PT.

ANUGERAH BARA KALTIM


Coal Mining

REKAP JAM KERJA MF 380 DI AREA PIT 12 KELAP BARAT


Periode : 01 October 2017 - 31 October 2017
RPM
tanggal shift Type code num jam start jam stop stand by jam start jam stop Break Down jam start jam stop Running hm awal hm akhir tot remark ACTUAL MAX by Kontrak
1-Oct 1 Pump MF 380 - 7:00 19:00 12.00 - 8,786.30 8,786.30 - Break Down / pipa pecah
1-Oct 2 Pump MF 380 - 19:00 7:00 12.00 - 8,786.30 8,786.30 - Break Down / pipa pecah
2-Oct 1 Pump MF 380 - 7:00 19:00 12.00 - 8,786.30 8,786.30 - Break Down / pipa pecah
2-Oct 2 Pump MF 380 - 19:00 7:00 12.00 - 8,786.30 8,786.30 - Break Down / pipa pecah
3-Oct 1 Pump MF 380 - 7:00 11:00 4.00 11:00 19:00 8.00 8,786.30 8,794.30 8.00 running ( 7:00 - 11:00 stand by / pipa pecah) 1345 1800
3-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,794.30 8,806.30 12.00 running 1345 1800
4-Oct 1 Pump MF 380 - 7:00 19:00 12.00 - 8,806.30 8,806.30 - Break Down / pipa pecah
4-Oct 2 Pump MF 380 - 19:00 7:00 12.00 - 8,806.30 8,806.30 - Break Down / pipa pecah
5-Oct 1 Pump MF 380 11:00 13:00 2.00 - 7:00 19:00 10.00 8,806.30 8,816.30 10.00 running (11:00 - 13:00 stand by P2H) 1390 1800
5-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,816.30 8,828.30 12.00 running 1390 1800
6-Oct 1 Pump MF 380 9:00 11:00 2.00 - 7:00 19:00 10.00 8,828.30 8,838.30 10.00 running (9:00-11:00 stand by/low fuel) 1400 1800
6-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,838.30 8,850.30 12.00 running 1400 1800
7-Oct 1 Pump MF 380 - 12:00 14:00 2.00 7:00 19:00 10.00 8,850.30 8,860.30 10.00 running (12:00-14:00 breakdown/service) 1400 1800
7-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,860.30 8,872.30 12.00 Running 1400 1800
8-Oct 1 Pump MF 380 - - 7:00 19:00 12.00 8,872.30 8,884.30 12.00 Running 1400 1800
8-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,884.30 8,896.30 12.00 Running 1400 1800
9-Oct 1 Pump MF 380 10:00 11:00 1.00 - 7:00 19:00 11.00 8,896.30 8,907.30 11.00 running (pukul 10:00- 11:00 P2H) 1400 1800
9-Oct 2 Pump MF 380 - - - - time sheet g nyambung 1400 1800
10-Oct 1 Pump MF 380 9:00 10:00 1.00 - 7:00 19:00 11.00 8,907.30 8,918.30 11.00 Running 1400 1800
10-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,918.30 8,930.30 12.00 Running 1400 1800
11-Oct 1 Pump MF 380 12:00 19:00 7.00 - 7:00 12:00 4.00 8,930.30 8,934.30 4.00 Running (pukul 12:00-19:00 stand by / swapantau) 1400 1800
11-Oct 2 Pump MF 380 19:00 7:00 12.00 - 8,934.30 8,934.30 - stand by / swapantau
12-Oct 1 Pump MF 380 19:00 7:00 12.00 - - 8,934.30 8,934.30 - stand by / intruksi ABK
12-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,934.30 8,946.30 12.00 running 1400 1800
13-Oct 1 Pump MF 380 - 7:00 19:00 12.00 - 8,946.30 8,946.30 - Break down (problem injektor)
13-Oct 2 Pump MF 380 - 19:00 7:00 12.00 8,946.30 8,946.30 - Break down (problem injektor)
14-Oct 1 Pump MF 380 - 7:00 19:00 12.00 - 8,946.30 8,946.30 - Break down (problem injektor)
14-Oct 2 Pump MF 380 - 19:00 7:00 12.00 - 8,946.30 8,946.30 - Break down (problem injektor)
15-Oct 1 Pump MF 380 - 7:00 19:00 12.00 8,946.30 8,946.30 - Break down (problem injektor)
15-Oct 2 Pump MF 380 - 19:00 7:00 12.00 8,946.30 8,946.30 - Break down (problem injektor)
16-Oct 1 Pump MF 380 - 7:00 9:00 2.00 9:00 19:00 10.00 8,946.30 8,956.30 10.00 Running 1500 1800
16-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,956.30 8,968.30 12.00 Running 1500 1800
17-Oct 1 Pump MF 380 - - 7:00 19:00 12.00 8,968.30 8,979.30 11.00 Running 1500 1800
17-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 8,979.30 8,991.30 12.00 Running 1500 1800
18-Oct 1 Pump MF 380 - - 7:00 19:00 12.00 8,991.30 9,002.30 11.00 Running 1500 1800
18-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 9,002.30 9,014.30 12.00 Running 1500 1800
19-Oct 1 Pump MF 380 - - 7:00 19:00 12.00 9,014.30 9,025.30 11.00 Running 1500 1800
19-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 9,025.30 9,037.30 12.00 Running 1500 1800
20-Oct 1 Pump MF 380 - - 7:00 19:00 12.00 9,037.30 9,049.30 12.00 Running 1500 1800
20-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 9,049.30 9,061.30 12.00 Running 1500 1800
21-Oct 1 Pump MF 380 8:00 10:00 2.00 - 7:00 19:00 10.00 9,061.30 9,071.30 10.00 Running (pukul 8:00-10:00 P2H) 1500 1800
21-Oct 2 Pump MF 380 - - 19:00 7:00 12.00 9,071.30 9,083.30 12.00 Running 1500 1800
22-Oct 1 Pump MF 380 - - 7:00 19:00 12.00 9,083.30 9,093.30 10.00 Running (pukul 8:00-10:00 P2H) 1500 1800
22-Oct 2 Pump MF 380 - 19:00 7:00 12.00 - 9,093.30 9,093.30 - Break down (penyambungan pipa)
23-Oct 1 Pump MF 380 11:00 19:00 8.00 7:00 11:00 4.00 9,093.30 9,097.30 4.00 Running(pukul 12:00 - 19:00, intruksi dari PT. ABK persiapan proper) 1800
23-Oct 2 Pump MF 380 19:00 12:00 17.00 - 9,097.30 9,097.30 - Stand By intruksi PT. ABK (Persiapan Proper) 0
24-Oct 1 Pump MF 380 7:00 12:00 5.00 - 9,097.30 9,097.30 - Stand By intruksi PT. ABK (Persiapan Proper) 0
24-Oct 2 Pump MF 380 19:00 12:00 17.00 - 9,097.30 9,097.30 - Stand By intruksi PT. ABK (Persiapan Proper) 0
25-Oct 1 Pump MF 380 7:00 14:00 7.00 14:00 19:00 5.00 9,097.30 9,102.30 5.00 Running (pikul 7:00 - 14:00 stand by / Proper) 1500 1800
25-Oct 2 Pump MF 380 - 19:00 7:00 12.00 9,102.30 9,114.30 12.00 Running 1500 1800
26-Oct 1 Pump MF 380 - 7:00 19:00 12.00 9,114.30 9,125.30 11.00 Running 1500 1800
26-Oct 2 Pump MF 380 - 19:00 7:00 12.00 9,125.30 9,137.30 12.00 Running 1500 1800
27-Oct 1 Pump MF 380 - 7:00 19:00 12.00 - 9,137.30 9,137.30 - Break down (Low Power)
27-Oct 2 Pump MF 380 - 19:00 7:00 12.00 - 9,137.30 9,137.30 - Break down (Low Power)
28-Oct 1 Pump MF 380 7:00 19:00 12.00 - 9,137.30 9,137.30 - No Time Sheet
28-Oct 1 Pump MF 380 - 19:00 7:00 12.00 9,137.30 9,149.30 12.00 Running 1300 1800
29-Oct 1 Pump MF 380 16:00 19:00 3.00 7:00 15:00 8.00 9,149.30 9,157.30 8.00 Running (pukul 16:00 - 19:00 stand by Low Fuel & opt. change shift) 1800
29-Oct 2 Pump MF 380 19:00 7:00 12.00 - 9,157.30 9,157.30 - stand by : opt. change shift)
30-Oct 1 Pump MF 380 7:00 10:00 3.00 10:00 19:00 9.00 9,157.30 9,166.30 9.00 Running 1300 1800
30-Oct 2 Pump MF 380 19:00 7:00 12.00 9,166.30 9,178.30 12.00 Running
123.00 188.00 398.00 392.00
9.00 383.00
Keterangan : -- Total Jam Running 392.00 Bakungan, 06 November 2017
-- Total Jam Stand By 123.00 PT. SIS PT. RCI PT. ABK
-- Total Jam Break Down 188.00
-- Total Jam Test Pump 0.50
-- Total Jam P2H 1.00
-- Total Jam HM Awal - HM Akhir 392.00
Total Jam Pemakaian Pompa MF 380 ( _______________ ) Doan Iskandar Kris Sugito Darmoko
Project Manager Mine Manager