazard prior to worker entry into a process area. Once in the process area,
worker safety is primarily dependant on personal H2S monitors.

Toxic gas detection performance targets shall be evaluated for locations where a release of toxic gas
can result in H2S concentration above the level that it considered immediately dangerous to life and
health (IDLH) (>100 ppm) downwind of the immediate hazard area.

The following three categories are used to define toxic gas detector performance requirements:

Gas Grade Gas Grade Definition


A Hydrocarbon Process with high exposure/risk
B Hydrocarbon Process with moderate exposure/risk
C Hydrocarbon Process with low or very low exposure/risk

Table 04–Toxic Gas Grade Definitions

Gas grade A is typically assigned to zones where personnel have a high risk of exposure/injury due
to a small gas release, while gas grade B is typically assigned to areas subject to a moderate risk of
injury from releases that are larger than pinhole size. Gas grade C is typically assigned to areas
where potential ground level concentration of H2S in excess of levels that can cause personnel injury
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 35 of 67

is not anticipated. Other performance target criteria will be as per P8363-PB-400-O-0004, “Zirku Fire
& Gas System Upgrade Project - Loss Prevention Philosophy.

6.3.6.3 Performance Target for Flammable Gas Detectors

Design of flammable gas detection to achieve general coverage in process areas requires that
flammable gas should be detected at an incipient stage so that necessary mitigation measures can
be taken to prevent escalation and significant losses.

Flammable gas detection performance targets shall be evaluated in locations where ignited gas
clouds could cause damage from explosion overpressure. In these locations, the smallest gas cloud
that has the potential to cause such damage shall be used to define requirements for placing
flammable gas detectors. Three categories are used to define gas detector performance
requirements as shown in below table 05.

Gas Grade Gas Grade Definition


A Hydrocarbon Process with high exposure/risk
B Hydrocarbon Process with moderate exposure/risk
C Hydrocarbon Process with low or very low exposure/risk

Table 05–Flammable Gas Grade Definitions

Gas grade A is typically assigned to zones subject to a high degree of confinement. 90% detector
coverage is set as the performance target associated with Grade A. Gas grade B is typically assigned
to areas subject to a moderate degree of confinement. 85% detector coverage is set as the
performance target associated with grade B. Gas grade C is typically assigned to open hydrocarbon
processing areas where the primary concern is migration of flammable gas to other hydrocarbon
processing areas. The performance target associated with grade C is 60% coverage.

The number and location of flammable gas detectors for general area coverage shall be assessed in
the Fire & Gas Mapping study through application of performance target defined above and based
on criteria which will outlined in in P8363-PB-400-O-0004, “Zirku Fire & Gas System Upgrade Project
- Loss Prevention Philosophy.

6.3.6.4 Performance Target for Fire (Flame) Detectors

Fire (Flame) detection system shall be designed on the principle of early detection of fire in its
incipient stage so that action can be taken to prevent escalation. The primary objective is early
detection and annunciation/alarm to inform personnel to evacuate the area safely if needed. A
secondary objective is to initiate fire suppression measures to minimise loss/damage to assets.

Incipient fire detection requires that sufficient numbers of flame detectors are strategically located to
provide adequate coverage. The categories used to establish performance targets for each fire
detection zone are shown in below table 06.

Fire Grade Fire Grade Definition


A Hydrocarbon Process with high exposure/risk
B Hydrocarbon Process with moderate exposure/risk
C Hydrocarbon Process with low or very low exposure/risk

Table 06–Fire (Flame) Grade Definitions


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 36 of 67

Grade A shall be used for zones in hydrocarbon handling areas where small fires could rapidly
escalate and/or cause significant damage in a short period of time. The performance targets
associated with Grade A is minimum 90% detector coverage. The performance targets associated
with Grade B is minimum 85% detector coverage. Grade C shall be used if Grade B level of detection
is considered conservative due to low hazard of hydrocarbon fire. For Grade C detector coverage
should meet minimum levels of 60%.

Radiant heat output (RHO) shall be used to specify Flame detector sensitivity and location. Fire
detection in area with high fire hazard exposure shall be sensitive to lower levels of RHO than fire
detection in locations with lower fire hazard exposure.

The radiant heat output levels that trigger alarm conditions and, if necessary, automatic control
actions are shown in below Table 06.

Fire Grade Fire Detection Sensitivity (RHO)


Alarm(kW) Automatic Control Action(kW)
A 10 10
B 10 50
C 100 250

Table 07–Fire Detector Sensitivity

Requirements for the number and location of flame detectors for general area coverage shall be
determined in the Fire & Gas Mapping study through application of performance targets defined
above.

6.4 FIRE AND GAS MODELLING

The F&G Mapping Study will be conducted after 30 % Model Review and updated after 90 % Model
Review, considering the criteria and performance described in section 6.3 above.

6.5 SELECTION OF TYPE OF F&G DETECTORS

6.5.1 Fire and Smoke Detection

A fire detection system shall be installed in any installation complying with the following two
conditions:

 Where there is a significant risk of occurrence of fire; and

 Where unabated, fire may lead to unacceptable risks to human life, assets or environment.

Based on the above criteria, fire detection systems will be provided in areas with significant
combustible or flammable inventories (e.g., process units, pumps, etc.), as well as all buildings and
transformer sheds.

Fire detection can be either accomplished by flame detection, combustion products (smoke) detection
or heat detection or a combination of more than one of these.

Smoke detectors shall not be used in open areas or heavily ventilated areas; hence their use is limited
to inside buildings. The most common areas suitable for smoke detection are the Operator
Shelter/Cabin, Local Equipment Room (LER) and Sub-stations.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 37 of 67

Photoelectric (Optical) type smoke detectors will be used for Project scope buildings like Substation,
LER and operator’s shelter/cabin.

In areas of LER and Substation, where incipient fire detection is required for an early response,
aspirated type smoke detectors also known as High Sensitivity Smoke Detection System (HSSD) or
Very Early Smoke Detection Apparatus (VESDA™ or equivalent) shall be used. HSSD detection will
be provided for alarm purposes only.

Multi-spectrum Infra-Red (3IR) flame detectors shall be used for fires resulting from process piping
and equipment. These detectors shall be strategically located in the plant areas. These detectors
should be shielded from direct solar radiation, reflected flare radiation and impact damage. Detectors
for general area coverage should be individually hardwired analogue inputs to the FGS logic solver.
Detectors should be suitable for plant electrical area classification requirements.

Fusible plugs are fire detectors that operate on the principal of heat detection as compared to 3IR
detectors that detect flames. These heat detectors are provided around the fire hazardous process
equipment and are connected to a pressurized pneumatic header system. In the event of a fire,
activation of a fusible plug causes a loss of pneumatic pressure. The low pneumatic pressure
activates a fail-open deluge valve initiating the flow of FW through a network of deluge piping and
deluge nozzles. Activation of the deluge system is upon detection by a single fusible plug (no voting
is required) and is limited only to the zone in which a fire has been detected.

6.5.1.1 Fire Detector - Optical Flame Detectors

Multi-spectrum Infra-Red type fire detector shall be used. These detectors shall be shielded from
direct solar radiation, and from incident and reflected flare radiation. Detectors should be suitable for
the hazardous area classification of the location where these detectors shall be installed.

The response time for these detectors shall be less than 10 seconds for a 1 ft. x 1 ft. of Heptane fire
at a distance of 50 feet. The field of view shall be 90 - 120 degrees.

6.5.1.2 Fire Detector - Linear Heat Detectors

The linear heat detectors shall be provided for detecting transformer fires. These shall be rated to
alarm at 85ºC

6.5.1.3 Fire Detector - Fusible Plugs

Fusible plugs operate on the principal of detecting heat and not flame or products of combustion.
Number of fusible plug heat detectors are generally installed in a given process areas surrounding
hazardous equipment requiring spray water application and will be connected to a pressurized
pneumatic header.

In the event of a fire, the fusible plug in the system melts and causes de-pressurization of the
pneumatic header that activates a deluge valve to apply FW through the deluge nozzles to the
protected equipment/area.

Both Fusible plugs and flame detection shall be used separately for deluge activation and should be
similar to the type which is currently being used in Zirku facility.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 38 of 67

6.5.1.4 Fire detector - Smoke

Smoke detectors shall not be used in open areas or heavily ventilated areas; hence their use is limited
to inside buildings and enclosures. The most common areas suitable for smoke detection are the
Operator Shelter/Cabin, Local Equipment Room and Sub-stations.

Photoelectric (Optical) type smoke detectors will be used for Project scope buildings like Substation,
LER and operator’s shelter/cabin., as per Loss Prevention Philosophy Doc. No. P8363-PB-400-O-
0004 for Zirku Fire & Gas System Upgrade Project, P8363.

In areas of LER and Substation, where incipient fire detection is required for an early response,
aspirated type smoke detectors also known as High Sensitivity Smoke Detection System (HSSD) or
Very Early Smoke Detection Apparatus (VESDA™ or equivalent) shall be used. False Floor, Ceiling
Voids and the Room Voids, Equipment Room and Electrical Room shall be provided with High
Sensitivity Smoke Detection System or Very Early Smoke Detection Apparatus (VESDA™ or
equivalent). Project scope building (SS116 & LER for Train#5 & 6) control panel will be covered by
HSSD (where feasible). HSSD detection will be provided for alarm purposes only.

In other building or enclosure where incipient fire detection is not required, photoelectric smoke
detectors should be used. The smoke detectors shall be spaced according to the NFPA 72. Smoke
detectors shall not be installed more than 60 cm below the ceiling. The detectors shall be evenly
distributed, with particular attention given to friezes and dropped girders, ventilation air inlet and outlet
ducts, and temperatures near the ceiling.

6.5.2 Gas Detection

A gas detection system shall be provided to monitor areas where flammable or toxic gases may
potentially be released in hazardous concentration. The gas detection system shall alert personnel
to the presence and location of the hazardous condition. Upon detection of a condition that exceeds
pre-set limits / Alarm Set point; suitable audible and visual alarms will sound locally and remotely in
a continuously manned location.

Flammable gas detector shall be provided around high leak potential equipment, areas where gas
may accumulate or migrate to, Air Lock Room of LER and HVAC air intakes if the buildings are
located in areas where flammable gases can potentially become present. Hydrogen Sulphide gas
detector shall be provided where it may migrate to Air Lock Room of LER and HVAC air intakes if the
buildings are located in areas where Hydrogen Sulphide gas can potentially become present.

Flammable and toxic gas detectors shall be provided in the HVAC air intake and the Air Lock Room
of LER.

Flammable and toxic gas detectors shall be provided in the HVAC air intake of Substation.

Hydrogen Sulphide point type detectors will be located along any new approach way and along new
working platforms and escape routes as well as around high leak potential equipment.

6.5.2.1 Toxic Gas Detector

Point type Hydrogen Sulphide (H2S) gas detectors will be provided for outdoor areas where loss of
containment of sour process streams is determined to be a credible scenario.

Toxic gas detectors shall be based on MOS (Metal Oxide Semiconductor) technology in line with
P8363 Fire and Gas Upgrade Project. These shall have a detection range of 0 - 50 PPM and have a
sensitivity of ±2 ppm or 10% of calibration gas concentration, whichever is higher.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 39 of 67

6.5.2.2 Hydrocarbon Gas Detector

Point type hydrocarbon detectors shall be provided for areas where loss of containment of
hydrocarbon process streams is determined to be a credible scenario.

Point hydrocarbon gas detectors shall be based on IR technology, having a detection range of 0-100
% LEL.

6.5.2.3 Hydrogen Gas Detector

Hydrogen gas detectors will be provided in Battery room of New Substation (SS-116). These
detectors shall be catalytic type having a range of 0-100% LEL and certified for hazardous area
classification of gas group IIC.

6.6 ALARM SYSTEM

6.6.1 Type of Alarm

The fire & gas alarm system will be supplemented by zone-by-zone audible alarms (sounders) and
visual alarms (beacons) indicating fire and hydrocarbon/toxic gas (H2S) in the zones. The detection
of fire by a single fire detector within a given zone shall automatically generate a distinct local audible
and visual fire alarm for all notification appliances within the associated zone. Fire alarm shall also
generate an audible and visual alarm at the FGS operator console at central alarm location and at
other FGS console locations. Similarly the activation of gas detector (flammable or H2S) within a
given fire & gas zone shall automatically generate a distinct local audible and visual gas alarm at all
notification appliances within the associated fire & gas zone. Gas alarm shall also generate an audible
and visual alarm at the FGS operator console at central alarm location and at other FGS console
locations.

The audible & visual alarms will be mounted on single masts in outdoor plant area, outside the doors
of buildings and within the buildings as appropriate.

The color coding for visual alarms are as follows:

 BLUE - indicates the presence of hydrocarbon/toxic gas within the fire & gas zone

 RED - indicates fire within the fire & gas zone

The tone used for audible alarms in case of fire, flammable gas and toxic detection is as follows:

 As per P8363, sounder shall be dual tone type, the second tone of the dual sounder shall not be
configured at present and will be used for any future change. In case of fire detection and in case
of gas detection in F&G zone, the sounder tone of 1 sec on, 1 sec off shall be initiated.

The fire alarm will take precedence over the gas alarm if multiple detection occurs (i.e. simultaneous
gas and fire detection).

6.6.2 Alarm Settings

The alarm settings for fire and gas detectors are as follows:

 Hydrocarbon gas point detector for general area coverage; high alarm at 20% LEL & high-high
alarm at 60% LEL
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 40 of 67

 Hydrocarbon gas point detector for HVAC air intake; high alarm at 10% LEL & high-high alarm
at 20% LEL

 Hydrogen gas point detector for buildings; high alarm at 20% LEL & high-high alarm at 60% LEL

 Hydrogen Sulphide (H2S) gas point detector for general area coverage; high alarm at 5 ppm &
high-high alarm at 15 ppm

 Hydrogen Sulphide (H2S) gas point detector for HVAC air intake; high alarm at 5 ppm & high-
high alarm at 10 ppm

 Linear heat detectors for transformers and cable cellar of substation; alarm at 85 0C

6.7 FIRE AND GAS CONTROL MONITORING

The fire and gas detection and alarm system, control & monitoring shall be done through F&G
operator station (HMI-Human Machine Interface), F&G Auxiliary consoles, F&G system display
screen, and F&G Matrix Panels.

6.7.1 F&G Operator Station (HMI)

The F&G Operator Station shall have the capability for overall monitoring and control of the Fire &
Gas System. The existing HMI are located in the existing control room building (ZCC), existing Fire
station and new F&G Engineering Operator Workstation of 5th and 6th oil trains in LER for Oil Train#5
and 6 .The F&G Operator Station shall have the capability to show the F&G graphic display for
individual zones and produce alarms in case of fire or gas detection.

The engineering operator workstation in LER for Oil Train#5 and 6 and Operator Workstation shall
be for monitoring only and not be provided with access to control the fire & gas system; however, if
needed, these operator stations shall have the capability to be programmed for control & monitoring.

6.7.2 F&G Auxiliary Console

New F&G Auxiliary Console will be located in the existing Zirku Control Center (ZCC) and LER for
Train#5 and 6. The Auxiliary Consoles shall have the push buttons for deluge activation and shall
provide deluge, inergen confirmed activation status and F&G alarms.

The Auxiliary Console shall have the following minimum indications:

 Separate indications will be available for buildings (LER or SS116)

 Common indications will be available for process areas (F&G Zone 128 – Separator Area, F&G
Zone 129 – Heat Exchangers Area and F&G Zone 127 – Operator Cabin)

 Indication for single and confirmed fire detection in fire & gas zone of Buildings or Process Area

 Indication for single and confirmed H2S gas detection in fire & gas zone of Buildings or Process
Area

 Indication for single and confirmed HC gas detection in fire & gas zone of Buildings or Process
Area

 Indication for single and confirmed H2 gas detection in SS116, Battery Room
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 41 of 67

 Indication for Manual Alarm Call Point in fire & gas zone of Buildings or Process Area

 Any deluge system activation status in plant area

 Room-wise Inergen system discharge status in buildings (SS116 & LER)

 Building-wise (SS116 & LER) Auto mode indication of Inergen system

 Building-wise (SS116 & LER) Manual mode indication of Inergen system

 Building-wise (SS116 & LER) Inhibit mode indication of Inergen system

 Common audible alarm (for fire/gas detection) in fire & gas zone of Buildings or Process Area

 Common fault alarm (for fire/gas detectors) in fire & gas zone of Buildings or Process Area

Reference shall be made to the Fire & Gas Detector Cause and Effect (Doc No- A3-400-J-1255_001)
and Instrumentation Console Layout Drawings for details.

6.7.3 F&G Display

Existing F&G System Display Screens are located in the existing Zirku Control Center (ZCC) and the
fire station.

The display screens have the following minimum information for all fire & gas zones:

 Indication for fire detection;

 Indication for confirmed fire detection;

 Indication for H2S gas detection;

 Indication for confirmed H2S gas detection;

 Indication for HC gas detection;

 Indication for confirmed HC gas detection;

 Audible alarm for fire and gas detection;

 Common fault indication for fire and gas detection;

6.7.4 F&G Matrix Panel

Existing F&G Matrix Panel (400-FGP-0002) is located in the existing Zirku Control Center (ZCC).

The Existing Matrix Panel has the following information, Train 5 F&G Detection will lead into:

 Indication for confirmed fire detection as part of existing indication for UZ Process

 Indication for confirmed H2S gas detection as part of existing indication for UZ Process

 Indication for confirmed HC gas detection as part of existing indication for UZ Process

 Audible alarm (for fire/gas detection) as part of existing indication for UZ Process

 Common fault alarm (for fire/gas detectors) as part of existing indication for UZ Process

New Cabinet door-mounted F&G Matrix Panels are located in the Substation SS116 and LER for Oil
Train#5 & 6.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 42 of 67

The Matrix Panels shall have the following information:

 Indication for confirmed fire detection for affected building (SS116 or LER)

 Indication for confirmed H2S gas detection for affected building (SS116 or LER)

 Indication for confirmed HC gas detection for affected building (SS116 or LER)

 Audible alarm (for fire/gas detection) for affected building (SS116 or LER)

 Common fault alarm (for fire/gas detectors) for affected building (SS116 or LER)

Reference shall be made to the Fire & Gas Detector Cause and Effect (Doc No- A3-400-J-1255_001)
for details.

6.8 ALARM, VOTING LOGIC AND ACTION

Any fire or gas detector upon activation shall provide an audio and visual alarm locally and at a
continuously manned location. The voting logic for fire, flammable gas and toxic gas detectors will be
as per Loss Prevention Philosophy Doc. No. P8363-PB-400-O-0004, for “Zirku Fire & Gas System
Upgrade Project, P8363.

FEED stage Fire and Gas Cause and Effect will be updated to detail the actions with respect to Fire
and Gas detection within Train 5, New Substation Building (SS-116), New LER for Train 5 and 6 and
New Operator Cabin.

As part of PROJECT scope, where automatic action will be required in response to fire and gas
detection, a minimum of two detectors will be provided utilizing 2ooN voting logic, with both detecting
the fire/gas prior to initiation of automatic action. Some of the major actions and voting logic for
detectors are indicated below.

In 2ooN voting logic, if one detector is in fault condition and if N > 2, then this voting arrangement will
be degraded to be 2oo (N-1).

In 2oo2 voting logic, if one detector is in fault condition, then this voting arrangement will be degraded
to be 1oo1.

For inline mixer area, the existing F&G Philosophy and the existing cause and effect will be utilized
for any project scope modifications.

6.8.1 Fire Detection

The voting logic for Multiple IR fire detectors shall be as follows:

 A single detector (1ooN Voting logic) shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field within
the fire and gas zone

 Alarm at existing FGS operator station (HMI) in existing ZCC and existing Fire Station
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 43 of 67

 Common audible alarm & visual indication (fire alarm – process area) at New F&G
Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (fire alarm – process area) at New F&G
Auxiliary Console in new LER for Oil Train#5 & 6

 Any two detectors (2ooN Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Audible alarm & visual indication (confirmed fire) at Existing F&G Matrix Panel in existing
ZCC

 Common audible alarm & visual indication (fire confirmed- process) at New F&G Auxiliary
Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (fire confirmed- process) at New F&G Auxiliary
Console in new LER for Oil Train#5 & 6

 Activation of Deluge System of Fire Zone (Complete Train 5 is considered as a single


fire zone as per FERA Report)

 Start of Fire Water Pumps

 Initiation of ESD-2 without depressurization (Any depressurization of the system will be


manually activated by the operator).

The voting logic for linear heat detectors for transformers and cable cellar and fusible plugs for deluge
shall be as following.

 The linear heat detectors shall activate at 850 C. Linear heat detectors upon activation (1oo1
voting) shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field within
the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (fire confirmed – SS116) at New F&G Auxiliary
Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (fire confirmed – SS116) at New F&G Auxiliary
Console in new LER for Oil Train#5 & 6

 Audible alarm & visual indication (confirmed fire) at New F&G Matrix Panel (Cabinet
door-mounted) in Substation 116

 Electrical de-energization of affected transformer for transformer area LHDs

 The activation of deluge water spray system of transformers shall be local manual from the
deluge skid or remote manual from Auxiliary console at ZCC or LER and will not be activated
based on LHD.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 44 of 67

 Voting logic is not applicable to fusible plugs and linear heat detectors.

 The Pressure Low Signal by a Pressure Transmitter of pneumatic trim within the deluge skid, in
case of fusible plug detection shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field within
the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indications (fire confirmed - process and any deluge
activation) at New F&G Auxiliary Console in existing ZCC

 Audible alarm & visual indication (confirmed fire) at Existing F&G Matrix Panel in existing
ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indications (fire confirmed - process and any deluge
activation) at New F&G Auxiliary Console in new LER for Oil Train#5 & 6

 Activation of respective solenoid valve to open the deluge valve

 Start of Fire Water Pumps

 Initiation of ESD-2 without depressurization (Any depressurization of the system will be


manually activated by the operator).

 The Pressure High Signal by a Pressure Transmitter (downstream of deluge valve) within the
deluge skid, in case of operation of deluge valve shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field within
the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indications (fire confirmed - process and any deluge
activation) at New F&G Auxiliary Console in existing ZCC

 Audible alarm & visual indication (confirmed fire) at Existing F&G Matrix Panel in existing
ZCC

 Alarm at FGS operator station(HMI) in new LER

 Common Audible alarm & visual indications (fire confirmed - process and any deluge
activation) at New F&G Auxiliary Console in new LER

 Start of Fire Water Pumps

 Initiation of ESD-2 without depressurization (Any depressurization of the system will be


manually activated by the operator).

The voting logic for smoke detectors shall be as follows:

 A single detector (1ooN Voting logic) shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field
(building) within the fire and gas zone
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 45 of 67

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (fire alarm – process area for Operator Cabin
or fire alarm – new LER or fire alarm – SS116) at New F&G Auxiliary Console in existing
ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (fire alarm – process area for Operator Cabin
or fire alarm – new LER or fire alarm – SS116) at New F&G Auxiliary Console in new
LER for Oil Train#5 & 6

 Any two detectors (2ooN Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Audible alarm & visual indication (fire confirmed – new LER or fire confirmed SS116) at
New F&G Auxiliary Console in existing ZCC

 Audible alarm & visual indications (fire confirmed – new LER or fire confirmed SS116) at
New F&G Auxiliary Console in new LER for Oil Train#5 & 6

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Audible alarm & visual indication (confirmed fire) at New F&G Matrix Panel (Cabinet
door-mounted) in Substation 116 or LER for Oil Train#5 & 6 Add a note in the document -
"Per Company philosophy, on
 Shutdown of HVAC for affected building confirmed fire, Switchgear
isolation is done manually".

 Release doors though Access Control System (LER for Oil Train#5 & 6 or SS116)

 Activation of Inergen alarms and subsequent discharge of Inergen system within affected
room of building

 A single smoke detector shall be provided in HVAC Air Intake and Air Lock Room of LER for
detection of smoke ingress from plant area, for alarm purposes only.

 A single smoke detector shall be provided in HVAC Air Intake of Substation for detection of smoke
ingress from plant area, for alarm purposes only.

 A single smoke detector shall be provided in Operator Cabin in line with P8363 Project for alarm
purposes only.

 A single smoke detector shall be provided in Analyser Shelter for alarm purposes only.

6.8.2 Flammable Gas Detection

 Alarm setting for High Alarm for flammable gas detectors for general area coverage shall be set
at 20% LEL and High-High Alarm at 60% LEL.

 Alarm setting for point hydrogen (H2) gas detection in battery room shall be 20% LEL for High
alarm and 60% LEL for High-High alarm.

 Alarm setting for High Alarm for flammable gas detectors for HVAC air intakes of SS116 & LER
and Air Lock Room of LER shall be set at 10% LEL and High-High Alarm at 20 % LEL.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 46 of 67

 Upon High Alarm (10 % LEL, 1oo3), Flammable gas detectors installed in HVAC air intakes of
SS116 & LER and Air Lock Room of LER, shall close the damper of fresh air intake and put the
HVAC in a recirculation mode.

 A single HC gas detector in plant F&G Zone, 20 % and 60% LEL (1ooN Voting logic) shall
generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field within
the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (HC gas alarm – process area) at New F&G
Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common Audible alarm & visual indication (HC gas alarm – process area) at New F&G
Auxiliary Console in new LER for Oil Train#5 & 6

 Any two HC gas detectors in plant F&G Zone, 60 % LEL (2ooN Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Audible alarm & visual indication (confirmed gas) at Existing F&G Matrix Panel in existing
ZCC

 Common audible alarm & visual indication (HC gas confirmed – process area) at New
F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indications (HC gas confirmed – process area ) at New
F&G Auxiliary Console in new LER for Oil Train#5 & 6

 Initiation of ESD-2 without depressurization (Any depressurization of the system will be


manually activated by the operator).

 Electrical Isolation of Operator Cabin

 A single HC gas detector at HVAC Air Intake (SS116 or LER) or Air Lock Room of LER, 10 %
and 20% LEL (1oo3 Voting logic) shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the building
within the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (HC gas alarm – New LER or HC gas alarm
– SS116) at New F&G Auxiliary Console in existing ZCC
 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (HC gas alarm – New LER or HC gas alarm
– SS116) at New F&G Auxiliary Console in new LER for Oil Train#5 & 6
 HVAC in recirculation mode for affected building
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 47 of 67

 Any two HC gas detectors at HVAC Air Intake (SS116 or LER) or Air Lock Room of LER, 20 %
LEL (2oo3 Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (HC gas confirmed – new LER or HC gas
confirmed – SS116 ) at New F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indications ((HC gas confirmed – new LER or HC gas
confirmed – SS116) at New F&G Auxiliary Console in new LER for Oil Train#5 & 6

 Audible alarm & visual indication (confirmed HC gas) at New F&G Matrix Panel (Cabinet
door-mounted) in Substation or LER for Oil Train#5 & 6

 Shutdown HVAC

 Release doors though Access Control System (LER or SS116)

 Initiation of ESD-2 without depressurization resulting into Electrical Isolation of Project


buildings (LER and SS116). Any depressurization of the system will be manually
activated by the operator).

 A single HC Gas Detector shall be provided in Operator Cabin, for alarm purposes

 A single HC Gas Detector shall be provided in Analyzer Shelter, for alarm purposes only.

 A single H2 gas detector inside battery room, 20 % and 60% LEL (1oo2 Voting logic) shall
generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the building
within the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (H2 gas alarm – SS116 Battery Room) at New
F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (H2 gas alarm – SS116 Battery Room) at New
F&G Auxiliary Console in new LER for Oil Train#5 & 6

 Inhibit Charging

 Two H2 gas detectors inside battery room, 60 % LEL (2oo2 Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (H2 gas confirmed - SS116 Battery Room) at
New F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indications (H2 gas confirmed - SS116 Battery Room)
at New F&G Auxiliary Console in new LER for Oil Train#5 & 6
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 48 of 67

 Audible alarm & visual indication (confirmed HC gas) at New F&G Matrix Panel (Cabinet
door-mounted) in Substation

 Electrical Isolation of Batteries

6.8.3 Toxic Gas Detection

The toxic gas of interest in this project is H2S, because the facility processes crude with H2S.

The High Alarm for H2S gas detectors for general area coverage shall be set at 5 ppm and High-High
Alarm at 15 ppm respectively.

The High Alarm for H2S gas detectors for HVAC air intake of SS116 & LER and Air Lock Room of
LER shall be set at 5 ppm and High-High Alarm at 10 ppm respectively. Upon High Alarm, Toxic gas
detectors installed in HVAC air intake of SS116 & LER and Air Lock Room of LER, shall close the
damper of fresh air intake and put the HVAC in a recirculation mode.

 A single H2S gas detector in plant F&G Zone, 5 ppm and 15 ppm (1ooN Voting logic) shall
generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the field within
the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (H2S gas alarm – process area) at New F&G
Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (H2S gas alarm – process area) at New F&G
Auxiliary Console in new LER for Oil Train#5 & 6

 Any two H2S gas detectors in plant F&G Zone, 15 ppm (2ooN Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Audible alarm & visual indication (confirmed H2S gas) at Existing F&G Matrix Panel in
existing ZCC

 Common audible alarm & visual indication (H2S gas confirmed – process area ) at New
F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indications (H2S gas confirmed – process area) at New
F&G Auxiliary Console in new LER for Oil Train#5 & 6

 A single H2S gas detector at HVAC Air Intake (SS116 or LER) or Air Lock Room of LER, 5 ppm
and 10 ppm (1oo3 Voting logic) shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the building
within the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 49 of 67

 Common audible alarm & visual indication (H2S gas alarm – new LER or H2S gas
alarm – SS116) at New F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication ((H2S gas alarm – new LER or H2S gas
alarm – SS116) at New F&G Auxiliary Console in new LER for Oil Train#5 & 6

 HVAC in recirculation mode for affected building

 Any two H2S gas detectors at HVAC Air Intake (SS116 or LER) or Air Lock Room of LER, 10
ppm (2oo3 Voting Logic) shall generate:

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (H2S gas confirmed – new LER or H2S gas
confirmed – SS116 ) at New F&G Auxiliary Console in existing ZCC

 Alarm at FGS operator station(HMI) in new LER

 Common audible alarm & visual indications (H2S gas confirmed – new LER or H2S gas
confirmed – SS116 ) at New F&G Auxiliary Console in new LER

 Audible alarm & visual indication (confirmed H2S gas) at New F&G Matrix Panel (Cabinet
door-mounted) in Substation or LER

 Shutdown HVAC

 Release doors though Access Control System (LER or SS116)

 A single H2S Gas Detector shall be provided in Operator Cabin, for alarm only.

6.9 FIRE AND GAS MAPPING STUDY

Fire & Gas detector coverage shall be evaluated to confirm that the required detection criteria to
provide the required alarms and control action have been met. The purpose of detector coverage
assessment is to confirm that the selected detector layout complies with generally accepted industry
performance targets if the system is correctly installed, operated and maintained.

The detector layout shall be analyzed to determine how effective the proposed detector layout
detectors with the given voting logic will be in detecting an incipient hazard and initiating a specified
safety action. This analysis may reveal the need to improve coverage and / or reduce nuisance trips
die to hardware failures.

6.10 LOCATION AND INSTALLATION REQUIREMENTS OF FIRE AND GAS DETECTORS

Fire & gas detector location shall be optimised based on fire & gas mapping study and shown in F&G
layout drawings. Elevation at which these detectors shall be installed will be defined during F&G
study.

6.11 MANUAL ALARM CALL POINT

Manual Alarm Call Points (MACP) are currently installed in Satah Plant only. Other facilities in the
Zirku site do not have MACP; therefore provision of MACP is not envisaged in this project to maintain
consistency with the existing installation.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 50 of 67

MACP shall be installed near the exit doors of all buildings.

 MACP inside the building shall generate:

 Audible alarm & visual indications (sounders and fire beacons) locally in the building
within the fire and gas zone

 Alarm at Existing FGS operator station (HMI) in existing ZCC and existing Fire Station

 Common audible alarm & visual indication (manual alarm call point act – process area
for Operator Cabin or manual alarm call point act – new LER or manual alarm call point
act – SS116) at New F&G Auxiliary Console in existing ZCC

 Audible alarm & visual indication (confirmed fire) at New F&G Matrix Panel (Panel Door
Mounted) in Substation SS116 or LER for Oil Train#5 & 6

 Alarm at FGS operator station(HMI) in new LER for Oil Train#5 & 6

 Common audible alarm & visual indication (manual alarm call point act – process area
for Operator Cabin or manual alarm call point act – new LER or manual alarm call point
act – SS116) at New F&G Auxiliary Console in new LER for Oil Train#5 & 6

6.12 INTEGRATION WITH EXISTING F&G SYSTEM

New F&G system shall be based on an independent, stand-alone Invensys Triconix system and
connected to existing Plant Wide F&G system that was developed under a separate project (P8363)
by other Contractor.

Integration with existing F&G system (like existing ZCC, existing Fire station) will be reflected in the
cause and effect for the fire & gas detection (Doc. No. - A3-400-J-1255_001).

6.13 INTERFACE WITH NEW ESD SYSTEM

Interface with Train5 new system ESD (To activate ESD-2) already indicated in section 6.7 which will
be detailed out in the cause and effect for the fire & gas detection (Doc No. - A3-400-J-1255_001)
and OIL Train #5 & BOP Control System Architecture (Doc No- A3-401-J-0551_001 / 002)
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 51 of 67

7 ACTIVE FIRE PROTECTION

7.1 GENERAL

Fire protection systems, both active and passive, will be provided to control a fire event and minimize
escalation potential associated with it in order to facilitate safe escape and evacuation of personnel
from the impacted area and prevent damage to assets, critical plant equipment and / or structures.

The basic objective for active fire protection is to limit or prevent the escalation of a fire, to avoid risk
to life and to minimize asset damage until the source of hazard has been isolated.

The Active Fire Protection system shall be designed to fulfill the following:

 To Extinguish / control the fire at the early stage.

 Cooling adjacent plant and equipment exposed to thermal radiation

A single major fire occurrence at any given time is considered as the design basis for worst case FW
demand for fire fighting

This document lists the applicable codes and standards that are to be used for active fire protection
for PROJECT, and summarises their applicable requirements. Active fire protection shall mainly be
provided by automatically and manually operated fixed fire suppression systems, in conjunction with
portable and mobile fire-fighting equipment.

Following will be the minimum Fire Protection measures provided for new PROJECT facilities:

 Fire ring main;

 Hydrants and Fire Hose Cabinets;

 Locally operated monitors at grade for water or foam application, permanently connected to a 1.0
m3 capacity foam storage tank, with a minimum capacity of 360 m3/hr (1500USGPM). The
monitor nozzles shall be capable of varying the water flow pattern from straight jet to fog;

 Remotely operated elevated monitors for water or foam application, with a minimum capacity of
360 m3/hr(1500GPM) and the monitor nozzles shall be capable of varying the water flow pattern
from straight jet to fog;

 Water Deluge systems;

 Manual Foam Application by monitors for suppression of pool fire;

 Strategically placed hand held or wheeled fire extinguishers throughout the project facilities;
suitable for type A, B, and C fires; and

 Clean agent (Existing facilities at Zirku uses Inergen) fire extinguishing system for New
Substation Building and LER Building rooms.

Existing firewater network shall be extended to cover the PROJECT facilities and to ensure that
adequate firewater can be provided to fight a fire and cool adjacent process equipment and shall be
designed to meet the PROJECT requirements, ensuring the expected maximum firewater demand
will be delivered.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 52 of 67

A Fire & Explosion Risk Assessment (FERA) Report shall be prepared in the early stage of the project
to define the fire and explosion protection measures (active and passive fire protection, fire/ blast
walls etc.) required to mitigate fire and/or explosion hazards from the new facilities under this project
scope. FERA shall assess effects on personnel as well as assets and business risk. Also the hazards
from existing facilities to new facilities, as identified from different existing HSE studies, shall be
assessed and protection measures will be defined for the new project facilities.

The FERA study shall be used for reviewing/defining active and passive fire protection requirements.

Based on fire protection design, Fire Protection Performance Targets study will be performed for
PROJECT and report will be submitted for COMPANY approval.

FERA report shall identify Fire Zones for PROJECT facility. While performing FERA study, existing
fire zoning will be used as reference. FERA defined three new zones for PROJECT facility i.e.Train5,
New Electrical Substation Building (SS-116) and LER. Inline Mixer Equipment and project scope tie-
ins, will be considered as part of the existing fire zones. These Fire zones are created in order to
segregate hazards and limit the probability of escalation from one area to another. The extent of the
fire zone is determined by defining the boundaries based on acceptable level of thermal radiation in
case of fire and blast overpressure in case of a vapor cloud explosion.

Where existing facilities are modified within the PROJECT scope, site specific existing HSE or Loss
Prevention philosophies and guidelines will be applied for the design, including guidelines applicable
to the following aspects of safety engineering:

 Fire Zone

 Flammable and Toxic Gas Detection

 Fire Detection

 Active Fire Protection

 Passive Fire Protection

 Explosion Protection

Fire protection equipment shall be selected and installed based on hazards within each particular
zone.

7.2 FIRE PROTECTION SYSTEM DESIGN

7.2.1 Firewater Demand

Existing firewater network shall be extended to cover the new PROJECT facilities. Extension involves
predominantly new build within the unit and tie-in and extension of the existing firewater network.

Based on Existing Fire Water Pump Data Sheet, the two operating fire water pumps will deliver 150
% of rated capacity, 4050 m3/h @ head of 130 meter (12.7barg)

However Existing Fire water pump & driver adequacy report, concludes that as per performance tests
conducted for existing fire water pumps, electrical pump can be safely operated within the range of
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 53 of 67

120% of rated capacity (i.e. 1620 m3/h @ head of 160meter (15.6barg)) because the required motor
power is within the rated motor power. When two pumps will be operating at 120 %, 2 x 1620 m3/hr
i.e. 3240 m3/hr can be delivered safely.

The existing Zirku Facilities fire water main is designed for FW flow rate of 3,500 m3/hr (15,400 GPM).

As per API RP 2001, the maximum firewater flow rate for process areas handling gas or combustible
liquid should be 1140m3/hr (19000 l/min); however this flow rate is only valid if the firefighting is done
using only monitors and hose streams. This flow rate may be used only as a guide; however it will
not be applicable to this project as deluge system are provided.

The worst case fire water demand for the 5th Oil Train of the PROJECT shall be calculated to confirm
that the existing firewater supply is adequate to provide the required firewater to the unit tie-ins and
at required flow rate and pressure. The ring main for the 5th Oil Train shall be supplied from two
different isolatable sections of the existing FW ring main.

Section 6.2.1.2 of API RP 2001 provides guidance for determining water flow rates for process areas.
Where partial or total protection is provided by fixed water spray, sprinkler, or foam systems, the flow
rate should be the sum of the flow rates required for proper operation of the fixed systems, plus an
allowance for simultaneous operation of monitors and hose streams.

The worst case FW demand shall be calculated based on the assumption that only one fire event will
happen at any given time based on API guidance and industry practice.

As per FERA report, the basis for fire water demand calculation to be considered for PROJECT is
that all deluge systems in a Fire Zone shall be activated in case of fire involving any equipment in the
fire zone.

Based on Section 8.5.3.7 of NFPA15, supplemental water application from two hose streams
114m3/hr (500 GPM) shall be provided for all fire scenarios in oil train.

Based on Section 7.4.4.3.6 of NFPA15, supplemental water application from one hose stream 57
m3/hr (250 GPM) shall be provided for all fire scenarios in transformer yard.

Based on NFPA, API and industry practice, the FW demand calculation shall be based on the
combination of:

 FW demand for foam application for controlling/suppressing the fire. The foam application rate of
6.5 lpm/min/m2, provided by monitors, for pool fires in non-diked spill areas, shall be used as per
NFPA 11. Consideration will be given for one no. of 360 m3/h monitors for pool fire application.

 FW for cooling of nearby exposed equipment (fixed water deluge systems for oil train fire zone)

 FW requirement for a minimum of two hand held hoses of 114 m3/hr (500GPM) capacity (each
outlet having capacity of 57 m3/hr (250 GPM).

Firewater hydraulic calculations shall be performed updating FEED fire water network model for the
integrated fire water network including new and the existing system using latest version of Pipenet™
to ensure that the line sizes are adequate to deliver the required FW at the required pressure to all
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 54 of 67

users and to ensure that the FW pressure at the farthest hydrant in the new FW ring main is minimum
at 6.9 barg (100 psig).

7.2.2 Fire Water Application Rates

Minimum Water Application Rates for exposure protection of Desalter, Separators, Heat Exchangers
and Transformers as per NFPA 15, is provided in the table below. Detailed list of equipment provided
with Deluge Protection for the Project is captured in section 7.3.2 of this document.

Equipment/Scenario Application
Density

Extinguishment

Cable Trays and Cable Runs 015gpm/ft2


[6.1 (L/min/m2)]

Control of Burning

Pumps, compressors and related equipment that handle flammable liquids 0.50 gpm/ft2
or gases (shafts, seals, and other critical parts) [20.4 (L/min)/m2]

Flammable and Combustible Liquid Pool Fires 0.30 gpm/ft2


[12.2 (L/min)/m2]

Exposure Protection

Desalters, Separators, Heat exchangers 0.25 gpm/ft2


[10.2 (L/min)/m2]

Horizontal Structural Steel 0.10 gpm/ft2


[4.1 (L/min)/m2]

Vertical Structural Steel 0.25 gpm/ft2


[10.2 (L/min)/m2]

Cable Trays and Cable Runs (spill fire protection) 0.30 gpm/ft2
[12.2 (L/min)/m2]

Transformers 0.25 gpm/ft2


[10.2 (L/min)/m2]

Table 08–Fire Water Application Rates


BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 55 of 67

7.2.3 Firewater Mains

 Existing firewater network shall be extended to cover the new PROJECT facilities. Two Tie-ins
TP-151A/B and TP-153A/B will be executed on existing Fire water network to extend fire water
mains for PROJECT facilities. PROJECT facilities (i.e. Train 5, new buildings) shall be
surrounded by (looped with) fire water ring mains equipped with hydrants, monitors, hose reels,
deluge systems and isolation block valves. The looped piping including provision of isolation
valves shall ensure the supply of water from two different directions if a section of the fire water
main is taken out of service for maintenance.

 Fire water mains (ring and branches) shall be equipped with post indicator isolation valves (PIV),
so that any section of the grid can be taken out of service and the grid can still supply water
through adjacent sections to protect the installations. The isolation valves shall be of butterfly
type. A 4-way junction shall always be fitted with three valves, while a 3-way junction (a Tee)
shall be equipped with two valves.

 Fire water mains shall be installed underground to provide protection against physical damage
due to impact or an event. The fire water ring main system shall not run through the bund areas
of storage tanks or on top of bund walls.

 Fire water mains shall be provided with full-bore flushing valves and connections so that all
sections and dead ends can be properly flushed out. Flushing connections shall be sized for a
fluid velocity of not less than 3 m/s as per section 10.2 of NFPA 15.

 The capacity of fire water mains shall be based on the maximum demand. The maximum flow /
velocity in the system not to exceed 3.5 m/s.

 Sizing of distribution piping shall be determined in accordance with the hydraulic requirements of
the maximum probable fire water demand.

 Material selected for FW piping will be suitable for service in accordance with Piping Material
specification. The material of construction for underground (UG) FW ring main shall be GRE,
transition material starting from underground till upstream of deluge valve and isolation valves of
hydrants, monitor and hose reels shall be Cement lined Carbon Steel (CS), AG Wet piping for
deluge branches and isolation valves of hydrants, monitor and hose reels shall be Super Duplex
Stainless Steel (SDSS) and AG Dry Piping (downstream of deluge valve/elevated monitor valve)
shall be of Cu-Ni material.

 The FW distribution system shall be designed in accordance with NFPA 24.

7.2.4 Existing Fire Protection in BOP Area

New Inline mixer area will be located next to existing mixer. Furthermore, as part of PROJECT scope
existing Inert Gas system will be demolished and new Air receiver, Air Dryer units will be installed in
existing Unit-424. All these modifications will be performed within the existing plot area of Unit-424 &
Inline Mixer Area.

The adequacy of existing fire protection facilities shall be assessed for areas involving brownfield
modifications. The existing fire protection system drawings shall be utilized for the adequacy
assessment. Moreover, the site visit shall be conducted to confirm the actual site details.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 56 of 67

The adequacy assessment shall be conducted as part of fire water demand calculation (Doc. No.
P7564-CN-400-O-0003).

7.3 FIXED FIRE PROTECTION EQUIPMENT

Fire protection equipment data sheets and specification will be prepared ensuring that the equipment
is compatible with existing site connections and that the make and model used in the existing plant
is specified for sake of standardization. However, wherever it not feasible in terms of change in
technology and market availability etc., then CONTRACTOR shall select equipment from
COMPANY’s approved vendor list and this will be subject to approval of COMPANY.

7.3.1 Hydrants

Hydrants will be provided around the facility at regular intervals. Hydrant spacing will not exceed 60
m around building and utility areas and 30 m around the process units (New Oil Train5). FEED Stage
Fire Protection Equipment Layout will be reviewed and updated for EPC Stage.

Hydrants shall be provided with four 65mm (2 ½ in.) connections. At any given time, use of more than
2 hydrant outlets is not envisaged; hence the FW demand calculation is based on two outlets with
capacity of 114m3/hr (500 gpm) for hose allowances. Hydrant outlet shall be pressure regulating type
(4 X 2 ½” size valves with female coupling to BS336, complete with cap & chain). Hydrant outlets
shall be compatible with the hydrants currently installed on-site and the site fire brigade equipment.
The discharge capacity per hydrant valve outlet will be 57 m3/hr (250 GPM) as per NFPA 14, Section
7.10.3.1 at a discharge pressure of 6.9 barg (100 psig) as per NFPA 14, Section 7.8.2.1.

It is recommended that the hydrants will be selected of same make and model as installed in the
existing facilities for standardisation and ease of maintenance. However, wherever it not feasible in
terms of change in technology and market availability etc., then CONTRACTOR will select Hydrant
from COMPANY’s approved vendor list.

Concrete paved area shall be provided around monitors (minimum 2.5 m x 2.5 m) and hydrant posts
(2 m x 2 m) with safe drainage of leaking / spilled water from the equipment.

The hydrants and monitors shall be protected from vehicular impact and mechanical damage.

7.3.2 Deluge System

The terms "deluge system" and "water spray system" are equivalent. Fixed water deluge systems
are installed to provide cooling (Exposure protection) or fire intensity control (Control of burning). As
a general rule, these are not to be used to extinguish fires, except when these provide a mean to
apply foam to extinguish hydrocarbon pool fires. A deluge system consists of a number of spray
nozzles, always open, fitted onto a length of pipe (generally a ring), kept dry and in the deluge system,
the water flow is controlled by a (or a set of) deluge valve(s).

Deluge system should generally be provided to protect the equipment identified as part of FERA
study. Some of generic criteria for deluge protection requirement are follows:

 Process equipment including vessels and shell & tube heat exchangers, if isolatable HC liquid
inventory is greater than 5 m3. Deluge shall also be installed, regardless of liquid inventory, if
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 57 of 67

mobile fire-fighting means are not available or adequate or if unit layout does not allow for efficient
use of fire monitors.

 Pressure vessels which might be exposed to a significant fire and which are located where
adequate cooling cannot be provided from hose streams and monitors.

 Pumps meeting all the three conditions given below:


0
 Handling fluid above its Auto Ignition Temperature (AIT) or 40 F above its Flash Point, and

 Located in close proximity to other equipment(including adjacent pumps) or structures that


could be quickly damaged by the pump fire, and

 Located where protection by monitors or hose streams would be difficult or impractical.

Note-1: The pumps in HC service are canned type centrifugal pumps. The suction drum (can) of the pump
containing HC inventory is below grade. The suction and discharge connections with associated piping is
above grade only. Therefore, these pumps are not considered to be deluged based on FERA Report.

 Transformers which contain between 1,000 (1 MVA) and 6,000 Litre (8 MVA) oil depending on
their rating- Protection shall be provided by water spray on all exposed exterior surfaces as per
section 7.4.4 of NFPA 15.

 Pipe racks and cable trays, only within battery limits, if determined necessary after FERA. FERA
did not recommend any deluge system for Pipe rack and Cable trays.

As part of PROJECT scope, deluge system will be provided for the following equipment based on
FERA study,

Process Equipment Transformer

1. Inlet Feed Separator (401-V-501) 1. A7-TR-12

2. Gas Oil Separator (401-V-502) 2. A7-TR-22

3. First Stage Desalter (401-V-503) 3. A7-TR-13

4. Second Stage Desalter (401-V-504) 4. A7-TR-23

5. Feed Crude Pre Heater (401-E-501- 5. A7-TR-14


A~F)

6. Feed Crude Pre Heater (401-E-501- 6. A7-TR-24


G~M)
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 58 of 67

Process Equipment Transformer

7. Feed Crude Pre Heater (401-E-501- 7. A6-TRS-16


R~O)

8. Hot Oil Exchanger (401-E-502A/B)

Table 9–Equipment’s protected with Deluge System

Fixed deluge systems shall be designed using a recognized technique for the hydraulic analysis of
these systems. Hydraulic calculations shall be performed for each deluge system. The design of the
water spray system shall be in compliance with NFPA 15.While calculating FW flow rate for deluge
application, an allowance of 20% for wind losses and an additional 10% for flow balancing (hydraulic
balance losses) will be considered. A minimum pipe size of 1” for dry piping of deluge systems shall
be provided.

Deluge system shall be provided for respective protected equipment with all required elements
including deluge valve, associated piping, valves and fittings, including all associated
instruments/panels, air piping, SOVs, air bottles etc. as per project specification.

Each fire water deluge spray system shall be provided with two separate connections from two
different sections of the fire water distribution network sized for 100% of the demand. One of the
connections will be provided with automatic deluge valve and the other connection will be equipped
with a manually operated valve. As part of PROJECT, the automatic deluge valve and manually
operated valve connections will be routed from the same side of fire main and these connections will
be separated by a block/isolation valve.

Deluge valve shall be “fail open” type and its status should be line monitored on FGS panel. However
as part of PROJECT, basic deluge valve has no moving parts and does not require any supervision.
The deluge valves will preferably be located upwind or crosswind of the predominant wind direction
of the equipment being protected. Deluge valves shall be provided with by-pass arrangement with
isolation valves for each deluge valve in order to remove the deluge valve for maintenance / repair,
etc.

Deluge valves shall be elastomeric type. Manual butterfly valves in deluge system (isolation valves)
shall be UL listed or equivalent. Make and model of existing deluge valves should also be reviewed
during selection for standardization.

Automatic fire water deluge valve skids shall be located minimum 15 m away from the protected
equipment/area and the manual valve will be located at least 30 m away from the protected
equipment. If the manual valve cannot be located away, then thermal shield or any other form of
protection form thermal radiation shall be provided to ensure that the valve is approachable and
operable during a fire emergency.

Adequate arrangements shall be made to protect the deluge valve assembly from elements (sun,
sand and insects) by locating under a sunshade. The area around the deluge valve assembly should
be fully accessible under all weather conditions and shall have adequate provisions for drainage.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 59 of 67

The nozzles shall be UL (Underwriters Laboratories Inc.) listed, FM (Factory Mutual) approved or
meet any other equivalent approval. Nozzles shall be either "Type D" or "Projector Type". Nozzles
shall be of the medium velocity type (about 20 m/s) in order to provide the proper formation of water
droplets around protected equipment. As per NFPA 15 section 8.1.2, for medium-velocity type nozzle,
minimum operating pressure of any nozzle protecting outdoor hazards (equipment) shall be 20 psi
(1.4 bar). As per NFPA 15 section 12.3.3.1, for high velocity type nozzle, operating pressure at
hydraulically most remote nozzle shall be not less than 50 psi (3.4 bar).

Nozzles shall be designed to minimise plugging and shall be provided with only an orifice, a splitter
and a deflector. Nozzles with internal vanes or strainers are not recommended. The nozzle orifice
shall be at least 5 mm in diameter and the nozzle internal configuration shall allow easy cleaning.
Nozzles shall be made of brass or bronze (suitable for sea water application). Special care shall be
given to compatibility between the piping and nozzle metallurgy.

Spray nozzles shall be selected to achieve the density without dry spots with adequate coverage and
the nozzles shall be located within 600 mm from the equipment to be protected.

7.3.3 Monitors

Locally operated water monitors shall be located around the Train 5 process facilities to provide
exposure protection for equipment from thermal radiation. These monitors shall also be capable of
foam application and shall be permanently connected to a foam tank of 1.0 m3 capacity. The monitors
shall be so located that they remain accessible during a fire.

Elevated monitors shall be provided for Train 5 process facilities where obstructions prevent the
effective use of ground level monitors. Elevated monitors shall be supported on top level of Pipe rack
Structure. Elevated monitors shall be capable of being remotely operated from field at ground level.
Elevated monitor will be provided with foam connection for foam application when needed.

Elevated Monitors and the monitors at ground level shall be sized for a minimum flow of 360m3/hr
(1500USGPM).The nozzles shall be adjustable from straight stream to full fog mode.

Monitors shall be turret mounted, capable of 360 degree rotation, and lockable in any position.

FEED stage Fire Protection Equipment Layouts will be reviewed and updated for the Project.

7.3.4 Fire Hose Cabinets

Hose cabinets should be constructed to provide good air circulation inside and should be provided
with screening for protection against vermin. At least 6 in. clearance shall be provided between
swinging door bottom and the ground.

Special firefighting equipment such as breathing apparatus, protective clothing, forcible entry tools,
power tools, hand lights, etc. should not be stored in these cabinets.

One hose cabinet will be provided to be shared between two hydrants. Preferable location of Fire
Hose Cabinet shall be in the middle of two hydrants. The table below should serve as a guide for the
list of recommended equipment in the hose cabinet. The contents of project scope hose cabinets
shall be aligned with existing hose cabinets.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 60 of 67

Quantity Description

1 X 200 ft. (61 m) 2 1/2 in. (65 mm) lined hose

4 x 20 m 2 1/2 in. (65 mm) lined hose

1 X 100 ft. (30 m) 1 1/2 in. (38 mm) lined hose

2 Foam nozzles for 2 1/2 in. (65 mm) hose, with


aspirating foam tubing, foam proportioner etc.

2 Combination spray, solid stream, shutoff


nozzles for 1 1/2 in. (38 mm) hose

2 Combination spray, solid stream, shutoff


nozzles for 2 1/2 in. (65 mm) hose

1 Hydrant wrench

4 Spanners for 1 1/2 in. (38 mm) hose

4 Spanners for 2 1/2 in. (65 mm) hose

4 Spare hose washers (1 1/2 in. and 2 1/2 in. [38


and 65 mm])

1 Gated wye (2 1/2 in. by 1 1/2 in. [65 by 38 mm])

2 Adapter fittings (2 1/2 in. by 1 1/2 in. [65 to 38


mm])

Table 10–Fire Hose Cabinet Contents

7.3.5 Hose Reels

Control of small or medium-sized incipient fires can be accomplished by using live hose reels. For
optimum operation in fighting fires, 620–690 kPag (90–100 psig) nozzle pressure is desirable. Live
hose reels shall be equipped with 45 m (100 ft.) length of 38 mm (1½ in.) fire hose size and adjustable
fog nozzles of 38 mm (1½ in.) size. The nozzles shall be the adjustable, straight-stream-to-fog type
complete with ball shutoff valve.

Live hose reels shall be located such that Train5 process area can be reached by streams from two
hose reels, each with a 38 mm (1½ in.) hose size with 45 m (150 ft.) of hose length. The hose shall
be the non-collapsible suitable for at least 10.3Kg/cm2g (150 psig) working pressure and 41.4Kg/cm2g
(600 psig) bursting pressure.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 61 of 67

7.4 PORTABLE FIRE PROTECTION EQUIPMENT

7.4.1 Portable Fire Extinguishers

Fire extinguishers shall be provided for PROJECT facilities as a first line of defense to cope with fires
of limited size. Following type of fire extinguishers will be provided for PROJECT facilities. Size, type
and location shall conform to the applicable requirements of NFPA 10, Standard for Portable Fire
Extinguishers.

 Dry chemical powder extinguishers

 Carbon dioxide extinguishers

 Wheeled dry chemical powder extinguishers including protective cover

Portable and hand-held, ABC type, dry chemical powder fire extinguishers shall be provided in
process area(s), utility area(s), inside buildings and near transformers.

Wheeled, ABC type, dry chemical powder fire extinguishers shall be provided at strategic locations
for the process facilities of Train # 5.

Portable and hand-held, carbon dioxide fire extinguishers shall be provided for buildings.

7.4.2 Foam Units

The following number of Portable Foam Units will be provided for purpose of one-man operation in
the application of foam.

 New Oil Train#5 - 4Nos

 New Mixer Area - 1No

Foam Unit will be kept under sunshade. Foam concentrate storage (140L tank) will be chemically
resistant, suitable for storage of all kinds of foam concentrate storage. Foam tank will be provided
with inline variable educator with (0-6%) selector metering valve. Foam tank will be with fire hose,
foam branch pipe, frame and hose rack. Foam tank shall be UL Listed / FM approved.

7.5 FIRE PROTECTION FOR BUILDINGS

The Project buildings include:

 New Substation Building (SS-116),

 New Local Equipment Room Building and

 Operator Cabin

As part of PROJECT, the following fire protection measures shall be considered for Project buildings:

 Fire extinguishers;

Portable and hand-held, ABC type, dry chemical powder fire extinguishers shall be provided in
buildings.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 62 of 67

Portable and hand-held, carbon dioxide fire extinguishers shall be provided within the building
rooms having the potential for electrical fires.

 Clean Agent Fire extinguishing systems

(Inergen IG-541) for New Substation Building SS-116 and New Local Equipment Room

7.5.1 Clean Agent Fire Extinguishing System

A total flooding Clean Agent Fire Extinguishing system (e.g. Inergen IG-541) shall be provided for
new Substation Building (SS-116) and new Local Equipment Room in the following rooms.

Building Description Room Name Space / Void

Switchgear Room Room Void


Substation SS-116 Building
Battery Room Room Void

Local Equipment Room Room Void, Floor void

Room Void, Ceiling Void,


Local Equipment Room Control Office
Floor Void
Building

Room Void, Ceiling Void,


Telecom Room
Floor Void

Table 11–Building Rooms Protected with Clean Agent Fire Extinguishing System

The system shall have Central Bank Cylinder arrangement with 100% connected reserve cylinders
of the extinguishing media.

All cylinders shall be located in an enclosure adjacent to the protected building. The enclosure shall
protect the cylinders from exposure to direct sun and environmental elements (sand).

In the event of a fire and upon the activation of the fire detection system, the air intakes to the area
protected by total flooding gaseous systems shall be closed and the HVAC system shall shut down.

The fire extinguishing system shall be designed in accordance with the provisions of NFPA 2001,
“Standard on Clean Agent Fire-Extinguishing Systems”.

In occupied areas, the gaseous extinguishing system shall be equipped with a time delay and pre-
discharge alarm siren to provide personnel with advanced warning and time to vacate the area before
the gas is discharged into the room.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 63 of 67

8 PASSIVE FIRE PROTECTION

8.1 GENERAL PRINCIPLES

Passive protection should be preferred over active protection as it is inherently more reliable than the
latter. Active protection measures require routine testing and maintenance to ensure operability when
needed during an emergency. Also manual or automatic intervention is needed for its activation. On
the contrary, passive protection measures are low maintenance and do not require intervention to
initiate activation.

8.2 FIRE PROOFING

Fireproofing performs its function without relying on activation. The prime function of passive fire
protection is to retard the rate of temperature increase of a given substrate. The principle value of
fireproofing is realized during the early stages of a fire when efforts are primarily directed at controlling
the event. If fireproofing is not provided, ESDV in a fire zone may fail to operate, equipment supports
carrying heavy loads may collapse during this critical period and escalation may take place. If an
intense fire persists for a prolonged period, fireproofing may have no significant effect on the final
extent of property damage.

As a general rule, fire proofing is provided for protection against flammable liquid pool fires; however
fire proofing may also be considered if a credible exposure from jet fire is determined by Fire and
Explosion Risk Analysis. In general it is not cost effective to apply fireproofing on supporting steel
structures to protect against jet fires.

The justification for Passive Fire Protection (PFP) is based on assumptions that typical unprotected
structural members will lose about 50% of its strength at 5380C (10000F). As per API 2218, ½ inch
thick structural steel will reach 5380C (10000F) in approximately 6 minutes when exposed to gasoline
fire on one side. It is therefore necessary to protect part of the structure and/or some equipment in
order to meet the requirements regarding safety to life, protection of environment and assets. The
aim of PFP is to protect the equipment and structure until firefighting activities can be initiated. PFP
primarily protects personnel, escape routes, critical structure members, and equipment when
exposed to pool fire.

The performance of PFP (in terms of fire resistance), is determined as the period of time (in minutes)
during which the PFP protects the structure or the equipment. The PFP shall:

1. Ensure that the structure fulfils its load-bearing capacity throughout the fire exposure for the
defined time.

2. Prevent spread of flames and hot fumes throughout the fire exposure period.

3. Ensure that unexposed side of the partition does not reach unacceptable surface temperatures.

Fire rated walls shall also be provided to control the spread of fire between two sections of a building
that have different levels of criticality for continued operation of the facility.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 64 of 67

The results of the Fire and Explosion Risk Assessment Study will determine the supports and
structures requiring PFP.

Furthermore, Passive Fire Protection Schedule Report (Doc No- P7564-GD-428-O-0001) will be
developed based on API 2218 and FERA outcomes.

Based on Passive Fire Protection schedule, Passive Fire Protection Layouts will be updated for the
Project. Passive Fire Protection layout will indicate support of equipment, structures and ESDV valves
to be fire proofed.

8.3 EXPOSURE PROTECTION OF BUILDINGS

Based on FERA findings, building exterior walls shall be designed to withstand the thermal radiation
that they can be exposed to in the event of a fire in the adjoining area.

Fire rating for external and internal walls will be indicated in Technical Specification of Architectural
Building Material &Construction Works (Doc No-P7564-TS-400-A-0001) / Architectural drawing of
buildings.

Exterior walls of New Substation Building (SS-116) facing towards transformers and walls separating
transformers from each other shall be protected against exposure to outdoor transformer fires by
utilizing a combination of separation distances, fire rated walls and water spray system.

Transformers indicated in section 7.3.2 table will be protected by deluge system as per NFPA 15.

8.4 EXTENT AND DURATION OF FIRE PROOFING

Fire Potential Equipment will be identified as per API 2218. The API 2218 and FERA study shall be
used for defining passive fire protection requirements for PROJECT Scope Facilities.

Flammable liquid pools can collect on impermeable floor surfaces either at grade or on solid elevated
surface. Such surfaces can sustain a pool fire. As a general rule, for flammable liquid pool fires, up
to 12 m diameter from the potential source of leak, a passive fire protection from grade or solid
elevated surface to 9.0 m height shall be considered adequate to maintain stability and integrity of
the vertical structure members of the pipe rack and supports shall be fire proofed in accordance with
API 2218 to protect vessels, either horizontal or vertical.

When failure of structural members that support equipment has the potential to add fuel to escalate
the fire, fireproofing should be considered for the vertical and horizontal steel support members from
grade up to the highest level at which the equipment is supported.

Fireproofing shall be considered for steel saddles that support horizontal heat exchangers,
condensers, coolers, drums and receivers that have diameters greater than 750 mm (30 inches) if
the narrow vertical distance between the concrete pier and the shell of the vessel exceeds 300 mm
(12 inches).

The length of time during which a steel structure needs to maintain its integrity depends on the type
of plant, availability of fire-fighting services, and risk of escalation. The minimum protection time
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 65 of 67

against a hydrocarbon fire shall be based on the outcome of FERA. FERA report identified
fireproofing duration of 90 minutes for supports and structures.

In cases where structures cannot be cooled by water, increasing the fire resistance to a longer
duration shall be considered. Where effective water cooling is not feasible (e.g. due to the
configuration of the structure), the required duration of the PFP depends on the estimated time for
the fire to burn out or be extinguished.

Where significant flammable liquid inventories exist, consideration will be given to providing PFP to
supporting structures of vessels.

Cables used for activation of emergency systems e.g. F & G detection & alarm, shut down, blow
down, escape, evacuation and fire protection equipment shall be fire resistant type. Cables used for
normal loads shall be flame retardant type.

Pneumatic Instruments lines within a fire hazardous area will be constructed from Type 904L
Stainless Steel tubing and will not require fireproofing.

The ESD valve actuator should be fire-proofed for at least 30 minutes duration to provide enough
time for emergency isolation/depressurization.

The hydrocarbon fire test as defined in UL 1709 is applicable to all fireproofing systems provided on
steel supports and structures within processing facilities. This fire is more severe than the cellulose
type of fire which is usually referred to in building regulations.

Criteria of Fire Hazard scenario envelope (Based on API 2218), Passive fire protection requirements
and schedule of fire potential equipment will be detailed out in PROJECT document “ Passive Fire
Protection Schedule Report (Doc No- P7564-GD-428-O-0001). Fire Proofing Layouts showing fire
proofing zones shall be developed based on Passive Fire Protection Schedule.

9 BLAST OVERPRESSURE PROTECTION

Explosion protection shall be accomplished by the following design provisions:

 Segregating ignition sources from combustible / flammable inventories;

 Selecting appropriate electrical equipment to meet the requirements of electrical area


classification; and

 Providing adequate separation between areas where an explosion or fire is possible and other
process areas or buildings.

Based on FERA, the blast overpressure exposure to a building shall be used for design of buildings
to ensure that the building structure is capable of withstanding the overpressure to which it is
subjected. The building shall be reinforced, if needed, to protect the structure against the effects of
overpressure.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 66 of 67

10 EMERGENCY COMMUNICATION SYSTEM

10.1 GENERAL

The Telecommunications system shall be designed to provide continuous operation with no single
point of failure. The system's backup resources shall prevent communications impairment if a failure
should occur. The telecommunications system shall function efficiently under emergency conditions
as well as normal operations. Hence Telecommunication system power source shall be redundant
UPS with 24 hours of autonomy time.

The purpose of the Communication System is:

 To provide effective audible, and where needed, visual, internal communication to all personnel
under normal and emergency operating conditions;

 To notify personnel of hazardous or emergency operating conditions and change of status;

 To provide communications for rescue activities;

 To keep personnel informed of potentially hazardous work activities; and

 To provide external communication.

External communication between sites will be provided using the Hybrid IP-PABX through Etisalat.

Operator communication consoles in the main control room will provide access to the plant
telecommunications systems including telephone, Public Address (PA), and radio ETS. The design
and layout of the communications console and its integration with the other operator console
functions will be based on Telecom Design Basis.

Refer Telecommunication Basis of Design for additional design considerations (Doc No-P7564-BD-
540-T-001).

10.2 EMERGENCY TELEPHONE SYSTEM

The existing emergency telephone system is a special purpose telephone, alert and call locating
system and its purpose is to provide an extremely reliable emergency communication & signaling
system. It is used to address emergency voice messages to either all or selected areas of the Zirku
complex.

The emergency telephone system is one-way system (no dial), on which a call can be initiated only
from the outside emergency call post to the ZCC control room operator

The existing Emergency Telephone System (ETS) shall be extended to the 5th Oil Train area and
engineering design shall be done taking into account future requirement & provisions needed for the
6th oil train.

10.3 PABX and Telephone System

The existing telephone system is provided for normal voice communication to all areas of the facility.
BROWNFIELD PROJECTS
ZIRKU FACILITIES CAPACITY ENHANCEMENT (TRAIN-5)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING (EPC) WORK
PROJECT NO. P-7564

COMPANY Doc No. : Rev. No. : A4


P7564-GD-400-O-0001 LOSS PREVENTION PHILOSOPHY Date : 16/09/2019

Document Class: A Page: 67 of 67

Additional analogue outdoor and indoor IP telephones to the Hybrid IP-PABX shall be considered for
5th Oil Train area and engineering design shall be done taking into account future requirement &
provisions needed for the 6th oil train.

Power to the Hybrid IP-PABX, plant area network and telephone sets shall be supplied from the UPS.
(Note: all telecom systems shall be supplied from redundant UPS power with 24 hours of autonomy
time).

10.4 PUBLIC ADDRESS AND GENERAL ALARM SYSTEM

The existing Public Address and General Alarm (PAGA) system is installed to alert personnel of
hazardous or emergency conditions.

An integrated PAGA system is provided to make verbal announcements, in buildings where


personnel may be present during normal operation, and to annunciate audible alarm signals in all
parts of the plant. Flashing beacons for high noise level areas (i.e. above 85dBA) in addition to audio
alarms should be installed in plant areas.

The PAGA system shall be extended to the 5th Oil train area. The design shall ensure that the PAGA
system provides complete coverage to all areas of the installation where personnel have access in
the event of emergency; the PA announcements would advise all non-operations, personnel of the
emergency and proceed to their muster points or leave the plant area entirely. The public address /
general alarm (PAGA) system shall enable voice broadcasts to any selected area as well as to all
areas of the plant. Public address and general alarm systems shall be powered by
Telecommunication system power source which shall be redundant UPS with 24 hours of autonomy
time.

You might also like