You are on page 1of 1

Komplek Ruko Green Village, Blok V3, No.

12, Sukaluyu, Teluk Jambe Timur


Karawang 41361, Jawa Barat, Telp: 021-31719551, 083875238328
Email : muliasuksesteknik@yahoo.com

To :
PT. TOYOTA MOTOR MANUFACTURING INDONESIA QUOTATION Date : 23 Oktober 2023
Jl. Permata Raya Lot DD1, KIIC No : 324/QUO-MST/X/2023
Karawang, 41361 Attn : Mr. Widjarnarko
Fax : (021) 8904228, 6521642
Telp : (021) 8904222, : Mr. Ronny Pramulya
Fax : (0267) 647160
: Mr. Deny Surya Yudha
: Mr. Sutardi
PROJECT NAME : PANTRY & TEMPAT WHUDU MUSHOLA : Mr. Supriyanto
LOCATION : CONTROL ROOM UTILITY TMMIN KP#1

According to your requirement, we would like to submit our offer with the following :
NO DESCRIPTION QTY UNIT U'PRICE T'PRICE
I PREPARATION
Survey 1.00 lot 200,000 200,000
Safety Equitment & Tool 1.00 lot 500,000 500,000
Safety Activity & Anzen Leader 1.00 lot 1,000,000 1,000,000
Cleaning During Contruction 1.00 lot 800,000 800,000
Mob Demob & Transfortasi 1.00 lot 1,000,000 1,000,000
Scafollding Set 1.00 lot 500,000 500,000
SubTotal : 4,000,000
II MATERIAL
1 Besi Beton M 10 5.00 Bt 148,000 740,000
2 Besi Beton M 8 5.00 Bt 93,000 465,000
3 Besi Behel M 12 5.00 Bt 148,000 740,000
4 Pasir 5.00 colt 350,000 1,750,000
5 batu Split 1.00 colt 350,000 350,000
6 Semen Tiga Roda 15.00 sak 82,000 1,230,000
7 Papan Cor 6.00 lbr 38,000 228,000
8 kayu Kaso 4 x 6 2.00 ikat 60,000 120,000
9 Bata Hebel 7,5 cm 2.00 M³ 850,000 1,700,000
10 M.U Hebel 3.00 sak 178,000 534,000
13 Granite 60 x 60 meja Dapur Roman 3.00 Dus 403,400 1,210,200
14 Granite 60 x 60 cm Dinding Dapur Roman 6.00 Dus 403,400 2,420,400
15 Pipe pvc 1" AW 3.00 Bt 152,400 457,200
16 Pipe 1/2" aw 4.00 Bt 86,000 344,000
16 Fitting Pvc aw 1.00 lot 500,000 500,000
17 Granite Lantai Dapur Roman 4.00 Dus 403,400 1,613,600
19 Kramic Lantai Tempat Whudu Roman 3.00 Dus 252,000 756,000
20 Kramic Dinding Tempat Whudu Roman 4.00 Dus 268,000 1,072,000
21 Kran Air T23B13 TOTO 2.00 set 412,500 825,000
22 Kichen se Dapur Atas (Plywood & HPL) 1.00 M¹ 1,950,000 1,950,000
23 KIchen set Dapur Bawah Rak Piring (Plywood & HPL) 1.50 M¹ 1,950,000 2,925,000
24 Cat Dulux Weathershild 2,5 kg 2.00 kl 325,000 650,000
22 Valve / Stop Kran 1.00 set 375,000 375,000
23 Stop kontack Listrick 3.00 Titik 275,000 825,000
SubTotal : 23,780,400
III CONSUMABLE
3 Ember Aduk 3.00 pcs 35,000 105,000
4 Pengki 2.00 pcs 35,000 70,000
5 Mata Gerinda Cutting 4" 5.00 pcs 8,000 40,000
6 Mata Gerinda Beton 4" 1.00 pcs 268,000 268,000
7 Kawat Bendrat 3.00 kg 45,000 135,000
8 Rol,Kuas Cat,Bak Cat 1.00 lot 200,000 200,000
9 Sealent 5.00 pcs 74,000 370,000
10 Isolasi 2.00 pcs 25,000 50,000
11 Plastick Sheet 2.00 rol 175,000 350,000
11 Kaca mata safety 3.00 pcs 35,000 105,000
12 Karung 20.00 pcs 9,000 180,000
13 Kain Majun 10.00 kg 25,000 250,000
14 Benang & Selang Timbang 1.00 lot 100,000 100,000
15 Paku Besi 5.00 kg 47,500 237,500
SubTotal : 2,460,500
IV DEMOLIST WORK
1 Bobok Dinding Toilet 1.00 lot 1,500,000 1,500,000
2 Buang Puing Bobokan 1.00 lot 750,000 750,000
SubTotal : 2,250,000
V INSTALATION WORK
1 Pebesian , Bikisting Cor & Install Granite Meja Dapur 1.00 lot 2,000,000 2,000,000
2 Install Granite Lantai & Dinding Dapur 1.00 lot 1,750,000 1,750,000
3 Pasang Bata Hebel & Cor Tempat Whudu 1.00 lot 1,500,000 1,500,000
4 Install Kramic Lantai & Dinding Tempat Wudhu 1.00 lot 1,750,000 1,750,000
5 Install Pipa Air & Conetion 1.00 lot 500,000 500,000
6 Finishing Perapian & pengecatan 1.00 lot 750,000 750,000
SubTotal : 8,250,000

Total : 38,280,400
overhead 10% : 3,828,040
Grand Total : 42,108,440
Rounded : 42,100,000
Condition :
1. Delevery time : ASAP
2. Price doesn't include tax ( PPN 10% )
3. Payment : 2 week After delevery completed