You are on page 1of 9

Missouri University of Science and Technology

Scholars' Mine
International Conference on Case Histories in (1998) - Fourth International Conference on Case
Geotechnical Engineering Histories in Geotechnical Engineering

Mar 8th - Mar 15th

Foundations Performance of Large Diameter Tanks


J. L. M. Clemente
Bechtel Corporation, Gaithersburg, Maryland

A. Desai
Bechtel Corporation, Gaithersburg, Maryland

H. Senapathy
Bechtel Corporation, Gaithersburg, Maryland

L. W. Young Jr.
Bechtel Corporation, Gaithersburg, Maryland

Follow this and additional works at: http://scholarsmine.mst.edu/icchge


Part of the Geotechnical Engineering Commons

Recommended Citation
Clemente, J. L. M.; Desai, A.; Senapathy, H.; and Young, L. W. Jr., "Foundations Performance of Large Diameter Tanks" (1998).
International Conference on Case Histories in Geotechnical Engineering. 53.
http://scholarsmine.mst.edu/icchge/4icchge/4icchge-session01/53

This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International
Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright
Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact
scholarsmine@mst.edu.
265
Proceedings: Fourth International Conference on Case Histories in Geotechnical Engineering, St. Louis, Missouri,
March 9--12, 1998.

FOUNDATION PERFORMANCE OF LARGE DIAMETER TANKS

J. L. M. Clemente A. Desai, H. Senapathy, L. W. Young, Jr. Paper No. 1.18


Bechtel Corporation Bechtel Corporation
Gaithersburg, Maryland - USA - 20878 Gaithersburg, Maryland - USA - 20878

ABSTRACT

The paper presents a detailed case history of foundation performance of six 60-m diameter, 15-m high, floating roof fuel oil tanks and
six 96.8-m diameter, 20-m high, fixed roof process water tanks built for a large power plant. Tank walls were supported by concrete
ringwall footings. General subsurface conditions at the site are discussed, along with proposed site grading and the rationale for tank
foundation selection. Because vibro-replacement improvement of site soils had been used beneath settlement-sensitive structures.
there was skepticism regarding the decision to support the tanks on unimproved soils. To allay doubts about the adequacy of tank
foundation performance, a staged hydrotesting procedure and an extensive settlement monitoring program were developed and imple-
mented. The excellent tank hydrotesting results demonstrated that ground improvement was not needed due to the more settlement-
tolerant nature of the tanks.

KEYWORDS

Tanks, settlement, hydrotesting, floating roof, fixed roof

INTRODUCTION conditions, extensive analysis, and the more settlement-


tolerant nature of these tanks.
Twelve large-diameter tanks (six floating roof fuel oil tanks
and six fixed roof process water tanks) were erected in con- The following sections provide summary descriptions of the
nection with a five-unit, oil-fired power plant being built next tanks, site, and subsurface conditions; the tank foundation
to an existing power plant of similar size and layout. Vibro- selection strategy; development of the hydrotesting/settlement
replacement improvement of soils had been used for support of monitoring program; and the results of tank hydrotesting.
the adjacent existing plant and tanks and was a1so needed for
the new plant structures. Thus, vibro-replacement
improvement of the soils beneath these 12 new tanks was TANKS AND TANK FARM LAYOUT
perceived to be required as well. However, careful char-
acterization of subsurface conditions beneath the tanks and The six floating roof fuel oil tanks are 60 rn in diameter and 15
settlement analyses indicated that the tanks could be built m high and are located immediately south of the existing
without ground improvement. Available experience with tank power plant. The six fixed roof process water tanks are 96.8 m
hydrotesting further supported this conclusion. A compromise in diameter and 20 m high and are located east of the new
was reached that allowed the tanks to be supported on unim- power plant, several hundred meters north of the fuel oil tanks
proved ground, provided a comprehensive staged hydrotesting and immediately north of the existing power plant. The lay-
program with extensive settlement monitoring was developed outs of these two tank farms are shown on Fig. l, which also
and implemented. The tanks were then erected and hydro- includes information to be referenced in subsequent sections.
tested and excellent settlement performance was observed. It (It should be noted that Fig. I shows the layout of the two tank
was confirmed that vibro-rcplaccmcnt ground improvement farms together to save space in this paper. The tank farms are
was not needed, due to careful characterization of subsurface actually several hundred meters apart, as indicated above.)

Fourth International Conference on Case Histories in Geotechnical Engineering


Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
266
SITE AND SUBSURFACE CONDITIONS

The site is located on a coastline where the topography is gen-


erally flat and virtually no vegetation is present. The existing
grade is about El. -2m with respect to plant datum (-2m PD)
at both the process water and fuel oil tank farm areas. About
4.4 m of structural fill was placed in the process water tank
farm area to reach final grade at El. +2.4 m PD. Minor
grading was required in the fuel oil tank farm area to reach
final grade at El -1.8 m PD.

Subsurface conditions disclosed by SPT borings drilled at the


fuel oil tank farm area are illustrated by the typical subsurface
T1'11 profile shown on Fig. 2. Also included on Fig. 2 are typical
~_;_ _._ _1 _ --- _ BH 22 fuel oil tanks and final grade information. The stratigraphy
includes a 2-m thick upper layer of generally loose to medium
(a) Process Water Tank Farm dense, fine, silty sand underlain by about 2 m of generally soft
to medium stiff silts/clays. Another 4 m of silty sands are
' ' -r --- encountered beneath the clay layer on the western portion of
the fuel oil tank farm. Intermittent ledges of coralline lime-
stone are encountered in a generally dense sand matrix beneath
the silty sand (8 m depth) and silts/clays (4 m depth.) This
sand layer with coralline limestone is identified as the coral
layer on Fig. 2. SPT refusal was often encountered in the
coralline limestone, which was then cored. Ground water was
encountered at a depth of about 2 m below existing grade at
the time of drilling. Laboratory consolidation tests on repre-
sentative, undisturbed samples of the silt/clay layer disclosed
the following typical values: OCR = 2.3, CR = 0.21, RR =
0.03 and cv = 4.2 m 2/yr.

Subsurface conditions disclosed by SPT borings drilled at the


process water tank farm area are illustrated by the typical sub-
surface profile shown on Fig. 3. Also included on Fig. 3 are
typical process water tanks and final grade information. The
stratigraphy is similar to that encountered by the SPT borings
drilled at the fuel oil tank farm area, except that the coral layer
is consistently encountered at a depth of about 8 m below
grade. Ground water was encountered at a depth of about 2 m
below existing grade at the time of drilling. Laboratory con-
solidation tests on representative, undisturbed samples of the
silt/clay layer disclosed resu1ts similar to those at the fuel oil
!•• I tank farm area.
NOTES: I
.•~ ... T:w*f..nl~
ShoNI H~ il/1 DIII'II'N'II from '
l.ll:.,.,,....,. ...
- - - L.ccallorw al tt. .......
l'lgor. l Alld)
I
fDr SUl.urfKI l'rOfllll. TANK FOUNDATION SELECTION
I
LEGEND: '
eSptT!ORING
• TEST PIT
I When the existing plant and tanks were buill, the soils beneath
• PLATE LOAO TEST
all plant structures and tanks were improved with stone
PH
columns installed to the top of the coral layer. A similar
======lJ·
l=i' ground improvement program was developed for the new plant
structures, but ground improvement beneath the new tanks
(b) Fuel Oil Tank Farm generally was not deemed necessary. The case for not using
ground improvement beneath the more settlement-tolerant
tanks was made based on the careful characterization of sub-
Fig. 1 Process water and fuel oil tank farms surface conditions (summarized above), settlement calcula-
tions, available tank settlement criteria, experience with
Fourth International Conference on Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
5. ~--····· ·····~-:_..:.-:--:-.:. ···;.:...:.~··· .. . ... ·;..:...:._. ~ . ...... .5
00
c
FDT 6 F015 FOT 4
,_,w Q FOT7 . . • • . • • • • • I • • • • • • . 0
w RAD:EI. -I.Bm
~
N zE -5 .. ----~
lff;l :'?:: :: :::: ::: ~ - - .,., ~;; ~-,_:;--:.,:_-;-_-_~ "- '-.. - .:_: ..:..:
....-5
~ ol
"'l
"'~
·- '"' -10 ...
<(2
I!
11
11
IB
''11'
--- . ... -10
>:J 2?

"'"'
::r
Wf-
_j<( -15 ..
58
Jl
~

B
30
21
CORAL ,, ..........-15
" wo .. ···2J ~· :1)' " ' " " • •U21

~ f-
37
J8
•D !)
52
5l
77
"" z -20.... ~_7"'. ~1.,_. 46-·· ... ........-2C
"'...
-§, ~
"
" s -25...
-'
. ............-25

(]] ~
L
QJ 5 5
~
PWT 9 PWT 7 PVfT 5
QJ
Finish Grade [1. 2.4r1
~ E Q 0
~ BH-12 ·siR.UCtURi\L FILL. . BH:_·13 BH'-H
.,
'-'
~ -5. ~ .... ~ Y SAND
G
- l~
9 ..
..... -5
~
::?:
::0
8 SILTS AND CLAYS '15 "
13
~ -- -- . -- -- f---. . --
... --
... --
... --
... --. -10
"'~ f-
~
0
-1Q 2

,,"
27
-- . . -- .. 38.
27

" .
23 .•
"
""'"'"
26 -15
f- -15. .. 22 . . . ..... . . 20 . . .
z J5
CORAL
2B

""' "44
57 33
~
~
_J
(l_
-2G .. 46
7f "46· - 39· -20
""'
"(l
~
z
0
-25 . . . ..""
J7
.0
=-
... 20. . . . . !10 .
"
50
27
32. -25

" f-
" HO.,IZONTAL SCALE- METERS " -30
~
>
-30 7Q

~
..
' . . . ..
"
46. N
Fourth International Conference on_Jw
Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
w -35
""--
-35
"'_,
http://ICCHGE1984-2013.mst.edu
268
erecting and hydrotcsting tanks, and the development of a where: ui, ui·l> ui+l ::::; out-of-plane differential movement, in
comprehensive staged hydrotesting program with extensive mm, for three neighboring, equally
settlement monitoring. spaced tank shell points
L = distance, in mm, between equally
spaced points i, i-1, i+ 1
Tank Settlement Criteria
The maximum tolerable out-of-plane distortion is 1/450, or
The following tolerable settlement criteria were adopted as a 0~22 percent. For a 96.8-m (96,800-mm) diameter tank and
basis for evaluating tank performance during hydrotcsting. eight equally-spaced settlement markers, such as the process
These criteria are based on published literature (Rosenberg water tanks, the maximum tolerable value of ~Sop is 84 nun,
and Journeaux 1982) and have been used extensively for tank and for a 60-m (60,000-mm) diameter tank and eight equally-
settlement performance evaluation. spaced settlement markers, such as the fuel oil tanks, the
maximum tolerable value of ~Sop is 52 mm.
Shell Settlement. Uniform settlement of the concrete ringwall
footing is generally not used as a tolerable settlement criterion, Bottom Plate Settlement. Edge-to-center distortion is defined
because uniform settlements do not cause detrimental effects as the maximum difference in measured settlement between
to either the tank shell or bottom. Uniform settlement of the the center of the tank bottom over the radius of the tank, i.e.,
concrete ringwall footing can generally be accommodated by
providing flexible tanklpipe connections. Edge-to-center distortion = (Sc - SE)/R = ~SEcfR (3)

Planar tilt is defined as the difference in measured settlement where: SE = settlement under the edge of the tank, in
between two diametrically opposed points on the tank shell mm
divided by the diameter of the tank, i.e., Sc = settlement under the center of the tank, in
mm
Planar tilt= (S 1 - S2)/D = <l.S.,ID (1) R tank radius, in mrn
ll.SEC difference between Sc and SE = differential
where: St. S2 = settlement of two diametrically opposed settlement between the edge and center of
points of the tank shell, in mm the tank, in mm
D tank diameter, in mm
~So = difference between S1 and S2 = differential The maximum tolerable edge-to-center distortion is 1/50, or 2
settlement between two diametrically percent. For a 48.4-m (48,400-mrn) radius tank, such as the
opposed points of the tank shell, in mm process water tanks, the maximum tolerable value of
differential settlement (ll.SEcl is 968 nun, and for a 30-m
The maximum tolerable planar tilt is 1/200, or 0.5 percent. (30,000-mm) radius tank, such as the fuel oil tanks, the
For a 96.8-m (96,800-mm) diameter tank, such as the process maximum tolerable value of differential settlement (llSEc) is
water tanks, the maximum tolerable value of differential 600 mm.
settlement (ll.S 0 ) is 484 mm, and for a 60-m (60,000-mm)
diameter tank, such as the fuel oil tanks, the maximum
tolerable value of differential settlement (l.\S 0 ) is 300 mm. Settlement Analyses
When a perfect planar tilt occurs, all points along the concrete
ringwall footing remain on a plane with a slight tilt from the Settlement analyses were performed using the typical consoli~
horizontal. dation parameters previously described for the silt/clay layer,
and elastic parameters for the granular soils (including struc-
Out-of-plane distortion is illustrated in Fig. 4 (Rosenberg and tural fill to be placed in the process water tank area). Based on
Joumeaux 1982). If a perfect planar tilt of the tank occurs, a the SPT N-values, an elastic modulus of 17,500 kPa was
plot of the settlements along the perimeter of the tank would selected for the natural granular soils in the process water tank
result in the cosine-shaped curve shown in Fig. 4. When the area, and a value of 13,500 kPa was selected in the fuel oil
tilt is not perfect, points of the concrete ringwall footing move storage area. The elastic modulus of granular structural fill
away from the slightly tilted plane described in the previous was selected to be 22,500 kPa, based on previous experience.
paragraph. The result is that when settlements along the
perimeter of the tank are plotted, they do not fall on the Consolidation settlement analysis of the silt/clay layer was
cosine-shaped curve shown in Fig. 4. An out-of-plane performed using the TCON Version 4.99 software package
differential movement (u) described in Fig. 4 develops, and the (TAGA 1993) that allows the simulation of load application
out-of-plane distortion is defined as: with time.

Out-of-plane distortion= [u,- (u;~ 1 /2 + u,. 112)]/L =ll.So,IL (2)

Fourth International Conference on Case Histories in Geotechnical Engineering


Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
269
Actual Maximum Elevation I Minimum Settlement

Settlement Measurement
Point (Typical) ---..........
-------.. 8 2

3
1----+--- Reference Radius

Plan V1ew of Top of Shell _ / 5


Showing D1stort1on Due to
Out-of-Plane Tilt Towards
Settlement Measurement Actual Minimum Elevation I Maximum Settlement
Point No. 6

/'o<1-if------- True Cosine Cur.te


For Planar Tilt

Out-of-Plane Distortion
At Measurement Point 7

Observed Settlement

Fig. 4 Planar & out-of-plant tilt evaluation (Rosenberg & Journeaux 1982)

Analysis results indicated settlements of 55 rnrn at the edge Staged Hydrotesting Program
and 100 mm at the center of the fuel oil storage tanks at the
end of hydrotesting. Calculated settlements were 140 mm at The following staged hydrotesting procedure was developed
the edge and 260 mm at the center of the process water tanks and implemented:
at the end of hydrotcsting. The TCON analyses also indicated
that the settlements in the silt/clay layer would stabilize within Step 1 - Install settlement monitoring markers at eight equally
a short period of time (weeks rather than months). spaced locations along the perimeter of the tanks.

The calculated settlements would result in edge-to-center dis- Step 2 - Obtain the "zero-loading" reading of each of the
tortions much smaller than the maximum tolerable values pre- settlement monitoring markers.
viously described. The calculated settlement values were also
within the range of tolerable limits included in the authors' Step 3 - Fill tank to 50 percent capacity. Obtain one set of
database of tank settlement measurements during hydrotesting readings immediately before filling the tank, one set of
(Senapathy et a/. 1994 ).

Fourth International Conference on Case Histories in Geotechnical Engineering


Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
270
readings twice a week during filling, and one set of readings Fuel Oil Tanks
immediately after filling the tank to 50 percent.
The time vs. settlement curves for the eight settlement markers
Step 4- Hold the 50 percent load and monitor settlement daily. located along the sides and at the center of FOT #4 are shown
The duration of hold was to be determined based on the in Fig. 5.
settlement performance of the tank. It was estimated that the
50 percent load would have to be held for about I week. The data in Fig. 5 indicate that the maximum settlement at the
edge of FOT #4 was Ill mm and the minimum settlement was
Steps 5 and 6 - Similar to Steps 3 and 4, but for 75 percent 38 mm. The average settlement along the edge of the tank was
load. about 71 mm, which is larger than the predicted 55 mm but
well within tolerable limits. The data in Fig. 5 also show how
Step 7- Similar to Step 3, but for 100 percent load (full tank.) quickly the settlements stabilized after loading stages were
reached. Based on these results, the hydrotesting procedure
Step 8 - Hold the full load and monitor settlement daily for 2 was changed to allow holding the 100 percent load for a period
weeks and then twice a week thereafter. The duration of hold of no more than 2 weeks for the remaining fuel oil tanks.
was to be determined based on the settlement performance of
the tank. It was estimated that the load would have to be held Figure 6 shows a plot of settlements for equally spaced
for about 6 weeks. markers located along the perimeter of FOT #4 and PWf #4 at
the end of hydrotcsting under 100 percent load. The figure
Settlement measurements were also made under the center of includes a continuous cosine-shaped curve that would
the first fuel oil tank (FOT #4) and the first process water tank represent a perfect tilt of the tank and actual settlement
(PWf #4) to be hydrotested. measurements that are represented by hollow squares. The
vertical distances between the hollow squares and the
continuous curve represent out-of-plane differential
SETILEMENT MONITORING RESULTS settlements at the settlement marker locations.

Detailed settlement monitoring result.;; arc presented for FOT The data in Fig. 6 indicate that the maximum out-of-plane
#4 and POT #4, i.e., the first fuel oil tank and the first process differential settlement for FOT #4 was about 23 mm. The
water tank to be hydrotested. Changes to the hydrotesting pro- maximum out-of-plane distortion was about 1/2,100, or 0.047
cedure based on the settlement behavior of FOT #4 and PWT percent. This value is about five times smaller than the 0.22
#4 are discussed. Remarks are offered regarding the settle- percent allowable.
ment behavior of the remaining tanks.

Time (days)

0
5 30 35 40 45

-20

-40

e
.s -60
E
~ --¢--#113
E --£:r#114
~
E -80
-6-#115
~

"' -e-#116 to 75%


--+-#161
·1 00
----#162
_.._#163 Hold
--#164
-120
_._Center at 75%
Load •• ..I....
0 10tl 100 %~~~dat
·140L---------------------------------------------------~~~~~~----~

Fig. 5 Time vs. settlement curve for fuel oil tank No. 4
Fourth International Conference on Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
271

.,
c F 0 T t 4
'0 -' - co Bin e c u ·~ .. 6 P W Tf 4
'w ' eosin• c u r • •

_.,
"
•" ·"
ffi
"~
~
·"
-

1---
~-------
-~
~
i

'

.
----
;!;/
-v v
---------

"~
w
>
-1 0 Q

-------------------
. _, 2 0 ~--~-.;__
... -
' '
-
-i .-----;;-
w - I I _____ ...,

-1.0
-~----~-4-
-I - - - A
- - - - I'
-1 eo
'" 13S
ANGLAil DISTANCE
tao 225
degrooo '" ,"

Fig. 6 Out-of-plane distortion

The maximum planar tilt for FOT #4 was 69 mm, which at the center of the tank was damaged while filling the tank to
corresponds to about 1/870 or 0.12 percent. This value is 50 percent capacity. Also, the holding period at 50 percent
more than 4 times smaller than the allowable. loading did not fully stabilize before the tank was filled to 75
percent capacity.
Figure 7 shows a plot of settlements of two points on the
perimeter where maximum and minimum edge settlements The data in Fig. 8 indicate that the maximum settlement at the
were measured, as well as the center of tank settlement for edge of PWT #4 was 154 mm and the minimum settlement
FOT #4 and PWT #4. The data in Fig. 7 indicate that the was 119 mm. The average settlement along the edge of the
maximum edge-to-center differential settlement for FOT #4 tank was about 136 mm, which is almost identical to the
was 87 mm. The maximum edge-to-center distortion was predicted 140 mm and well within tolerable limits. The data in
about 11870, or 0.29 percent. This value is more than 6 times Fig. 8 also show how quickly the settlements stabilized after
smaller than the allowable. the 75 percent and 100 percent loading stages were reached.
Based on these results, the hydrotesting procedure was
The settlement behavior of the remaining fuel oil tanks was changed to allow holding the 100 percent load for a period of
similar to that of FOT #4. no more than 2 weeks for the remaining process water tanks.

The data in Fig. 6 indicate that the maximum out-of-plane


Process Water Tanks differential settlement for PWT #4 was 13 mm at the southern
side of the concrete ringwall footing. The maximum out-of-
The time vs. settlement curves for the eight settlement markers plane distortion was about 11400, or 0.025 percent. This value
located along the sides and at the center of PWT #4 are shown is more than 8 times smaller than the allowable.
in Fig. 8. It can be observed that the settlement marker placed

F0 TI 4
T
_, 1"----
~
~
w
);;
~ ·1 0 0
5
0
z 1---
,..
0

·l 50

-- ---
w
>
w
"
~ --- -- --
w ·2 0 0 1------------~-+------"-',__,_____
- - -------~~--=-'==----+------~---1

·2 50
0.2 5 0 5 0 '7 5
RATIO OF iDIAMETAIC DISTANCE ALONG TANK·BASE)/OIAMETER

Fig. 7 Center·to-edge distortion


Fourth International Conference on Case Histories in Geotechnical Engineering
Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu
272
Time (days)
0
20 30 40

-20

-40

-60 Load to 50%.


"E
£.
~.,
E
•E
.. -8 0
-Q-#2
----tl.--#3
! ·1 00

-120
--·5
--e--.4

---··
--.--.7
-140
--•a
------ C en Ia r

-1 6 0

Fig. 8 Time vs. settlement curve for process water tank No. 4

The maximum planar tilt for PWT #4 was 23 mm, which served as the basis for the foundation selection strategy for 12
corresponds to about 1/4,400 or 0.023 percent. This value is large diameter tanks. The available data and rationale indi-
more than 22 times smaller than the allowable. cated that the tanks could be built without the then-perceived
notion that ground improvement would be required. The tanks
The center-of-bottom-plate settlement shown in Fig. 7 was were erected and hydrotcsted without using ground improve-
calculated based on the settlement analysis results and edge ment, and excellent settlement performance was observed. It
settlements shown in Fig. 8 (the settlement marker at the center was confirmed that vibro-replacement ground improvement
of the bottom plate was damaged, as shown by readings on was not needed, due to the more settlement-tolerant nature of
Fig. 8). The data in Fig. 7 indicate that the maximum edge-to- these tanks.
center differential settlement for PWT #4 was 94 mm. The
maximum edge-to-center distortion was about 1/515, or 0.19 REFERENCES
percent. This value is more than 10 times smaller than the
allowable_ Rosenberg, P_, and N. L. Journcaux [1982]. "Settlement
limitations for cylindrical steel storage tanks." Canadian
The settlement behavior of the remaining process water tanks Geotechnical Journal, Ottawa, Canada, 19:232-238.
was similar to that of PWT #4, except that edge settlements of
slightly more than 200 mm were observed for PWTs #7, #8 Senapathy, H., J_ Davie, and L. W. Young, Jr. [1994]_
and #9. However, maximum planar tilts, out-of-plane "Performance of a steel tank founded on a marine clay." Proc.
differential settlements, and distortions remained well below of Settlement '94, ASCE Geotechnical Special Publication No.
tolerable limits. 40, New York, Vol. I, pp. 830-84 L

TAGA [1993]_ TCON Version 4.99 - Consolidation settle-


CONCLUSIONS ment analysis software, Lafayette, California.

Careful characterization of subsurface conditions, detailed


settlement analyses, experience with tank hydrotesting, and the
development of an acceptable staged hydrotesting procedure

Fourth International Conference on Case Histories in Geotechnical Engineering


Missouri University of Science and Technology
http://ICCHGE1984-2013.mst.edu

You might also like