You are on page 1of 221

Study of Electrical Usage and Demand at the

Container Terminal





E\


7KDQK.KDQK7UDQ %(QJ06F 











6XEPLWWHGLQIXOILOPHQWRIWKHUHTXLUHPHQWVIRUWKH

GHJUHHRI'RFWRURI3KLORVRSK\












'HDNLQ8QLYHUVLW\

-XO\






















To Tam, Matthew and Chloe



Acknowledgements

I am particularly indebted to my principal supervisor Professor Alfred Deakin

Professor Saeid Nahavandi for his constant guidance and support throughout this

PhD. I am very grateful for his insights, assistance, patience and support over the last

few years. This thesis would not be completed without his encouragement and

support.

I also would like to thank my associate supervisor Dr. Doug Creighton for the

valuable guidance and advice he provided me during the course of my PhD.

I would especially like to thank Robert Reid of Robert Reid and Associates, a mentor

and colleague who arranged for permissions to collect data at Melbourne container

terminals for this study. He also provided access to data of overseas container

terminals for validating the results.

I acknowledge Patrick Stevedores, P&O Ports, Hutchison Port Holdings and Maher

Terminal Holding Corp. for their assistance in providing the data.

i
ABSTRACT

Modeling and simulation techniques are the tools to be used for optimizing the

operation and fully utilize access of a container terminal for a projected container

throughput. The container terminal operator uses these study results to make

decisions and planning for the redevelopment and/or expansion of the terminal.

Usually, a new terminal layout with new truck traffic and more container handling

machines is required to cope with the projected container throughput. It is then the

electrical engineers’ task to calculate the terminal maximum electrical load demand

and design the electrical infrastructure accordingly.

A container terminal is a specific engineering field and currently there is no standard

or guidance for electrical engineers to accurately calculate the maximum electrical

demand. This study of electrical usage and demand at the container terminal was a

practical approach to:

x addressing the problem of how to estimate/calculate the maximum electrical

demand of a container terminal with known number of electrical equipment

and

x contributing to the understanding of regenerative energy issue of container

handling cranes at the container terminal.

Operation and electrical data at a Melbourne container terminal were daily collected

for more than two (2) years for this study. Collected operation data was analysed

according to the number of containers, their weights and set temperature for

refrigerated containers (reefers). Container weights were used to calculate the

ii
electrical demand of the container handling cranes. Collected daily electrical data

was correlated to the number of reefers to determine the electrical demand of these

reefers. Maximum electrical demands of container handling cranes and reefers were

determined by analysing all calculated values over the whole data collection period.

Maximum electrical demand of the container terminal was then calculated by adding

the other loads at the terminal: office, lightings and workshop.

The maximum electrical demands of several container terminals in Australia, USA,

Canada and China were calculated using the results of this study and the other

method (the diversity factor method). These calculated maximum electrical demands

were compared with the actual electrical demands with pleasing results: whilst at

least 34% less than the value calculated using the other method, the electrical

demand calculated using the results of this study was indeed the MAXIMUM

DEMAND and still with ample spare capacity of at least 20% for the safety margin

and future expansion of the terminal.

iii
Tables of Contents

Table of Contents iv

List of Abbreviations viii

List of Figures ix

List of Tables xiii

List of Formula xiv

1. Introduction 1

1.1 Background information 1

1.2. Research aims and objectives 4

1.3. Outline of the thesis 6

2. Literature Review 7

2.1 Overview Papers 7

2.2 Electrical Energy Usage and Demand Papers 9

2.3 Formula for Electrical Power calculation 11

3. Electrical Assets Identification and Set up Data Collection Scheme 19

3.1 Identification of electrical assets at container terminal 20

3.1.1 Processes at container terminal 20

3.1.2 Electrical assets at container terminal 26

3.2 Definition of Electrical Demand 28

3.2.1 Definition from the Utilities 28

3.2.2 Definition from Electricity Bills and measured energy 29

3.2.3 Definition from Digital Power Meters 32

3.3 Focusing study on average electrical demand 34

iv
3.3.1 Reasons for focusing study on average demand instead of peak

demand 35

3.3.2 Decision of focusing the study on average demand 36

3.4 Set up at Melbourne Container Terminal for collecting data 36

3.5 Conclusions 40

4. Container Handling Cranes 42

4.1 Brief Discussion of container handling cranes 43

4.2 Load Profiles of Quay Crane – Comparison between AC and DC drive

systems 47

4.2.1 AC and DC quay cranes under study 48

4.2.2 Study results 49

4.2.3 Study conclusions 57

4.3 Container Weight Analysis 57

4.3.1 Weight of container – container ship and ISO standard 57

4.3.2 Weight of container at Melbourne Container Terminal 60

4.3.3 Results of analysing data collection 63

4.3.4 Conclusions of weight analysis 63

4.4 Calculate Demand & Energy usage of container handling cranes 67

4.4.1 Quay Crane and Maximum Electrical Demand 67

4.4.2 RMG and ASC and maximum Electrical Demand 70

4.5 Conclusions 72

5. Refrigerated Container 74

5.1 Brief Description of Refrigerated Container 74

5.2 Estimate Electrical Demand of Refrigerated Container 76

5.2.1 Maximum Demand of a Reefer Stack 77

v
5.2.1.1 Demand calculation using Australian Standard AS3000 77

5.2.1.2 Demand calculation using diversity factor 80

5.2.1.3 Other demand calculation method 81

5.2.1.4 Reefer demand information from Container Handbook 82

5.2.1.5 Demand calculation based on heat transfer & required cooling 83

5.3 Measure the actual reefer electrical demand 88

5.3.1 Description 88

5.3.2 Data collection and analysing 89

5.3.3 Results of analysing data collection 95

5.4 Comparison of maximum demand calculated by different methods 104

5.5 Conclusions 108

6. Reducing electrical maximum demand and energy usage 109

6.1 Reducing electrical maximum demand 109

6.1.1 Improving power factor to reduce maximum demand 109

6.1.2 Using cranes with DC drive system to reduce maximum

Demand 112

6.2 Reducing electrical energy usage 113

6.2.1 Using cranes with DC drive system to reduce energy usage 113

6.2.2 Utilisation of the regenerative energy to reduce energy usage 114

6.2.3 Reduce energy usage by lighting 123

6.2.4 Energy Storage and Peak Lopping 126

6.3 Conclusions 130

7. Verification of this study results 131

7.1 Calculation of the maximum demand at container terminal 132

7.1.1 Calculation to AS/NZS 3000:2007 133

vi
7.1.2 Calculation using diversity factors 134

7.1.3 Calculation using findings of this study 135

7.2 Maximum demand at Container Terminals 136

7.3 Comparison of the results 140

7.4 Conclusions 149

8. Conclusions and directions for future research 150

8.1 Conclusions 151

8.2 Directions for future research 153

Appendix

Appendix A Daily Container Report, Code of Excel macro & Results 155

Appendix B Daily Reefer Report, Code of Excel macro & Results 161

Appendix C Specific Heat Capacity of various Products 173

Appendix D Calculated Reefer Electrical Demand using Heat transfer and

Cooling require Method 174

Appendix E Data Volume 183

References 184

vii
List of Abbreviations

AC Alternating Current

AGV Automatic Guided Vehicle

ASC Automatic Stacking Crane

DC Direct Current

ESCAP Social Commission for Asia and the Pacific

EMS Energy Management System

RMG Rail Mounted Gantry

RTG Rubber Tyred Gantry

QC Quay Crane

SC Straddle Carrier

STS Ship to Shore Crane

SWL Safe Working Load

viii
List of Figures

3.1 Stowage plan of a container ship 20

3.2 Quay cranes 21

3.2 Straddle Carrier 21

3.4 Container ship unloading plan 21

3.5 Melbourne Container Terminal storage stack 22

3.6 Straddle Carrier deliver container to truck 23

3.7 Container ship loading 24

3.8 Processes at Container Terminal 25

3.9 Port Botany Terminal – November 2010 Electricity bill 29

3.10 Single Line Diagram with measuring devices locations 38

3.11 Energy Management System Layout 39

4.1 Different forms of quay cranes 44

4.2 Quay Cranes - Type of Lifts 45

4.3 Rail Mounted Gantries 46

4.4 Automatic Stacking Cranes 46

4.5 AC quay crane – Graph of powers vs. time (second) 50

4.6 DC quay crane – Graph of powers vs. time (second) 50

4.7 AC quay crane – Graph of powers vs. time (second) for one 51
loading cycle

4.8 DC quay crane – Graph of powers vs. time (second) for one 51
loading cycle

4.9 AC quay crane – Graph of power factor vs. time (second) for one 54
loading cycle

ix
4.10 DC quay crane – Graph of power factor vs. time (second) for one 54
loading cycle

4.11 AC quay crane – Graph of THD (%) vs. time (second) for one 56
loading cycle.

4.12 DC quay crane – Graph of THD (%) vs. time (second) for one 56
loading cycle.

4.13 Drawing showing stacking area at Melbourne Container Terminal 60

4.14 Number of container at Melbourne Container Terminal in 2007 – 66


2008

4.15 Percentage of 40’ container, empty container and heavy container 66


at Melbourne Container Terminal in 2007 – 2008

4.16 Average weight of container and TEU at Melbourne Container 67


Terminal in 2007 – 2008

4.17 Calculation of average electrical demand of quay crane 69

4.18 Calculation of average electrical demand of RMG/ASC 71

5.1 Refrigeration supply system for porthole container 75

5.2 Clip on unit for transport by road 75

5.3 Portholes at the end of a porthole container 75

5.4 Integral refrigerated containers 76

5.5 Photo showing Reefer location at Melbourne Container Terminal 89

5.6 Drawing showing Reefer location at Melbourne Container 89


Terminal

5.7 Electrical Demand per Reefer in 2007 96

5.8 Electrical Demand per TEU in 2007 98

5.9 Electrical Demand per Reefer in 2008 99

x
5.10 Electrical Demand per TEU in 2008 100

5.11 Electrical Demand per Reefer in 2009 101

5.12 Electrical Demand per TEU in 2009 102

5.13 Mix Reefer sizes in storage at Melbourne Container Terminal 107

6.1 Reducing electrical demand by improving power factor 112

6.2 Single line diagram of substation D 117

6.3 Energy consumption without utilization of regenerative energy 120

6.4 Energy consumption without utilization of regenerative energy 121

6.5 High mast lighting at container terminal 124

6.6 Container terminal at night 124

6.7 Quay Crane load profile 128

6.8 Proposal from Powercorp using flywheel technology to limit peak 129
demand at 500kW and allow 100kW regenerative energy to be
utilized by other load

6.9 Proposal from S and C using super capacitor technology to limit 129
peak demand at 400kW and capture all regenerative energy

7.1 East Swanson Dock terminal – actual and calculated maximum 140
electrical demands

7.2 West Swanson Dock terminal – actual and calculated maximum 141
electrical demands

7.3 Swanson Dock terminals – actual and calculated maximum 142


electrical demands

7.4 Port Botany terminal – actual and calculated maximum electrical 143
demands

7.5 Fisherman Islands terminal – actual and calculated maximum 144


electrical demands

xi
7.6 China – Yantian terminal – actual and calculated maximum 145
electrical demands

7.7 Canada – Fairview terminal – actual and calculated maximum 146


electrical demands

7.8 USA – Maher terminal – actual and calculated maximum electrical 147
demands

xii
List of Tables

3.1 Port Botany Terminal – Meter 1 data for November 2010 30

3.2 Port Botany Terminal – Meter 2 data for November 2010 31

3.3 Port Botany Terminal – Summary of Electricity foe November 2010 32

4.1 Main data of Quay cranes under observation 48

4.2 Results of measurement 53

4.3 Container ship capacity and deadweight 58

4.4 Dimension and Payload of container 59

4.5 Sample of Container daily Report 61

4.6 Results of running “CONTAINERS” macro 63

4.7 Weight Analysis of container at Melbourne Container Terminal 65

5.1 Maximum Demand non-domestic Electrical Installation 70

5.2 Cooling capacity of Reefer Power Unit 85

5.3 Calculated Average Electrical Demand of different reefer cargo 88

5.4 Example of Reefer daily Report 91

5.5 Example of Reefer power Report 92

5.6 Results (temperature analysis) of running “REEFERS” macro 94

5.7 Results (weight analysis) of running “REEFERS” macro 95

5.8 Reefer Electrical Average demand 97

5.9 Maximum Demand calculated using different methods 104

6.1 Extract from Yantian 2005 report on QC CONSUMPTION STUDY 115

6.2 Recorded consumed real energies at substation D 119

7.1 Calculated maximum demand at Australian Container Terminal 138

7.2 Calculated maximum demand at Overseas Container Terminal 139

7.3 Comparison of calculated and actual maximum Electrical Demand 148

xiii
List of Formulas

2.1 Basic motion formula – Distance 12

2.2 Basic motion formula – Distance 12

2.3 Hoist Power with Load 12

2.4 Lower Power with Load 12

2.5 Hoist acceleration Power with Load 13

2.6 Hoist deceleration Power with Load 13

2.7 Lower acceleration Power with Load 13

2.8 Lower deceleration Power with Load 13

2.9 Hoist motor acceleration Power with Load 13

2.10 Hoist motor deceleration Power with Load 13

2.11 Lower motor acceleration Power with Load 13

2.12 Lower motor deceleration Power with Load 13

2.13 Hoist total acceleration Power with Load 13

2.14 Hoist total Power with Load 13

2.15 Hoist total deceleration Power with Load 13

2.16 Lower total acceleration Power with Load 13

2.17 Lower total Power with Load 13

2.18 Lower total deceleration Power with Load 13

2.19 Hoist Power without Load 14

2.20 Lower Power without Load 14

2.21 Hoist acceleration Power without Load 14

2.22 Hoist deceleration Power without Load 14

2.23 Lower acceleration Power without Load 14

xiv
2.24 Lower deceleration Power without Load 14

2.25 Hoist motor acceleration Power without Load 14

2.26 Hoist motor deceleration Power without Load 14

2.27 Lower motor acceleration Power without Load 14

2.28 Lower motor deceleration Power without Load 14

2.29 Hoist total acceleration Power without Load 14

2.30 Hoist total Power without Load 14

2.31 Hoist total deceleration Power without Load 14

2.32 Lower total acceleration Power without Load 14

2.33 Lower total Power without Load 14

2.34 Lower total deceleration Power without Load 15

2.35 Friction Load with Load 15

2.36 Wind Load with Load 15

2.37 Main Hoist rope inflexibility with Load 15

2.38 Static Power in Adverse Wind with Load 15

2.39 Static Power in favourable wind with Load 16

2.40 Trolley acceleration Power 16

2.41 Trolley deceleration Power with Load 16

2.42 Trolley motor acceleration Power with Load 16

2.43 Trolley motor deceleration Power with Load 16

2.44 Cross travel total acceleration Power in adverse wind with Load 16

2.45 Cross travel total Power in adverse wind with Load 16

2.46 Cross travel total deceleration Power in adverse wind with Load 16

2.46 Cross travel total acceleration Power in favourable wind with Load 16

2.48 Cross travel total Power in favourable wind with Load 16

xv
2.49 Cross travel total deceleration Power in favourable wind with Load 16

2.50 Friction Load without Load 16

2.51 Wind Load without Load 17

2.52 Main Hoist rope inflexibility without Load 17

2.53 Static Power in Adverse Wind without Load 17

2.54 Static Power in favourable wind without Load 17

2.55 Trolley acceleration Power without Load 17

2.56 Trolley deceleration Power without Load 17

2.57 Trolley motor acceleration Power without Load 17

2.58 Trolley motor deceleration Power without Load 17

2.59 Cross travel total acceleration Power in adverse wind without Load 17

2.60 Cross travel total Power in adverse wind without Load 17

2.61 Cross travel total deceleration Power in adverse wind without Load 17

2.62 Cross travel total acceleration Power in favourable wind without 17


Load

2.63 Cross travel total Power in favourable wind without Load 17

2.64 Cross travel total deceleration Power in favourable wind without 18


Load

3.1 Total consumed Energy 31

3.2 Real Demand 31

3.3 Reactive Demand 31

3.4 Apparent Demand 32

3.5 Maximum Electrical Demand 32

5.1 Increase Temperature due to Heat transfer 86

5.2 Refrigerating Capacity for Cooling 86

5.3 Average Electrical Demand 87

xvi
7.1 Maximum Electrical Demand 133

7.2 AS/NZS:3000 calculation method – Reefer Load Demand 133

7.3 AS/NZS:3000 calculation method – Crane Load Demand 133

7.4 Diversity Factor Method – 20’ Reefer Load Demand 134

7.5 Diversity Factor Method – 40’ Reefer Load Demand 134

7.6 Diversity Factor Method – Reefer Load Demand 135

7.7 Diversity Factor Method – Crane Load Demand 135

7.8 Results from this study – Reefer load Demand 136

7.9 Results from this study – Crane load Demand 136

xvii
CHAPTER ONE

Introduction

1.1 Background information

Containerization is the use of transport containers to unitize cargo for supply,

transportation and storage without the need for intermediate handling of the content.

Since the introduction in 1956 [84], containerization of cargoes is becoming ever

more widespread worldwide and almost all products are now transported by

container.

In the Container Traffic Forecast [65] published by United Nation Economic and

Social Commission for Asia and the Pacific (ESCAP), container traffic has grown

substantially from 28.7 million twenty-foot equivalent units (TEUs) in 1990 to

113.6 million TEUs in 2005. This is corresponding to an average annual compound

growth of 9 percent. The forecast suggest continued trend of increasing of the

container traffic of annual compound of 7.6 percent till 2015 taking into account the

World Economic Crisis 2008/2009. It is expected a traffic of 235.7 million TEUs in

2015.

The growth in the container traffic leads to the growth in the capacity of the

container ship as the shipping lines prefer to use larger container ship to lower the

costs. It is claimed that the transportation cost per container for the sixth generation

container ship (Post-Suezmax) may be about 30% lower than that of a typical

1
5,000-6,000 TEUs container ship. Historical development of container ships [20,

22] is shown below:

1. First generation Small Feeder < 1,000 TEUs

2. Second generation Feeder 1,000 - 2,500 TEUs

3. Third generation Panamax 2,500 - 4,500/5,000 TEUs (draught of 12m)

4. Fourth generation Post-Panamax 4,500/5,000 - 10,000 TEUs (draught

of 13m)

5. Fifth generation Suezmax 10,000 - 12,000 TEUs (draught of 16.4m)

6. Sixth generation Post-Suezmax > 12,000 TEUs (draught of 21m)

With the intended increase of the cross section breadth and depth of the Suez Canal

over the coming ten years, the 18,000 TEUs container ship will also be able to pass

the Suez Canal [50]. On the other hand, a future container ship with a draught of 21

m would require existing ports to be dredged. Today, only the ports of Singapore

and Rotterdam are deep enough.

Given the expected growth of container traffic, most container terminals around the

world have terminal expansion and development projects that are either planned or

currently underway. Deploying more container handling machines, leasing more

land, changing operation mode are examples of such plans. Before spending any

money, all container terminal operators like to optimize their operation and fully

utilize their access (land, machines, labours etc.) to produce the maximum

2
productivity [33, 41, 68, 71, 86]. Modelling and simulation appear to be the best

tool for this optimization task.

A lot of simulations have been done to study and optimize the operation of existing

container terminal [23, 25, 27, 32, 35, 73, 74, 81, 83, 90, 108, 130, 174, 201] or

even design a new one. These simulations are carried out to find the impacts of

terminal layout [151], allocating berthing for ship [129, 131, 132, 152, 153, 154],

predicting number of cranes for certain handling rate [127], rail logistic, truck

logistic and even impact on in land transportation. However, none have been done

for the electricity power demand and consumption or the utilization of electrical

infrastructure of a container terminal.

Planing for a new container terminal or expanding an existing container terminal

must include the power demand at the initial design stage of such development.

Increasing number and size of container handling machines: Quay Cranes (QCs),

Rail Mounted Gantries (RMGs), Automatic Stacking Cranes (ASCs) and

Refrigerated Containers (Reefers) have brought a significant increase in electrical

power demand for container terminals [112]. Accurate assessment of the projected

electrical load is of critical importance as this electrical demand is used for:

- sizing and selection of principal electrical assets, thus impacting on the

capital cost of the electrical infrastructure,

- request an update or new electrical supply from the electrical power supply

company. Capital cost of electrical supply could be very high if the current

electrical network can not provide the requested demand.

3
1.2. Research aims and objectives

As container terminal is a specific engineering field and currently there is no

standard or guidance for electrical engineers to accurately calculate the electrical

demand [6], all are depended on the experiences of those engineers for this

estimation. This would normally lead to an over design of electrical infrastructure

and resulting in a very costly exercise if a new electrical switching station would be

built to supply the projected load demand. For example, in a recent re-development

of a container terminal in Australia, a load demand of 16MVA was stated for this

container terminal with 8 QCs, 5 RMGs and 800 refrigerated containers. A new

electrical switching station was required to supply such demand with a total cost of

around AUD 10 million. A similar size container terminal in Australia has an actual

load demand of only 4MVA.

There are number of private studies of energy consumption and power supply at

several container terminals that concern about their electrical bills [95].

Presentations [18] and information [70, 98, 136] about electrical demand and

energy usage of electrical machines are now a requirement as part of technical

documents to be submitted to electrical supply tenders called by all container

terminal operators.

The main aims of this research are: how to estimate/calculate the maximum

electrical demand of a container terminal with known number of electrical

equipments? What is the likely electrical energy usage for a container terminal with

a known through put? A practical approach is used to find out the answers:

4
x With the permission of the container terminal management, installing a

power monitoring system consist of a server and number of digital power

meters for logging electrical data. At the same time, details of containers at

the terminal are provided for every day and monthly electrical invoices are

also obtained for comparison. . The monthly electrical invoices are also

obtained for confirmation of the analysed results. Data have been collected

for over two (2) years.

x Learning the spreadsheet simulation technique from simulation conferences

papers [165, 166, 168, 169, 171, 177, 178, 179, 181, 182, 183, 184].

x Calculation and spread sheet simulation are performed to estimate the

electrical load of the machine. Examining the working of the smart meter,

how power supply company calculate the demand and analysing the

collected data. Results are used for estimating the total demand of the

terminal.

x Electrical energy consumptions at several other container terminals around

the world are also obtained to confirm the study results.

The environment concern of green house emission is also looked at by investigating

how to reduce such electrical demand end energy consumption - the design of

electrical network, the application of the new technical innovations such as

synchronizing operation of multiple machines and using peak lopping device.

This research looks into the gap left by previous researches and studies related to

container terminals. Hopefully, it will clarify some electrical issues contribute to

the knowledge of designing and operation of the container terminals.

5
1.3. Outline of the thesis

This thesis consists of eight chapters. In the next chapter, an introduction to

electrical power demand and energy usage at a container terminal and review of

related literature are presented. Chapter 3 outlines the operating environment of

container terminal, identifies the electrical assets to be studied, investigate how

electrical consumption is measured and charged then describe the set up of data

collection scheme. Chapter 4 looks at the container handling machines group

consists of Quay Cranes (QCs), Rail Mounted Gantries (RMGs) and Automatic

Stacking Cranes (ASCs). A brief discussion and focus on what would be studied

followed by obtaining the quay cranes’ specifications and profiles, discusses the

drive systems (DC and AC) and analysing the weights of containers in stack of

Melbourne Container Terminal from collected data and finally calculate the

electrical demand and energy usage of the container handling machines group.

Chapter 5 investigates the refrigerated containers, methods of calculating the

refrigerated container’s electrical demand, describes another way of calculation.

The actual (more than two years) measurements and calculation results are

tabulated for comparison. Chapter 6 discusses several ways of reducing the

maximum electrical demand and energy usage at container terminal ranging from

the design of electrical network to utilise the regenerative energy, requesting for net

metering scheme, the use of energy storage and peak lopping devices and lighting

level at the container terminal. Chapter 7 verifies the finding of this study by

showing the comparison between the actual electrical demand and the calculated

maximum electrical demand of several container terminals around the world.

Finally, chapter 8 will summarised the thesis, make concluding remarks as well as

recommendations for future research.

6
CHAPTER TWO

Literature Review

To the best of the author’s knowledge from the literature review and long time

working in the port, there was no published academic research into the electrical

energy usage and demand at container terminal. Literatures [49, 51, 52, 118, 195,

196, 197, 200, 205] on the rail/traction area had also been reviewed to find any

applicable information for use. Because of the lack of published research in this

field, the author had to rely on the commercial articles written for magazines

specialised in this field, the presentation at commercial conference as well as the

internal reports of various container terminal operators and electrical supply

companies for review and gather information.

The reviewed papers are grouped into following categories:

x container terminal overview papers to provide an understanding of the


operation of container terminal,
x electrical energy usage and demand papers to find what have been done in
this field and
x formulas for electrical power demand calculation.

2.1 Overview Papers

A detailed literature review on the transhipment of containers at a container

terminal was given by Vis and Koster in 2002 [135]. Different type of material

7
handling as well as planning and control level involving the movement of

containers. The processes at container terminal are discussed next with the detailed

descriptions of each process with reference to relevant information when required.

These pre berth allocation, unload and loading of container ships, transportation of

containers from ship to storage area, stacking these containers and delivering them

to owner directly or by inter-terminal transportation. In the conclusion, they stated

that the majority of published papers only address single type of handling machine

so that the future work shall be concentrate in addressing multiple types of handling

machines for optimising the operation at container terminal.

On the same topic, Stahlbock and Vob [54] provided a comprehensive literature

review of research on optimising methods applied to container terminal operations.

The paper began with an update on the new challenges that the container terminal

operators have to overcome, especially with the requirement of handling new mega

size container ships capable of carrying 10,000 TEU to 12,000 TEU. They then

discussed the container terminal operation system and its sub system such as the

handling equipment, human recourses and supporting system. Research on

optimising methods was discussed in details of few particular subsystems that have

big impact on the operation such as berth allocation and stacking logistics. They

concluded the review with a summary; they also identified and suggested a number

of promising and interesting topics for future research.

8
2.2 Electrical Energy Usage and Demand Papers

It was reported early this year (March 2012) in the Port Technology International

[7] that a simulation model had been developed by Kim Le of AECOM for studying

the electric power of yard cranes. The concern about the increasing of required

electrical demand, especially when a large number of cranes are installed and

connected to the electrical grid at the container terminal, and the lack of suitable

method for calculating this demand was the reason for such study. The most

interesting result from this simulation study is that for 36 yard cranes with 700 KW

demand each totalling of 25,200 kW, the average demand of all 36 machines is only

1,000 kW and for a percentile of 99%, a demand of 3,240 kW is required. However,

the critical information is not provided: yard crane electrical data, container weight,

travel distances etc. for the readers to make use of the results. To an electrical

engineer reader, it appeared to have mixed up between electrical energy

consumption (kWHr) and electrical demand (kW) terminologies.

In the “Efficient use of energy in container cranes” article of the same magazine

Port Technology International, edition 48 [26], Fredrik Johanson of ABB described

the regenerative energy issue of electrical powered cranes and suggested ways for

utilising this energy especially for automatic stacking cranes.

In the “Driving innovation: high handling efficiency, low energy use” article of the

Port Technology International, edition 47 [28], Gottwald Port Technology described

a successful innovation for its mobile crane – using energy storage system to

capture the regenerative energy when the crane lowering and discharge this energy

when the crane hoisting.

9
Another useful information was described in the “Crane life cycle costs” in the Port

Technology International edition 20 [128] by Gerhard Fischer of Siemens that the

average net amount of energy required to move a container was 1.94 kWHr.

At the Terminal Operators Conference in 2005, Robert Reid of Robert Reid and

Associates had present a paper titled “Design, Installation and Electrical

Management of Container Terminals with Large Electrical Demand” [110]. An

overview of the electrical infrastructure of the container terminal and regulatory

requirements in Australia had been discussed. The finance impact as well as

benefits would be achieved by reducing the electrical demand. In discussion of the

electrical demand, the paper raised concern about the lack of accurate method for

calculating the maximum electrical demand. The actual facts were also presented:

average weight of container traffic, the large size of container handling cranes as

well as their characteristic, the affect of number of refrigerated containers in the

terminal, and the actual electrical energy consumption by the container terminal.

The paper concluded by stating that accurately calculating the maximum electrical

demand is really needed for designing a new container terminal or upgrading the

existing one.

In a presentation to DP World the terminal operator at Brisbane Port in 2011 [18]

for an Automatic Stacking Cranes (ASC) project, G Nordman of ABB presented an

Excel spreadsheet simulation for 12 ASCs. With a known operating characteristic of

one ASC, the simulation was performed with various operating conditions such as

fix hoisting delay between machines and assuming operating of multiple ASCs at

the same time would not cause any issue for the electrical supply network.

Following data is of interested:

10
For one ASC Maximum Demand 930 kW
Average Demand 69 kW

For 12 ASCs at hoisting delay of 20 seconds:


Maximum Demand 2,167 kW
Average Demand 822 kW

2.3 Formula for Electrical Power calculation

Part of tender documents submitted for bidding to supply container handling cranes

is that theoretical calculation of electrical power under pre-set operating conditions.

The author had access to the document of successful tenders providing the container

crane to various container terminals in Australia [70, 98, 136]. For this study,

electrical demand calculation would have to be performed and reviewing these

documents for formulas used in electrical power calculation has the advantage of all

needed formulas are available saving time in reviewing a lot of different text books

[121, 207, 210] for needed formulas.

When calculating the maximum electrical demand, boom hoist and long travel

motions can be ignored because:

x the boom motion is only used to put the crane in the working position to

start loading/unloading containers and to stow the boom at the end of its

work,

x other motions are not available when boom hoist is in use.

x the boom’s electrical motor is not as large as the hoist’s electrical motor, the

demand is not the maximum demand

x other motions are not available when long travel is in use

11
x the long travel’s electrical motor is not as large as the hoist’s electrical

motor, the demand is not the maximum demand

Basic motion formulas:

s vt (Eq. 2.1)

1 2
s at  v0 t (Eq. 2.2)
2

Where v speed in m/sec

v0 initial speed in m/sec

s travel distance in m

t travel time in second

The following naming index conventions are used on all formulas in this section:

Nxy Power (in Watts) with:


x = 1 for motion with load, x = 2 for motion without load
y = 1, 2,… for different powers

Pwxyz Total Power (in Watts) with:


w : w = 1 for motion with load and w = 2 for motion without
load
x : H for Hoisting, L for Lowering, XT for cross Travel and
LT for Long Travel.
y : A for acceleration, D for deceleration & nothing for motion
at constant speed
z : W for travel against wind, NW for travel with wind, nothing
for hoist motion

A. Hoist/Lower motion

The following formulas are used to calculate the average demand of the hoist
motion:

With load (lift container)

V1
Hoist Power N 11 ( LL  LS ) * g * (Eq. 2.3)
60 * u

12
V3
Lower Power N 12 ( LL  LS ) * g * *u (Eq. 2.4)
60

(V1 / 60) 2
Hoist acceleration Power N 13 ( LL  LS ) * (Eq. 2.5)
t1 * u

(V1 / 60) 2
Hoist deceleration Power N 14 ( LL  LS ) * *u (Eq. 2.6)
t2

(V3 / 60) 2
Lower acceleration Power N 15 ( LL  LS ) * *u (Eq. 2.7)
t5

(V3 / 60) 2
Lower deceleration Power N 16 ( LL  LS ) * (Eq. 2.8)
t6 * u

2 (2 * S * n1 / 60) 2
Hoist motor accel. Power N 17 WK h * (Eq. 2.9)
1000 * t1

2 (2 * S * n1 / 60) 2
Hoist motor decel. Power N 18 WK h * (Eq. 2.10)
1000 * t 2

Lower motor accel. Power


2 (2 * S * (V3 / V1 ) * n1 / 60) 2
N 19 WK h * (Eq. 2.11)
1000 * t 5

Lower motor decal. Power


2 (2 * S * (V3 / V1 ) * n1 / 60) 2
N 20 WK h * (Eq. 2.12)
1000 * t 6

Hoist accel. Power (W) P1HA N 11  N 13  N 17 (Eq. 2.13)

Hoist Power (W) P1H N 11 (Eq. 2.14)

Hoist decel. Power (W) P1HD N 11  N 14  N 18 (Eq. 2.15)

Lower accel. Power (W) P1LA N 12  N 15  N 19 (Eq. 2.16)

Lower Power (W) P1L N 12 (Eq. 2.17)

Lower decel. Power (W) P1LD N 12  N 16  N 20 (Eq. 2.18)

13
No load - without load

V2
Hoist Power N 21 LS * g * (Eq. 2.19)
60 * u

V4
Lower Power N 22  LS * g * *u (Eq. 2.20)
60

(V2 / 60) 2
Hoist acceleration Power N 23 LS * (Eq. 2.21)
t3 * u

(V2 / 60) 2
Hoist deceleration Power N 24  LS * *u (Eq. 2.22)
t4

(V4 / 60) 2
Lower acceleration Power N 25 LS * *u (Eq. 2.23)
t7

(V4 / 60) 2
Lower deceleration Power N 26  LS * (Eq. 2.24)
t8 * u

(2 * S * n2 / 60) 2
Hoist motor accel. Power N 27 WK 2 * (Eq. 2.25)
1000 * t 3

(2 * S * n2 / 60) 2
2
Hoist motor decel. Power N 28 WK * (Eq. 2.26)
1000 * t 4

Lower motor accel. Power


n2 2
(2 * S * (V4 / V2 ) * )
N 29 WK 2 * 60 (Eq.2.27)
1000 * t 7

Lower motor decel. Power


n2 2
(2 * 3.14 * (V4 / V2 ) * )
N 30 WK 2 * 60 (Eq. 2.28)
1000 * t 8

Hoist accel. Power (W) P2 HA N 21  N 23  N 27 (Eq. 2.29)

Hoist Power (W) P2 H N 21 (Eq. 2.30)

Hoist decel. Power (W) P2HD N21  N24  N28 (Eq. 2.31)

14
Lower accel. Power (W) P2 LA N 22  N 25  N 29 (Eq. 2.32)

Lower Power (W) P2 L N 22 (Eq. 2.33)

Lower decel. Power (W) P2 LD N 22  N 26  N 30 (Eq. 2.34)

Where
LL Weight of load (container) in tones
LS Weight of spreader & headblock (lifting device) in tones
V1 Hoist speed with load in m/min
V2 Hoist speed without load in m/min
V3 Lower speed with load in m/min
V4 Lower speed without load in m/min
t1 Hoist acceleration time with load in seconds
t2 Hoist deceleration time with load in seconds
t3 Hoist acceleration time without load in seconds
t4 Hoist deceleration time without load in seconds
t5 Lower acceleration time with load in seconds
t6 Lower deceleration time with load in seconds
t7 Lower acceleration time without load in seconds
t8 Lower deceleration time without load in seconds
n1 Hoist motor speed with load in rpm
n2 Hoist motor speed without load in rpm
WKh2 Total rotational inertia (include gearbox, drum, load) in kgm2
u Overall efficiency
g Gravity (9.81m/sec2)
ʌ Constant Pi = 3.14
N1i Hoist/Lower with load Power in Watts (i = 1,2,3….9)
N2i Hoist/Lower without load Power in Watts (i = 1,2,3….9)

B. Cross Travel motion

The following formulas are used to calculate the average demand of the hoist
motion:

With load (container)

Friction Load L11 (TL  LL  LS ) * c (Eq. 2.35)

Wind Load L12 A1 * Q (Eq. 2.36)


3
1000 * (1  v ) * ( LL  LS )
Main hoist rope inflexibility load L13 (Eq. 2.37)
2

Static power in adverse wind


V xt
N 11 ( L11  L12  L13 ) * g * (Eq. 2.38)
60 * 1000 * u

15
Static power in favourable wind
V xt
N 12 ( L11  L13 ) * g * (Eq. 2.39)
60 * 1000 * u

V xt 2
( )
Trolley acceleration power N 13 (TL  LL  LS ) * 60 (Eq. 2.40)
t xt1 * u

V xt 2 u
Trolley deceleration power N 14 TL * ( ) * (Eq. 2.41)
60 t xt1

n xt 2
(2 * S * )
Motor acceleration power N 15 WK 2 xt * 60 (Eq. 2.42)
1000 * t xt1

n xt 2
(2 * S * )
Motor deceleration power N 16 WK 2 xt * 60 (Eq. 2.43)
1000 * t xt1

Cross travel acc. power in adverse wind (W)


P1LXTAW N 11  N 13  N 15 (Eq. 2.44)

Cross travel power in adverse wind (W) P1 XTLW N 11 (Eq. 2.45)

Cross travel deceleration power in adverse wind (W)


P1 XTDW N 11  N 14  N 16 (Eq. 2.46)

Cross travel acc. power in favourable wind (W)


P1 XTANW N 12  N 13  N 15 (Eq. 2.47)

Cross travel power in favourable wind (W) P1 XTNW N 12 (Eq. 2.48)

Cross travel decal. power in favourable wind (W)


P1 XTDNW N 12  N 14  N 16 (Eq. 2.49)

Cross travel without load

16
Friction Load L21 (TL  LS ) * c (Eq. 2.50)

Wind Load L22 A2 * Q (Eq. 2.51)

1000 * (1  v 3 ) * LS
Main hoist rope inflexibility load L23 (Eq. 2.52)
2

Static power in adverse wind (W)


V xt
N 21 ( L21  0.5 L22  L23 ) * g * (Eq. 2.53)
60 * 1000 * u

Static power in favourable wind (W)


V xt
N 22 ( L21  L23 ) * g * (Eq. 2.54)
60 * 1000 * u

V xt 2
( )
Trolley acceleration power (W) N 23 (TL  LS ) * 60 (Eq. 2.55)
t xt 2 * u

V xt 2 u
Trolley deceleration power (W) N 24 (TL  LS ) * ( ) * (Eq. 2.56)
60 t xt 2

n xt 2
(2 * S * )
Motor acceleration power (W) N 25 WK 2 xt * 60 (Eq. 2.57)
1000 * t xt12

n xt 2
(2 * S * )
Motor deceleration power (W) N 26 WK 2 xt * 60 (Eq. 2.58)
1000 * t xt 2

Cross travel acc. power in adverse wind (W)


P2 XTAW N 21  N 23  N 25 (Eq. 2.59)

Cross travel power in adverse wind (W) P2 XTW N 21 (Eq. 2.60)

Cross travel deceleration power in adverse wind (W)


P2 XTDW N 21  N 24  N 26 (Eq. 2.61)

Cross travel acc. power in favourable wind (W)


P2 XTANW N 22  N 23  N 25 (Eq. 2.62)

17
Cross travel power in favourable wind (W) P2 XTNW N 22 (Eq. 2.63)

Cross travel decal. power in favourable wind (W)


P2 XTDNW N 22  N 24  N 26 (Eq. 2.64)

Where
LL Weight of load (container) in tones
LS Weight of spreader & headblock (lifting device) in tones
TL Weight of trolley in tones
A1 Wind area with load in m2
A2 Wind area without load in m2
Q Wind pressure in kg/m2
v Sheave efficiency
Vxt Trolley speed in m/min
txt1 Cross travel acceleration time in seconds
txt2 Cross travel deceleration time in seconds
nxt Cross travel motor speed in rpm
WKxt2 Total rotational inertia (include gearbox, drum, load) in kgm2
u Overall efficiency
g Gravity (9.81m/sec2)
c Friction coefficient in kg/t
ʌ Constant Pi = 3.14
N1i Cross Travel with load Power in Watts (i = 1,2,3….9)
N2i Cross Travel without load Power in Watts (i = 1,2,3….9)

18
CHAPTER THREE

Electrical Assets Identification and Set up Data

Collection Scheme

Before any study of electrical usage and demand at the container terminal can be

started, all electric powered assets have to be identified. The term electric powered

asset or electrical asset refers to the asset that actual connects to electrical grid and

consumes electricity not asset that providing electric power. For example, quay

cranes are electrical assets but the high voltage switchgears connecting these cranes

to the electrical grid are not.

Understanding of how energy and demand are defined, measured and charged by

the power supply companies (the Utilities) is also important as it help to focus the

study as well as deciding what and how to collect data for this study.

Three main topics will be described and discussed in this chapter:

- Identification of all electric powered assets at container terminal,

- Electricity bills and measured data supplied by the Utilities – to focus the

study and set up data collection scheme,

- Describe the data collection system at Melbourne Container Terminal.

19
3.1 Identification of electrical assets at container terminal

3.1.1 Processes at container terminal

The container terminal knows in advance the expected arrival time of a container

ship, the number of containers to be exchanged and the ship stowage plan so that a

unloading plan and/or loading plan can be prepared, equipment and labour can be

allocated to work on that container ship. Figure 3.1 shows a typical container ship

stowage plan that is the lay out of the ship and container positions.

When the container ship arrives, QCs as shown in Figure 3.2 working according to

a prepared unloading plan take the import containers off the ship and put on the

wharf. The containers are then transferred to the storage stack be transport vehicles

such as Forklifts or Straddle Carriers (SCs) – Figure 3.3 - that travel between the

QCs and the storage stack.

Figure 3.1 Stowage plan of a container Ship

20
Figure 3.2 Quay Cranes Figure 3.3 Straddle Carrier

Figure 3.4 Container ship unloading plan

21
Equipment, such as straddle carriers (SCs), Rubber Tyred Gantries (RTGs), Rail

Mounted Gantries (RMGs) then put these containers into the storage stack

according to a prepared storage plan. Figure 3.4 shows a typical unloading plan

with container identification and details, position on the ship and unloading

sequence.

The storage stack consists of a number of lanes where containers can be stored for a

certain period. Dry cargo containers and refrigerated containers are stored in

different areas. Containers can be stored several high depend on the equipment used

in this storage stack. Melbourne Container Terminal use mainly SCs for container

transportation and stacking. Its storage stack is shown in Figure 3.5.

After a certain period the containers are retrieved from the stack and transported by

vehicles to transportation modes like trucks or trains to leave the container terminal.

Figure 3.6 shows SC delivers container to the truck.

Figure 3.5 Melbourne Container Terminal storage stack

22
Figure 3.6 Straddle Carrier deliver container to truck

To load export containers onto a ship, these processes are also executed in reverse

order. A typical loading plan is shown in Figure 3.7 and Figure 3.8 provides a

summary of container processes at a Container Terminal.

Most of the container terminals make use of manned equipments. However, a few

terminals are semi-automated using unmanned equipment for transport of

containers such as driver less SCs are used in Patrick Terminal in Brisbane, driver

less Rail Mounted Gantries (RTGs) are also tried at Patrick Terminal in Sydney,

some terminals in Rotterdam use Automated Guided Vehicles (AGVs) and

Automated Stacking Cranes (ASCs). Australian Container Terminals in Brisbane

and Sydney are currently re-developing their sites for use ASCs.

23
Figure 3.7 Container ship loading plan

24
Figure 3.8 Processes at Container Terminal

25
3.1.2 Electrical assets at container terminal

As a large electrical user and having a number of machines powered at high voltage

(HV) typically at 11kV level, container terminals are usually under HV tariff.

Following the above description, container terminal administration office is the first

area to look at for electrical assets. Typically, it consists of the following:

x working areas and amenities (general office, first aid office, meeting room,

canteen, toilet, …) for its work forces,

x control tower/room for computer system to observe and monitor all terminal

activities,

x air conditioning, lighting and communication systems.

Electrical power at low voltage (three phase 415V in Australia) is required for these

services. Supply is normally via a step down transformer located near the office to

reduce the voltage drop.

Next type of electrical asset is the container handling equipment group: QCs, RTGs,

RMGs, ASCs, AGVs, SCs and Forklift. However, RTGs, AGVs, SCs and Forklift

are mobile machines which are either not electric powered or not connected to

electric grid. In other words, they are not electrical assets for the purposes of this

study. QCs, RMGs and ASCs are giant and very fast electric powered machines

which give the impression that they use a high amount of energy and require a very

high electrical demand. Due to their size and the capability of travel a relative long

distance (few hundreds meters), they are powered by HV, typically at 11kV.

26
Next electrical asset would be the refrigerated containers that require low voltage

electrical power to keep their cargo at the correct temperatures. Designated areas

with electrical infrastructure to allow these refrigerated containers to be connected

to the electrical grid are in the storage stack. These designated areas are normally

located close to the electrical substation to limit the voltage drop.

As container terminals are operated on 24 hours a day and 7 days a week basic,

lightings are required for night operation. Low voltage electrical supply to these

lightings is from the mention electrical substations.

A maintenance workshop is also a requirement at any container terminal; it is where

the repair and maintenance works to be carried out to keep all electrical assets in

good working order. Welding machines, lathes, power tools, measurement

instruments, spares,.. are in this workshop which required low voltage electric

power supply.

These electrical assets are divided into three groups for detailed study:

x Container cranes group consists of QCs, RMGs and ASCs assets

x Refrigerated containers group

x Other load group consists of Office, Workshop and Lighting assets

Container group will be studied in Chapter 4, Chapter 5 investigates the refrigerated

container group. Demand of the other load group is well regulated and could be

calculated using the AS/NZS 3000 [62] or Construction handbook [21, 34] , it is the

responsibility of the building designer to provide the estimated demand; the

installed demand of this load group was taken as the maximum demand for this

study.

27
3.2 Definition of Electrical Demand

Electrical demand could mean different thing among the Utilities. As the purpose of

this study is to calculate the electrical maximum demand at the container terminal, it

is important that a clear definition of the term “demand” is needed ([99] provides

basic information). This was achieved by checking information provided by the

Utilities, analysing the actual electricity bill and examining measuring devices.

3.2.1 Definition from the Utilities

The following definitions are obtained from several different Utilities in Australia:

United Energy

Maximum Demand = Energy consumption over ½ hr period/ Time (1/2 hr). The
Rolling Peak Demand Charge is based on the highest power (kVA at the highest
kW) delivered during Peak periods (defined as 7am to 7pm Local Time weekdays
excluding public holidays) over 12 months to the end of the billing period.

Powercor

Actual demand, which is measured as the energy consumption recorded over the
demand integration period divided by the demand integration period in hours (the
demand integration period is 15 minutes.

Energex

The customer’s connection point has a meter installed that is capable of measuring
energy consumption (kW.h) and demand (kW). This meter records total energy
consumption (kW.h) and demand over 30 minute periods. A customer’s demand is
the average demand (kW) over the 30 minute period.

Western Power

The metered demand (MD) is a rolling 12-month maximum haft-hourly demand.

28
The electrical demand is actually calculated as defined above was confirmed in the

next section by examining the electrical bills of the container terminal and the raw

measured electrical usage.

3.2.2 Definition from Electricity Bills and measured energy

Electricity bill of an industrial HV customer is different from a residential LV

customer. By law, all the different charges have to be disclosed. Figure 3.9 shows

the electricity bill of the container terminal in Port Botany Sydney for November

2010. For the purposes of this study, the following information is of interested:

Total energy usage: 826,565 kWh and Maximum demand: 2317.41 kVA

Figure 3.9 Port Botany terminal – November 2010 Electricity bill

29
It was noted that there is no information on the feed back energy from the container

terminal (when container handling machine in lowering mode), by experience it is

small amount and ignored by the Utilities. The Utilities provided the electrical data

as requested by the container terminal operator to ensure the charges were correct.

As shown on the electricity bill, there are two meters so that two set of metered data

were provided. Data are time stamped for every 30 minutes during November 2010.

Table 3.1 and Table 3.2 list only part of the electrical data as full listing is not

necessary.

Table 3.1 Port Botany terminal – Meter 1 data for November 2010

30
Table 3.2 Port Botany terminal – Meter 2 data for November 2010

Calculation was performed to find the total energy usage and maximum demand

during November 2010. Calculations are:

TotalEnergyUsage ¦ kWh (Eq. 3.1)

kWh
kW 2 * kWh as h = 30 minutes = 0.5 hours (Eq. 3.2)
h

kVArh
kVAr 2 * kVArh as h = 30 minutes = 0.5 hours (Eq. 3.3)
h

31
kVA kW 2  kVAr 2 (Eq. 3.4)

Demand Max MAX (kVA) (Eq. 3.5)

Calculations are also shown in Table 3.1 and Table 3.2 and the results are

summarised in Table 3.3

Table 3.3 Port Botany terminal – Summary of Electricity November 2010

Electricity Bill Metered Data Unit


Energy Usage
Meter 1 559,913 559,840 kWh
Meter 2 266,652 266,636 kWh
Total 826,565 826,476 kWh

Max Demand 2317.41 2301.40 kVA

The same results were found for all the electricity bills and metered data in 2010. It

was concluded that as defined by the Utilities, electrical demand is indeed

calculated from the metered energies over a time period of 30 minutes.

Digital meters are now used by the Utilities to measure the electrical usage; they are

capable of measuring the electrical demand. Information of how the digital meters

measure the electrical demand was examining in the next section for the definition.

3.2.3 Definition from the Digital Power meters

All digital power meters installed at large users including container terminal are

capable of recording energy both ways: deliver (from the electrical grid to the

customer (positive)) and receive (from the customer to the electrical grid

32
(negative)). However, unless the received energy is from small source (solar) or

agreed generator set the Utilities would not recognize this feed back energy.

The maximum electrical demand is calculated from the measured energies over a

period of 30 minutes as shown in the previous section. It is known that digital

meters are capable measure and calculate a lot more electrical parameters especially

the electrical demand value. It is possible that some Utilities may use this value

instead of calculate as previous section. To ensure this possibility would not affect

the out come, definition of electrical demand measured by the digital meters was

examined in this section.

Following descriptions are extracted from the manuals of some of the digital

meters that used at container terminals around the world:

ION 7300 series Power & Energy Meter from Schneider Electric [69]

Demand is a measure of average power consumption over a fixed time

interval. Peak (or maximum) demand is the highest demand level recorded

over the billing period.

Quantum Q1000 Multifunction Meter from SchlumbergerSema [156]

Demand is the average value of a measured quantity over a specified time.

9300 Series Power Meter from Siemens [11]

The demand modules (both Thermal Demand modules and Sliding Window

Demand module) are configured to calculate the average current demand

and kW, kVAR and kVA demand.

33
Mk Genius and Mk6E Energy Meters from EDMI [114]

The demand for the period is simply the accumulated energy divided by the

fraction of an hour that the demand period is.

DIN Integra 500 Series from Crompton [3]

Most electricity utilities base their charges on power consumption,

historically using a thermal maximum demand indicator (MDI) to measure

peak power consumption averaged over a number of minutes, thus avoiding

artificially high readings caused by surges.

It was confirmed that the digital meters calculate the electrical demand in the same

manner as the Utilities do from their metered energy values. That means value of

electrical demand is the same either it was read from the digital meter or calculated

by the Utilities.

The important result from the study so far is that electrical demand is the average

demand over a measure period. The measure period is 30 minutes for Melbourne

Container Terminal and Sydney Port Botany Container Terminal.

3.3 Focusing study on average electrical demand

With the understanding of maximum electrical demand as discussed in previous

section, the maximum demand calculation in later section would be the calculation

of the maximum average demand instead of the peak demand. Reasons for this

decision were given below.

34
3.3.1 Reasons for focusing study on average demand instead of peak
demand

Recall from previous section, the electrical demand is the average demand over a

measure period that is normally 15 minutes or 30 minutes. Since the main purpose

of this study was to calculate the maximum electrical demand at container terminal

for negotiation the power supply contract either new supply or an upgrade one,

similar term (the average demand) should be used.

Some digital power meters do have the ability to calculate and record the

instantaneous maximum demand (secondly). However, as there is no way of

distinguishing between the actual electrical demand from the user and the network

disturbances; this ability of the meter was usually ignored.

An analogue maximum demand ammeter, such as BIQ96 from Ziegler, could also

be used to measure the maximum current demand then maximum power demand

could be calculated if required. Information from http://www.ziegler-

instruments.com/pdf/Bieq-c-ch.pdf (accessed on 22 May 2012) states that: “The

thermal bimetallic movement indicates the mean rms value over 15 minutes

(optional 8 min.) And deflects a reset-table red slave pointer which shows the

maximum value reached.” It was noted that peak demand was not measured.

Although peak electrical demand is important for any electrical network, it may

cause voltage flickering and trigger the supply interruption on a weak network, peak

demand is really the protection issue, which is out of this study scope. It is possible

to reduce this peak demand value to a manageable figure by using a synchronized

35
movements (central control) [42] scheme or using a “peak lopping” device that

would be discussed in Chapter 6.

3.3.2 Decision of focusing the study on average demand

A container terminal with a large number of container handling cranes would face a

very large value of maximum electrical demand if peak values were used.

Information of how electrical energy and demand were measure, calculated and

charged at container terminal together with the above reasons, using average

electrical demand was the correct way to calculate/estimate the maximum electrical

demand of a container terminal.

3.4 Set up at Melbourne Container Terminal for collecting data

With the approval and permission of Patrick management team, the new 11kV HV

reticulation with an Energy Management System (EMS) was designed and installed

at Swanson Dock in the Port of Melbourne. The change over from the old electrical

supply network to the new ones without interruption to the daily operation of the

terminal was completed in early 2006.

The selected EMS was the Power Logic System Management Software from

Schneider Electric (previously owned by Square D) because it was the only system

that provides a complete solution at that time. The EMS was designed for the ease

of communicating and collecting measured electrical data from a large range of

power meters, protection relays as well as tripping units of low voltage circuit

breakers especially for devices from Schneider Electric.

36
Figure 3.10 shows the HV single line diagram and location of measuring devices

while Figure 3.11 shows the layout of the EMS system.

For a fast changing electrical load, such that the QC, RMG and ASC, Schneider’s

circuit monitor CM3250 was used. This device is a powerful power meter with in

built memory large enough to record electrical data every second for at least 5

hours.

For a slow changing or steady load, such as the refrigerated containers, metering

features of the digital protection relay (SEPAM series 40) and digital tripping

circuit of circuit breaker (MicroLogic 5) were utilised. These devices do not have

built-in memory, the required electrical values were measured and calculated then

pass on to the EMS server when there was a “data collect” signal was issued from

the EMS server. Electrical data collection period can be varied between 1 minute

and 1 hour.

Power Logic System Management Software version 4 was installed on a computer

server which runs Windows Server 2003 operating software. Electrical data,

voltages, currents, powers, energies, power factor and harmonics from each of the

devices (shown in Figure 3.11) were collected and save in a database every 15

minutes. Historical data could be archived when required.

The system was set up as a stand alone system that was not connected to the

container terminal computer network for security reasons. Remotely access was via

the World Wide Web by using the service of Iburst wireless network.

Unfortunately, the Iburst network was closed several years ago and the only way to

access this system was via local direct log in to the server.

37
Figure 3.10 Single Line Diagram with measuring devices locations

38
Figure 3.11 Energy Management System layout

39
With permission from management team of Patrick, the Melbourne Container

Terminal Operator, and utilizing the fast 1 second data recording feature of the

CM3250, load profiles of number of QCs were obtained. The QCs electrical

specifications, characteristic, measure conditions and results would be discussed in

Chapter 4.

The management team also permitted the daily weekday reports of number of

refrigerated containers and dry cargo containers that were in storage stack of the

terminal be generated and provided via email. These reports would be discussed in

Chapter 4 and Chapter 5.

Although all circuit monitor CM3250s and Power Logic System Management

Software V4 are still in working order providing invaluable data for the study and

any future work, they are discontinued and no longer available, Schneider Electric

claims latest software version, Power Logic ION Enterprise, and newer

measurement devices would be more user friendly and provide better results.

3.5 Conclusions

Understanding the processes at container terminals helps to identify the electrical

assets and focus the study on interested areas.

The definition of the electrical demand term that is referred to by the Utilities is

clarified by reviewing the Utilities’ electricity bills, examining the raw data of

measured electrical parameters and investigating how those electrical parameters

are defined in modern digital power meters (smart meters), it is confirmed that

40
electrical demand is the average demand over a measure period (usually 15

minutes or 30 minutes period) and is not the instantaneous demand. The tasks

of finding the maximum demand of electrical assets became easier with this

confirmation.

With the measurement scheme set up for data collection as described, the studyied

results could be verified. The electrical energy usage and maximum demand of

container cranes group would be investigated in the next chapter – Chapter 4

Container Handling Crane.

41
CHAPTER FOUR

Container Handling Crane

With the electrical assets of container terminal have been identified in previous

chapter, the electrical demand and energy usage for the big machine group –

container handling cranes – could now be studied. These machines are used to:

x move containers from container ship to ground or via versa (QCs),

x move containers into stacking area, shuffle them within the stacking area or

move containers out of stacking area for delivery either with driver (RMGs)

or driverless (ASC).

This chapter began with a brief discussion on these machines and their operation

then investigates the following:

x Quay crane profile – record load profiles of similar quay cranes with AC

drive and DC drive and compare the results for contribution to the AC verus

DC drive debate,

x Container weight – payload of container, capacity and deadweight of

container ship and analysing actual weights of containers (daily data

collected more than one year) in stack of Melbourne Container Terminal for

contribution to the debate of what size (lifting capacity) of quay crane is

needed.

42
The reasons why this study was only focusing on the maximum average demand

instead of the peak instantaneous demand would be discussed before demand

calculations were performed and conclusions were drawn.

4.1 Brief Discussion of container handling cranes

A modern container terminal would be dominated by the giant quay cranes that can

reach out over the ships to load or unload containers. They are mounted on rails and

will be able to long travel up and down the quay to exactly align themselves with

the “bays” in or over the ship’s hold, where the container is to be handled. The

outreach of the horizontal boom permits a trolley to cross travel from over the quay

to over the ship, a spreader with four locks suspended from the trolley. These locks

nest into the four corners of the containers, make fast and enable the container to be

hoisted out of (or lowered into) the ship hold. A crane driver in his cab alongside

the trolley has an excellent view of the process he is controlling.

Apart from the sizes of the quay cranes that are capable of serving different type of

container ships (Panamax, Post Panamax,…), quay cranes are different in look: ‘A

frame’ quay cranes are the most common cranes as they are the lightest and

cheapest quay cranes that can be built. Articulated boom or goose neck quay cranes

are used when there is a restriction in crane’s height. Under severe crane height

restriction due to the container terminal is on the adjacent airport’s flight path,

shuttle boom or low profile quay cranes have to be used. Figure 4.1 shows these

types of quay cranes.

43
Another way of classifying quay cranes is their lifting capability or safe working

load (SWL) and how they lift containers. As 30 tones is the SWL of each 20’ or

40’ container, latest design tandem lift quay crane capable of lifting 6 x 20’

containers should have the rated load of 180 tones. Figure 4.2 shows different types

of lifts.

Figure 4.1 Different forms of quay cranes

44
Source : www.lifttech.net

Figure 4.2 Quay cranes - Types of Lifts

On the quay ground handling equipment (straddle carriers, fork lifts or automatic

guided vehicles) moves the containers from the quay cranes to the stack and via

versa. The container is then moved into stacking area by the rail mounted gantries

(RMGs) or driverless automatic stacking cranes (ASCs). The same machine will

deliver containers to the truck or rail when required. In general, these machines are

very similar to the quay cranes without the boom motion, hoist/lower and cross

45
travel motions are for a short distance only. RMGs are shown in Figure 4.3 and

ASCs are shown in Figure 4.4.

Figure 4.3 Rail Mounted Gantries

Figure 4.4 Automatic Stacking Cranes (no driver)

Due to the need to travel a long distance (few hundreds meters) and handle the

heavy containers that is drawing large current over a long cable, these machines are

electrical powered at high voltage level and the drive system can either be an AC

drive system or a DC drive system. Unless specified, all machines are now come

with AC drive system simply because they can operate at or close to unity power

factor.

46
It was not able to record load profiles for RMG or ASC as the Melbourne Container

Terminal does not have any of these machines. However, it was expected the load

profiles of RMG and ASC are very similar to that of the quay cranes as:

x Hoist/Lower motion would be similar as the container loads are the same for

these machines,

x The long travel motion would be the predominant one as RMGs and ASCs

need only hoist/lower a short distance but long travel a very long distance.

x Demand and energy usage are also less than that of the quay crane due to the

nature of the long travel motion – overcome friction rather than lifting a

weight.

The Melbourne Container Terminal has both AC drive and DC drive quay cranes.

With the permission from the management team, load profile of these quay cranes

were obtained as described in next section.

4.2 Load Profiles of Quay Crane – Comparison between AC and


DC drive systems

Since the introduction of IGBT based AC drive products in the late 1980s, there has

been much debate on which technology – AC or DC drive – should be used by the

crane industry for new container cranes. The AC technology appears to win the

debate as today almost all container cranes are AC. However, the electrical power

demand and energy usage of container cranes have not been mentioned in any

debate. With the new “bigger and faster” container cranes being built, the high

electrical cost of running these container cranes must now be closely analysed.

47
With the permission of management team of Melbourne Container Terminal, load

profiles of two very similar quay cranes – one with AC drive system and the other

with DC drive system - had been obtained on 29 January 2008 and 13 February

2008. As described in chapter 3, the Schneider circuit monitor CM3250 was used at

the high voltage supply end of each quay crane to capture the electrical data every

second then uploaded to the Energy Management System data base. The operation

data (time, container number, weight, quay crane motion, load or unload) were also

recorded for analysis. Details were discussed below.

4.2.1 AC and DC quay cranes under study

As there were no exactly match pair of quay cranes at the container terminal, two

very similar quay cranes (physical size, mechanical arrangement, year of

manufactured) had to be selected to produce comparable results.

Almost only Hoist and Cross Travel motions are used in loading/unloading

containers to/from container ship. These motions produce the peak demand and

around 99% of the energy usage. Therefore, this study concentrated mainly on these

two motions. The main electrical data of these quay cranes was listed in Table 4.1.

Table 4.1 Main data of Quay cranes under observation

48
The AC quay crane uses AC drive system with Active Front End technology that is

full compensation can be made for power factor and harmonics. The DC quay crane

uses DC drive technology with harmonic filter to compensate the generated

harmonics.

4.2.2 Study results

It was expected the peak demand would be larger for AC drive technology due to

the fact that:

x the AC motor size that have to be larger in size to produce the same torque

and overload capability resulting in. larger rotational inertial, cooling

systems and power consumption,

x the AC drives technology requires two steps, conversion and inversion while

DC drive technology needs only conversion. This means extra power

requirement, larger cooling devices as more heat would be generated for the

AC drives.

Electrical data were captured during actual working conditions: loading containers

to container ship. At the same time, loading sequence and container weight are also

recorded. Figure 4.5 and Figure 4.6 show graph of Real Power (kW), Reactive

Power (kVAr) and Apparent Power (kVA) of the quay cranes working on the same

ship hold, ie. minimum usage of gantry motion.

49





N:
 N9$U
N9$

     




Figure. 4.5 AC quay crane – Graph of powers vs. time (second).






N:
 N9$U
N9$

    




Figure 4.6 DC quay crane – Graph of powers vs. time (second).

The first impression is that DC quay crane handled more containers, there are

regenerative Real Power (-ve kW), DC quay crane requires larger kVA demand.

This data is used to calculate the energy usage of the quay crane for handling each

container.

To make comparison, a loading cycle with the similar container weight and similar

travel distances are used. Figure 4.7 and Figure 4.8 show the Power graphs of the

AC and DC quay cranes when handling container weight 26.1T and 26T

respectively.

50




 N:
N9$U
 N9$
   




Figure 4.7 AC quay crane – Graph of powers vs. time (second) for one loading
cycle.






N:
 N9$U
N9$

    




Figure 4.8 DC quay crane –Graph of powers vs. time (second) for one loading
cycle.

A loading cycle comprises of::

- Lock the container to the spreader for a safe move,

- Hoist the container up, start cross travel (while hoisting) to sea side when
clear of all obstacles,

- Lower the container to its final position and unlock,

- Hoist the empty spreader up, start cross travel (while hoisting) to land side
when clear of all obstacles,

- Lower the empty spreader on top of the next container.

Therefore a graph of Power versus Time of a complete load cycle was expected to

have four peaks values. The Real Power should have two negative peaks

51
(regenerative when lowering). Figure 4.7 and Figure 4.8 confirmed these

expectations. The slightly differences in shape and duration were due to the

techniques of the quay crane drivers.

Peak Power Demand and Energy Usage

The results were summarised in Table 4.2. Theoretical average power demands

were calculated and also shown in the table for reference only. The formula were

from chapter two and actual mechanical data used in calculation of the average

demand would be shown in later section. To make a true comparison between AC

and DC quay cranes, the electrical conditions had to be the same. It was assumed

that the issue of poor power factor of DC drive quay crane was not a concern;

comparison was now based on the peak kW demand rather than the peak kVA

demand.

As shown in Table 4.2, peak demand from AC quay crane was 21.9% higher than

DC quay crane. When taking the Safe Working Load of the quay cranes into

account, the difference was still expected to be higher than 15%.

As discussed in Chapter 3, the Electrical Distribution Company (the Utility) does

not look at this instantaneous peak/maximum demand. The peak/maximum demand

was normally calculated from the “remotely read” energy kWHr and kVArHr every

15 or 30 minutes. That means the peak kW demand shown in the electrical bill was

actual the average kW demand.

52
Table 4.2 Results of measurement
Quay Crane with AC Drive DC Drive Differences
Load condition
Number of loads 29 47
Load Weights From 7T to 48.4T From 7T to 48.4T
Results
Net used energy (kWHr) 113.50 115.20
Average used energy per 3.91 2.45
For 26T load
Peak demand (kW) 1476 1211 21.88%
Average demand (kW) 147.75 105.26 40.37%
Cal. Ave. demand (kW) 152.01 126.83 19.85%

Power factor - Real time 0.087 – 1 0.006 - 0.838


Power factor - calculated 0.952 0.475

Total Harmonic Distortion


(THD)
Line Current
Ia (%) 1.9 - 51.9 5.6 - 49.7
Ib (%) 1.6 - 830.3 5.3 - 56.9
Ic (%) 1.6 - 93.1 63. -50.9
Line Voltage
Vab (%) 0.9 - 1.2 0.7 - 1.9
Vbc (%) 0.9 - 1.2 0.8 - 2.0
Va (%) 0.9 - 1.2 0.6 - 1.8

For 26T container load, the AC quay crane kW demand was 40% higher. Taking

into account the driver’s techniques, the final position of the container and other

containers on the ship, the difference was still expected to be in the low 20%.

With higher peak and average demand, the energy usage had to be higher for AC

drive quay crane. An average of 60% more energy was required to handle a

container during this observation. AC drive quay crane used 100% more energy

than DC drive quay crane had been observed at other time.


53
Power Factor

Figure 4.9 and Figure 4.10 show graph of Power Factor vs. Time of AC and DC

drive quay cranes when handling 26T container and the numerical results were

shown in Table 4.2. An average Power Factor was also shown in the graphs. This

average Power Factor (as seen by the Utility) was the ratio of kWHr and kVAHr.








3RZHU)DFWRU

$YHUDJH3)

    

Figure 4.9 AC quay crane – Graph of power factor vs. time (second) for one
loading cycle.











    3RZHU)DFWRU

$YHUDJH3)

Figure 4.10 DC quay crane – Graph of power factor vs. time (second) for one
loading cycle.

54
As expected, DC drive quay crane had a very poor power factor. However, it is

possible to solve this problem by using a dynamic power factor correction unit. A

dynamic power factor correction unit consists of capacitor banks and power

electronic switches. A microprocessor is used to control the switching to connect an

appropriate amount of corrective capacitance on the “per-cycle” basic (50 cycles

per second for 50Hz system) [55, 56]. The desired power factor can easily be

achieved.

“Crane Factor” from TM GE Automation system or “Pure wave AVC” from S and

C Electric Company are two examples of such unit.

The Melbourne Container Terminal used a Pure Wave AVC unit with a very good

result. For better utilization, the power factor correction unit was connected at the

main 11kV bus bar, which supplied three (3) DC drive quay cranes, two (2) AC

drive quay cranes and 500 outlets for refrigerated containers. Overall power factor

is always greater than 0.9.

So that with the right selection of equipment, poor power factor of DC drive quay

crane was no longer an issue.

Total Harmonic Distortion (TDH)

Measured TDHs of live voltage and current for AC and DC drive quay cranes

during the 26T loading cycle were plotted against time (second) as shown in Figure

4.11 and Figure 4.12. Different scales were used for voltages and currents.

55
 
 

 ,D

 ,E

,F
 
9DE
  9EF

 9FD

 
      

Figure 4.11 AC quay crane – Graph of THD (%) vs. time (second) for one
loading cycle.

 

  ,D
 ,E
 
,F

9DE
 
 9EF
 7+' /LQH  9FD

 
    

Figure 4.12 DC quay crane – Graph of THD (%) vs. time (second) for one
loading cycle.

The measurement shown an abnormal THD value of 830.3% of current on phase b.

AC drive quay crane achieves smaller variation of THDs of voltages and currents.

However, THDs of both AC and DC drive quay cranes were comparable.

56
4.2.3 Study conclusions

With observation and actual measured electrical data of quay cranes with AC drive

and DC drive systems, load profiles of these quay cranes were studied and

understood. It could be concluded that if proper power factor correction and

harmonic compensation were provided, a quay crane with DC drive technology was

a better choice as it produced lower Peak Demand and Energy Usage. However, this

conclusion was simply based on the electrical point of view. Other factors - such as

quay crane weight, wheel load, maintenance, spares, and cost – had to be

considered before making decision of selecting quay crane with AC or DC drive

system.

In the next section, the actual container weight at Melbourne Container Terminal

will be studied to have a better understanding of what sort of loads the container

handling machines have to work with and contribute information for the decision of

selecting the machines’ size.

4.3 Container Weight Analysis

Understanding of the weight of containers that were actually handled by the

container terminal would help in electrical demand calculation in later section.

4.3.1 Weight of container – container ship and ISO standard

Data of ship capacity and deadweight of a number of container ships are sourced

from [14] Wikipedia http://en.wikipedia.org/wiki/Container_ship#Size_categories.

Average container’s weight is calculated using deadweight figures as the weights of

containers.

57
Table 4.3 Container ship capacity and deadweight

Dimensions and weights of containers shown in Table 4.4 were sourced from [13]

www.atmgloballogistics.com/docsjpg/Documents/containerinfo.pdf, interested data

were:

Standard container:
20 foot Gross weight of 24 Tonnes
40 foot Gross weight of 30.48 Tonnes
Refrigerated container:
20 foot Gross weight of 30.48 Tonnes
40 foot Gross weight of 34 Tonnes

Compare these maximum container weight with the average weight of container

from container ship data, it could be said that the container ship would:

- expect to carry a number of empty containers or

- expect loaded containers are not at their maximum weights or

- expect to travel with full capacity or combination of these.

58
59
4.3.2 Weight of container at Melbourne Container Terminal

Collection of container weight data

Details of containers in stacking area as shown in Figure 4.13 at Melbourne

Container Terminal under this study were daily reported around 7:00AM via email.

Due to the limitation of current terminal operator system, these reports could only

be done manually during the week.

Figure 4.13 Container stacking area at Melbourne Container Terminal

Container details were collected every week day for more than one year from

February 2007 till August 2008. There were some period without reports due to the

change of the Terminal’s personnel and failure of recording equipment.

Container report contained information of all container (including reefers) in the

Terminal on a specific date. Each container was detailed as:

x location in the Terminal/Yard

x identification

x Category (import/export/transhipment)

60
x size (20 or 40 foot)

x weight (tonnes)

x commodity – eg. general cargo, paper, frozen juice (FZJC), frozen meet
(FZMT),…

x in bound carrier (container ship name/truck)

x out bound carrier (truck/container ship name)

Sample of container report is shown in Table 4.5.

Table 4.5 Sample of Container daily Report


Current Wt
Container No. Cat Len Comd I/B Carr O/B Car
Position Tns
BBK TOLU8971025 IMPORT 40' 29 OOG MMO9051 TRUCK
C 0211 1 KKTU7263932 IMPORT 20' 4.8 GENL CIM9071 TRUCK
C 0212 1 KKTU7521770 IMPORT 20' 6.1 GENL CIM9071 TRUCK
C 0214 1 MSCU6400084 IMPORT 20' 21.5 GENL MMO9051 TRUCK
C 0215 1 FCIU2217818 IMPORT 20' 24.1 GENL SDR9074 TRUCK
C 0215 2 INBU3282777 IMPORT 20' 20.2 GENL MMO9051 TRUCK
C 0217 1 NYKU2886113 IMPORT 20' 18.7 GENL CIM9071 TRUCK
C 0217 2 MSCU6972201 IMPORT 20' 19.2 GENL MMO9051 TRUCK
C 0611 1 CPSU6002343 IMPORT 40' 10.2 GENL SFB9055 TRUCK
C 0611 2 MSCU9148865 IMPORT 40' 22.6 GENL MMO9051 TRUCK
C 0613 1 GATU8487445 IMPORT 40' 14 GENL SFB9055 TRUCK
C 0613 2 SUDU5608733 IMPORT 40' 28.1 GENL SFB9055 TRUCK
C 0615 1 MSCU4319820 IMPORT 40' 17.5 GENL MMO9051 TRUCK
C 0615 2 GLDU0463460 IMPORT 40' 25.7 GENL MMO9051 TRUCK
C 0617 1 SUDU5848400 IMPORT 40' 19.8 GENL SFB9055 TRUCK
E 0204 2 MWCU5664991 EXPORT 20' 20.4 FZJC R31037G TAT9067
E 0205 1 PONU2850924 EXPORT 20' 20.5 FZJC R31037G TAT9067
E 0209 1 PONU2948783 IMPORT 20' 20.4 REEF SFB9055 TRUCK
E 0209 2 SUDU1089373 IMPORT 20' 17 REEF SFB9055 TRUCK
E 0210 1 SUDU1024691 IMPORT 20' 20.5 REEF SFB9055 RAIL
E 0301 1 CRLU1242231 EXPORT 40' 29.6 FZMT TRUCK TAT9067
E 0301 2 MWMU6431485 EXPORT 40' 22.7 CHMT R31037G TAT9067
E 0303 1 PONU2932426 EXPORT 20' 14.3 CHMT R30037G TAT9067
E 0303 2 MWCU5639751 EXPORT 20' 22 FZMT TRUCK TAT9067
E 0305 1 SUDU1013439 IMPORT 20' 18 REEF HSG9054 TRUCK
U 3401 1 KHS400488 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 3401 2 KHS400461 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 3501 1 MSCU7346218 TRANSSHIP 20' 23.9 TIMB HRT9069 TAT9067
U 3601 1 TOLU8986180 IMPORT 40' 16 OOG UKI9056 TRUCK
V 0101 1 MWCU5742760 IMPORT 20' 13 CHC MDH9077 TRUCK
V 0401 1 PONU2870221 EXPORT 20' 22.5 FZMT TRUCK TAT9067
V 0501 1 TRLU1044459 EXPORT 20' 16 FZMT TRUCK UVA9072
V 0601 1 CBHU2933183 EXPORT 40' 10.9 CHIL TRUCK OOF9079

4/02/2007 7:08:20 AM

61
Although there were some missing data as the results of changing personnel at the

Terminal and measurement equipment malfunction, the number of report were still

too great to be listed or printed. They are available in electronic form upon request.

The main purpose of this data collection scheme was to study the weight of

containers that are handled by the Melbourne Container Terminal to see if there was

a need for quay cranes with higher lifting capacity and to help in demand

calculation in later section.

From the container reports, the following steps were carried out for analysing the

data:

x counting the number of containers with weights less than 5T (empty),

between 5T and 10T, between 10T and 15T, between 15T and 20T, between

20T and 25T, between 25T and 30T and greater than 30T.

x counting the number of containers for import, export or other

(transhipment).

x tabulating these results and calculate the percentages of 40 foot containers,

percentage of containers weighted more than 30T and percentage of empty

containers.

Analysing the reports in their original forms would take too much time for

producing the above results. Microsoft Excel spreadsheet program was used and a

macro CONTAINERS was created to automate the described analysing task.

62
Information of the CONTAINERS macro can be found in Appendix A. Table 4.6

shows the analysed results after running the macro CONTAINERS.

Table 4.6 Results of running “CONTAINERS” macro

4.3.3 Results of analysing data collection

The analysing data of daily container reports were then combined into another table

as shown in Table 4.7 for a long term view of the weight of containers handle at

Melbourne Container Terminal. The analysis results were visualised in Figured

4.14, Figure 4.15 and Figure 4.16 and in numerical were:

x Average weight of 16.7 Tonnes per container

x Average weight of 11.7 Tonnes per TEU

x Less than 5% of containers were weighted more than 30 Tones,

x Around 15% containers were empty,

x Around 45% containers were 40 foot containers.

4.3.4 Conclusions of weight analysis

With collected daily reports of containers at Melbourne Container Terminal and the

analysed results as shown above, it could be concluded that:

63
x Recall from section 4.3.2.1, the maximum gross weight of container was 34

tonnes, from the collected data the container’s maximum weight was 32.5

tonnes with only less than 5% of handled containers were weighted more

than 30 tones. Quay cranes with lifting capacity (safe working load) of 40

tonnes or 50 tonnes are large enough to handle all of the loads in single lift

mode and most of the loads in twin lift mode. As information of the

incoming load (ship stowage plan, container weight,…) would be known in

advance, the container terminal operator could decide if twin lift or tandem

lift was needed for speeding up the unloading of the ship.

x Containers are handled by RMGs or ASCs at the stack yard, these machines

are most likely single lift type due to the need for fast process and the

complicity of computerised automation system. Therefore, a machine with

safe working load of 40 tones was appropriate size for RMG or ASC.

64
65
Melbourne Container Terminal
Number of Containers in stacking yard - 2007/2008







 1RRIFRQWDLQHU
Number


FRQWDLQHU
7(8







                  
)H 0 $ 0 -X -X $ 6 2 1 ' -D )H 0 $ 0 -X -X $
E DU SU D\ Q O XJ HS FW RY HF Q E DU SU D\ Q O XJ
                  
           

Date

Figure 4.14 Number of container at Melbourne Container Terminal in 2007


- 2008

Melbourne Container Terminal


Containers in stacking yard - 2007/2008






Percentage

ZHLJKW!7
 HPSW\FRQWDLQHU

FRQWDLQHU






                  
)H 0 $S 0 -X -X $X 6H 2 1 ' -D )H 0 $S 0 -X -X $X
E DU U  D\ Q O J S FW RY HF Q E DU U D\ Q O J
                 
              

Date

Figure 4.15 Percentage of 40’ container, empty container and heavy


container at Melbourne Container Terminal in 2007 - 2008

66
Melbourne Container Terminal
Containers in stacking yard - Average Weight






Weight (Tones)

'DLO\$YH&RQWDLQHUZHLJKW
'DLO\$YH7(8ZHLJKW
 $YH&RQWDLQHU:HLJKW
$YH7(8:HLJKW






                  
                  
                  
                  
  

Date

Figure 4.16 Average weight of container and TEU at Melbourne Container


Terminal in 2007 - 2008

4.4 Calculate Demand and Energy usage of container handling


cranes

All these container handling cranes are very similar. Only quay cranes have a boom

structure to allow loading/unloading containers to/from the container ship, this

boom has to be in stow position to avoid collision with the ship control bridge when

the container ship berthing or leaving the port. All machines use other motions:

hoist/lower, cross travel and long travel. The differences are the paths of travel.

Using the calculation formulas listed in Chapter 2 together with the actual

mechanical and electrical data of container handling machine to calculate the

demand and energy usage before conclusions were drawn.

4.4.1 Quay Cranes and maximum Electrical Demand

For QCs, the boom and long travel motions were ignored when calculating the

maximum electrical demand because:

67
x the boom motion is only used to put it in the working position to start

loading/unloading containers and to stow the boom at the end of its work,

x other motions are not available when boom hoist is in use.

x the boom’s electrical motor is not as large as the hoist’s electrical motor, the

demand is not the maximum demand,

x similarly the long travel’s electrical motor is not the largest and the demand

is not the maximum demand.

After the container ship was securely berthed along the wharf, the assigned several

quay cranes were long travelled to a ship bay, the boom then be lowered to working

position ready for loading/unloading containers to/from the container ship.

Hoist/lower and cross travel motions were needed for loading and unloading the

container and they were normally operated concurrently. Quay crane was long

travelled to the next bay when finish the current bay.

The unloading (or loading) cycle time was depended on the location of the

container on the ship to be unloaded (or the location for the container to be loaded

onto the ship) that was the required travel distances. Average cycle time was less

than two (2) minutes as most of the container terminals publish their crane rate

around 45 containers per hour. The cycle time was well within the electricity

measure period of 15 minutes or 30 minutes of the Utilities so that average demand

calculation method can be used. Figure 4.17 showed how the quay crane electrical

demand was calculated.

68
Figure 4.17 Calculation of average electrical demand of a quay crane

With actual specifications of at least four (4) different quay cranes from different

manufactures at Melbourne Container Terminal, a Microsoft Excel spreadsheet had

been created with all above formulas as the base model. Several simulations were

carried out:

x with a specific loading/unloading cycle, average demands was calculated for

different loads for each crane,

x with a specific crane, average demands were calculated for an actual

working shift,

It was found that:

69
x For a single lift operation (that is container load < 35 tones) with the same

cycle, the calculated average demands were slight different for different

quay cranes mainly because of the auxiliary loads.

x For a single lift operation, the calculated average demands were found to be

less than 250kW. Therefore the maximum demand for a single lift quay

crane is 250kW.

x For twin lift operation, the calculated average demands were found to be

less than 350kW. Therefore the maximum demand for a twin lift quay crane

is 350kW.

The average demand of RMG and ASC would be investigated in the next section

4.4.2 RMG and ASC and maximum Electrical Demand

RMGs and ASCs are very similar, the ASCs are actual the automation version of

the RMGs. Due to the working environment (within container stacking area with lot

of obstacle) and short lifting height and short cross travel distance, they are

normally single lift type and on “single motion” operation mode. For example, cross

travel motion only starts when hoist is at the top limit and long travel only starts

when cross travel motion is completed.

For stacking operation: after the container was delivered at the end of the stack by

staddle carrier, a RMG/ASC picked up the container, hoist to the top limit, cross

travelled to the safe position ready for long travel motion. The RMG/ASC then long

travelled to the pre-set row location in the stack, cross travelled to the correct lane

then lowered the container to its storage location, hoisted without load, cross

travelled to the travel position, long travelled back to the end of the stack and

70
complete the cycle by lowered to the next container. Deliver cycle was in reverse

order.

Again, the stacking (or deliver) cycle time was depended on the location of the

container in the stack to be stored (or the location of the container in the stack to be

pickup) that was the required travel distances. Average cycle time was also well

within the electricity measure period of 15 minutes or 30 minutes of the Utilities,

especially the cycle time of ASCs as they were controlled by computer and

optimised for speed. Figure 4.22 shows how the RMG/ASC electrical demand is

calculated.

Figure 4.18 Calculation of average electrical demand of a RMG/ASC

As there are not any RMG and ASC at Melbourne container terminal, these

machines specifications were obtained from other terminals: RMG specifications

were from Sydney container terminal at Port Botany and ASC specifications were

71
from Brisbane container terminal at Fisherman Island. Again a Microsoft Excel

spreadsheet had been created with all above formulas as the base model and similar

simulations were carried out:

x with a specific cycle, average demands were calculated for different loads

for each machine,

x with a specific machine, average demands were calculated for different

cycles.

Examples of these calculation simulations were listed in Appendix E.

It was found that:

x For the same cycle, the calculated average demands were slight different for

different RMG and ASC mainly because of the auxiliary loads.

x For container load of up to 35T, the calculated average demands were found

to be less than 200kW. Therefore the maximum demand for RMG and ASC

was 200kW.

4.5 Conclusions

Container handling cranes and their operation were briefly described to help

readers, who are not familiar with these machines, to have a basic understanding of

how they are operated.

The electrical characteristics of quay cranes with different drive systems: AC drive

and DC drive were recorded and comparisons were made as contribution to the

debate of AC verus DC control system.

72
Formulas for calculation of the average demand of two (2) main motions of the

container handling cranes listed in Chapter 2 were used for calculation. These

formulas were used with the actual specifications of quay cranes in Melbourne,

RMG in Sydney and ASC in Brisbane to perform the spreadsheet simulation for

finding the maximum demand of each type of machine.

The results were found to be:

x Maximum demand for a single lift quay crane was 250kW

x Maximum demand for a twinlift quay crane was 350kW

x Maximum demand for a RMG or ASC was 200kW

The next big electrical energy usage and large electrical demand – the refrigerated

containers – were investigated in the next chapter.

73
CHAPTER FIVE

Refrigerated Container

Following the study of big electrical machines at Melbourne Container Terminal in

previous chapter, the refrigerated containers - the next major electrical usage –

would be now studied in this chapter.

In contrary to the impression that the big and fast cranes would have a huge

electrical usage and demand, refrigerated containers were actually the biggest

electrical usage and demand at the Container Terminal due to their number and the

need of electrical power for refrigeration all the time. Just over one thousand (1000)

spaces for 20 foot refrigerated containers were available at Melbourne Container

Terminal.

It was important to estimate the electrical demand of refrigerated container as

accurate as possible because it would have a huge impact on designing and

installing the electrical infrastructure to provide power for those refrigerated

containers.

5.1 Brief Discussion of Refrigerated Container

Refrigerated Containers or Reefers are used for goods which need to be transported

at a constant temperature above or below freezing point. These goods are divided

into chilled goods and frozen goods, depending on the specified transport

74
temperature. They principally include fruit, vegetables, meat and dairy products,

such as butter and cheese.

As described in [4], there are two types of refrigerated containers:

a. Porthole refrigerated containers, also called insulated containers, do not

have their own refrigeration unit. They are thus reliant on an external supply

of cold air. Refrigeration units of various types, permanently installed on the

ship (Figure 5.1), permanently installed in the terminal or clip-on units

(Figure 5.2) for individual containers, are used for this.

Figure 5.1 Refrigeration supply system Figure 5.2 Clip-on unit for
for porthole container. transport by road.
Source: the container handbook [4]

Figure 5.3 Portholes at the end of a porthole container


Source: the container handbook [4]

b. Integral refrigerated containers (Figure 5.4), on the other hand, have an

integral refrigeration unit for controlling the temperature inside the

75
container. The refrigeration unit is generally powered by a 3 phase electric

power supply and is arranged in such a way that the external dimensions of

the container meet ISO standards.

Figure 5.4 Integral refrigerated containers

Technical details such as dimensions and construction as well as the reefer’s

operation and control were not discussed here as power usage and electrical demand

were the main purposes of this study.

Depending on the system used at the container terminal, the reefer maximum

electrical demand was the value of the permanent installed system or the individual

reefer or combination of both types.

5.2 Estimate Electrical Demand of Refrigerated Container

A permanent installed system at Container Terminal to supply cool air for portholes

reefers would only be run when there is a need for such refrigeration. The demand

of this system is only of interested if it is an electric powered system, the electrical

demand would therefore be the rated value of the system and be readily available

from the supplier.

76
For an integral refrigerated container, it would be harder to estimate the electrical

demand due to the fact that many different products (kept at different temperatures)

could be carried by the same reefer. A reefer does no longer require full power all

the time after cooled down to the set temperature, thus a diversity factor shall be

applied to a large number of reefers connected to the same power supply source. In

other words, an average electrical demand was to be estimated.

To reach that estimation with degree of accuracy, the following steps were carried

out:

x investigating current practice,

x developing a way for calculate electrical demands of reefers,

x analysing data collected over two (2) years period,

x comparing the three results then concluding with the required electrical

demand.

5.2.1 Maximum Demand of a Reefer Stack

It is a fortunate that the author had access to a number of electrical assessment

reports that were done for various container terminals by different consultant group.

Calculation of maximum demand was part of the reports and mostly done with

practical assumptions. Those calculation approaches were described in the

following section.

5.2.1.1 Demand calculation using Australian Standard AS3000

Australian Standard AS3000 [62] does have information about the maximum

demand of an electrical installation. Four methods are listed in the Standard:

calculation, assessment, measurement and limitation as per following extraction:


77
Extract from AS 3000 - 2007

2.2.2 Maximum demand

The maximum demand in consumers mains, sub-mains and final sub-circuits, taking
account of the physical distribution and intended usage of electrical equipment in
the electrical installation and the manner in which the present requirements might
vary, shall be determined using one of the methods set out in Items (a) to (d).

If the actual measured maximum demand is found to exceed that obtained by


calculation or assessment, the measured value shall be deemed to be the maximum
demand.

NOTE: Guidance on the determination of maximum demand is provided for basic


electrical installations in Appendix C.

(a) Calculation The maximum demand may be calculated in accordance with


the guidance given in Appendix C for the appropriate type of electrical
installation and electrical equipment supplied. It is recognized that there
may be considerable differences in loading from one electrical installation
to another. Alternative methods of calculating the maximum demand may be
used taking account of all the relevant information available for any
particular electrical installation.

(b) Assessment The maximum demand may be assessed where:


(i) the electrical equipment operates under conditions of fluctuating or
intermittent loading, or a definite duty cycle; or
(ii) the electrical installation is large and complex; or
(iii) special types of occupancy exist.

(c) Measurement The maximum demand may be determined by the highest rate
of consumption of electricity recorded or sustained over any 15 min period
or periods when demand is at its highest by a maximum demand indicator or
recorder.

(d) Limitation The maximum demand may be determined by the current rating
of a fixed setting circuit breaker, or by the load setting of an adjustable
circuit breaker.

78
The maximum demand of consumers mains and sub-mains may be determined by
the sum of the current settings of the circuit breakers protecting the associated final
sub-circuit/s and any further sub-main/s.

Table 5.1 Maximum Demand non-Domestic Electrical Installation*

1 2 3
Residential Institutions, Factories, shops, stores,
hotels, boarding offices, business
Load group houses, hospitals, premises, schools and
accommodation churches
houses, motel
A. Lighting other than in load 75% of connected load Full connected load
group F
B.
1000W for first outlet 1000W for first outlet
(i) Socket outlets not
plus 400W for each plus 750W for each
exceeding 10A other
additional outlet additional outlet
than those in B (ii)
(ii) Socket outlets not
exceeding 10A in
buildings or portions of
1000W for first outlet plus 100W for each
building provide with
additional outlet
permanent installed
heating or cooling
equipment or both.
Full current rating of Full current rating of
highest rated socket highest rated socket
(iii) Socket outlets exceeding
outlet plus 50% of full outlet plus 75% of full
10A
current ration of current ration of
remainder remainder
C. Appliances for cooking,
Full connected load of Full connected load of
heating and cooling, incl.
highest rated appliance highest rated appliance
instant water heaters but
plus 50% of full load of plus 75% of full load of
not appliances included in
remainder remainder
group D and J below.

* adapted from Table C2 of AS/NZS 3000

At container terminal, reefers are powered via a three phase 30 Amperes socket.

Using calculation method and guidance Table 5.1 as per above extraction, the

maximum demand of a reefer stack is given by:

Current _ Demand Max 30  ( Number _ of _ reefers  1) * 30 * 0.75 (A)

79
3 * Current _ Demand Max * 415
Demand Max (kVA)
1000

In 2010, a consultant used this method of calculation for the redevelopment project

at Webb dock in the port of Melbourne. Result from this calculation was very

conservative, it was found to be more than double the results from other calculation

methods.

5.2.1.2 Demand calculation using diversity factor

For an expansion of P&O Sydney Container Terminal project in 2006, a Maximum

Demand Analysis submitted by a consultant using the following approach to

estimate the maximum demand of a reefer stack:

i. examining reefer nameplate data and deciding rated load values for 20 foot

reefer and 40 foot reefer,

ii. calculating a diversity factor (DF) by:

- choosing a day for observation, measuring an actual demand, recording

number of connected reefers and ambient temperature on that day then

with selected value in (i), the diversity factor was calculated as:

Actual _ Demand
DF
Actual _ Re efer _ Number * Re efer _ Rated _ Load

80
- using historical maximum demand of an existing reefer stack and

assuming it occurred when the stack was full with a ration of 20 foot

reefers and 40 foot reefers is 2:1, the diversity factor was calculated as:

Historical _ Maximum _ Demand


DF
Number _ of _ Re eferStack _ full * Re efer _ Rated _ Load

- select the higher value of calculated diversity factor

iii. the maximum demand for such reefer stack was then given by

Demand Max DF * ( Number20'_ reefer * Load 20 '_ reefer  Number40 '_ reefer * Load 40 '_ reefer )

For Patrick Sydney Container Terminal redevelopment project in 2004, maximum

demand of a proposed reefer stack was calculated in the same way but with an

assumed diversity factor of 0.8 without any explanation.

5.2.1.3 Other demand calculation method

Another approach was used by consultant working on development of London

Gateway container terminal in England. Utilisation factor and simultaneous factor

are used in this approach. The definitions are:

Utilisation factor is the ratio of the Root Mean Square (RMS) power and the Peak

power.

Simultaneous factor is actually another name for diversity factor.

81
This approach was based on the information, especially the reefer’s average power

consumption value, in the Container Handbook [4] published by German Insurance

Association (Gesamtverband der Deutschen Versicherungswirtschaft e.V. (GDV).

i. using typical reefer’s nameplate rated load,

ii. the utilisation factor (UF) was calculated as:

RMS _ power 3.6


UF 0.24
Peak _ power 15

Where Peak power = 15 kW typical reefer peak load


RMS power = 3.6 kW/TEU obtained from the Container Handbook
1 x 40 foot container = 2 TEU
1 x 20 foot container = 1 TEU

iii. simultaneous factor was already covered in above calculation as average

power was actually used instead of RMS value,

iv. discussing about this specific installation and providing reasons for choosing

different UF value (usually a higher value) then use this UF to calculate the

maximum demand :

Peak _ Load reefer


Demand Max ( Number20 '_ reefer  2 * Number40 '_ reefer ) *
UF

5.2.1.4 Reefer demand information from Container Handbook

The technical aspects of reefers, especially the actual electrical consumption, were

discussed in details and described in chapter 8 of The Container Handbook [4] by

82
Dr. Yves Wild. On line version is available and full access to the book is provided

at http://www.containerhandbuch.de/chb_e/stra/index.html.

It appears that the published information was results of taking actual measurements

For the purposes of this study, the following conclusions of this discussion are of

interest:

For a very broad average value for all container types, ambient conditions and
cargo types, the value 3.6 kW/TEU can be used. A 20' container tends to be closer
to 4 kW and a 40' container tends towards 7 kW. As a result of new developments
and the associated improvements in the efficiency of the containers, this value is
dropping.

5.2.1.5 Demand calculation based on heat transfer and required cooling

Introduction

There is at least another way to calculate the reefer demand that was developed

during the course of this study. Considering the operation of the refrigeration unit as

the actual power consumption would depend on its operating status which has only

one purpose: keep the reefer at the required temperature.

Assuming the reefer was at the required temperature when connected to the

electrical grid at the container terminal. On the energy point of view, following

events would happen:

a) Since the required temperature was already reached, the refrigeration was

not required and because of the temperature difference, heat would be

transferred from ambient (high) to the reefer (low) through the reefer

surfaces trying to reach the equilibrium point,

83
b) When reefer temperature raises more than a preset value, the reefer

refrigeration unit would start drawing power from the electrical grid to cool

the cargo (ie. remove the above heat energy out of the reefer) and would not

be required when temperature drop to a preset value.

The cycle would be repeated with a time controlled defrost cycle (where the heating

element would be turned on) run independently.

The heat energy from event (a) had to be equal to the cooling energy from event (b)

because of the principle of energy conservation. Therefore the power consumption

of the reefer in this case is calculated as:

EnergyCool  Energy Auxiliary


Demand Average
Time Heat  TimeCool

Detailed calculation would be discussed later in this section; it is now to investigate

the reefer specifications from different manufacturers for data needed for this

demand calculation method.

Reefer Manufacturers’ Data

There are numbers of reefer manufacturers in the world, the best known are

Thermal King, Carrier, Maersk, Daikin and Mitsubishi. The specifications of the

power units for reefer of those manufacturers could be obtained on line via their

web sites [1, 5, 8, 9, 12].

The interested Cooling Capacity values from these specifications were tabulated in

Table 5.2. All reefer power units from different manufacturers were very

compatible in providing similar cooling capacity at the same temperature. For

example, they all had around 6kW at -18oC available for further cool the cargo

84
and/or compensate for the heat transfer. More power was available at higher

temperature and less power at lower temperature.

Table 5.2 Cooling capacity of Reefer Power Unit

Reefer Power Unit


Maker
Thermal King Carrier Maersk Mitsubishi
Model CRR40 ThinLine Marine Reefer Reefer CPE
Cooling
capacity at Watts Btu/hr Watts Btu/hr Watts Btu/hr(1) Watts Btu/hr(1)
1.7oC / 2oC 11,753 40,100 10,260 35,000 11,735 40,040 11,000 37,530
o
-18 C 6,009 20,500 6,008 20,500 6,540 22,310 6,280 21,430
-29oC 3,107 10,600 3,224 11,000 4,030 13,750 4,420 15,080
(1)
Converted from Watts figures

However, this cooling capacity of the reefer was not the electrical demand or power

required to keep the reefer at the set temperature, this electrical demand was in fact

the sum of:

x cooling power required to keep the cargo at set temperature within a tolerant

temperature band,

x all other reefer electrical loads – compressor, fan, lights, control

processor,…

Demand Calculation formulas and calculation examples

It was assumed that the reefer was at the required temperature, ie. the cargo had

been cooled, when it was at the Container Terminal waiting for loading onto

container ship. In low-temperature mode (below -10°C) the refrigeration unit was

run in on/off mode, whereas in chilled mode (above -10°C) the output of the

85
refrigeration circuit was regulated constantly. The operation is based on a

temperature range settings in the control section of the refrigeration unit (example ±

5oC) would:

x turn on the refrigeration unit when the cargo temperature rise to 5oC above

the required temperature.

x turn off the refrigeration unit when the cargo temperature drop 5oC below

the required temperature.

For the temperature increase over time t, the following equation applies for non-

respiring goods (goods with no respiration heat):

A.k
 t
'T (t ) 'Tambient  'Tambient * e mc p (Eq. 5.1)

where: t time without refrigeration (seconds)


ǻT average temperature increase of the load after time t (oC)
ǻTambient temperature different b/w internal and external of the reefer
(oC)
A surface area of the reefer (m²)
k heat transition coefficient of the reefer (W/m²K)
m mass of the load (kg)
cp specific heat capacity of the load (J/kgK) – see Table 5.3

For the cooling process the following equation can be used:


m .c p .' T
Q average (Eq. 5.2)
t
where: Qaverage average refrigerating capacity for cooling (W)
t cooling time (seconds)
ǻT cargo temperature after time t (oK)
m mass of the load (kg)
cp specific heat capacity of the load (J/kgK) – see table 5.3

The average electrical demand would be calculated as:

86
P * t 2  PAuxiliary * (t1  t 2 )
AverageDemand (Eq. 5.3)
t1  t 2

Where: P cooling capacity at cargo temperature (W)


PAuxiliary Auxiliary loads – controller, fan, lights… (W)
t1 time reefer temperature rise (Hour)
t2 time to cool reefer cargo (Hour)

Steps to calculate the average electrical demand of a reefer with specific cargo

were:

x known T, Tambient, m, k, temperature tolerant range, cooling capacity and A

(from reefer dimensions), using Specific Heat Capacity Table in Appendix

C and references [39, 66, 107, 146] to find value of cp,

x calculate time t1 using formula (Eq. 5.1), time that refrigeration is off and

reefer’s temperature is rising but still within the tolerant band,

x calculate time t2 using formula (Eq. 5.2), time that requires refrigeration to

cool reefer cargo to within tolerant band,

x calculate average demand using (Eq. 5.3).

Results of calculated electrical demand of reefers with different cargo and

assumption were tabulated in Table 5.3.

A number of calculations (shown in Appendix D) were done for a range of reefers

with different products that are at different temperature settings and carrying

different type of cargo as reported at Melbourne Container Terminal, it was

estimated that the electrical demand was between 2.5kW and 6kW. Thus the

electrical maximum demand for each reefer was 4.2 kW when applying a diversity

factor of 0.7.

87
Table 5.3 Calculated Average Electrical Demand of different reefer cargo

3URGXFW /HDQ%HHI %XWWHU *UDSHV 1RWHV


P NJ     
&S J/kgK)    IURP7DEOH
5HHIHU IRRW IRRW IRRW 
$ P     
. W/m²K)    IRUDJHGUHHIHU
ǻT (oC)    
o
ǻTambient ( C)    
o
T ( C)    
Tambient (oC)    
P (W)    IURPUHHIHUPDNHU
PAxiliary (W)    IURPUHHIHUPDNHU
t1 (Hr)    
t2 (Hr)    
Ave. Demand (kW)    

5.3 Measure the actual reefer electrical demand

5.3.1 Description

Reefers at the Melbourne Container Terminal under this study were located at two

areas namely E and L blocks, and were electrical powered via substations C and D

respectively. As mentioned in Chapter 3, the electrical parameters were recorded

every 15 minutes by the EMS server. Historical records could be set to report

automatically or manually.

Details of reefers within the Terminal were also reported daily around 7:00AM via

email. Due to the limitation of current terminal operator system, these reports could

only be done manually during the week.

By matching the number of reefers at each location with their power demands from

above reports, the average reefer actual power demand could be calculated.

88
Figure 5.5 Photo showing Reefer location at Melbourne Container Terminal

Figure 5.6 Drawing showing Reefer location at Melbourne Container


Terminal

5.3.2 Data collection and analysing

Reefer details and Power Demand were collected every week day for more than two

(2) years from February 2007 till August 2009. There were some periods without

89
reports due to the change of the Terminal’s personnel and failure of recording

equipment.

Reefer report contains information of all reefers in the Terminal on a specific date.

Each reefer was detailed as:

x location in the Terminal/Yard

x when (date & time) it is in the Terminal/Yard

x identification

x set temperature

x size (20 or 40 foot)

x weight (ton)

x commodity – eg. frozen juice (FZJC), frozen meet (FZMT),…

x in/out bound (import/export)

x others

Power Demand report contains data of electrical powers at four (4) reefer locations

shown in Figure 5.5 and Figure 5.6. Instantaneous apparent power, reactive power

and real power at specific time of specific date were reported.

Samples of the reefer report and power demand report were shown in Table 5.4 and

Table 5.5 respectively.

90
Table 5.4 Example of Reefer daily Report

Current
Yard In Container No. Temp C Len Wt Tns Comd Cat
Position
E 0109 1 WE2250 SUDU1010337 -18.0¡C 20' 21.4 REEF IMPORT
E 0111 1 SA2157 TOLU7804620 +5.0¡C 40' 21.5 REEF IMPORT
E 0203 1 SA0719 POCU2817218 -25.0¡C 20' 20.8 FZJC EXPORT
E 0203 2 SA0723 PONU2855314 -25.0¡C 20' 20.5 FZJC EXPORT
E 0204 1 SA0726 POCU2827392 -25.0¡C 20' 20.6 FZJC EXPORT
E 0204 2 SA0713 MWCU5664991 -25.0¡C 20' 20.4 FZJC EXPORT
E 0205 1 SA0721 PONU2850924 -25.0¡C 20' 20.5 FZJC EXPORT
E 0209 1 FR0919 PONU2948783 -18.0¡C 20' 20.4 REEF IMPORT
E 0209 2 FR0934 SUDU1089373 +10.0¡C 20' 17 REEF IMPORT
E 0210 1 FR1655 SUDU1024691 -18.0¡C 20' 20.5 REEF IMPORT
E 0301 1 FR0845 CRLU1242231 -18.0¡C 40' 29.6 FZMT EXPORT
E 0301 2 SA0719 MWMU6431485 -1.0¡C 40' 22.7 CHMT EXPORT
E 0303 1 FR0646 PONU2932426 -1.0¡C 20' 14.3 CHMT EXPORT
E 0303 2 FR1448 MWCU5639751 -18.0¡C 20' 22 FZMT EXPORT
E 0305 1 WE1832 SUDU1013439 +7.0¡C 20' 18 REEF IMPORT
E 0306 1 TH2045 CRXU5750618 -18.0¡C 20' 20.5 FZMT EXPORT
E 0308 1 SA1448 MWCU5650998 -1.0¡C 20' 16.2 CHMT EXPORT
E 0308 2 SA1451 PONU2974864 -1.0¡C 20' 15.8 CHMT EXPORT
E 0309 1 SA1444 MWCU5678892 -1.0¡C 20' 17 CHMT EXPORT
E 0309 2 SA1442 MWCU5801137 -1.0¡C 20' 17.1 CHMT EXPORT
V 0501 1 TH1353 TRLU1044459 -18.0¡C 20' 16 FZMT EXPORT
V 0601 1 WE1108 CBHU2933183 +13.0¡C 40' 10.9 CHIL EXPORT

4/02/2007 7:08:09 AM

Although there were some missing data as the results of changing personnel at the

Terminal and measurement equipment malfunction, the number of report were still

too great to be listed or printed. They are available in electronic form upon request.

It should be noted that the measured actual load were more than just the reefers,

they are actual the whole low voltage loads within the substation that consists of air

conditioning system, computer system, general lights, battery chargers, exhaust fans

etc. So that they were already counted for in estimate the Container Terminal

electrical demand. However, the Container Terminal lights were not included as the

reports were done from 7:00AM when those lightings were switched off.

91
92
The main purpose of this measurement scheme was to find the actual maximum

electrical demand of a reefer. The electrical demand could be express in term of

apparent demand (kVA) or real demand (kW) where:

Apparent _ Demand (kVA) Re al _ Demand * Power _ Factor

Power factor (PF) of a reefer was not a constant value, it was found to be between

0.5 and 0.7. The PF value vary between the reefer’s make, model and age. It may

even depend on the reefer status, for example PF may be different when

refrigeration is on (compressor + fan) or off (fan only). Therefore, the analysis

would concentrate on the maximum electrical real demand (in kW).

For each matching pair (same day) of reports shown in Table 5.4 and Table 5.5,

following steps were carried out for analysing the data:

x from the reefer report, counted the number of reefer at each reefer location

– E block east, E block West, L block East and L block West.

x at each reefer location counted the number of

o 20 foot reefers and 40 foot reefers

o for each reefer size, counted number of reefers in frozen mode (<

0oC), chill mode (> 0oC) or fan only mode,

o for each reefer size, counted number of reefers with weight < 10T,

between 10T and 20T, and > 20T,

x from the power report, noted the powers at the same time or at closest time

to the reefer report time,

93
x tabulating these results and calculating the average demand for each reefer

at each reefer location.

Analysing the reports in their original forms would take too much time for

producing the usable results. Microsoft Excel spreadsheet program was used and a

macro REEFERS was created to automate the analysing task in following manner:

x using an Excel file with pre-format tables for entering the analysis results,

x combining the reports, rearranging the data, performing the calculation, and

entering the results into the pre-format tables.

x saving the information in a new Excel file for further analysis.

Information of the REEFERS macro could be found in Appendix B. Table 5.6 and

Table 5.7 showed the analysed results after running the macro REEFERS.

Table 5.6 Results (temperature analysis) of running “REEFERS” macro

94
Table 5.7 Results (weight analysis) of running “REEFERS” macro

5.3.3 Results of analysing data collection

Following information from the daily analysed result Excel file was extracted and

tabulated in another Microsoft Excel file:

x number of 20 foot reefers

x number of 40 foot reefers

x average apparent power, real power and power factor of each reefer

A sample of such data was shown in Table 5.8. Average electrical demand per TEU

(not shown) was also calculated and saved in different columns of the same

worksheet using Excel function.

95
The daily average Electrical Demand per reefer and per TEU were then plotted

against time for year 2007, 2008 and 2009 as shown in Figures 5.7 to Figure 5.12.

So that the maximum value - purpose of this measurement - could be found quickly.

The aim of analysing of collected data is to find the maximum actual average

electrical demand of reefer, make comparison to the calculated values and come up

with the final value of the electrical demand as the result of this study.

Melbourne Container Terminal


kW per Reefer 2007








Demand (kW)

/%ORFN(DVW
 /%RFN:HVW
(%ORFN(DVW

(%ORFN:HVW








 HF

 H E
  HE
  HE
  HE
 DU
 DU
 DU
 SU
 SU
 SU
 SU
 D\
 D\
 D\
 D\
 XQ
 XQ
 XQ
 XO
 XO
 XO
 XO
 XJ
 XJ
 XJ
 XJ
 XJ
 HS
 HS
 HS
 FW
 FW
 FW
 FW
 RY
 RY
 HF
)

'
)
)
)
0
0
0
$
$
$
$
0
0
0
0
-
-
-
-
-
-
-
$
$
$
$
$
6
6
6
2
2
2
2
1
1
'
'

HF

Date

Figure 5.7 Electrical Demand per Reefer in 2007

96
 


97
Melbourne Container Terminal
kW per TEU 2007

/%ORFN(DVW

/%RFN:HVW
(%ORFN(DVW
 (%ORFN:HVW

Demand (kW)



                                      
) ) ) ) 0 0 0 $ $ $ $ 0 0 0 0 - - - - - - - $ $ $ $ $ 6 6 6 2 2 2 2 1 1 ' ' '
HE HE HE HE D D D SU SU SU SU D D D D XQ XQ XQ XO XO XO XO XJ XJ XJ XJ XJ HS HS HS FW FW FW FW RY RY HF HF HF
U U U \ \ \ \
Date

Figure 5.8 Electrical Demand per TEU in 2007

98
Melbourne Container Terminal
kW per Reefer 2008









 /%ORFN(DVW
/%RFN:HVW
(%ORFN(DVW

(%ORFN:HVW

Demand (kW)







                        
                        
DU U U U U U U U U U U U U U Y Y Y Y F F F F F F F
D D D D S S S S S S S S S R R R R H H H H H H H
0 0 0 0 0 $ $ $ $ $ $ $ $ $ 1 1 1 1 ' ' ' ' ' ' '
                        
Date

Figure 5.9 Electrical Demand per Reefer in 2008

99
Melbourne Container Terminal
kW per TEU - 2008





 /%ORFN(DVW
/%RFN:HVW
(%ORFN(DVW
 (%ORFN:HVW

Demand (kW)





                        
                        
DU U U U U U U U U U U U U U Y Y Y Y F F F F F F F
D D D D S S S S S S S S S R R R R H H H H H H H
0 0 0 0 0 $ $ $ $ $ $ $ $ $ 1 1 1 1 ' ' ' ' ' ' '
                        
Date

Figure 5.10 Electrical Demand per TEU in 2008

100
Melbourne Container Terminal
kW per Reefer 2009







/%ORFN(DVW
 /%RFN:HVW
(%ORFN(DVW

Demand kW
(%ORFN:HVW






                                
- - - ) ) ) ) 0 0 0 0 0 $ $ $ $ 0 0 0 0 - - - - - - - - - $ $ $ $
DQ DQ DQ HE HE HE HE D D D D D S S S S D D D D XQ XQ XQ XQ XQ XO XO XO XO X X X X
U U U U U U U U U \ \ \ \ J J J J
Date


Figure 5.11 Electrical Demand per Reefer in 2009

101


Melbourne Container Terminal


kW per TEU - 2009





 /%ORFN(DVW
/%RFN:HVW
 (%ORFN(DVW

Demand kW
(%ORFN:HVW






                                
- - - ) ) ) ) 0 0 0 0 0 $ $ $ $ 0 0 0 0 - - - - - - - - - $ $ $ $
DQ DQ DQ HE HE HE HE D D D D D S S S S D D D D XQ XQ XQ XQ XQ XO XO XO XO X X X X
U U U U U U U U U \ \ \ \ J J J J
Date

Figure 5.12 Electrical Demand per TEU in 2009

102
The following were observed from these plots:

a. In early 2007, reefer electrical demand at L block West and E block East was

high with average maximum of 5kW and a few exceptions with the highest

value of 7.64kW on 7 June 2007. However, from August 2007 the reefer

electrical demand was consistently less than 4kW at all location.

b. In 2008, the reefer electrical demand was also less than 4kW

c. In 2009, the reefer electrical demand was similar to data in 2008 that was less

than 4kW but with larger variation and few exceptions that electrical demand

exceeded 4kW with the highest of 5.41 kW on 22 Jan 2009.

d. With above observation, it was safe to conclude that the maximum average

electrical demand per reefer was 4kW.

e. Electrical demand per TEU plot had similar shape to the corresponding

electrical demand per reefer plot as it was averaged over a higher number. The

maximum average electrical demand per TEU was found to be 3kW.

103
5.4 Comparison of maximum demand calculated by different

methods

A reefer stack with 510 outlets (power plugs) was used for calculating the maximum

demand using different methods that described above. The results were tabulated in

Table 5.9 for comparison. All assumptions were also listed in this table.

Table 5.9 Maximum Demand calculated using different methods

As shown in the table, the maximum demand calculation using heat transfer and

required cooling method gave the best result when compared to the actual

measurement.

The information from The Container Handbook was the second closest one. It stated

that “…improvements in the efficiency of the containers, this value is dropping…”,

however, the new value had not yet been published.

104
AS3000 calculation method was too conservative with a result almost triple the actual

measurement. The maximum current that can safety flow in the circuit was used for

calculation instead of the maximum current required by the reefer power unit.

Therefore, it could be stated that the calculation was for the maximum capacity of the

electrical infrastructure

Results from the other two methods were on the high side as too many assumptions

were made so that accuracy could not be always guaranteed.

Following reasons were used to help deciding which value of the reefer electrical

demand to be used for estimating the electrical power demand of a Container Terminal:

x As mentioned before, the measure electrical demands were for all low voltage

loads that included air conditioning system, general lights, battery chargers,

exhaust fans, general power supply etc. There were always activities (substation

maintenance work, charging electrical tools,…) within the Container Terminal

that required electrical power resulting in a higher measured electrical demand.

The collected data were large enough to enable the inclusion of those extra

loads and ignoring a few abnormal values.

x There was a potential problem with reefer load which is known to the industry

as “hot boxes”. The “hot boxes” are reefers that are not cold down to the

required set temperature when delivered to the Container Terminal for loading

onto a ship in a few day times. During these stays, electrical power is used to

reduce these reefer temperatures to the required values. This cost shifting

105
exercise will increase the reefer electrical demand at the Container Terminal

and might cause the “spikes” in the above plots.

x The electrical demand per reefer was calculated for each reefer, it was not

distinguishing between the 20 and 40 foot reefers. In the author opinion, it was

the best way to use in estimating the average reefer electrical demand. The

reason for this is that both type of reefers were using the same refrigerated unit

especially the ones from Thermo King and Carrier the two leading reefer

manufacturers. By using number of reefer instead of the TEU number, the

calculated electrical demand would actually on the high side thus produce a

safety factor in electrical demand estimation. It was also noted that when the

ration between 20 foot reefers and 40 foot reefer was 2/1 then the maximum

demand will be the same using either demand per reefer value or demand per

TEU value.

x It was normal practice to store 20 and 40 foot reefers together as shown in

Figure 5.13 . As a result, there was always empty or unused space in the reefer

area. For example, with a “two high” stacking area, a 40 foot reefer could not be

put on top of two 20 foot reefers or via versa. A “stacking factor”, which is

defined as the ratio between the actual number of reefers and the available

reefer spaces, could be used to describe this situation. By experiences, a

stacking factor of 0.7 could be used for this Melbourne Container Terminal. Not

applying this stacking factor, the estimate Reefer Electrical Demand would

have a safety margin for error.

106
x Two years of daily observation was indeed a long time observation, collected

data would produce a reliable and accurate result that cover all variations due

to:

o number of reefer traffic in different seasons during the years,

o number of reefer with different cargo types (foods, fruits, dairies

products,…),

o extra loads from normal operation within the container terminal

Figure 5.13 Mix Reefer sizes in storage at Melbourne Container Terminal

Studying the comparison of the electrical demands estimated by using different

methods together with all above reasons, the result from actual measured reefer

electrical data would come first as the most reliable value to be used.

107
Therefore, an electrical demand of 4kW per reefer could be used for calculating the

Container Terminal electrical demand and decision of applying stacking factor or not

would be left for the engineer who would calculate the total electrical demand of the

terminal.

5.5 Conclusions

Refrigerated Containers were briefly described. Several different methods of

calculating the average electrical demand of a number of refrigerated containers were

presented and explained. A new approach to calculate electrical demand based on

energy conservation principle was also described with calculation example. The actual

electrical demand was also measured for more than two (2) years and the data were

carefully studied to yield a result of an electrical demand of 4kW for a 20 or 40 foot

reefer.

The study of major electric powered assets at the Container Terminal was now

completed producing results for calculating the maximum electrical demand of the

container terminal. The next chapter would exploring ways of reducing the total

electrical demand of the Terminal before verifying the results against the actual data.

108
CHAPTER SIX

Reducing electrical maximum demand & energy usage

The maximum demand of container terminal was now can be calculated with the

findings from previous chapters. However, before going to verify and check the

accuracy of such calculation and conclude the study, it was worth to discuss the

possibilities of reducing electric demand and energy usage at container terminal, a

required task for today terminal operator [17, 44].

This chapter investigates the methods of reducing the electrical demand and energy

usage at container terminal.

6.1 Reducing electrical maximum demand

Due to the operation conditions at container terminal, the author could see only two

ways to reduce the maximum demand: improving power factor and using cranes with

DC instead of AC drive system. Details were in the following sections.

6.1.1 Improving power factor to reduce maximum demand

Recalling the power triangle:

Apparent Power (VA)


Reactive Power (VAr)
Phase angle

109
Real Power (W)

And the power factor is defined by:

Re al _ Power
PF
Apparent _ Power

Most of the container terminals are on kVA tariff which the charged electrical demand

is the apparent power (kVA) and since the real power cannot be changed, the only way

to reduce the kVA demand is to increase the power factor or reducing the reactive

power component.

As accessed in Chapter 3, there were three groups of electrical load at a container

terminal: container handling cranes, refrigerated containers (reefers) and other loads.

The typical power factors of these groups were:

x Container handling cranes :

with AC drive system - power factor is between 0.9 and 0.95

with DC drive system - power factor varies from 0.3 to 0.6

x Reefers: power factor around 0.6

x Other electrical loads: power factor around 0.8

The overall power factor at container terminal varies between 0.5 and 0.7 depending on

how many cranes with DC drive system at the container terminal, how often the cranes

are used and the number of refrigerated containers are in the yard. Improving power

factor would significantly reduce the electrical demand at the terminal. For example,

110
the kVA demand would be reduced by 22% if the power factor increases from 0.7 to

0.9. Power capacitors are used to improve the power factor and they are referred as

“power factor correction” or “VAR compensation” unit. There are two types of

compensation devices:

x Static – using mechanical contactor for switching capacitors in/out to provide

the required reactive power. Used for slow change or constant load such as

reefers.

x Dynamic [55, 126] – using solid state contacts for switching capacitors in/out to

provide the required reactive power. Used for fast change load such as cranes.

Typical cost for a static unit was about $90 per kVAr and about $200 per kVAr for a

dynamic power factor correction unit.

Melbourne container terminal had a very poor power factor around 0.5 due to all quay

cranes were with DC drive system. Although this terminal was on kW (real power

tariff) and there would be no financial benefit for improving the power factor, a 2

MVAr dynamic power factor correction unit was installed in 2006 to reduce the

terminal kVA demand and provide the spare capacity for connecting two new quay

cranes to the existing electrical infrastructure network without any upgrade work. The

effect of such installation was shown in Figure 6.1.

From Figure 6.1, maximum demand was 3100 kVA at power factor of 0.5 before the

commissioning of the power factor correction unit. This demand was reduced to 1800

kVA at unity power factor, a reduction of 42% and provided a spare capacity of 1300

111
kVA for new load or a substantial reduction of running cost (electricity bill) for the

terminal.

Reducing demand might also help to eliminate the voltage sag and flickering problems

for container terminal with weak power supply.

Figure 6.1 Reducing electrical demand by improving power factor

6.1.2 Using cranes with DC drive system to reduce maximum demand

Since the introduction of IGBT based AC drive products in the late 1980s, there had

been much debate on which technology – AC or DC drive – should be used by the

crane industry for new container cranes. References [15, 93, 148] give good guides for

selection between AC and DC drive.

112
It was fortunate that profiles of both quay cranes with DC and AC drive systems were

obtained in this study as described in Chapter 4 to enable the comparison of the peak

demand of different drive systems. Full details of comparisons were presented at the 6th

International Conference on Power Quality and Supply Reliability [58].

As detailed studied in Chapter 3 and Chapter 4, the maximum demand was the average

demand over the 15 or 30 minute interval and from Table 4.2, the AC quay crane kW

demand was 40% higher than that of the DC quay crane. Taking into account the

driver’s techniques, the final position of the container and other containers on the ship,

the difference was still expected to be in the low 20%.

Therefore, if all DC drive system was used on all container handling cranes and with

power factor correction unit(s) deployment, at least a 20% reduction in maximum

demand could be achieved. Dynamic power factor correction had to be used to provide

the correction as container handling cranes were the fast changing loads.

6.2 Reducing electrical energy usage

There were number of ways to reduce the energy usage at container terminal

6.2.1 Using cranes with DC drive system to reduce energy usage

Again as detailed studied in Chapter 4, with higher peak and average demand, the

energy usage had to be higher for AC drive quay crane. An average of 60% more

113
energy was required to handle a container during this observation. AC drive quay crane

used 100% more energy than DC drive quay crane had been observed at other time.

An 2005 internal study of energy consumption of quay cranes at Yantian international

container terminal in China [95] found similar results as shown in Table 6.1.

6.2.2 Utilisation of the regenerative energy to reduce energy usage

Depending on the capacity of the terminal there were a number of major items of plant

and equipment consuming electrical energy. These included:

x Container handling cranes (when hoisting, trolleying and raising the boom plus

auxiliary loads such as air conditioners, fans, lighting, …),

x Refrigerated containers (reefers),

x Offices and workshops,

x Lighting.

However when a container handling crane was lowering a load or the boom being

lowered, the relevant drive system motors became generators producing electrical

energy (regenerative energy) and sending it back into the electrical distribution

network.

114
Table 6.1 Extract from Yantian 2005 internal report on QC ENERGY CONSUMPTION STUDY

DC Quay crane
AC Quay crane

115
This regenerative energy could be utilized within the container terminal by other

loads (other cranes, reefers, office,…) reducing the electrical energy demand from

the network. However, if the container terminal did not have sufficient overall

demand capacity to absorb this regenerative energy or had an internal electrical

distribution not configured to utilise this energy, the regenerative energy was then

returned to the network that was lost to the container terminal.

Magnitude of regenerative energy

As described in Chapter 3, a data collection scheme was set up at the Melbourne

container terminal with digital meter installed at every switch and circuit breaker.

Figure 6.2 shows the single line diagram of substation D at Melbourne container

terminal where supply to each of the quay cranes was fitted with digital meter

where the recorded consumed energies are presented in this section.

Accumulated real energies (kWHrs) were recorded for each quay crane; refer

supply and overall supply (feeder). Energy usage and regenerative energy were

calculated for different scenario and tabulated in Table 6.2 where:

x In : energy flows from the electrical network to the load

x Out: energy flows from the load to the electrical network (regenerative)

x Sum : calculated sum for quay cranes and Terminal

116
Figure 6.2 Single line diagram of substation D

With data collected for 18 months tabulated in Table 6.2, followings are observed:

x Regenerative energy from quay crane varied between 17.63% and 24.73%

of consumed energy of such crane.

x If all quay cranes and reefer were individual metered – past practice at the

Port of Brisbane in Australia - then the regenerative energy was 9.21% of

the terminal’s total energy consumption.

x These quay cranes were supplied from the same feeder and operate

independently of each other. The regenerative energy was partly utilised

(some quay cranes were lifting while the other were lowering) so that the

overall regenerative energy was 11.45% of the quay cranes’ energy

117
consumption or 4.40% of terminal’s total energy consumption. This amount

of energy would be lost if there was no other load.

x With the reefer supply on the same feeder, the regenerative energy was

further utilised and the net regenerative energy lost to the network was only

0.47%.

Interesting articles on this topic could be found at [26, 28, 31]. The above
observations were shown in Figure 6.3 and Figure 6.4.

118
Table 6.2 Recorded consumed real energies at substation D

Date 3/12/2008 18/06/2010 Consumption


Time 11:30 10:30 3/12/08 to 18/6/10 Regenerative Energy (%)
kWhrs kWhrs kWhrs
No.4 In 1,054,642 1,802,957 748,315
Out 194,554 326,499 131,945 17.63%
No.5 In 443,207 1,382,928 939,721
Out 101,166 302,547 201,381 21.43%
No.6 In 785,137 1,250,772 465,635
Out 172,753 262,183 89,430 19.21%
No.7 In 1,495,173 2,882,382 1,387,209
Out 339,424 682,453 343,029 24.73%
No.8 In 1,530,626 2,762,080 1,231,454
Out 323,057 614,833 291,776 23.69%
L Block – EAST Total 4,816,574 7,179,158 2,362,584

L Block – WEST Total 7,488,193 11,838,147 4,349,954

Terminal – Sum In 17,613,552 29,098,424 11,484,872


Individual metered Out 1,130,954 2,188,515 1,057,561 9.21%
Quay crane - Sum In 4,195,230 11.45% of cranes
Out 480,457 4.40% of terminal
In 18,125,541 29,033,309 10,907,768
Feeder No. 2
Out 21,381 72,920 51,539 0.47%

119
Figure 6.3 Energy consumption without utilization of regenerative energy

120
Figure 6.4 Energy consumption with utilization of regenerative energy

121
Reducing Energy usage with the design of electrical infrastructure

As shown in Figure 6.3, if the container handling cranes and reefer supply were

individually metered then regenerative energy could not be utilised and would be lost.

This practice was used in the past at the Port of Brisbane in Australia as part of its

electricity redistribution from the Utilities.

Today, most of the container terminals have multiple feeders with a single meter

number so that the amount of utilised regenerative energy is depended on how the

electrical infrastructure was designed and what kind of base load (reefers, office,

workshop,…) it has.

Awareness of the existing of regenerative energy and its source when designing the

new electrical infrastructure or re-configuring the existing one of a container terminal

would help to reduce the electrical energy usage (up to 9.21% in Melbourne container

terminal case).

Reducing energy usage with ‘net metering’

Reference [150] provides good information. On this topic.This topic was presented at

the 2008 International Universities Power Engineering Conference in Italy [59].

122
The digital energy meters now used are capable of measuring and recording the

quantity of energy flow both from the electrical network into the container terminal and

the regenerative energy fed back into the network.

Under most electrical tariff structures the Utilities are not required to compensate the

consumer for regenerative energy or at least only charge the ‘net’ electricity. However,

the container terminal as a large electricity user in a competitive electricity market

would be in a strong position in negotiating for a supply contract which recognised the

presence of regenerative energy and only charge the ‘net’ electricity. To get a desired

result, the personnel who do the negotiation for the power supply contract should be

aware of the regenerative energy issue.

6.2.3 Reduce energy usage by lighting

Container terminal is a 24 hours per day operation area, lighting was fundamental to

the safe and secure of the container terminal for both vehicle and foot traffic. The

correct light levels were required to avoid simple trip and slip hazards to personnel and

the safe handling of goods and equipment that exists in a busy environment. Guide for

such lighting level could be found in [2] and [19].

123
Figure 6.5 High mast lighting at container terminal

To provide lighting for a large area with as uniform as possible, the high intensity

discharge (HID) lamps had to be mounted on high masts normally at 30 metres as

shown in Figure 6.5. Container terminal at night was shown in Figure 6.6.

Figure 6.6 Container terminal at night

124
For any redevelopment plan at the container terminal to cope with the forecast

throughput, there was no doubt that electrical infrastructure, especially the terminal

lighting system, would have to be part of the plan. Any electrical work had to meet all

new requirements from latest Standard, the existing lighting levels had to be checked

and the terminal operators would look to use the latest technologies to improve its

lighting system and reduce the energy usage.

There were several options to consider when upgrade the lighting system and saving

energy usage:

Prismalence system: most luminaries produce a globe like output, only a part of the

light volume reach the target area, the rest becomes stray light or glare. Prismalence

uses the prismatic lenses system to create pyramids of light where the target area is the

same while the light volume and glare is much less. A claim that its 150W unit is

comparable to a 400W high pressure sodium lamp. However, Prismalence could not

make an offer to a recent lighting upgrade project in Sydney due to the requirements

that existing high masts have to be used.

LED lighting system: similar to the prismalence system, the LEDs emit light in a

single forward direction. Properly designed LED modules can produce high lumen

output at lower wattage. They are also ‘instant-on’ and illuminate immediately upon

powering and even “dim” to any required level of luminance. However, maximum

mounting height for LED system is between 10 to 15 metres that is not suitable for high

mast application. A claim that a 2100W Phoenix LED system is comparable to a

125
5600W traditional lighting system for a RTG has been achieved. Saving maintenance

cost is also a main feature of the LED lighting system.

Active reactor system: the Active Reactor is a device for the efficient control and

operation of high intensity discharge (HID) lamps. The device uses a microchip and

electronics to control the starting and running of 150 watt to 2000 watt high pressure

sodium and metal halide lamps commonly used in street lighting, floodlighting and

industrial lighting. The Active Reactor delivers substantial energy savings, green house

gas reductions and lamp life extension when used with HID lamps. A claim of:

x saving 18% of energy usage and increase lamp life of 50% for metal halide

lamps

x saving 25% of energy usage and increase lamp life of 100% for high pressure

sodium lamps

had been achieved. Active reactor can also “dim” the lamps to lower lighting output

level to save energy and the lamps can be switch on to full power within seconds rather

than minutes as traditional lamp control system.

Depend on which system the container terminal operators choose to use, a saving of at

least 20% of energy usage could be achieved.

6.2.4 Energy Storage and Peak Lopping

As discussed in previous sections, regenerative energy existed at any container terminal

with modern container handling cranes. If the container terminal had no base load for

126
utilising this energy and could not get a “net metering” arrangement then energy

storage device could be used. Information on energy storage development and

application can be found at [36, 38, 40, 47, 67, 96, 122, 123, 133] for distributed

network or at [75, 76, 78, 79, 91, 92, 94, 97, 100, 103, 104, 109, 113, 117] for smaller

projects. The energy storage device could store and discharge the energy when the need

arise. Applications of these devices have been proven in transportation: rail [85], bus

and cranes. Current technology used for electrical storage devices is based on flywheel

[29, 30, 89] or super capacitor [16, 60, 61, 63]

It is possible to program the device to only discharge the stored energy when the

demand is higher than a pre-set value, that is peak lopping or peak shaving operation.

As amount of regenerative energy is not large enough for this kind of operation, the

device would get its major energy from the electrical network and top up with

regenerative energy and discharge the stored energy when required.

By lopping the peak, that is reducing the high demand some issues of the terminal’s

electrical supply (such as protection settings, voltage drop, light flickering due to the

very high peak demand in short time) could be eliminated.

Peak lopping device had been proposed to use for enable the connection of a new quay

crane to a weak electrical supply in Western Australia in 2007. Two different proposals

were submitted:

x flywheel solution by Powercorp (Australia) and

x super capacitor solution by S and C (America).

127
It was not in the scope of this study to explain the principle and how the system work

so that only the expected results were shown to prove technologies are available to use.

Figure 6.7 showed the load profile of the quay crane. Figure 6.8 showed the Powercorp

proposal which would kick in when the demand was greater than 500kW. Figure 6.9

showed the S and C proposal which would activate when the crane demand was greater

than 400kW.

Electronic Shock Absorber (ESA) Power






kW






       
Time - seconds

Figure 6.7 Quay crane load profile

128


& U D Q H 3 R Z H U >N : @













       
&UDQH$FWXDO3RZ HU>N:@ &UDQH3RZ HUDIWHU3RZ HU6WRUH,QWHUYHQWLRQ>N:@ 7LPH>V@

Figure 6.8 Proposal from Powercorp using flywheel technology to limit peak
demand at 500kW and allow 100kW regenerative energy to be utilized by other
load

Net Source Power










kW










       
Time - seconds

Figure 6.9 Proposal from S and C using super capacitor technology to limit
peak demand at 400kW and capture all regenerative energy.

129
6.3 Conclusions

It was possible to reduce the electrical maximum demand and the energy usage at

container terminal as presented in this chapter.

Using container handling cranes with DC drive system would reduce both the demand

and energy usage, However, it might not be practical as the trend in production are for

AC drive system so that cost and delivery time of cranes with DC drive system would

not be justifiable.

The most effective way of reducing maximum demand is to improve the power factor;

a reduction of 50% had been achieved.

Utilising the regenerative energy and upgrading the lighting system would reduce the

energy usage at the container terminal. A saving at least 5% as in Melbourne container

terminal case.

In the next chapter, the findings from this study would be used to calculate the

maximum electrical demand of several different container terminals around the world,

the results would be then compared with the actual demand of those container terminal

for verification purposes.

130
CHAPTER SEVEN

Verification of this study results

The study of electrical usage and demand at the container terminal was based on the

operation data collected at Melbourne container terminal in Australia. Fortunately, the

findings of this study could be checked/verified as electrical energy and demand data of

a number of container terminals around the world were generously provided by Robert

Reid and Associates, the consultant who did the review electrical energy consumption

and management for those container terminals.

The majority of the utilities are now using kVA tariff for maximum demand charge to

reflect the true impact of the maximum demand on the electrical network. Therefore,

the kVA demand was used for results verification in this chapter.

This chapter begins with the description of how maximum electrical demand was

calculated by different methods:

x using “calculation method” of AS/NZS 3000:2007 [62],

x using “assessment method” of AS/NZS 3000:2007 [62] or the diversity factors

method as the norm in this field,

x using the findings of this study – the new improve assessment method.

131
For each of the container terminals, that electrical data were available, expected

maximum electrical demand was calculated and the results were plotted against the

actual demand of that container terminal. By inspecting these plots, conclusions could

be drawn about the accuracy of using findings from this study for calculation of

maximum demand at container terminal.

7.1 Calculation of the maximum demand at container terminal

Three (3) different methods were used to calculate the maximum demand at container

terminal and the results were tabulated for comparison. All demands were in kVA and

following demand symbols were used:

PR Maximum reefer demand in kVA

PQC Maximum crane demand in kVA

PL Maximum terminal lighting demand in kVA

PW Maximum workshop demand in kVA

PO Maximum office demand in kVA

The differences from these calculations were how to calculate the reefer demand and

the container handling crane demand. All other loads were as their rated values (or as

installed) and would be the same for all three calculation methods; they were normally

expressed in kW and were converted to kVA using power factor of 0.8.

Lighting load PL in kVA

Workshop load PW in kVA

Office load PO in kVA

132
Maximum demand at container terminal is then:

PMAX = PR + PQC + PL + PW + PO (Eq. 7.1)

7.1.1 Calculation to AS/NZS 3000:2007

This method of calculation was based on the “Calculation method” mentioned

in AS/NZS 3000:2007 [62].

Reefer load (load group B (iii) from Table C2)

Current _ Demand Max 30  ( Number _ of _ reefers  1) * 30 * 0.75

3 * Current _ Demand Max * 415


PR (Eq. 7.2)
1000

Crane load (load group E from Table C2)

Assumptions:

Hoist motor power for typical 60T cranes is PC = 1100kW

PQC 1.25 * PC1  0.75 * PC 2  0.5 * PC 3  .....  0.5 * PCn (Eq. 7.3)

Where PC1 …PCi Hoist motor power of crane 1, … crane i and

PC1 > PC2 >….> PCi

Using only the hoist motor data as it is the largest motor on any container

handling crane. The motor power is normally given in kW, using power factor

133
of 0.95 to convert to kVA as most container handling cranes are now with AC

drive system.

Maximum demand of the container terminal was calculated using Eq. 7.1

7.1.2 Calculation using diversity factors

This method is normally used in this engineering field, it can also be described

as estimation of the maximum demand using “Assessment method” mentioned

in AS/NZS 3000:2007 [62].

Reefer load

Assumptions: Ratio of 40’ and 20’ reefers is 1:2

Rated load of 20’ reefer is 10.4 kVA

Rated load of 40’ reefer is 13.5 kVA

Reefer diversity factor is 0.5

N * 13.5
Demand of 40’ reefers P40 (Eq. 7.4)
3

2 * N *10.4
Demand of 20’ reefers P20 (Eq. 7.5)
3

Where N is the number of reefer outlets (sockets, plugs)

134
Reefer demand PR = 0.5 *(P40 + P20) (Eq. 7.6)

All demands are in kVA.

Crane load

Assumptions: Crane rated current @ 11kV 62.6A

Crane diversity factor is 0.5

Crane demand PQC 0.5 * 3 * 11 * 62.6 * N (Eq. 7.7)

Where N is the number of cranes

Maximum demand of the container terminal was then calculated using Eq. 7.1

7.1.3 Calculation using findings of this study

Findings from this study:

Reefer demand 4 kW or 6.67 kVA @ pf of 0.6

Reefer stacking factor SF = 0.7

Crane demand 250 kW or 263 kVA @ pf of 0.95 (AC drive)

At most of container terminals, 20’ and 40’ reefers are stacked together causing

some unusable reefer outlets. A stacking factor is defined as the ratio between

used and available reefer outlets. A stacking factor of 0.7 (as typical value

found at Melbourne container terminal) would be used for any reefer stack that

135
has more than 100 reefer outlets and a stacking factor of 1 was used for reefer

stack with less than 100 outlets.

This calculation method is actually the new improved assessment method as

mentioned in [] as the actual operating data of container terminal were

examined/assessed resulting in a new way of calculating the maximum demand

at container terminal.

Reefer demand PR = SF * N * 4 / 0.6 (Eq. 7.8)

Crane demand PQC = 250 * C / 0.95 (Eq. 7.9)

Where N is the number of reefer outlets

SF is the reefer stacking factor

C is the number of cranes

Maximum demand of the container terminal was then calculated using Eq. 7.1

7.2 Maximum demand at Container Terminals

Calculations were done for comparison to the actual demand of the following

container terminals whose electrical energy consumption data were available:

x Melbourne container terminal No. 1 at East Swanson Dock

x Melbourne container terminal No. 2 at West Swanson Dock

x Combined Melbourne two terminals with data on the same time frame

x Sydney container terminal at Port Botany

x Brisbane container terminal at Fisherman Islands

136
x Yantian international container terminal – China

x Fairview container terminal – Canada

x Maher container terminal - USA

Calculation results were tabulated in Table 7.1 for Australian container terminals and in

Table 7.2 for overseas container terminals. Following were observations from these

tables:

x Maximum demand calculated from the findings of this study was the lowest

value for all container terminals,

x Except for the USA container terminal, calculation of maximum demand using

the findings from this study produced a reduction of between 34% and 47% of

maximum demand calculated using the Assessment method [62] that was the

norm in this field,

x USA container terminal had a very large base load (office, lighting,..) as it had

to accommodate the custom building and lighting for a large area. However, a

reasonable reduction of 28% in the estimated maximum demand was obtained

using the findings of this study.

x Chinese container terminal had even a larger base load than the USA container

terminal but a better reduction in estimated maximum demand (45%) due to the

fact that it had a very large number of quay cranes. It was noted that this

terminal had a lot of yard gantry cranes (around 200 machines) but they were

not electric powered so that they were not counted in this study and comparison.

137
138
139
It was good to find out a new way of calculating the maximum demand of

container terminal with an impressive reduction compared to the old way.

However, all the efforts were wasted if the new result was not stood up when

comparing to the actual demand at container terminal: the calculated maximum

demand should indeed be the MAXIMUM DEMAND. Therefore, in the next

section, comparison between calculated maximum demand and actual demand of

container terminal were performed to verify the usefulness of this new way of

calculation.

7.3 Comparison of the results

Figure 7.1 East Swanson Dock terminal – actual and calculated maximum

electrical demands

140
The results from Table 7.1 were visualized in the Figure 7.1 and the maximum

demand that was calculated using the new method was indeed the MAXIMUM

demand. It was about 47% less than the old assessment method of calculation. It

was also still 30% higher than the actual maximum demand so that there is safety

margin and scope for future terminal expansion.

Figure 7.2 West Swanson Dock terminal – actual and calculated maximum

electrical demands

The results from Table 7.1 were again visualized in the Figure 7.2 for the

Melbourne container terminal No. 2 – the West Swanson Dock terminal. The

calculated maximum demand using the new method was also the MAXIMUM

demand. It was about 46% less than the old assessment method of calculation and

was 30% higher than the actual maximum demand.

141
Figure 7.3 Swanson Dock terminals – actual and calculated maximum

electrical demands

As the available electrical energy consumption data were time stamped and the

same for both Melbourne container terminals, data from these two container

terminals were combined to create a larger terminal for study. Again, the results

from Table 7.1 were visualized in Figure 7.3 with similar observation: the

calculated maximum demand using the new method was also the MAXIMUM

demand. It was about 47% less than the old assessment method of calculation and

was 40% higher than the actual maximum demand.

142
Figure 7.4 Port Botany terminal – actual and calculated maximum electrical

demands

For Sydney container terminal, the results from Table 7.1 were visualized in the

Figure 7.4 with similar reduction in the calculated value compared to the old

calculation method. However, the new maximum demand was about 69% higher

than the actual maximum demand. This could only be understood with the terminal

operation conditions during the observation period:

x there were a couple of old quay cranes that have lower safe working load –

lower demand

x reefer traffic was low during this time period.

A maximum demand of 3940kVA was shown on the current electricity bill of this

terminal. It was around 30% spare capacity instead of 69%.

143
Figure 7.5 Fisherman Islands terminal – actual and calculated maximum

electrical demands

The results from Table 7.1 for Brisbane container terminal were visualized in the

Figure 7.5 and the calculated maximum demand using the new method was indeed

the MAXIMUM demand. It was about 34% less than the old assessment method of

calculation and 30% higher than the actual maximum demand of the terminal. The

reason for the smaller reduction in maximum demand was that this terminal had a

poor power factor (shown in the electrical energy consumption as around 0.6).

144
Figure 7.6 China – Yantian terminal – actual and calculated maximum

electrical demands

Yantian container terminal was a large and very busy terminal, there were a huge

number of machines in the terminal – more than 70 quay cranes and more than 200

yard gantry cranes. The yard gantry cranes were not electric powered at the time of

study so that they were not included. It was in the process of converting these

machines into electric powered. As only monthly electrical energy consumptions

were available, the analysis was not as good as other terminals.

Results for the Chinese container terminal from Table 7.2 were visualized in the

Figure 7.6 The calculated maximum demand was about 45% less than the old

assessment method of calculation and 26% higher than the actual maximum

demand.

145
Figure 7.7 Canada – Fairview terminal – actual and calculated maximum

electrical demands

In contrary, the Fairview container terminal in Canada is a relative small container

terminal with only three (3) quay cranes and 72 reefer outlets. However, it is also a

very busy terminal with regular shipments. Figure 7.7 shows almost a repeatable

pattern of peaks that when the quay cranes were working.

Results from Table 7.2 were visualised in Figure 7.7, the calculated maximum

demand was about 34% less than the old assessment method of calculation (due to

reefer poor power factor) and 58% higher than the actual maximum demand.

146
Figure 7.8 USA – Maher terminal – actual and calculated maximum

electrical demands

The Maher container terminal in USA is also an unusual terminal, it has a very large

base loads – lightings to cover a large stacking area and large office building to

accommodate the Custom office. Its base load of more than 2000 kW compared to

Melbourne terminal of 300 kW and both container terminals handled the same

number of containers. Real power (kW) tariff was used for this terminal so that

calculations and graphics were shown in kW.

The calculated maximum demand was only 28% less than the old assessment

method of calculation and 21% higher than the actual maximum demand. These

results were due to the rather larger base loads. However, there was still ample

spare capacity for safety margin and future expansion of terminal using this new

calculation method.

147
Summary of the comparisons were tabulated in Table 7.3 with following results

when using the new method of maximum demand calculation:

x compared to the old assessment method, a reduction of around 45% could be

achieved for terminals with good power factor and around 34% for terminal

with poor power factor. As most modern container handling cranes have AC

drive system, the power quality (power factor) was all due to the reefers (0.6

or lower) and could be improved using the power factor correction or

automatic VAR compensation unit.

x As the study findings were the results of analysing the actual container

terminal operation data, calculation of maximum demand using these

finding would always be higher than the actual demand. Such safety margin

was found to be more than 20%.

Table 7.3 Comparison of calculated and actual maximum demand

148
7.4 Conclusions

The maximum electrical demand of container terminal was calculated using method

described in [62] and the new improved method. The results from the new improved

method produced a more realistic value when comparing to other methods – a

reduction of at least 35% for the required maximum demand. And the new

maximum demand calculation at a container terminal result was also proved to be a

MAXIMUM DEMAND when compared to the actual demand of that terminal.

Using the new results for designing or upgrading a container terminal would require

smaller rated electrical infrastructure – switchgears, cables, size of substations. In

other words, a substantial saving in layout capital cost especially if the Utilities

insists of building a new electrical substation (that the terminal operator has to

contribute a major portion of the cost) to deliver the requested maximum demand.

The container terminal operator would also get a saving in running cost as the

requested maximum demand is charged as part of the monthly electricity bill and

this portion is around a fifth of the bill. A reduction of at least 35% maximum

demand would produce a big saving.

149
CHAPTER EIGHT

Conclusions and directions for future research

The main objective of this research was to find a way of calculating the maximum

electrical demand at container terminal. There is a trend to build larger container

ship and bigger container handling cranes to care for the forecast increase in

container traffic for both dry cargos and refrigerated products. The main electrical

consumptions at container terminal are from those container handling cranes and

refrigerated containers. However, to the best of the author’s knowledge from the

literature review and long time working in the port, there was no published

academic research into the electrical energy usage and demand at container

terminal. The lack of published research and understanding about the electrical

demand and consumption at container terminal leading to over size the terminal

electrical infrastructure and wasting the needed capital for other work. To fill this

gap, actual operation data (container throughput and electrical energy consumption)

of Melbourne container terminal had been collected for over two years for

analysing, comparing to theoretical calculation and conclusions were drawn in this

research for a better way of determining the maximum demand at container

terminal.

This chapter summarises the findings of the research and recommends directions for

future research.

150
8.1 Conclusions

The main electrical demand and consumption at container terminal are from the

container handling cranes and refrigerated containers. Container handling cranes

were detailed studied in Chapter 4 via the following study steps:

x Examining the load profile of quay cranes with AC and DC drive system to

understand the characteristics of these machine,

x Analysing container weight at container terminal from the collected data,

x Calculate the electrical demand for various loads (container weights) at

different location under loading (from land to container ship) and unloading

(from container ship to land) conditions using actual cranes data and

container weights.

The concluded results for this part of the study are:

for quay cranes: use 250kW for single lift cranes and 350 kW for twin lift

cranes as the maximum electrical demand value,

for rail mounted gantry or automatic stacking crane: use 200 kW for each

machine as the maximum electrical demand,

Similarly, the refrigerated containers (reefers) were detailed examined in Chapter 5

via the following study steps:

151
x Several methods of how to calculate the maximum demand of reefers were

presented. These methods are more often than not used by the industry for

calculation leading to a very conservative result.

x Power consumption by a reefer while in the container terminal is the power

required to keep that reefer at the pre-set temperature. Thus a new way of

calculating the demand of a reefer based on the heat transfer and required

cooling was developed and presented.

x Analysing the reefers data that were collected for over two (2) years and

computed the reefer’s actual demand.

x Results from different methods were compared and conclusion was drawn.

The concluded results for this part of the study is that 4 kW to be used for each

reefer as the maximum electrical demand.

Finally, the findings of this research were checked with the actual electrical demand

at a number of container terminals around the world in Chapter 7. The results were

very satisfactory with the calculated maximum demand was indeed the MAXIMUM

DEMAND with a large enough margin for safety and future expansion of the

container terminal.

In summary, the findings from this study provided a simpler way of calculating the

maximum demand at container terminal with a more accurate result leading to a

substantial saving to the container terminal operator both in capital layout for

electrical infrastructure investment and running cost of electricity.

152
8.2 Directions for future research

Despite of extensive time and effort spent on this study, it can be further improved

in many aspects. Followings are recommended for future research:

This thesis uses the number of container handling cranes and their average power

(kW) when handle the containers to compute the maximum demand for the

container handling cranes. There is another way of calculate their demand by

looking at the energy (kWHr) required to move a container and the number of

container throughput during a period (Hr) then compute the demand (kW). Be

reminded that the container handling cranes consume energy during idle time. This

method might produce a better result.

Originally, the simulation technique was intended to be used for this study of

electrical energy usage and demand at container terminals. However, suitable

simulation software (with electrical calculation module) was not available at the

time so that spreadsheet calculation was used. It appears that such simulation

software is now available as described in the news [7]. The actual container

terminal operation data collected for this thesis is still valid and can be used for

such model.

In this thesis, the weights of containers in stacking yard were analysed. This is not

the weight that would be lifted by the quay cranes as most of them capable of

operate in twin lift mode if the weight is within the quay cranes’ Safe Working

Load (SWL). Future research should look into the process of determining the

loading and unloading plans including the operation mode (single lift or twin lift) of

the quay cranes for better design input data for simulation model.
153
This study assumes all refrigerated containers (reefers) are at the set temperature

when arrive at the container terminal so that their electrical demand are computed

according to that assumption. However, there is an increased trend in the number of

“hot boxes” in Australia terminals. “Hot boxes” refers to the refrigerated containers

that are not cooled down to the required temperature when delivered to the

container terminal. During their stay, these “hot boxes” will draw electrical power

from the terminal electrical infrastructure for continuing the cooling process. In the

extreme case, they even use the power of container ship for cooling down to the

required temperature when arrive at the final destination. Future research should

pay attention on this fact as a large number of “hot boxes” would affect the out

come.

154
APPENDIX A

Daily container report, Code of Exel macro and Results

A1. Daily container report

For more than a year, the number of containers in the yard of Melbourne container

terminal was reported in the format shown below. As there are more than 6000

containers in the yard, only the report format and about 100 containers were listed.

Current Plan
Position Container No. Cat Len Wt Tns Comd I/B Carr O/B Car IMO Ql
BBK TOLU8971025 IMPORT 40' 29 OOG MMO9051 TRUCK
C 0211 1 KKTU7263932 IMPORT 20' 4.8 GENL CIM9071 TRUCK
C 0212 1 KKTU7521770 IMPORT 20' 6.1 GENL CIM9071 TRUCK
C 0212 2 TOLU4589550 IMPORT 20' 23.7 GENL MMO9051 TRUCK
C 0213 1 NYKU2778443 IMPORT 20' 2.7 GENL CIM9071 TRUCK
J 2007 1 MSCU1544371 TRANSSHIP 20' 23.9 NICK HRT9069 KRI9068
J 2007 2 MSCU2703626 TRANSSHIP 20' 28.2 GENL HRT9069 KRI9068
J 2007 3 GLDU0332520 TRANSSHIP 20' 28.3 GENL HRT9069 KRI9068
J 2008 1 MSCU3183895 TRANSSHIP 20' 23.9 NICK HRT9069 KRI9068
J 2008 2 MSCU1266795 TRANSSHIP 20' 28.3 GENL HRT9069 KRI9068
L 0701 2 OOLU6092070 EXPORT 40' 24.3 FZMT TRUCK OOF9079
L 0703 1 CBHU2647235 TRANSSHIP 20' 11 REEF KKO9790 OOF9079
L 0705 1 APRU5074912 IMPORT 40' 27 REEF KKO9790 TRUCK
L 0707 1 APRU5083107 IMPORT 40' 27.5 REEF KKO9790 TRUCK
L 0709 1 CRLU1217218 EXPORT 40' 24.5 FZFS TRUCK KRI9068
L 0801 1 PCIU5999285 EXPORT 40' 29 FZMT TRUCK OOF9079
L 0801 2 OOLU5961950 EXPORT 40' 25 FZMT TRUCK OOF9079
R 1009 2 MSCU9196760 IMPORT 40' 24.9 PPR AYU9081 TRUCK
R 1011 1 TRIU5674370 IMPORT 40' 26.8 PPR AYU9081 TRUCK
R 1011 2 MSCU8661092 IMPORT 40' 27.8 PPR AYU9081 TRUCK
R 1013 1 MSCU4167923 IMPORT 40' 28.1 PPR AYU9081 TRUCK
R 1013 2 TRIU5449569 IMPORT 40' 27.2 PPR AYU9081 TRUCK
R 1015 1 AMFU5001852 IMPORT 40' 14.1 MCH AYU9081 TRUCK
R 1015 2 GATU8547842 IMPORT 40' 25.4 TIM UKI9056 TRUCK
R 1101 1 TGHU0215794 IMPORT 20' 6.2 GENL AYU9081 TRUCK
R 1101 2 CRXU0755448 IMPORT 20' 6.6 EFE AYU9081 TRUCK
R 1102 1 MISU2363934 IMPORT 20' 23 GRAI MWA9062 TRUCK
R 1102 2 TTNU2945935 IMPORT 20' 23 GRAI MWA9062 TRUCK
R 1104 1 MISU2376818 IMPORT 20' 23 GRAI MWA9062 TRUCK
R 1106 1 MEDU1200496 IMPORT 20' 15.3 MIP AYU9081 TRUCK
R 1107 1 ECMU1377022 IMPORT 20' 6.5 FOD AYU9081 TRUCK

155
R 1108 1 TRLU8912861 IMPORT 20' 15.3 MIP AYU9081 TRUCK
R 1111 1 MEDU1564409 IMPORT 20' 21.7 PPR AYU9081 TRUCK
R 1113 1 LCRU2002026 IMPORT 20' 20.6 PPR AYU9081 TRUCK
R 1201 1 ECMU9753189 IMPORT 40' 18 GEN UKI9056 TRUCK
R 1201 2 TCKU9511018 IMPORT 40' 11.1 GEN UKI9056 TRUCK
R 1203 1 SUDU5785934 IMPORT 40' 20.3 GENL HSG9054 TRUCK
R 1203 2 HLXU4195509 IMPORT 40' 14.1 GENL HSG9054 TRUCK
R 1211 1 TCNU9302922 IMPORT 40' 25.7 TIM UKI9056 TRUCK
R 1213 1 GESU4282530 IMPORT 40' 10 GEN UKI9056 TRUCK
R 1213 2 TRLU7085310 IMPORT 40' 14.9 GEN UKI9056 TRUCK
U 2601 2 KHS400473 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 2701 1 KHS400609 EXPORT 40' 24.5 STEL TRUCK OOF9079
U 2801 1 KHS400497 EXPORT 40' 31.5 STEL TRUCK OOF9079
U 2801 2 KHS400457 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 2901 1 KHS400630 EXPORT 40' 24.5 STEL TRUCK OOF9079
U 2901 2 KHS400602 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 3001 1 HLXU4603998 IMPORT 40' 25 OOG SFB9055 TRUCK
U 3101 1 MSCU7347404 TRANSSHIP 20' 16.8 TIMB HRT9069 TAT9067 V
U 3201 1 SUDU4881580 IMPORT 40' 11.1 OOG SFB9055 TRUCK T
U 3301 1 TOLU4694257 IMPORT 20' 23.1 OOG CIM9071 TRUCK
U 3401 1 KHS400488 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 3401 2 KHS400461 EXPORT 40' 32.5 STEL TRUCK OOF9079
U 3501 1 MSCU7346218 TRANSSHIP 20' 23.9 TIMB HRT9069 TAT9067 V
U 3601 1 TOLU8986180 IMPORT 40' 16 OOG UKI9056 TRUCK
V 0101 1 MWCU5742760 IMPORT 20' 13 CHC MDH9077 TRUCK
V 0201 1 PCIU5797598 EXPORT 20' 21.4 FZMT TRUCK OOF9079
V 0301 1 MAEU5661079 EXPORT 20' 22.5 FZMT TRUCK TAT9067 V
V 0401 1 PONU2870221 EXPORT 20' 22.5 FZMT TRUCK TAT9067 V
V 0501 1 TRLU1044459 EXPORT 20' 16 FZMT TRUCK UVA9072
V 0601 1 CBHU2933183 EXPORT 40' 10.9 CHIL TRUCK OOF9079

4/02/2007 7:08:20 AM

A2. Code listing of Excel macro CONTAINER

The daily report was analysed to gather interested information, in this case the

weight of the container. As ever daily report had more than 6000 containers data, an

Excel macro CONTAINER had been written to automate the task. The Visual Basic

code is listed below:

Sub Container()
'
' Container Macro

156
‘ count number of containers
‘ count number of 20’ containers and calculate the TEU
‘ count number of containers that weighted
‘ < 5T, b/w 5T and 10T, b/w 10T and 15T, b/w 15T and 20T,
‘ b/w 20T and 25T, b/w 25T and 30T and > 30T
‘ calculate average weight of each container and TEU

' Macro recorded 26/02/2007 by Thanh
'
' Keyboard Shortcut: Ctrl+c
'
Dim LRow As Integer
Dim counter As Integer
Dim content As Single
Dim RDate As String
Dim work1 As String
Dim Dtype As String
Dim Weight As Single

Weight = 0
Range("L2").FormulaR1C1 = "=LEFT(RC[-11],1)&LEFT(RC[-8],2)"
Range("L2:L2").Select
Selection.Copy
ActiveCell.Offset(1, 0).Range("A1").Select
Range(Selection, ActiveCell.SpecialCells(xlLastCell)).Select
ActiveSheet.Paste
ActiveCell.SpecialCells(xlLastCell).Select
ActiveCell.Offset(0, -2).FormulaR1C1 = "=ROW() - 2"
LRow = ActiveCell.Offset(0, -2).Value
RDate = ActiveCell.Offset(0, -11).Value
ActiveCell.Offset(0, -2).Value = ""
ActiveCell.Offset(0, 0).Value = ""
Range("E2").Select
For counter = 1 To LRow - 1
Dtype = ActiveCell.Offset(counter - 1, 7).Value
If Left(Dtype, 1) = "?" Then
ActiveCell.Offset(counter - 1, 7).Value = "Other" & Right(Dtype, Len(Dtype) - 1)
End If
content = ActiveCell.Offset(counter - 1, 0).Value
Weight = Weight + content
If content < 5 Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"1"
ElseIf content >= 5 And content < 10 Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"2"
ElseIf content >= 10 And content < 15 Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"3"
ElseIf content >= 15 And content < 20 Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"4"

157
ElseIf content >= 20 And content < 25 Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"5"
ElseIf content >= 25 And content < 30 Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"6"
Else
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"7"
End If
Dtype = ActiveCell.Offset(counter - 1, -2).Value
If Left(Dtype, 1) = "E" Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"E"
ElseIf Left(Dtype, 1) = "I" Then
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"I"
Else
ActiveCell.Offset(counter - 1, 7).Value = ActiveCell.Offset(counter - 1, 7).Value &
"O"
End If
Next counter
work = ActiveWorkbook.Name
If Right(work, 3) = "XLS" Then
work = Left(work, Len(work) - 4)
End If
Workbooks.Open Filename:= _
"C:\Documents and Settings\All Users\Application
Data\Microsoft\Container_Form.xls"
Sheets("Summary Weight").Copy After:=Workbooks(work).Sheets(1)
Workbooks("Container_Form.xls").Close
Range("I101").Select
ActiveCell.Value = Weight
Range("B7").Select
For counter = 0 To 22
ActiveCell.Offset(counter, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-1]&""201?"")"
ActiveCell.Offset(counter, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-2]&""202?"")"
ActiveCell.Offset(counter, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-3]&""203?"")"
ActiveCell.Offset(counter, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-4]&""204?"")"
ActiveCell.Offset(counter, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-5]&""205?"")"
ActiveCell.Offset(counter, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-6]&""206?"")"
ActiveCell.Offset(counter, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-7]&""207?"")"
ActiveCell.Offset(counter, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-8]&""20?I"")"
ActiveCell.Offset(counter, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-9]&""20?E"")"
ActiveCell.Offset(counter, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-10]&""20?O"")"

158
ActiveCell.Offset(counter + 29, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-1]&""401?"")"
ActiveCell.Offset(counter + 29, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-2]&""402?"")"
ActiveCell.Offset(counter + 29, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-3]&""403?"")"
ActiveCell.Offset(counter + 29, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-4]&""404?"")"
ActiveCell.Offset(counter + 29, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-5]&""405?"")"
ActiveCell.Offset(counter + 29, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-6]&""406?"")"

ActiveCell.Offset(counter + 29, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work) &


"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-7]&""407?"")"
ActiveCell.Offset(counter + 29, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-8]&""40?I"")"
ActiveCell.Offset(counter + 29, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-9]&""40?E"")"
ActiveCell.Offset(counter + 29, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-10]&""40?O"")"
ActiveCell.Offset(counter + 58, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-1]&""451?"")"
ActiveCell.Offset(counter + 58, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-2]&""452?"")"
ActiveCell.Offset(counter + 58, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-3]&""453?"")"
ActiveCell.Offset(counter + 58, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-4]&""454?"")"
ActiveCell.Offset(counter + 58, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-5]&""455?"")"
ActiveCell.Offset(counter + 58, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-6]&""456?"")"
ActiveCell.Offset(counter + 58, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-7]&""457?"")"
ActiveCell.Offset(counter + 58, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-8]&""45?I"")"
ActiveCell.Offset(counter + 58, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-9]&""45?E"")"
ActiveCell.Offset(counter + 58, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work) &
"'!R2C12:R" & Trim(Str(LRow)) & "C12,RC[-10]&""45?O"")"
Next counter
' Range("AB32").Select
' ActiveCell.Offset(0, 0).FormulaR1C1 = "='Power Report'!R17C2"
' ActiveCell.Offset(0, 1).FormulaR1C1 = "='Power Report'!R17C3"
' ActiveCell.Offset(0, 2).FormulaR1C1 = "='Power Report'!R17C4"
' ActiveCell.Offset(1, 0).FormulaR1C1 = "='Power Report'!R17C5"
' ActiveCell.Offset(1, 1).FormulaR1C1 = "='Power Report'!R17C6"
' ActiveCell.Offset(1, 2).FormulaR1C1 = "='Power Report'!R17C7"
' Range("AB36").Select
' ActiveCell.Offset(0, 0).FormulaR1C1 = "='Power Report'!R17C14"
' ActiveCell.Offset(0, 1).FormulaR1C1 = "=-'Power Report'!R17C15"
' ActiveCell.Offset(0, 2).FormulaR1C1 = "='Power Report'!R17C16"

159
' ActiveCell.Offset(1, 0).FormulaR1C1 = "='Power Report'!R17C17"
' ActiveCell.Offset(1, 1).FormulaR1C1 = "=-'Power Report'!R17C18"
' ActiveCell.Offset(1, 2).FormulaR1C1 = "='Power Report'!R17C19"
' ActiveWindow.ScrollColumn = 24
Range("A93").Select
ActiveCell.Offset(0, 9).Value = "='" & Trim(work) & "'!A" & Trim(Str(LRow + 2))
ActiveCell.Offset(0, 10).Value = "='" & Trim(work) & "'!B" & Trim(Str(LRow + 2))
End Sub

A3. Results from running the macro CONTAINER


The analysed results were:

160
APPENDIX B

Daily reefer report, Code of Excel macro and Results

B1. Daily reefer and power reports

For more than a year, the number of refrigerated containers (reefers) in the yard of

Melbourne container terminal and electrical demand at a specific time were

reported in the format shown below.

Daily reefer report

As there are more than 400 reefers, only the report format and about 50 reefers were

listed.

Current Wt Plan
Position Yard In Container No. Temp C Len Tns Comd Special Ql Cat
E 0109 1 WE2250 SUDU1010337 -18.0¡C 20' 21.4 REEF #NAME? IMPORT
E 0111 1 SA2157 TOLU7804620 +5.0¡C 40' 21.5 REEF #NAME? IMPORT
E 0203 1 SA0719 POCU2817218 -25.0¡C 20' 20.8 FZJC #NAME? V EXPORT
E 0203 2 SA0723 PONU2855314 -25.0¡C 20' 20.5 FZJC #NAME? V EXPORT
E 0204 1 SA0726 POCU2827392 -25.0¡C 20' 20.6 FZJC #NAME? V EXPORT
E 0204 2 SA0713 MWCU5664991 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT
E 0205 1 SA0721 PONU2850924 -25.0¡C 20' 20.5 FZJC #NAME? V EXPORT
E 0209 1 FR0919 PONU2948783 -18.0¡C 20' 20.4 REEF #NAME? IMPORT
E 0209 2 FR0934 SUDU1089373 +10.0¡C 20' 17 REEF #NAME? IMPORT
E 0408 1 FR2116 MAEU5667816 -20.0¡C 20' 18.4 FZMT #NAME? V EXPORT
E 0408 2 SA0005 PONU2927292 -1.0¡C 20' 18.8 CHMT #NAME? V EXPORT
E 0409 1 TH1943 SUDU1047871 -20.0¡C 20' 22.7 FZMT #NAME? EXPORT
E 0409 2 FR0750 FSCU5214236 -20.0¡C 20' 22.1 FZMT #NAME? EXPORT
E 0411 1 FR2112 CRLU1213721 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT
E 0411 2 SA1453 MWCU6818556 -1.0¡C 40' 21 CHMT #NAME? V EXPORT
E 0501 1 FR2134 CRLU1319800 -21.0¡C 40' 29.6 FZMT #NAME? EXPORT
E 0501 2 FR2145 MSCU7406641 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT
E 0503 1 FR0851 SCZU8263108 -18.0¡C 20' 16.9 FZMT #NAME? EXPORT
E 0503 2 FR1212 MAEU5661274 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT
E 0504 1 FR0006 PONU2933931 -1.5¡C 20' 15.3 CHMT #NAME? V EXPORT
E 0504 2 FR2125 MWCU5661950 -1.5¡C 20' 13.5 CHMT #NAME? V EXPORT
E 0505 1 WE1650 KNLU2782677 -21.0¡C 20' 23.7 FZMT #NAME? V EXPORT
E 0505 2 TH1433 MWCU5691235 -1.0¡C 20' 16.8 CHMT #NAME? V EXPORT
E 0506 1 TH1731 MSCU3618149 -18.0¡C 20' 22 FZFS #NAME? V EXPORT

161
E 0506 2 TH1734 MSCU3612475 -18.0¡C 20' 22.1 FZFS #NAME? V EXPORT
E 0507 1 FR1759 PONU2917761 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT
E 0507 2 FR1800 PONU2882310 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT
E 0511 1 FR0110 HLXU7750415 +18.0¡C 40' 17.7 REEF #NAME? IMPORT
E 0511 2 FR0445 MWCU6963322 -18.0¡C 40' 28.6 REEF #NAME? IMPORT
E 0603 1 WE2054 MWCU5618595 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT
E 0603 2 TH1443 MWCU5726178 +4.0¡C 20' 20.3 CHIL #NAME? V EXPORT
E 0604 1 WE1652 PONU2865539 -21.0¡C 20' 23.6 FZMT #NAME? V EXPORT
E 0604 2 TH1156 MWCU5702659 0.0¡C 20' 16 CHMT #NAME? V EXPORT
E 0605 1 WE1651 POCU2831690 -21.0¡C 20' 16.7 FZMT #NAME? V EXPORT
E 0605 2 FR0639 MWCU5711687 -1.0¡C 20' 13.6 CHMT #NAME? V EXPORT
E 0606 1 WE1633 MWCU5669822 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT
E 0606 2 WE1635 MWCU5622506 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT
E 0607 1 WE1637 MWCU5800980 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT
E 0607 2 WE1645 MWCU5628551 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT
L 0801 2 FR2245 OOLU5961950 -20.0¡C 40' 25 FZMT #NAME? EXPORT
L 0807 1 WE1547 GESU9341050 -20.0¡C 40' 25.5 FZPY #NAME? EXPORT
L 0807 2 WE1957 CBHU2983760 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT
L 1001 1 WE1653 CRXU6805715 -18.0¡C 40' 21.9 REEF #NAME? IMPORT
L 1003 1 FR1417 MWCU5672596 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT
L 1003 2 FR1654 CRLU3807430 +4.0¡C 20' 12.5 CHIL #NAME? EXPORT
L 1004 1 TH0532 SUDU1031052 -18.0¡C 20' 21.6 REEF #NAME? IMPORT
L 1005 1 FR1358 SCZU8677047 -18.0¡C 20' 14.9 FZFS #NAME? EXPORT
L 1005 2 FR1351 SCZU8262354 -18.0¡C 20' 15.2 FZFS #NAME? EXPORT
L 2105 1 TU2039 MWMU6363457 -1.0¡C 40' 25.4 CHMT #NAME? V EXPORT
L 2105 2 TU2145 MWMU6342290 -1.5¡C 40' 24.7 CHMT #NAME? V EXPORT
L 2107 1 WE0113 MWMU6306631 -1.5¡C 40' 26 CHMT #NAME? V EXPORT
L 2107 2 TH0128 MWCU6718120 -1.5¡C 40' 24.9 CHMT #NAME? V EXPORT
L 2109 1 WE1755 SUDU1102691 -18.0¡C 20' 19.7 REEF #NAME? IMPORT
L 2109 2 WE1827 SUDU1043304 -18.0¡C 20' 21.2 REEF #NAME? IMPORT
L 2110 1 FR2321 GESU9336310 -20.0¡C 20' 17.8 FZMT #NAME? EXPORT
L 2111 1 TH1730 CRLU7229514 -1.0¡C 40' 29 CHMT #NAME? V EXPORT
L 2111 2 FR0915 MWMU6430555 -1.0¡C 40' 29.1 CHMT #NAME? V EXPORT
L 2201 1 FR1412 FSCU5645249 -18.0¡C 40' 29 FZMT #NAME? EXPORT
L 2203 1 FR0003 CBHU2652695 +15.0¡C 20' 8.3 REEF #NAME? IMPORT
L 2203 2 FR1815 CBHU2675509 -15.0¡C 20' 20.9 REEF #NAME? IMPORT
L 2205 1 FR0650 MWCU5601329 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT
L 2207 1 FR1656 FBLU6207507 -20.0¡C 20' 18 FZMT #NAME? EXPORT
L 2209 1 FR1135 MSCU5611272 FAN 40' 29.1 FANT V EXPORT
L 2211 1 FR1149 TRIU8282372 +15.0¡C 40' 17.2 CONF #NAME? EXPORT
L 2301 1 FR0807 GCEU7720400 +15.5¡C 40' 16 REE #NAME? IMPORT
L 2303 1 FR2121 PONU2976471 -20.0¡C 20' 17 FVG #NAME? IMPORT
L 2304 1 FR0214 GCEU3128603 +3.0¡C 20' 23 CEE #NAME? IMPORT
V 0201 1 FR1940 PCIU5797598 -18.0¡C 20' 21.4 FZMT #NAME? EXPORT
V 0301 1 FR0106 MAEU5661079 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT
V 0401 1 TH2240 PONU2870221 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT
V 0501 1 TH1353 TRLU1044459 -18.0¡C 20' 16 FZMT #NAME? EXPORT
V 0601 1 WE1108 CBHU2933183 +13.0¡C 40' 10.9 CHIL #NAME? EXPORT

4/02/2007 7:08:09 AM

162
Daily power report

As reefer report was generated every day at round 7:00AM, the power monitoring system also reported power demand around that time for
analysis.

5HHIHU3RZHUXVDJH            
5HSRUW6WDUW7LPH $0          
5HSRUW(QG7LPH           
$0
5HSRUW*HQHUDWHG           
2Q $0
            
            
            
            
 6XE&/9PDLQ&% (DVW  6XE&/9PDLQ&% :HVW  6XE'/9PHWHU(DVW/EORFN 6XE'/9PHWHU:HVW/EORFN
 $SSDUHQW 5HDFWLYH 5HDO $SSDUHQW 5HDFWLYH 5HDO $SSDUHQW 5HDFWLYH 5HDO $SSDUHQW 5HDFWLYH 5HDO
3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU 3RZHU
7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO 7RWDO
$0            
$0            
$0            
$0            
$0            
$0            
$0            
$0            
            
 'DWH7LPH           
3RZHUHG%\ 3ULQWHG2Q:HGQHVGD\-XQH$0       

163
B2. Code listing of Excel macro REEFER

The daily reefer and power reports were analysed to gather interested information, in

this case the power demand of the whole reefer pads (there are 4 reefer pads at

Melbourne container terminal – L block East, L block West, E block East and E block

West). As ever daily report had more than 400 reefers data, an Excel macro REEFER

had been written to automate the task. The Visual Basic code is listed below:

Sub Reefers()
'
' Reefers Macro
' Macro recorded 7/02/2007 by Thanh
'
' Keyboard Shortcut: Ctrl+r
'
Dim LRow As Integer
Dim counter As Integer
Dim content As Integer
Dim RDate As String
Dim work1 As String

work1 = ActiveWorkbook.Name
For Each w In Workbooks
If Right(w.Name, 3) = "txt" Or Right(w.Name, 3) = "TXT" Then
work = w.Name
End If
Next w
Sheets("Sheet1").Copy After:=Workbooks(work).Sheets(1)
Sheets("Sheet1").Name = "Power Report"
Workbooks(work1).Close savechanges:=False
Sheets(1).Select
Range("L2").FormulaR1C1 = "=LEFT(RC[-11],1)&MID(RC[-11],3,2)&LEFT(RC[-
7],2)"
Range("N2").FormulaR1C1 = "=IF(LEFT(TRIM(RC[-
10]),1)=""c"",RIGHT(TRIM(RC[-10]),LEN(TRIM(RC[-10]))-2),TRIM(RC[-10]))"
Range("M2").FormulaR1C1 =
"=IF(LEN(RC[1])>3,VALUE(LEFT(RC[1],LEN(RC[1])-2)),-100)"
Range("L2:N2").Select
Selection.Copy
ActiveCell.Offset(1, 0).Range("A1").Select

164
Range(Selection, ActiveCell.SpecialCells(xlLastCell)).Select
ActiveSheet.Paste
ActiveCell.SpecialCells(xlLastCell).Select
ActiveCell.Offset(0, -2).FormulaR1C1 = "=ROW() - 2"
LRow = ActiveCell.Offset(0, -2).Value
RDate = ActiveCell.Offset(0, -13).Value
ActiveCell.Offset(0, -2).Value = ""
ActiveCell.Offset(0, -1).Value = ""
ActiveCell.Offset(-1, -1).Value = ""

ActiveCell.Offset(-2, -1).Range("A1").Select
Range(Selection, "M2").Select
Selection.Copy
Selection.PasteSpecial Paste:=xlPasteValues, Operation:=xlNone, SkipBlanks _
:=False, Transpose:=False
Range("N2").Select
For counter = 1 To LRow - 1
content = ActiveCell.Offset(counter - 1, -1).Value
If content = -100 Then
ActiveCell.Offset(counter - 1, 0).Value = ActiveCell.Offset(counter - 1, -
2).Value & "F"
ElseIf content < 0 Then
ActiveCell.Offset(counter - 1, 0).Value = ActiveCell.Offset(counter - 1, -
2).Value & "-"
Else
ActiveCell.Offset(counter - 1, 0).Value = ActiveCell.Offset(counter - 1, -
2).Value & "+"
End If
content = ActiveCell.Offset(counter - 1, -8).Value
If content < 10 Then
ActiveCell.Offset(counter - 1, 1).Value = ActiveCell.Offset(counter - 1, -
2).Value & "1"
ElseIf content > 20 Then
ActiveCell.Offset(counter - 1, 1).Value = ActiveCell.Offset(counter - 1, -
2).Value & "3"
Else
ActiveCell.Offset(counter - 1, 1).Value = ActiveCell.Offset(counter - 1, -
2).Value & "2"
End If
work = ActiveCell.Offset(counter - 1, -3).Value
If Trim(work) = "EXPORT" Then
ActiveCell.Offset(counter - 1, 0).Value = ActiveCell.Offset(counter - 1,
0).Value & "E"
ActiveCell.Offset(counter - 1, 1).Value = ActiveCell.Offset(counter - 1,
1).Value & "E"
Else

165
ActiveCell.Offset(counter - 1, 0).Value = ActiveCell.Offset(counter - 1,
0).Value & "I"
ActiveCell.Offset(counter - 1, 1).Value = ActiveCell.Offset(counter - 1,
1).Value & "I"
End If
Next counter
Columns("L").ClearContents
Columns("M").ClearContents
work = ActiveWorkbook.Name
If Right(work, 3) = "XLS" Then
work = Left(work, Len(work) - 4)
End If
Workbooks.Open Filename:= _
"C:\Documents and Settings\All Users\Application
Data\Microsoft\Reefer_Form.xls"
Sheets("Summary Temp").Copy After:=Workbooks(work).Sheets(2)
Windows("Reefer_Form.xls").Activate
Sheets("Summary Weight").Copy After:=Workbooks(work).Sheets(3)
Sheets("Summary Temp").Select
Workbooks("Reefer_Form.xls").Close
Range("B2").Select
For counter = 1 To 13
ActiveCell.Offset(counter + 5, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-1]&""20+?"")"
ActiveCell.Offset(counter + 5, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-2]&""20-?"")"
ActiveCell.Offset(counter + 5, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-3]&""20F?"")"
ActiveCell.Offset(counter + 5, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 5, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 5, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-6]&""40+?"")"
ActiveCell.Offset(counter + 5, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-7]&""40-?"")"
ActiveCell.Offset(counter + 5, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-8]&""40F?"")"
ActiveCell.Offset(counter + 5, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 5, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-10]&""40?E"")"
ActiveCell.Offset(counter + 5, 11).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-1]&""20+?"")"
ActiveCell.Offset(counter + 5, 12).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-2]&""20-?"")"

166
ActiveCell.Offset(counter + 5, 13).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-3]&""20F?"")"
ActiveCell.Offset(counter + 5, 14).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 5, 15).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 5, 16).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-6]&""40+?"")"
ActiveCell.Offset(counter + 5, 17).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-7]&""40-?"")"
ActiveCell.Offset(counter + 5, 18).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-8]&""40F?"")"
ActiveCell.Offset(counter + 5, 19).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 5, 20).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-10]&""40?E"")"
Next counter
For counter = 1 To 12
ActiveCell.Offset(counter + 25, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-1]&""20+?"")"
ActiveCell.Offset(counter + 25, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-2]&""20-?"")"
ActiveCell.Offset(counter + 25, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-3]&""20F?"")"
ActiveCell.Offset(counter + 25, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 25, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 25, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-6]&""40+?"")"
ActiveCell.Offset(counter + 25, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-7]&""40-?"")"
ActiveCell.Offset(counter + 25, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-8]&""40F?"")"
ActiveCell.Offset(counter + 25, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 25, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-10]&""40?E"")"
ActiveCell.Offset(counter + 25, 11).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-1]&""20+?"")"
ActiveCell.Offset(counter + 25, 12).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-2]&""20-?"")"
ActiveCell.Offset(counter + 25, 13).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-3]&""20F?"")"
ActiveCell.Offset(counter + 25, 14).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-4]&""20?I"")"

167
ActiveCell.Offset(counter + 25, 15).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 25, 16).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-6]&""40+?"")"
ActiveCell.Offset(counter + 25, 17).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-7]&""40-?"")"
ActiveCell.Offset(counter + 25, 18).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-8]&""40F?"")"
ActiveCell.Offset(counter + 25, 19).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 25, 20).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-10]&""40?E"")"
Next counter
For counter = 1 To 2
ActiveCell.Offset(counter + 45, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-1]&""20+?"")"
ActiveCell.Offset(counter + 45, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-2]&""20-?"")"
ActiveCell.Offset(counter + 45, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-3]&""20F?"")"
ActiveCell.Offset(counter + 45, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 45, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 45, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-6]&""40+?"")"
ActiveCell.Offset(counter + 45, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-7]&""40-?"")"
ActiveCell.Offset(counter + 45, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-8]&""40F?"")"
ActiveCell.Offset(counter + 45, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 45, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C14:R" & Trim(Str(LRow)) & "C14,RC[-10]&""40?E"")"
Next counter
Range("AB32").Select
ActiveCell.Offset(0, 0).FormulaR1C1 = "='Power Report'!R15C14"
ActiveCell.Offset(0, 1).FormulaR1C1 = "=-'Power Report'!R15C15"
ActiveCell.Offset(0, 2).FormulaR1C1 = "='Power Report'!R15C16"
ActiveCell.Offset(1, 0).FormulaR1C1 = "='Power Report'!R15C17"
ActiveCell.Offset(1, 1).FormulaR1C1 = "=-'Power Report'!R15C18"
ActiveCell.Offset(1, 2).FormulaR1C1 = "='Power Report'!R15C19"
Range("AB36").Select
ActiveCell.Offset(0, 0).FormulaR1C1 = "='Power Report'!R15C2"
ActiveCell.Offset(0, 1).FormulaR1C1 = "='Power Report'!R15C3"
ActiveCell.Offset(0, 2).FormulaR1C1 = "='Power Report'!R15C4"

168
ActiveCell.Offset(1, 0).FormulaR1C1 = "='Power Report'!R15C5"
ActiveCell.Offset(1, 1).FormulaR1C1 = "='Power Report'!R15C6"
ActiveCell.Offset(1, 2).FormulaR1C1 = "='Power Report'!R15C7"
ActiveWindow.ScrollColumn = 24
Range("Y5").Select
ActiveCell.Offset(0, 11).Value = "='" & Trim(work) & "'!A" & Trim(Str(LRow +
2))
ActiveCell.Offset(0, 12).Value = "='" & Trim(work) & "'!B" & Trim(Str(LRow + 2))
Sheets("Summary Weight").Select
Range("B2").Select
For counter = 1 To 13
ActiveCell.Offset(counter + 5, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-1]&""201?"")"
ActiveCell.Offset(counter + 5, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-2]&""202?"")"
ActiveCell.Offset(counter + 5, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-3]&""203?"")"
ActiveCell.Offset(counter + 5, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 5, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 5, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-6]&""401?"")"
ActiveCell.Offset(counter + 5, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-7]&""402?"")"
ActiveCell.Offset(counter + 5, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-8]&""403?"")"
ActiveCell.Offset(counter + 5, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 5, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-10]&""40?E"")"
ActiveCell.Offset(counter + 5, 11).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-1]&""201?"")"
ActiveCell.Offset(counter + 5, 12).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-2]&""202?"")"
ActiveCell.Offset(counter + 5, 13).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-3]&""203?"")"
ActiveCell.Offset(counter + 5, 14).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 5, 15).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 5, 16).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-6]&""401?"")"
ActiveCell.Offset(counter + 5, 17).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-7]&""402?"")"

169
ActiveCell.Offset(counter + 5, 18).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-8]&""403?"")"
ActiveCell.Offset(counter + 5, 19).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 5, 20).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-10]&""40?E"")"
Next counter
For counter = 1 To 12
ActiveCell.Offset(counter + 25, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-1]&""201?"")"
ActiveCell.Offset(counter + 25, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-2]&""202?"")"
ActiveCell.Offset(counter + 25, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-3]&""203?"")"
ActiveCell.Offset(counter + 25, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 25, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 25, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-6]&""401?"")"
ActiveCell.Offset(counter + 25, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-7]&""402?"")"
ActiveCell.Offset(counter + 25, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-8]&""403?"")"
ActiveCell.Offset(counter + 25, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 25, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-10]&""40?E"")"
ActiveCell.Offset(counter + 25, 11).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-1]&""201?"")"
ActiveCell.Offset(counter + 25, 12).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-2]&""202?"")"
ActiveCell.Offset(counter + 25, 13).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-3]&""203?"")"
ActiveCell.Offset(counter + 25, 14).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 25, 15).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 25, 16).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-6]&""401?"")"
ActiveCell.Offset(counter + 25, 17).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-7]&""402?"")"
ActiveCell.Offset(counter + 25, 18).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-8]&""403?"")"
ActiveCell.Offset(counter + 25, 19).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-9]&""40?I"")"

170
ActiveCell.Offset(counter + 25, 20).FormulaR1C1 = "=COUNTIF('" &
Trim(work) & "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-10]&""40?E"")"
Next counter
For counter = 1 To 2
ActiveCell.Offset(counter + 45, 0).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-1]&""201?"")"
ActiveCell.Offset(counter + 45, 1).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-2]&""202?"")"
ActiveCell.Offset(counter + 45, 2).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-3]&""203?"")"
ActiveCell.Offset(counter + 45, 3).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-4]&""20?I"")"
ActiveCell.Offset(counter + 45, 4).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-5]&""20?E"")"
ActiveCell.Offset(counter + 45, 5).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-6]&""401?"")"
ActiveCell.Offset(counter + 45, 6).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-7]&""402?"")"
ActiveCell.Offset(counter + 45, 7).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-8]&""403?"")"
ActiveCell.Offset(counter + 45, 8).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-9]&""40?I"")"
ActiveCell.Offset(counter + 45, 9).FormulaR1C1 = "=COUNTIF('" & Trim(work)
& "'!R2C15:R" & Trim(Str(LRow)) & "C15,RC[-10]&""40?E"")"
Next counter
Range("AB32").Select
ActiveCell.Offset(0, 0).FormulaR1C1 = "='Power Report'!R15C14"
ActiveCell.Offset(0, 1).FormulaR1C1 = "=-'Power Report'!R15C15"
ActiveCell.Offset(0, 2).FormulaR1C1 = "='Power Report'!R15C16"
ActiveCell.Offset(1, 0).FormulaR1C1 = "='Power Report'!R15C17"
ActiveCell.Offset(1, 1).FormulaR1C1 = "=-'Power Report'!R15C18"
ActiveCell.Offset(1, 2).FormulaR1C1 = "='Power Report'!R15C19"
Range("AB36").Select
ActiveCell.Offset(0, 0).FormulaR1C1 = "='Power Report'!R15C2"
ActiveCell.Offset(0, 1).FormulaR1C1 = "='Power Report'!R15C3"
ActiveCell.Offset(0, 2).FormulaR1C1 = "='Power Report'!R15C4"
ActiveCell.Offset(1, 0).FormulaR1C1 = "='Power Report'!R15C5"
ActiveCell.Offset(1, 1).FormulaR1C1 = "='Power Report'!R15C6"
ActiveCell.Offset(1, 2).FormulaR1C1 = "='Power Report'!R15C7"
ActiveWindow.ScrollColumn = 24
Range("Y5").Select
ActiveCell.Offset(0, 11).Value = "='" & Trim(work) & "'!A" & Trim(Str(LRow +
2))
ActiveCell.Offset(0, 12).Value = "='" & Trim(work) & "'!B" & Trim(Str(LRow + 2))
End Sub

171
B3. Results from running the macro REEFER
The analysed results were:

172
APPENDIX C

Specific Heat Capacity of various products

Source: Container Handbook [4]

173
APPENDIX D

Calculate reefer electrical demand using heat transfer and cooling required method

ǻTambient Tambient PAxiliary Ave.


Current Plan K
Yard In Container No. Temp C Len Wt Tns Comd Special IMO Cat Cp (J/kgK) (i) A (m2) ǻT (oC) T (oC) P (W) (ii) t1 (Hr) t2 (Hr) Demand
Position Ql (W/m²K) (oC) (oC) (W) (iii) (kW)
E 0109 1 WE2250 SUDU1010337 -18.0¡C 20' 21.4 REEF #NAME? IMPORT 1670 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.19 3.31 3.97
E 0111 1 SA2157 TOLU7804620 +5.0¡C 40' 21.5 REEF #NAME? IMPORT 1930 135.26 0.5 2 30.0 5.0 35.0 12000 2500 11.76 1.92 4.19
E 0203 1 SA0719 POCU2817218 -25.0¡C 20' 20.8 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 50.0 -15.0 35.0 6000 2500 15.79 4.83 3.91
E 0203 2 SA0723 PONU2855314 -25.0¡C 20' 20.5 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 50.0 -15.0 35.0 6000 2500 15.56 4.76 3.91
E 0204 1 SA0726 POCU2827392 -25.0¡C 20' 20.6 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 50.0 -15.0 35.0 6000 2500 15.64 4.79 3.91
E 0204 2 SA0713 MWCU5664991 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 50.0 -15.0 35.0 6000 2500 15.49 4.74 3.91
E 0205 1 SA0721 PONU2850924 -25.0¡C 20' 20.5 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 50.0 -15.0 35.0 6000 2500 15.56 4.76 3.91
E 0209 1 FR0919 PONU2948783 -18.0¡C 20' 20.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.79 2.53 3.97
E 0209 2 FR0934 SUDU1089373 +10.0¡C 20' 17 REEF #NAME? IMPORT 3060 74.97 0.5 2 25.0 10.0 35.0 15000 2500 32.14 1.93 3.35
E 0210 1 FR1655 SUDU1024691 -18.0¡C 20' 20.5 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.83 2.54 3.97
E 0301 1 FR0845 CRLU1242231 -18.0¡C 40' 29.6 FZMT #NAME? V EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
E 0301 2 SA0719 MWMU6431485 -1.0¡C 40' 22.7 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.14 1.69 4.41
E 0303 1 FR0646 PONU2932426 -1.0¡C 20' 14.3 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.12 1.06 3.66
E 0303 2 FR1448 MWCU5639751 -18.0¡C 20' 22 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.04 3.59 3.97
E 0305 1 WE1832 SUDU1013439 +7.0¡C 20' 18 REEF #NAME? IMPORT 3060 74.97 0.5 2 28.0 7.0 35.0 15000 2500 30.25 2.04 3.45
E 0306 1 TH2045 CRXU5750618 -18.0¡C 20' 20.5 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.28 3.34 3.97
E 0308 1 SA1448 MWCU5650998 -1.0¡C 20' 16.2 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 9.19 1.21 3.66
E 0308 2 SA1451 PONU2974864 -1.0¡C 20' 15.8 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.97 1.18 3.66
E 0309 1 SA1444 MWCU5678892 -1.0¡C 20' 17 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 9.65 1.27 3.66
E 0309 2 SA1442 MWCU5801137 -1.0¡C 20' 17.1 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 9.71 1.27 3.66
E 0310 1 SA1450 PONU2889736 -1.0¡C 20' 15.6 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.85 1.16 3.66
E 0310 2 SA1447 MWCU5712929 -1.0¡C 20' 16.8 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 9.53 1.25 3.66
E 0403 1 FR1249 MWCU5685490 -18.0¡C 20' 22 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.04 3.59 3.97
E 0403 2 FR1317 MWCU5616139 -21.0¡C 20' 17.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 8.35 5.74 3.72
E 0404 1 WE1647 POCU2841003 -21.0¡C 20' 23.7 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 11.24 7.72 3.72
E 0404 2 FR0014 PONU2930589 -1.5¡C 20' 13.9 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 7.78 1.03 3.67
E 0405 1 FR2111 MWCU5681221 -1.0¡C 20' 12.3 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 6.98 0.92 3.66
E 0405 2 FR2130 PONU2956829 -1.5¡C 20' 13.6 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 7.61 1.01 3.67
E 0407 1 TH1150 MAEU5685996 -18.0¡C 20' 18 FZPY #NAME? EXPORT 1590 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.16 2.65 3.97
E 0407 2 FR1801 MWCU5708127 -18.0¡C 20' 22.4 FZPY #NAME? EXPORT 1590 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.15 3.30 3.97
E 0408 1 FR2116 MAEU5667816 -20.0¡C 20' 18.4 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.89 6.00 3.71
E 0408 2 SA0005 PONU2927292 -1.0¡C 20' 18.8 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 10.67 1.40 3.66
E 0409 1 TH1943 SUDU1047871 -20.0¡C 20' 22.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.97 7.40 3.71
E 0409 2 FR0750 FSCU5214236 -20.0¡C 20' 22.1 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.68 7.20 3.71
E 0411 1 FR2112 CRLU1213721 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
E 0411 2 SA1453 MWCU6818556 -1.0¡C 40' 21 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 6.61 1.56 4.41
E 0501 1 FR2134 CRLU1319800 -21.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 56.0 -21.0 35.0 3000 2500 7.78 9.65 4.16
E 0501 2 FR2145 MSCU7406641 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
E 0503 1 FR0851 SCZU8263108 -18.0¡C 20' 16.9 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.48 2.75 3.97
E 0503 2 FR1212 MAEU5661274 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT 2600 74.97 0.5 2 31.0 4.0 35.0 12000 2500 20.04 1.88 3.53
E 0504 1 FR0006 PONU2933931 -1.5¡C 20' 15.3 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 8.56 1.14 3.67
E 0504 2 FR2125 MWCU5661950 -1.5¡C 20' 13.5 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 7.55 1.01 3.67


E 0505 1 WE1650 KNLU2782677 -21.0¡C 20' 23.7 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 11.24 7.72 3.72
E 0505 2 TH1433 MWCU5691235 -1.0¡C 20' 16.8 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 9.53 1.25 3.66
E 0506 1 TH1731 MSCU3618149 -18.0¡C 20' 22 FZFS #NAME? V EXPORT 1900 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.91 3.87 3.97
E 0506 2 TH1734 MSCU3612475 -18.0¡C 20' 22.1 FZFS #NAME? V EXPORT 1900 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.97 3.89 3.97
E 0507 1 FR1759 PONU2917761 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT 2600 74.97 0.5 2 31.0 4.0 35.0 12000 2500 20.04 1.88 3.53
E 0507 2 FR1800 PONU2882310 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT 2600 74.97 0.5 2 31.0 4.0 35.0 12000 2500 20.04 1.88 3.53
E 0508 1 SA1858 PONU2859562 +15.0¡C 20' 14.5 WINE #NAME? EXPORT 3770 74.97 0.5 2 20.0 15.0 35.0 15000 2500 42.68 2.02 3.18
E 0511 1 FR0110 HLXU7750415 +18.0¡C 40' 17.7 REEF #NAME? IMPORT 3060 135.26 0.5 2 17.0 18.0 35.0 15000 2500 27.84 2.01 3.51
E 0511 2 FR0445 MWCU6963322 -18.0¡C 40' 28.6 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 6.05 3.55 4.72
E 0603 1 WE2054 MWCU5618595 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.87 7.33 3.71
E 0603 2 TH1443 MWCU5726178 +4.0¡C 20' 20.3 CHIL #NAME? V EXPORT 3640 74.97 0.5 2 31.0 4.0 35.0 12000 2500 36.52 3.42 3.53
E 0604 1 WE1652 PONU2865539 -21.0¡C 20' 23.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 11.19 7.69 3.72
E 0604 2 TH1156 MWCU5702659 0.0¡C 20' 16 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 35.0 0.0 35.0 10000 2500 9.35 1.19 3.63
E 0605 1 WE1651 POCU2831690 -21.0¡C 20' 16.7 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 7.92 5.44 3.72
E 0605 2 FR0639 MWCU5711687 -1.0¡C 20' 13.6 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 7.72 1.01 3.66
E 0606 1 WE1633 MWCU5669822 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT 1670 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.28 3.02 3.97
E 0606 2 WE1635 MWCU5622506 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT 1670 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.28 3.02 3.97
E 0607 1 WE1637 MWCU5800980 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT 1670 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.28 3.02 3.97
E 0607 2 WE1645 MWCU5628551 -18.0¡C 20' 19.5 FZCH #NAME? V EXPORT 1670 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.28 3.02 3.97
E 0608 1 FR0933 MAEU5697575 -21.0¡C 20' 16.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 5.81 4.00 3.72
E 0610 1 TH1518 PONU2856326 -18.0¡C 20' 22.2 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.14 3.62 3.97
E 0611 1 TH1141 MWCU6263490 -1.0¡C 40' 30.4 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 9.56 2.26 4.41
E 0611 2 TH1214 MSCU7444868 -1.0¡C 40' 17 CHIL #NAME? V EXPORT 1880 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.50 1.78 4.41
E 0701 1 TH1227 CRLU1250685 0.0¡C 40' 22.9 GRAP #NAME? EXPORT 3680 135.26 0.5 2 35.0 0.0 35.0 10000 2500 20.37 4.68 4.37
E 0703 1 TH1722 APRU5002743 -23.3¡C 40' 23.2 REEF #NAME? IMPORT 1340 135.26 0.5 2 58.3 -23.3 35.0 3000 2500 4.46 5.76 4.19
E 0705 1 TH1709 APRU5067575 +15.6¡C 40' 11.7 REEF #NAME? IMPORT 3060 135.26 0.5 2 19.4 15.6 35.0 15000 2500 16.00 1.33 3.65
E 0707 1 TH1941 SUDU1064056 -20.0¡C 20' 22.2 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.72 7.24 3.71
E 0707 2 SA0711 SUDU1051573 -1.0¡C 20' 15.7 CHMT #NAME? EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.91 1.17 3.66
E 0709 1 21-Mar CRLU3112849 -21.0¡C 20' 22.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 10.72 7.37 3.72
E 0711 1 TH1759 WLSU5614141 -21.0¡C 40' 32.5 FZMT #NAME? EXPORT 1760 135.26 0.5 2 56.0 -21.0 35.0 3000 2500 8.54 10.59 4.16
E 0711 2 SA0919 MNLU9723540 -1.0¡C 40' 26 GRAP #NAME? EXPORT 3680 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 22.46 5.32 4.41
E 0801 1 FR2128 CRLU1277109 -1.5¡C 40' 26.2 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 8.13 1.95 4.44
E 0805 1 MO0521 MWMU6397586 -1.5¡C 40' 26.5 CHMT EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 8.22 1.97 4.44
E 0807 1 SA1723 PONU2862993 -21.0¡C 20' 23.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 11.19 7.69 3.72
E 0808 1 FR0501 SUDU1147660 -20.0¡C 20' 22.5 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.87 7.33 3.71
E 0809 1 MO0503 MWCU6677150 -1.5¡C 40' 26 CHMT EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 8.06 1.94 4.44
E 0811 1 SU2335 PONU4912711 -1.5¡C 40' 24.2 CHMT #NAME? EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 7.51 1.80 4.44
E 0901 1 SA0715 SUDU4723820 -1.0¡C 40' 24.7 CHMT #NAME? EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.77 1.84 4.41
E 0905 1 FR2059 CGMU2976761 -25.0¡C 20' 11.7 FFS #NAME? IMPORT 1900 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 5.58 4.12 3.77
E 0907 1 FR2009 MWCU5667753 +4.0¡C 20' 22.7 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 28.05 2.63 3.53
E 0907 2 FR2035 MWCU5643793 +4.0¡C 20' 23.2 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 28.66 2.69 3.53
E 0910 1 FR2107 MWCU5748074 -20.0¡C 20' 15.6 FVG #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.14 5.49 3.71
E 0910 2 FR2114 PONU2946040 +4.0¡C 20' 21.8 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 26.93 2.52 3.53
E 0911 1 FR1015 GCEU7710989 -18.0¡C 40' 25 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 6.95 4.07 4.72
E 1003 1 TH1513 GCEU2952906 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 1003 2 FR0617 SCZU8663932 -20.0¡C 20' 21.9 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.58 7.14 3.71
E 1004 1 MO0046 PONU2859177 -20.0¡C 20' 17.8 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.60 5.80 3.71
E 1006 1 MO0049 MWCU5711624 -1.5¡C 20' 14.4 CHMT #NAME? EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 8.06 1.07 3.67
E 1007 1 TH1722 TOLU5676350 -20.0¡C 20' 22.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.97 7.40 3.71
E 1007 2 FR0315 CRLU3122298 c+6.0¡C 20' 21.7 CHEE #NAME? EXPORT 2850 74.97 0.5 2 29.0 6.0 35.0 15000 2500 32.75 2.29 3.48
E 1008 1 TH0632 SUDU1133413 -20.0¡C 20' 21 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.14 6.84 3.71


E 1008 2 TH0634 CRXU5275035 -20.0¡C 20' 19.9 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.61 6.49 3.71
E 1009 1 TH0736 SUDU1091637 -18.0¡C 20' 20.5 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.28 3.34 3.97
E 1009 2 SU2335 MAEU5688892 -20.0¡C 20' 18 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.70 5.87 3.71
E 1010 1 SU2337 KNLU2779924 -1.5¡C 20' 15.4 CHMT #NAME? EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 8.62 1.15 3.67
E 1011 1 FR1018 SUDU5118633 -18.0¡C 40' 30.5 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.48 4.97 4.72
E 1103 1 SA1337 CRLU3117007 +14.0¡C 20' 12 REEF #NAME? IMPORT 3060 74.97 0.5 2 21.0 14.0 35.0 15000 2500 27.23 1.36 3.21
E 1105 1 WE1648 MAEU5661401 -18.0¡C 20' 22.3 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.19 3.63 3.97
E 1107 1 WE2157 AKLU6702760 +15.0¡C 20' 8.1 REEF #NAME? IMPORT 3060 74.97 0.5 2 20.0 15.0 35.0 15000 2500 19.35 0.92 3.18
E 1108 1 TH1727 POCU2817075 -21.0¡C 20' 23.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 11.19 7.69 3.72
E 1108 2 FR0100 MWCU5609994 +4.0¡C 20' 15.8 CHIL #NAME? V EXPORT 3640 74.97 0.5 2 31.0 4.0 35.0 12000 2500 28.42 2.66 3.53
E 1110 1 WE1954 CRLU3135000 -20.0¡C 20' 9.9 REEF #NAME? T IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 3.64 2.46 3.71
E 1111 1 27-Mar APRU5036281 -20.0¡C 40' 25.3 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.77 8.25 4.15
E 1111 2 WE1022 CBHU2996242 -18.0¡C 40' 28.4 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.90 4.63 4.72
E 1206 1 MO0653 TRIU6480933 -18.0¡C 20' 22 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.04 3.59 3.97
E 1207 1 SA1445 NYKU7621689 0.0¡C 20' 8 CHIL #NAME? EXPORT 1880 74.97 0.5 2 35.0 0.0 35.0 10000 2500 6.56 0.84 3.63
E 1208 1 TH2013 SUDU1103363 -20.0¡C 20' 20.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.95 6.71 3.71
E 1209 1 TH2007 TOLU7440092 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 1209 2 SA0437 TRLU1035061 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 1210 1 TH1958 SCZU8676462 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 1210 2 FR1105 TRLU1058719 -18.0¡C 20' 16.5 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.28 2.69 3.97
E 1211 1 TH2236 MSCU7427407 -18.0¡C 40' 29.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.26 4.84 4.72
E 1303 1 FR1941 MWCU5679116 +4.0¡C 20' 17.6 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 21.74 2.04 3.53
E 1304 1 FR2027 MWCU5632931 +4.0¡C 20' 22.8 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 28.17 2.64 3.53
E 1305 1 FR2053 MWCU5706103 +4.0¡C 20' 22.6 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 27.92 2.62 3.53
E 1305 2 FR2100 MWCU5610296 +4.0¡C 20' 23.7 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 29.28 2.74 3.53
E 1308 1 FR2133 PONU2967459 +4.0¡C 20' 22.6 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 27.92 2.62 3.53
E 1308 2 FR2138 MWCU5740535 +12.0¡C 20' 12 CHC #NAME? IMPORT 3640 74.97 0.5 2 23.0 12.0 35.0 15000 2500 29.44 1.62 3.28
E 1309 1 TH2012 SUDU1012140 -20.0¡C 20' 19 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.18 6.19 3.71
E 1311 1 FR1949 GCEU7791403 -20.0¡C 40' 16.5 FPT #NAME? IMPORT 1900 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 4.77 5.81 4.15
E 1311 2 FR1954 CGMU4812601 -20.0¡C 40' 28 REEF #NAME? IMPORT 1340 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 5.71 6.95 4.15
E 1406 1 FR0929 HLXU3714111 -25.0¡C 20' 5.7 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 1.92 1.41 3.77
E 1406 2 FR0936 PONU2939077 -18.0¡C 20' 16.7 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 6.38 2.07 3.97
E 1408 1 FR1959 PONU2863881 +12.0¡C 20' 10.1 CHC #NAME? IMPORT 3640 74.97 0.5 2 23.0 12.0 35.0 15000 2500 24.78 1.36 3.28
E 1408 2 FR2103 SCZU8097753 -20.0¡C 20' 16.5 FPT #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.60 5.81 3.71
E 1411 1 FR1956 MWCU6902219 -20.0¡C 40' 27.3 REEF #NAME? IMPORT 1340 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 5.57 6.77 4.15
E 1501 1 21-Mar TRIU8600410 -21.0¡C 40' 26.3 FZMT #NAME? V EXPORT 1760 135.26 0.5 2 56.0 -21.0 35.0 3000 2500 6.91 8.57 4.16
E 1503 1 TH1604 MWCU5683965 -18.0¡C 20' 22 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.04 3.59 3.97
E 1504 1 FR1600 PONU2895723 -25.0¡C 20' 10.5 FZIC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 6.62 4.88 3.77
E 1504 2 FR1909 MWCU5700759 -1.0¡C 20' 12.9 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 7.32 0.96 3.66
E 1505 1 TH1436 MAEU5663929 -21.0¡C 20' 14.9 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 7.07 4.86 3.72
E 1505 2 TH1439 MWCU5654226 -1.0¡C 20' 15.1 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.57 1.12 3.66
E 1506 1 TH1431 PONU2894671 -1.0¡C 20' 15.5 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.80 1.15 3.66
E 1506 2 FR1419 MSCU3620655 -1.0¡C 20' 8.6 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 4.88 0.64 3.66
E 1509 1 FR0430 MWCU6722691 -18.0¡C 40' 26.4 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 5.59 3.28 4.72
E 1604 1 SA1722 SUDU1137173 -18.0¡C 20' 18.4 FZFS #NAME? EXPORT 1900 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.96 3.24 3.97
E 1604 2 SA1720 SUDU1084833 -18.0¡C 20' 18.2 FZFS #NAME? EXPORT 1900 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.86 3.20 3.97
E 1605 1 FR0932 HLXU3700519 -25.0¡C 20' 6.3 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 2.12 1.56 3.77
E 1605 2 FR0938 HLXU2706507 -25.0¡C 20' 7.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 2.39 1.76 3.77
E 1608 1 TH1435 MWCU5665067 -1.0¡C 20' 15.1 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.57 1.12 3.66
E 1608 2 FR2124 MWCU5749091 -1.5¡C 20' 14.5 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 8.11 1.08 3.67
E 1611 1 FR1947 CRLU5130939 -20.0¡C 40' 27 REEF #NAME? IMPORT 1340 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 5.50 6.70 4.15


E 1611 2 FR1951 GESU9068074 -20.0¡C 40' 27.5 REEF #NAME? IMPORT 1340 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 5.61 6.82 4.15
E 1707 1 WE0705 MWCU5719800 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
E 1707 2 WE0710 MWCU5605622 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
E 1708 1 WE0706 PONU2871887 -25.0¡C 20' 20.5 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.93 9.53 3.77
E 1708 2 WE0702 MWCU5613295 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
E 1807 1 SA0805 MSCU3620070 -20.0¡C 20' 28 REEF #NAME? IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.30 6.95 3.71
E 1810 1 TH0857 MWCU5706187 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
E 1811 1 FR0117 HLXU4767688 +18.0¡C 40' 20.5 REEF #NAME? IMPORT 3060 135.26 0.5 2 17.0 18.0 35.0 15000 2500 32.25 2.32 3.51
E 1903 1 TH0750 SUDU5134640 -1.0¡C 40' 25.9 CHMT #NAME? EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 8.15 1.93 4.41
E 1903 2 TH1424 CRLU6212820 -18.0¡C 40' 26.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.42 4.35 4.72
E 1905 1 FR0538 SUDU5098856 -20.0¡C 40' 29 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 7.77 9.45 4.15
E 1905 2 FR1315 SUDU5001586 -20.0¡C 40' 21.8 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 5.84 7.11 4.15
E 2006 1 TH1443 MWCU5800871 -1.0¡C 20' 23.1 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 13.11 1.72 3.66
E 2006 2 FR0404 MWCU5617536 c+3.0¡C 20' 23.7 CHEE #NAME? V EXPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 32.30 3.13 3.56
E 2007 1 SA0721 PONU2899267 -1.0¡C 20' 13.9 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 7.89 1.03 3.66
E 2103 1 FR1556 SUDU5199722 -20.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 7.93 9.65 4.15
E 2103 2 MO0226 SUDU5085334 -20.0¡C 40' 28.9 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 7.74 9.42 4.15
E 2105 1 MO0522 SUDU5131759 -20.0¡C 40' 29 FZMT EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 7.77 9.45 4.15
E 2105 2 MO0543 CRLU6212498 -20.0¡C 40' 29.1 FZMT EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 7.79 9.48 4.15
E 2107 1 WE1034 MAEU5673697 -18.0¡C 20' 22 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.04 3.59 3.97
E 2108 1 SA0717 MWCU5742395 -18.0¡C 20' 18.1 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.08 2.95 3.97
E 2109 1 20-Mar PONU2854452 -21.0¡C 20' 18.3 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 8.68 5.96 3.72
E 2109 2 SA0712 PONU2934162 -18.0¡C 20' 22.3 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.19 3.63 3.97
E 2110 1 21-Mar MAEU5676649 -21.0¡C 20' 17.9 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 8.49 5.83 3.72
E 2110 2 24-Mar MWCU5631977 -21.0¡C 20' 18.3 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 8.68 5.96 3.72
E 2111 1 21-Mar MWCU6675521 -21.0¡C 40' 27.9 FZMT #NAME? V EXPORT 1760 135.26 0.5 2 56.0 -21.0 35.0 3000 2500 7.33 9.09 4.16
E 2201 1 WE1712 GESU9341002 -20.0¡C 40' 30.3 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 8.11 9.88 4.15
E 2203 1 SA0149 CRLU6213600 -0.5¡C 40' 28.9 PEAR #NAME? EXPORT 1760 135.26 0.5 2 35.5 -0.5 35.0 10000 2500 12.11 2.83 4.39
E 2205 1 SA0155 SUDU5064141 -0.5¡C 40' 28.7 PEAR #NAME? EXPORT 1760 135.26 0.5 2 35.5 -0.5 35.0 10000 2500 12.03 2.81 4.39
E 2207 1 TH0755 MWCU5694316 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
E 2208 1 TH0523 GCEU3131232 -20.0¡C 20' 23.2 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 11.21 7.56 3.71
E 2208 2 TH0916 TRLU1062200 -18.0¡C 20' 21.9 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.99 3.57 3.97
E 2209 1 SA0133 CGMU2977351 c-2.0¡C 20' 23.8 CHEE #NAME? EXPORT 1670 74.97 0.5 2 37.0 -2.0 35.0 6000 2500 16.37 3.68 3.60
E 2209 2 SA0130 CGMU2980782 c-2.0¡C 20' 23.7 CHEE #NAME? EXPORT 1670 74.97 0.5 2 37.0 -2.0 35.0 6000 2500 16.30 3.66 3.60
E 2210 1 TH0521 CRXU5157623 -20.0¡C 20' 18.4 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.89 6.00 3.71
E 2210 2 SA0434 GCEU2960748 -20.0¡C 20' 19.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.52 6.42 3.71
E 2211 1 WE0710 MWCU6764320 -1.0¡C 40' 22.6 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.11 1.68 4.41
E 2211 2 TH0753 MWCU6788322 -1.0¡C 40' 25 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.86 1.86 4.41
E 2301 1 SA0153 SUDU4711114 -0.5¡C 40' 29.1 PEAR #NAME? EXPORT 1760 135.26 0.5 2 35.5 -0.5 35.0 10000 2500 12.20 2.85 4.39
E 2301 2 FR0445 CRLU8102951 -18.0¡C 40' 28 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 5.93 3.47 4.72
E 2305 1 TH1227 TRLU1060001 -18.0¡C 20' 23 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.54 3.75 3.97
E 2305 2 TH1404 TOLU7440209 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 2307 1 WE0238 PONU2950991 c+3.0¡C 20' 23.6 CHEE #NAME? V EXPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 32.17 3.11 3.56
E 2307 2 WE0700 PONU2909257 -1.0¡C 20' 14.5 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 8.23 1.08 3.66
E 2308 1 WE0510 TRIU6481518 -20.0¡C 20' 22.3 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.77 7.27 3.71
E 2308 2 WE0512 TRLU1035518 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 2310 1 TH1033 MWCU5725119 -25.0¡C 20' 13.3 FZFS #NAME? EXPORT 1900 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 6.35 4.68 3.77
E 2310 2 TH1241 MAEU5677898 -18.0¡C 20' 20.3 FZPY #NAME? EXPORT 1590 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.20 2.99 3.97
E 2311 1 WE0707 PONU4833607 -1.0¡C 40' 22.7 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.14 1.69 4.41
E 2311 2 TH1510 MWCU6297340 0.0¡C 40' 20 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 35.0 0.0 35.0 10000 2500 6.48 1.49 4.37
E 2401 1 TH0940 OOLU6404835 0.0¡C 40' 23.2 GRAP #NAME? EXPORT 3680 135.26 0.5 2 35.0 0.0 35.0 10000 2500 20.63 4.74 4.37


E 2401 2 FR1049 GESU9204695 -18.0¡C 40' 29 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.06 4.73 4.72
E 2406 1 TH0441 PONU2872780 c-2.0¡C 20' 23.7 CHEE #NAME? V EXPORT 1670 74.97 0.5 2 37.0 -2.0 35.0 6000 2500 16.30 3.66 3.60
E 2406 2 TH0443 PONU2873299 c-2.0¡C 20' 23.7 CHEE #NAME? V EXPORT 1670 74.97 0.5 2 37.0 -2.0 35.0 6000 2500 16.30 3.66 3.60
E 2407 1 TH0501 MWCU5600390 c-2.0¡C 20' 23.7 CHEE #NAME? V EXPORT 1670 74.97 0.5 2 37.0 -2.0 35.0 6000 2500 16.30 3.66 3.60
E 2407 2 TH0445 PONU2966909 c+3.0¡C 20' 23.7 CHEE #NAME? V EXPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 32.30 3.13 3.56
E 2408 1 FR0502 SUDU1020269 -20.0¡C 20' 22.6 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.92 7.37 3.71
E 2409 1 FR2223 SUDU5212418 -20.0¡C 40' 25.3 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.77 8.25 4.15
E 2411 1 2-Mar TRIU8823013 -20.0¡C 40' 25.4 FZMT #NAME? STORAG 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.80 8.28 4.15
L 0103 1 FR0218 GCEU2013744 +3.0¡C 20' 23 CEE #NAME? T IMPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 31.35 3.03 3.56
L 0103 2 FR0225 GCEU3127551 +3.0¡C 20' 23 CEE #NAME? IMPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 31.35 3.03 3.56
L 0107 1 FR1552 PONU2886125 -1.0¡C 20' 12.6 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 7.15 0.94 3.66
L 0107 2 FR2030 MWCU5694419 +4.0¡C 20' 18.9 CHIL #NAME? V EXPORT 3640 74.97 0.5 2 31.0 4.0 35.0 12000 2500 34.00 3.19 3.53
L 0109 1 FR0656 MWCU6717170 -1.0¡C 40' 22.4 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.05 1.67 4.41
L 0109 2 FR0653 PONU4955061 -1.0¡C 40' 21.7 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 6.83 1.62 4.41
L 0111 1 24-Mar ZCSU5829329 -21.0¡C 40' 29 FZMT #NAME? EXPORT 1760 135.26 0.5 2 56.0 -21.0 35.0 3000 2500 7.62 9.45 4.16
L 0111 2 TU1536 CRXU6968646 -18.0¡C 40' 29.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.26 4.84 4.72
L 0203 1 FR0907 PCIU5812877 0.0¡C 20' 12.5 KIWI #NAME? EXPORT 1970 74.97 0.5 2 35.0 0.0 35.0 10000 2500 10.74 1.37 3.63
L 0203 2 FR1220 GCEU2953651 -20.0¡C 20' 18.5 FZPY #NAME? EXPORT 1590 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.07 5.45 3.71
L 0204 1 TH1639 OOLU3840141 +4.0¡C 20' 11.2 BUTR #NAME? EXPORT 2600 74.97 0.5 2 31.0 4.0 35.0 12000 2500 14.39 1.35 3.53
L 0204 2 FR1225 GESU9297846 -18.0¡C 20' 23 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.54 3.75 3.97
L 0205 1 TH1304 OOLU3847207 +3.0¡C 20' 13.6 CHEE #NAME? EXPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 18.54 1.79 3.56
L 0205 2 TH1928 PCIU5797941 -21.0¡C 20' 19.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 9.34 6.42 3.72
L 0206 1 TU2330 GESU9338837 0.0¡C 20' 23 CHEE #NAME? EXPORT 1670 74.97 0.5 2 35.0 0.0 35.0 10000 2500 16.75 2.13 3.63
L 0206 2 WE1030 PCIU5802354 -18.0¡C 20' 21.5 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.79 3.50 3.97
L 0207 1 TU1639 PCIU5799271 -18.0¡C 20' 23 FZBU #NAME? EXPORT 1260 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.26 2.68 3.97
L 0207 2 WE0551 OOLU3854546 -21.0¡C 20' 22.1 FZFS #NAME? EXPORT 1900 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 11.32 7.78 3.72
L 0208 1 26-Mar GESU9337213 -20.0¡C 20' 19.9 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.61 6.49 3.71
L 0208 2 27-Mar GESU9337070 -18.0¡C 20' 20 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.03 3.26 3.97
L 0209 1 FR0641 MWCU5702725 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
L 0209 2 FR0645 POCU2829498 -25.0¡C 20' 20.6 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.99 9.58 3.77
L 0210 1 FR0649 POCU2840901 -25.0¡C 20' 20.6 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.99 9.58 3.77
L 0210 2 FR0658 POCU2829559 -25.0¡C 20' 20.6 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.99 9.58 3.77
L 0211 1 FR1616 SUDU4710294 -18.0¡C 40' 30.5 FZBU #NAME? EXPORT 1260 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 6.07 3.56 4.72
L 0301 1 FR1142 PCIU5970609 0.0¡C 40' 24 GRAP #NAME? EXPORT 3680 135.26 0.5 2 35.0 0.0 35.0 10000 2500 21.34 4.91 4.37
L 0301 2 FR1426 PCIU5979041 -18.0¡C 40' 12.8 FZIC #NAME? EXPORT 2510 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 5.08 2.97 4.72
L 0303 1 FR0912 MSCU3626503 -1.0¡C 20' 10.7 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 6.07 0.80 3.66
L 0303 2 FR1245 MAEU5668561 +15.0¡C 20' 14.3 WINE #NAME? V EXPORT 3770 74.97 0.5 2 20.0 15.0 35.0 15000 2500 42.09 2.00 3.18
L 0304 1 FR1812 CBHU2637807 +20.0¡C 20' 20.8 REEF #NAME? T IMPORT 3060 74.97 0.5 2 15.0 20.0 35.0 15000 2500 67.49 2.36 3.01
L 0305 1 FR1549 PONU2930892 -1.0¡C 20' 12.6 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 7.15 0.94 3.66
L 0306 1 FR0006 TRIU6403752 -23.3¡C 20' 15 REE #NAME? IMPORT 1600 74.97 0.5 2 58.3 -23.3 35.0 3000 2500 6.21 4.44 3.75
L 0306 2 FR0221 GCEU2019315 +3.0¡C 20' 23 CEE #NAME? IMPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 31.35 3.03 3.56
L 0307 1 FR1625 MAEU5698165 -18.0¡C 20' 22 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.04 3.59 3.97
L 0307 2 FR2226 MWCU5686671 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.87 7.33 3.71
L 0308 1 WE1758 GESU9338708 -20.0¡C 20' 19.9 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.61 6.49 3.71
L 0308 2 FR0402 GESU9338082 c+2.0¡C 20' 23.6 CHEE #NAME? EXPORT 2850 74.97 0.5 2 33.0 2.0 35.0 10000 2500 31.16 3.74 3.57
L 0309 1 FR0655 MWCU6869553 -1.0¡C 40' 26.1 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 8.21 1.94 4.41
L 0311 1 FR1445 OOLU6311352 +1.0¡C 40' 26 GRAP #NAME? EXPORT 3680 135.26 0.5 2 34.0 1.0 35.0 10000 2500 23.82 5.32 4.32
L 0401 1 FR1143 MWSU9024166 0.0¡C 40' 24 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 35.0 0.0 35.0 10000 2500 7.77 1.79 4.37
L 0401 2 SA1219 PONU4956617 -1.0¡C 40' 29.3 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 9.22 2.18 4.41
L 0403 1 WE2322 CRXU5297836 -20.0¡C 20' 9.7 FZFS #NAME? EXPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 5.06 3.41 3.71
L 0404 1 WE2228 TRLU1055263 -20.0¡C 20' 10 FZFS #NAME? EXPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 5.22 3.52 3.71


L 0404 2 WE2229 IRNU2804531 -20.0¡C 20' 10.7 FZFS #NAME? EXPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 5.58 3.76 3.71
L 0405 1 FR0643 POCU2816187 -25.0¡C 20' 20.8 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 13.12 9.67 3.77
L 0407 1 TH1609 GESU9298170 -20.0¡C 20' 20.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.00 6.75 3.71
L 0407 2 FR0408 GESU9338992 c+3.0¡C 20' 23.6 CHEE #NAME? EXPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 32.17 3.11 3.56
L 0408 1 FR1635 PCIU5808542 -18.0¡C 20' 17.2 FZBU #NAME? EXPORT 1260 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 6.18 2.01 3.97
L 0408 2 FR1947 CBHU2656216 -18.0¡C 20' 20.8 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.43 3.39 3.97
L 0409 1 FR1220 MWCU6790989 -1.0¡C 40' 30.3 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 9.53 2.26 4.41
L 0411 1 FR1416 MSCU7328528 -1.0¡C 40' 21.2 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 6.67 1.58 4.41
L 0501 1 MO0510 GESU9289769 -18.0¡C 40' 29.8 FZMT EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.29 4.86 4.72
L 0503 1 TU0712 CBHU2643100 -18.0¡C 20' 17 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.53 2.77 3.97
L 0503 2 TH1046 CBHU2674185 -18.0¡C 20' 14.4 FZBU #NAME? EXPORT 1260 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 5.17 1.68 3.97
L 0504 1 TH1741 PCIU5814041 +18.0¡C 20' 8.6 REEF #NAME? IMPORT 3060 74.97 0.5 2 17.0 18.0 35.0 15000 2500 24.41 0.97 3.08
L 0507 1 TU2024 PCIU5805939 -21.0¡C 20' 20.1 FZMT #NAME? EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 9.53 6.55 3.72
L 0508 1 WE0109 POCU2841718 -20.0¡C 20' 17.8 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.60 5.80 3.71
L 0508 2 WE0614 MSCU3610940 -18.0¡C 20' 17.9 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.98 2.92 3.97
L 0509 1 TH0529 MWCU5748367 -1.0¡C 20' 18.9 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 10.73 1.41 3.66
L 0509 2 TH0539 PONU2972352 -20.0¡C 20' 18.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.99 6.06 3.71
L 0510 1 WE0008 POCU2828871 -20.0¡C 20' 17.4 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.41 5.67 3.71
L 0510 2 WE0026 PONU2976126 -1.5¡C 20' 15 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.5 -1.5 35.0 10000 2500 8.39 1.12 3.67
L 0601 1 TH1330 MSCU7439753 +13.0¡C 40' 11.4 CHIL #NAME? EXPORT 3640 135.26 0.5 2 22.0 13.0 35.0 15000 2500 16.24 1.54 3.80
L 0601 2 TH1331 CRLU1277520 +13.0¡C 40' 11.4 CHIL #NAME? EXPORT 3640 135.26 0.5 2 22.0 13.0 35.0 15000 2500 16.24 1.54 3.80
L 0603 1 WE1143 OOLU3831746 +4.0¡C 20' 16.5 CHEE #NAME? EXPORT 2850 74.97 0.5 2 31.0 4.0 35.0 12000 2500 23.24 2.18 3.53
L 0603 2 TH0525 GESU9339031 -20.0¡C 20' 20.4 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.85 6.65 3.71
L 0604 1 FR1314 OOLU3828336 +15.0¡C 20' 15.9 CONF #NAME? EXPORT 3350 74.97 0.5 2 20.0 15.0 35.0 15000 2500 41.59 1.97 3.18
L 0604 2 FR1355 PCIU5802903 0.0¡C 20' 15 GRAP #NAME? EXPORT 3680 74.97 0.5 2 35.0 0.0 35.0 10000 2500 24.07 3.07 3.63
L 0605 1 TH1430 MWCU5644022 -18.0¡C 20' 22.3 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 11.19 3.63 3.97
L 0607 1 TH1518 CRLU1206907 +13.0¡C 40' 8.2 CHIL #NAME? EXPORT 3640 135.26 0.5 2 22.0 13.0 35.0 15000 2500 11.68 1.11 3.80
L 0609 1 FR1215 KNLU4724520 +15.0¡C 40' 19.7 CONF #NAME? EXPORT 3350 135.26 0.5 2 20.0 15.0 35.0 15000 2500 28.56 2.44 3.68
L 0611 1 FR1640 SUDU1123328 -18.0¡C 20' 20.9 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.98 2.59 3.97
L 0701 1 FR1206 MNLU9720216 +15.0¡C 40' 21.9 CONF #NAME? EXPORT 3350 135.26 0.5 2 20.0 15.0 35.0 15000 2500 31.75 2.72 3.68
L 0701 2 FR1318 OOLU6092070 -21.0¡C 40' 24.3 FZMT #NAME? EXPORT 1760 135.26 0.5 2 56.0 -21.0 35.0 3000 2500 6.39 7.92 4.16
L 0703 1 TH1734 CBHU2647235 -18.0¡C 20' 11 REEF #NAME? TRANSSH 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 4.20 1.36 3.97
L 0705 1 TH2002 APRU5074912 -18.0¡C 40' 27 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 5.72 3.35 4.72
L 0707 1 TH1955 APRU5083107 -18.0¡C 40' 27.5 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 5.82 3.41 4.72
L 0709 1 TH0638 CRLU1217218 -18.0¡C 40' 24.5 FZFS #NAME? EXPORT 1900 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.35 4.31 4.72
L 0801 1 WE1612 PCIU5999285 -18.0¡C 40' 29 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.06 4.73 4.72
L 0801 2 FR2245 OOLU5961950 -20.0¡C 40' 25 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.69 8.15 4.15
L 0806 1 TH1731 CBHU2648714 -18.0¡C 20' 11.1 REEF #NAME? TRANSSH 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 4.24 1.38 3.97
L 0807 1 WE1547 GESU9341050 -20.0¡C 40' 25.5 FZPY #NAME? EXPORT 1590 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.17 7.51 4.15
L 0807 2 WE1957 CBHU2983760 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
L 1001 1 WE1653 CRXU6805715 -18.0¡C 40' 21.9 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 4.64 2.72 4.72
L 1003 1 FR1417 MWCU5672596 +4.0¡C 20' 15.6 BUTR #NAME? EXPORT 2600 74.97 0.5 2 31.0 4.0 35.0 12000 2500 20.04 1.88 3.53
L 1003 2 FR1654 CRLU3807430 +4.0¡C 20' 12.5 CHIL #NAME? EXPORT 3640 74.97 0.5 2 31.0 4.0 35.0 12000 2500 22.49 2.11 3.53
L 1004 1 TH0532 SUDU1031052 -18.0¡C 20' 21.6 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.25 2.68 3.97
L 1005 1 FR1358 SCZU8677047 -18.0¡C 20' 14.9 FZFS #NAME? EXPORT 1900 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.07 2.62 3.97
L 1005 2 FR1351 SCZU8262354 -18.0¡C 20' 15.2 FZFS #NAME? EXPORT 1900 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 2.67 3.97
L 1101 1 MO0602 HDMU5934579 -18.0¡C 40' 29.3 FZMT EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.15 4.77 4.72
L 1103 1 26-Mar MWCU5741151 -1.0¡C 20' 17 CHMT #NAME? V EXPORT 1340 74.97 0.5 2 36.0 -1.0 35.0 10000 2500 9.65 1.27 3.66
L 1103 2 26-Mar PONU2928792 -20.0¡C 20' 19.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.47 6.39 3.71
L 1104 1 26-Mar CBHU2635173 +9.0¡C 20' 23.1 CHEE #NAME? EXPORT 2850 74.97 0.5 2 26.0 9.0 35.0 15000 2500 39.05 2.44 3.38
L 1104 2 26-Mar CBHU2637670 +9.0¡C 20' 23.1 CHEE #NAME? EXPORT 2850 74.97 0.5 2 26.0 9.0 35.0 15000 2500 39.05 2.44 3.38


L 1105 1 WE0924 PONU2951093 +4.0¡C 20' 18.1 CHIL #NAME? V EXPORT 3640 74.97 0.5 2 31.0 4.0 35.0 12000 2500 32.56 3.05 3.53
L 1105 2 WE1101 PONU2880235 +4.0¡C 20' 18.2 CHIL #NAME? V EXPORT 3640 74.97 0.5 2 31.0 4.0 35.0 12000 2500 32.74 3.07 3.53
L 1106 1 WE2316 MWCU5691847 -20.0¡C 20' 17.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.50 5.74 3.71
L 1106 2 WE2332 MWCU5630707 -20.0¡C 20' 21.1 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.19 6.88 3.71
L 1107 1 WE1936 CRLU1251249 -18.0¡C 40' 29.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.26 4.84 4.72
L 1107 2 TH0607 MNLU9721613 -18.0¡C 40' 27.9 FZPY #NAME? EXPORT 1590 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.01 4.11 4.72
L 1201 1 WE2157 PCIU5989060 -18.0¡C 40' 29.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.26 4.84 4.72
L 1203 1 WE1821 SUDU1054090 -18.0¡C 20' 21.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.06 2.62 3.97
L 1204 1 SA0157 PONU2957511 +4.0¡C 20' 21.7 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 26.81 2.51 3.53
L 1205 1 FR1649 CRLU3149452 -18.0¡C 20' 21.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.06 2.62 3.97
L 1206 1 WE2247 SUDU1054401 -18.0¡C 20' 21.5 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.21 2.67 3.97
L 1207 1 TH0523 SUDU1090203 -18.0¡C 20' 22.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.56 2.78 3.97
L 1207 2 TH0532 CRLU3166969 -18.0¡C 20' 21.7 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.29 2.69 3.97
L 1301 1 FR1319 OOLU6400660 0.0¡C 40' 22.4 GRAP #NAME? EXPORT 3680 135.26 0.5 2 35.0 0.0 35.0 10000 2500 19.92 4.58 4.37
L 1401 1 26-Mar GESU9307311 -20.0¡C 40' 31 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 8.30 10.10 4.15
L 1401 2 TH1357 GESU9204062 -20.0¡C 40' 25.5 FZPY #NAME? EXPORT 1590 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.17 7.51 4.15
L 1403 1 26-Mar GESU9319729 -18.0¡C 40' 29.8 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.29 4.86 4.72
L 1403 2 WE1313 CBHU2941975 +13.0¡C 40' 10.9 CHIL #NAME? EXPORT 3640 135.26 0.5 2 22.0 13.0 35.0 15000 2500 15.53 1.47 3.80
L 1405 1 WE1459 GESU9273192 -18.0¡C 40' 28.5 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.92 4.64 4.72
L 1405 2 WE1715 GESU9340855 -18.0¡C 40' 28.5 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.92 4.64 4.72
L 1407 1 FR0620 OOLU6092260 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
L 1407 2 FR0903 CRLU1234914 -18.0¡C 40' 25 HFSF #NAME? EXPORT 1590 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 6.28 3.68 4.72
L 1501 1 23-Mar ZCSU5971009 -18.0¡C 40' 30.2 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.40 4.92 4.72
L 1503 1 FR1416 SUDU1146160 -18.0¡C 20' 25 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 12.54 4.07 3.97
L 1504 1 FR2224 OOLU3832341 -20.0¡C 20' 21 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.14 6.84 3.71
L 1601 1 FR2247 MSCU7434772 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
L 1603 1 FR1633 MWCU6709046 -18.0¡C 40' 29.7 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 6.29 3.69 4.72
L 1605 1 FR1628 PONU4728026 -18.0¡C 40' 28.8 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 6.10 3.57 4.72
L 1605 2 FR1631 CRLU5153678 +1.0¡C 40' 21.5 REEF #NAME? IMPORT 3060 135.26 0.5 2 34.0 1.0 35.0 10000 2500 16.38 3.66 4.32
L 1702 1 TH2157 MNLU8720356 -18.0¡C 20' 18.1 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 9.08 2.95 3.97
L 1702 2 FR1150 OOLU3842587 -18.0¡C 20' 17.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.88 2.88 3.97
L 1801 1 FR1336 OOLU6110569 0.0¡C 40' 20.1 GRAP #NAME? EXPORT 3680 135.26 0.5 2 35.0 0.0 35.0 10000 2500 17.88 4.11 4.37
L 1807 1 FR1139 MSCU4916826 FAN 40' 29.1 FANT V EXPORT 1 135.26 0.5 2 35.0 35.0 10000 2500 2.50
L 1903 1 26-Mar MWCU5695082 -20.0¡C 20' 22.2 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.72 7.24 3.71
L 1903 2 26-Mar PONU2896360 -20.0¡C 20' 19.4 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.37 6.32 3.71
L 1904 1 24-Mar SUDU1003106 +12.8¡C 20' 15.9 REEF #NAME? IMPORT 3060 74.97 0.5 2 22.2 12.8 35.0 15000 2500 34.04 1.80 3.25
L 1904 2 WE2138 NYKU7557281 -18.0¡C 20' 11.9 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 4.55 1.48 3.97
L 1905 1 TU1301 PONU2872250 -21.0¡C 20' 22.6 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 10.72 7.37 3.72
L 1905 2 TU2043 PONU2973364 -20.0¡C 20' 19.9 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.61 6.49 3.71
L 1906 1 WE1754 SUDU1037493 -18.0¡C 20' 19.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.41 2.41 3.97
L 2003 1 WE1108 MSCU3619063 +1.0¡C 20' 17 CHEE #NAME? EXPORT 2850 74.97 0.5 2 34.0 1.0 35.0 10000 2500 21.77 2.69 3.60
L 2003 2 FR2114 MWCU5603276 -20.0¡C 20' 17.5 FVG #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.13 6.16 3.71
L 2004 1 WE2356 SCZU8670490 -20.0¡C 20' 17.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 6.40 4.32 3.71
L 2004 2 TH0846 CGMU2971754 -25.0¡C 20' 8.8 ICRM #NAME? IMPORT 1880 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 4.16 3.06 3.77
L 2005 1 TH1548 MSCU3629544 +4.0¡C 20' 17.5 CHEE #NAME? EXPORT 2850 74.97 0.5 2 31.0 4.0 35.0 12000 2500 24.65 2.31 3.53
L 2007 1 FR2145 MWCU5673273 +12.0¡C 20' 12.3 CHC #NAME? IMPORT 3640 74.97 0.5 2 23.0 12.0 35.0 15000 2500 30.18 1.66 3.28
L 2008 1 FR2048 CGMU2978701 -20.0¡C 20' 14.5 REEF #NAME? IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 5.33 3.60 3.71
L 2008 2 FR2055 ANNU5015892 +4.0¡C 20' 21.6 REE #NAME? IMPORT 3060 74.97 0.5 2 31.0 4.0 35.0 12000 2500 32.66 3.06 3.53
L 2009 1 SA0717 PONU4938017 -1.0¡C 40' 24.5 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.71 1.82 4.41
L 2011 1 FR0104 CRLU1305303 -1.5¡C 40' 25.6 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 7.94 1.91 4.44
L 2101 1 26-Mar PONU4871802 -1.5¡C 40' 25.6 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 7.94 1.91 4.44


L 2103 1 26-Mar CRLU3602960 -18.0¡C 20' 25 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 12.54 4.07 3.97
L 2103 2 26-Mar CRLU3603740 -18.0¡C 20' 20 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.03 3.26 3.97
L 2104 1 26-Mar GESU9336691 0.0¡C 20' 23.5 CHEE #NAME? EXPORT 1670 74.97 0.5 2 35.0 0.0 35.0 10000 2500 17.11 2.18 3.63
L 2104 2 26-Mar CBHU2669912 +9.0¡C 20' 22.8 CHEE #NAME? EXPORT 2850 74.97 0.5 2 26.0 9.0 35.0 15000 2500 38.54 2.41 3.38
L 2105 1 TU2039 MWMU6363457 -1.0¡C 40' 25.4 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 7.99 1.89 4.41
L 2105 2 TU2145 MWMU6342290 -1.5¡C 40' 24.7 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 7.66 1.84 4.44
L 2107 1 WE0113 MWMU6306631 -1.5¡C 40' 26 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 8.06 1.94 4.44
L 2107 2 TH0128 MWCU6718120 -1.5¡C 40' 24.9 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.5 -1.5 35.0 10000 2500 7.72 1.85 4.44
L 2109 1 WE1755 SUDU1102691 -18.0¡C 20' 19.7 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.52 2.44 3.97
L 2109 2 WE1827 SUDU1043304 -18.0¡C 20' 21.2 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.10 2.63 3.97
L 2110 1 FR2321 GESU9336310 -20.0¡C 20' 17.8 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.60 5.80 3.71
L 2111 1 TH1730 CRLU7229514 -1.0¡C 40' 29 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 9.12 2.16 4.41
L 2111 2 FR0915 MWMU6430555 -1.0¡C 40' 29.1 CHMT #NAME? V EXPORT 1340 135.26 0.5 2 36.0 -1.0 35.0 10000 2500 9.15 2.17 4.41
L 2201 1 FR1412 FSCU5645249 -18.0¡C 40' 29 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.06 4.73 4.72
L 2203 1 FR0003 CBHU2652695 +15.0¡C 20' 8.3 REEF #NAME? IMPORT 3060 74.97 0.5 2 20.0 15.0 35.0 15000 2500 19.83 0.94 3.18
L 2203 2 FR1815 CBHU2675509 -15.0¡C 20' 20.9 REEF #NAME? IMPORT 1340 74.97 0.5 2 50.0 -15.0 35.0 6000 2500 8.47 2.59 3.91
L 2205 1 FR0650 MWCU5601329 -25.0¡C 20' 20.4 FZJC #NAME? V EXPORT 2510 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 12.86 9.48 3.77
L 2207 1 FR1656 FBLU6207507 -20.0¡C 20' 18 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.70 5.87 3.71
L 2209 1 FR1135 MSCU5611272 FAN 40' 29.1 FANT V EXPORT 1 135.26 0.5 2 35.0 35.0 10000 2500 2.50
L 2211 1 FR1149 TRIU8282372 +15.0¡C 40' 17.2 CONF #NAME? EXPORT 3350 135.26 0.5 2 20.0 15.0 35.0 15000 2500 24.93 2.13 3.68
L 2301 1 FR0807 GCEU7720400 +15.5¡C 40' 16 REE #NAME? IMPORT 3060 135.26 0.5 2 19.5 15.5 35.0 15000 2500 21.76 1.81 3.65
L 2303 1 FR2121 PONU2976471 -20.0¡C 20' 17 FVG #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.87 5.98 3.71
L 2304 1 FR0214 GCEU3128603 +3.0¡C 20' 23 CEE #NAME? IMPORT 2850 74.97 0.5 2 32.0 3.0 35.0 12000 2500 31.35 3.03 3.56
L 2306 1 SA0530 ANNU5019223 +4.0¡C 20' 21.6 REE #NAME? IMPORT 3060 74.97 0.5 2 31.0 4.0 35.0 12000 2500 32.66 3.06 3.53
L 2306 2 SA0537 GCEU2954323 -20.0¡C 20' 19.8 REEF #NAME? IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 7.28 4.91 3.71
L 2308 1 FR2056 MAEU5667652 -20.0¡C 20' 20 REEF #NAME? IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 7.36 4.96 3.71
L 2308 2 FR2103 CGMU2971008 -20.0¡C 20' 16.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 6.03 4.07 3.71
L 2309 1 SA0524 GCEU2029210 -20.0¡C 20' 17.4 FPT #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.07 6.12 3.71
L 2309 2 SA0528 MWCU5686100 -20.0¡C 20' 16.9 FVG #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.81 5.95 3.71
L 2310 1 FR1957 GESU9084199 -25.0¡C 20' 10.5 FFS #NAME? IMPORT 1900 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 5.01 3.69 3.77
L 2401 1 SU1740 SUDU5202662 +18.0¡C 40' 17 REEF #NAME? IMPORT 3060 135.26 0.5 2 17.0 18.0 35.0 15000 2500 26.74 1.93 3.51
L 2403 1 SA1824 SUDU5118968 -18.0¡C 40' 22 REEF #NAME? IMPORT 1340 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 4.66 2.73 4.72
L 2403 2 SU1737 SUDU5203231 +18.0¡C 40' 17.3 REEF #NAME? IMPORT 3060 135.26 0.5 2 17.0 18.0 35.0 15000 2500 27.21 1.96 3.51
L 2503 1 SA0534 PONU2965482 -20.0¡C 20' 17.1 FVG #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.92 6.02 3.71
L 2505 1 FR2110 CGMU5500402 -23.0¡C 20' 17.5 FFS #NAME? IMPORT 1900 74.97 0.5 2 58.0 -23.0 35.0 3000 2500 8.65 6.16 3.75
L 2506 1 FR2119 MWCU5616674 +4.0¡C 20' 23.7 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 29.28 2.74 3.53
L 2509 1 FR2044 PONU2895873 -20.0¡C 20' 18.5 FMT #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.65 6.51 3.71
L 2510 1 FR1939 MWCU5675281 +4.0¡C 20' 20.6 CEZ #NAME? IMPORT 2500 74.97 0.5 2 31.0 4.0 35.0 12000 2500 25.45 2.38 3.53
L 2510 2 FR2000 PONU2964064 -20.0¡C 20' 16.1 FVG #NAME? IMPORT 1900 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 8.40 5.66 3.71
L 2511 1 TH0543 MSCU7445015 +3.0¡C 40' 29.3 VEGS #NAME? EXPORT 3850 135.26 0.5 2 32.0 3.0 35.0 12000 2500 29.90 5.22 4.28
L 2511 2 TH0532 MSCU7402477 -20.0¡C 40' 31.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 8.46 10.30 4.15
L 2601 1 26-Mar MNLU9722076 -18.0¡C 40' 29.5 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.20 4.81 4.72
L 2601 2 26-Mar GESU9340710 -20.0¡C 40' 29.5 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 7.90 9.61 4.15
L 2603 1 WE1219 GESU9271820 -20.0¡C 40' 25.5 FZPY #NAME? EXPORT 1590 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 6.17 7.51 4.15
L 2603 2 WE1430 CBHU2964712 +13.0¡C 40' 11.4 CHIL #NAME? EXPORT 3640 135.26 0.5 2 22.0 13.0 35.0 15000 2500 16.24 1.54 3.80
L 2605 1 FR1547 MOLU5541765 +15.0¡C 20' 16.7 CONF #NAME? EXPORT 3350 74.97 0.5 2 20.0 15.0 35.0 15000 2500 43.68 2.07 3.18
L 2605 2 FR1548 OOLU3890348 +15.0¡C 20' 10.7 CONF #NAME? EXPORT 3350 74.97 0.5 2 20.0 15.0 35.0 15000 2500 27.99 1.33 3.18
L 2606 1 WE0609 GESU9298246 -20.0¡C 20' 20 FZMT #NAME? EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 9.66 6.52 3.71
L 2606 2 FR1354 OOLU3849684 -21.0¡C 20' 21.7 FZMT #NAME? EXPORT 1760 74.97 0.5 2 56.0 -21.0 35.0 3000 2500 10.29 7.07 3.72
L 2609 1 WE1504 GESU9340428 -18.0¡C 40' 29.6 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.23 4.82 4.72
L 2609 2 TH1736 TRIU8295127 -20.0¡C 40' 30.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 55.0 -20.0 35.0 3000 2500 8.22 10.01 4.15


L 2611 1 27-Mar GESU9318810 -18.0¡C 40' 30 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 8.34 4.89 4.72
L 2611 2 WE0611 GESU9342117 -18.0¡C 40' 28.7 FZMT #NAME? EXPORT 1760 135.26 0.5 2 53.0 -18.0 35.0 6000 2500 7.98 4.68 4.72
TE 0128 1 FR0922 HLXU3737483 -25.0¡C 20' 21.2 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 7.14 5.26 3.77
TE 0128 2 FR0921 HLXU3729600 -25.0¡C 20' 21.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 7.10 5.24 3.77
TE 0228 1 FR0926 FBLU6207404 -25.0¡C 20' 21.3 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 7.17 5.29 3.77
TE 0228 2 FR0930 HLXU3716412 -25.0¡C 20' 21.5 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 7.24 5.34 3.77
TE 0328 1 FR0924 CRXU5269351 -25.0¡C 20' 21.3 REEF #NAME? IMPORT 1340 74.97 0.5 2 60.0 -25.0 35.0 3000 2500 7.17 5.29 3.77
TW 0108 1 TH0527 SUDU1040460 -18.0¡C 20' 22.9 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.75 2.84 3.97
TW 0108 2 TH0534 SUDU1072956 -18.0¡C 20' 22.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.44 2.74 3.97
TW 0109 1 WE1830 SUDU1036141 -18.0¡C 20' 21.2 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.10 2.63 3.97
TW 0109 2 TH0522 SUDU1061611 -18.0¡C 20' 22.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.56 2.78 3.97
TW 0110 1 WE1801 SUDU1101210 -18.0¡C 20' 20.6 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.87 2.56 3.97
TW 0110 2 TH0521 SUDU1070444 -18.0¡C 20' 22.2 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.48 2.75 3.97
TW 0111 1 TH0525 SUDU1001037 -18.0¡C 20' 23 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.78 2.85 3.97
TW 0111 2 WE1803 SUDU1002157 -18.0¡C 20' 19.7 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.52 2.44 3.97
TW 0112 1 WE1833 SUDU1060913 -18.0¡C 20' 21.3 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.14 2.64 3.97
TW 0112 2 WE1758 SUDU1081623 -18.0¡C 20' 20.7 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 7.91 2.57 3.97
TW 0113 1 WE1750 CRXU5271111 -18.0¡C 20' 21.2 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.10 2.63 3.97
TW 0208 2 TH0529 SUDU1048008 -18.0¡C 20' 23 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.78 2.85 3.97
TW 0209 1 WE1829 SUDU1045056 -18.0¡C 20' 21.3 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.14 2.64 3.97
TW 0209 2 WE1811 SUDU1010738 -18.0¡C 20' 21.3 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.14 2.64 3.97
TW 0210 1 WE1803 SUDU1072365 -18.0¡C 20' 21 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.02 2.61 3.97
TW 0210 2 WE1837 CRLU3157210 -18.0¡C 20' 21.2 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.10 2.63 3.97
TW 0211 1 TH0519 SUDU1051260 -18.0¡C 20' 22.1 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.44 2.74 3.97
TW 0211 2 WE1811 SUDU1003908 -18.0¡C 20' 21 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.02 2.61 3.97
TW 0212 1 WE2249 CRXU5269480 -18.0¡C 20' 21.4 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.17 2.66 3.97
TW 0212 2 WE2246 SUDU1031330 -18.0¡C 20' 21.5 REEF #NAME? IMPORT 1340 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.21 2.67 3.97
V 0101 1 FR2134 MWCU5742760 +12.0¡C 20' 13 CHC #NAME? IMPORT 3640 74.97 0.5 2 23.0 12.0 35.0 15000 2500 31.90 1.75 3.28
V 0201 1 FR1940 PCIU5797598 -18.0¡C 20' 21.4 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 10.74 3.49 3.97
V 0301 1 FR0106 MAEU5661079 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.87 7.33 3.71
V 0401 1 TH2240 PONU2870221 -20.0¡C 20' 22.5 FZMT #NAME? V EXPORT 1760 74.97 0.5 2 55.0 -20.0 35.0 3000 2500 10.87 7.33 3.71
V 0501 1 TH1353 TRLU1044459 -18.0¡C 20' 16 FZMT #NAME? EXPORT 1760 74.97 0.5 2 53.0 -18.0 35.0 6000 2500 8.03 2.61 3.97
V 0601 1 WE1108 CBHU2933183 +13.0¡C 40' 10.9 CHIL #NAME? EXPORT 3640 135.26 0.5 2 22.0 13.0 35.0 15000 2500 15.53 1.47 3.80

4/02/2007 7:08:09 AM Max 4.72 kW


Min 2.50 kW
(i)
Notes Value of CP is obtained from Table 5.3 Average 3.91 kW
(ii) and (iii)
Values are from reefer's manufacturer data


APPENDIX E

Data Volume

183
REFERENCES

[1] Carrier, “Specification of Refrigerated Container ThinLine series”, available


online at http://www.container.carrier.com , access on May 2012.

[2] CASA, “Manual of Standards Part 139”, Aerodromes, Australian


Government Civil Aviation Safety Authority version 1.10, Section 9.21 pp.
142-143, May 2012.

[3] Crompton, “DIN Integra 500 Series”, Technical Specification


(http://www.cromptonwesterncanada.com) page 13, access March 2012.

[4] German Marine Insurers, “Container Handbook”, available online at


http://www.containerhandbuch.de/chb_e/wild/index.html, access April
2012.

[5] Daikin Industries, “Specification of Refrigerated Container Zestia series”,


available online at www.daikinreefer.com/zestia/specifications-options/,
access on May 2012.

[6] ElectroTechnik, “CableCALC Pro 2012+, Max Demand”, www.elek.com.au


access 15/05/2012.

[7] Kim Le, “Analysing electric yard cranes with simulation”, Port Technology
International Journey, Edition 53, pp. 60-61, Spring 2012.

[8] Maersk, “Specification of Refrigerated Container Star Cool brochures”,


available at http://www.starcool.dk/media/71592/star cool (lowres).pdf,
access June 2012.

[9] Mitsubishi Heavy Industries, “Marine Transport Refrigeration Units”,


available at http://mhins.mhi.co.jp/english/transport/marine-ref02.html ,
access May 2012.

[10] P.Barrade and Prof. A Rufer, “Voltage Drop compensation for weak
distribution Systems: simulation for study and implementation”,
http://leiwww.epfl.ch, pp1-13, access 10/03/2012.

[11] Siemens, “9300 Series Power Meter”, User’s Guide


(http://www.sea.siemens.com) access March 2012.

[12] Thermo King, “Specification of Refrigerated Container Magnum series”,


available online at www.thermoking.com/products/australia/container/,
access on May 2012.

[13] ATM Global Logistics, “Container Dimension and Payload”, available


online at

184
www.atmgloballogistics.com/docsjpg/Documents/containerinfo.pdf, access
on March 2012.

[14] Wikipedia, “Container Ship”, wikipedia web site Wikipedia


http://en.wikipedia.org/wiki/Container_ship#Size_categories, access
12/3/2012.

[15] ABB group, “Guide to variable speed drives’, Technical Guide Book No. 4,
ABB group document No. 3AFE61389211 rev C, 12 May 2011, pp 27-39,
2011.

[16] Andrew Burke, “Ultracapacitor Technology for Utility Application”, 2011


Electrical Energy Storage Application and Technologies conference, San
Diego USA Oct 2011, pp 197-198, 2011.

[17] Charles Haine, “How terminal operators deal with carbon management”,
GreenPort on line Magazine, www.greenport.com published 18/03/2011.

[18] G. Nordman, “ASC Power and Energy”, ABB presentation to DPW in


Brisbane, 2011.

[19] John Bensalhia, “Lighting the way”, GreenPort on line Magazine,


www.greenport.com published 05/01/2011.

[20] Nedyakov, T., T. Andreeva – Nedyalkova, “Trends in the container shipping


and need of a new generation container terminals and container vessels”,
MTM International Virtual Journal Issue 3, pp. 20-23, 2011.

[21] Rawlinsons, “Electrical Services – Maximum Demand”, Australian


Construction Handbook Edition 29, Rawlinsons Publishing, pp. 512, 2011.

[22] Tororin Nedyalkov, Teodora A. Nedyakova, “Trend in the container


shipping and need of a new generation container terminals and container
vessels”, International Virtual Journal issue 3, 2011, pp. 20-23, 2011.

[23] Yan Liu, Takakuwa S., “Modeling the materials handling in a container
terminal using electronic real-time tracking data”, Proceedings of the 2011
Winter Simulation Conference, pp. 1591-1598, 2011.

[24] Dwight MacCurdy, “Static Energy Storage System Demonstration


Program”, Public Interest Energy Research (PIER) Program – Final Project
Report for California Energy Commission, CEC-500-2012-068, 31 pages,
2010.

[25] Eelco van Asperen, Bram B., Rommert Dekker, “Evaluating container
stacking rules using simulation”, Proceedings of the 2010 Winter Simulation
Conference, pp.1924-1933, 2010.

[26] Fredrik Johanson, “Efficient use of energy in container cranes”, Port


Technology International Journey, Edition 48, pp. 51-54, Winter 2010.

185
[27] Galuszka A., Skrzypczyk K., Bereska D., Pacholczyk M., “Re-Handling
Operations in Small Container Terminal Operated by Reach Stackers”,
World Academy of Science, Engineering and Technology Vol. 70, pp. 674-
677, 2010.

[28] Gottwald Port Technology GmbH, “Driving innovation: high handling


efficiency, low energy use”, Port Technology International Journey, Edition
47, pp. 78 – 80, Summer 2010

[29] Jim Arseneaux, “Development of a 100 kWh/100 kW Flywheel Energy


Storage Module”, US Department of Energy, 2010 Energy Storage Systems
Project Update Conference, Poster, 2010.

[30] Jim Arseneaux, “Beacon Power 20MW Flywheel Frequency Regulation


Plant”, Presentation at 2010 Update Conference in Washington DC USA,
US Department of Energy – Energy Storage System Program, 2010.

[31] L.A. Baranov, Yu. A. Brodskii, V.A. Grechishnikov, A.I. Podaruev, V.N.
Pipynin, M.V. Shevlyugin, “Estimation of efficiency of stationary capacitor
storage in subway based on experimental measurements of the operation of
traction power-supply system”, Russian Electrical Engineering Vol. 81(1),
pp. 42-44, 2010.

[32] Lee, Y., & Lee, Y-J. (2010). A heuristic for retrieving containers from a
yard. Computers & Operations Research, 37(6), pp. 1139-1147, 2010.

[33] Nguyen, V.D. & Kim, K.H., “Minimizing empty trips of yard trucks in
container terminals by dual cycle operations”, Industrial Engineering and
Management Systems, 9(1), pp. 28-40, 2010.

[34] Rawlinsons, “Australian Construction Handbook”, Rawlhouse Publishing


edition 28, 2010.

[35] Wong, A., & Kozan, E., “Optimization of container process at seaport
terminals”, Journal of the Operational Research Society, 61(4), pp. 658-665,
2010.

[36] Bradford Roberts, “Capturing Grid Power”, IEEE power and energy
magazine , July/August 2009 issue pp. 33-41, 2009.

[37] Caserta, M., Schwarze, S., and Voß, S., “A new binary description of the
blocks relocation problem and benefits in a look ahead heuristic”,
Evolutionary Computation in Combinatorial Optimization: Lecture Notes in
Computer Science, 2009.

[38] Chet Lyons, “A Smart Grid Approach To Regulation And Ramping”, Renew
Grid Magazine August 2009 Supplement , 2009.

186
[39] Kotz, Freiichel, Towsend, “Appendix D, table 1 of Chemistry and Chemical
Reactivity Edition 7”, Thomson Learning Academic Resource, pp. A13,
2009.

[40] Kuldeep Sahay; Bharti Dwivedi; “Design and Analysis of Supercapacitors


Energy Storage System for Energy Stabilization of Distribution Network”,
Electrical Power Quality and Utilisation Journal Vol.XV, No.1, 2009 pp.
49-56, 2009.

[41] Mak K.L., Zhang L., “Simultaneous Scheduling of Import and Export
Containers Handling in Container Terminal”, World Congress on
Engineering Vol. 1, pp. 604-609, 2009.

[42] Markus Christerson, “Modern interface between the TOS and the Crane
Control System”, Port Technology International Edition 41, p 54, 2009.

[43] Nguyen, V.D. & Kim, K.H., “A dispatching method for automated lifting
vehicles in automated port container terminals”, Computers & Industrial
Engineering, 56(3), pp. 1002-1020, 2009.

[44] R. Reid, B. Roberts, T. Tran, “Management of Dynamic Power Demands for


Large Container Port Loads”, presented at Terminal Operators Conference
2009, 28 slices, 2009.

[45] Springer-Verlag Berlin Heidelberg, 37-48 Caserta, M., Voß, S., and
Sniedovich, M., “Applying the corridor method to a blocks relocation
problem”, OR Spectrum. DOI 10.1007/s00291-009-0176-5 (online
available), 2009.

[46] Caserta, M., Schwarze, S., and Voß, S. , “A mathematical formulation for
the blocks relocation problem”, Working Paper, Institute of Information
Systems, University of Hamburg, 2008.

[47] C. Vartanian, “The coming convergence renewables, smart grid and


storage”, IEEE Energy 2030 Conference, November 2008.

[48] D. Rastler, “New Demand for energy storage”, Electric Perspect Vol. 33 No.
5, pp. 30-47, 2008.

[49] D. Hetherington, G. White, “Understanding power supply from a railway


operating company’s perspective”, 3rd IET Professional Development
Course on Railway Electrification Infrastructure and Systems, pp. 25-33,
2008.

[50] Ghislain Lorthiois, “Container Shipping: impact of mega-containerships on


Ports in Europe and the Med”, Marseille Maritime 2008 – The
Mediterranean Basin Shipping Future Conference, 2008.

[51] Henning P.H., Fuchs H.D., Le Roux A. D., Mouton H.T., “A 1.5MW seven-
cell series-stacked converter as (NEUROSCIENCE) an active power filter

187
and regeneration converter for a DC traction substation”, IEEE Transaction
on Power Electronics abstracts, pp 2230, September 2008.

[52] M.V. Shevlyugin, “Power-saving circuits of railway traction power supply


based on superconducting inductive energy storage”, Russian Electrical
Engineering Vo. 79(7), pp. 377-381, 2008.

[53] Safe work Victoria, “Working safely with containers”, A Handbook for
Workplaces, 2008.

[54] Stahlbock, D., and Vob, S., “Operations research at container terminal: a
literature update”, OR Spectrum, 30(1), pp. 1-52, 2008.

[55] Srithorn, P.; Sumner, M.; Liangzhong Yao; Parashar, R.,“The Control of a
STATCOM with Supercapacitor Energy Storage for Improved Power
Quality”, Smart Grids for Distribution, 2008 International Educational
Technology Conference, pp. 1-4, 2008.

[56] Srithorn, P.; Sumner, M.; Liangzhong Yao; Parashar, R.; “Power System
Stabilization Using STATCOM with Supercapacitors”, Industry
Applications Society Annual Meeting, 2008, pp.1–8, 2008.

[57] Thouraya Benna, Manfred gronalt, “Generic Simulation for Rail-Road


Container Terminals”, Proceedings of the 2008 Winter Simulation
Conference, pp. 2656-2660, 2008.

[58] T. Tran, S. Nahavandi, R. Reid, “Power Demnad and Energy Usage of


Container Crane – Comparison between AC and DC Drives”, Proceedings
of the 6th International Conference on Power Quality and Supply Reliability
(PQ2008), pp. 37-40, 2008.

[59] T. Tran, S. Nahavandi, R. Reid, “Design of Electrical Infrastructure at


Container Terminal and Net Metering”, 43rd International Universities
Power Engineering Conference (UPEC 2008), 4 pages, 2008.

[60] Xiao Li; Changsheng Hu; Changjin Liu; Dehong Xu; “Modeling and control
of aggregated Supercapacitor Energy Storage system for wind power
generation”, 2008 Industrial Electronics Conference, pp.3370- 3375, 2008.

[61] Abbey, C.; Joos, G., “Supercapacitor Energy Storage for Wind Energy
Applications”, IEEE Transactions on Industry Applications, Volume
43,Issue 3, May-June 2007, pp. 769–776, 2007.

[62] AS/NZS, “Electrical Installations”, Australian/New Zealand Standard


3000:2007, pp. 60-61, 364-365, 2007

[63] B. Ricardo, V. M. Joeri, T. Xavier, L. Bernard, “Super Capacitor


Applications in Public Transportation”, EET-2007 European Ele-Drive
Conference, May 30-June 1, 2007.

188
[64] Schneider Electric, “PowerLogic SMS 4.0 System Manager Software”,
Schneider Electric Document No. 63220-060-228C1, Aug 2004.

[65] ESCAP, “Regional shipping and port development strategies (container


traffic forecast): Economic and Social Commission for Asia and the
Pacific”, United Nations, 2007.

[66] Food Science, “Temperature rises in frozen cartons when containers are off
power”, Meat Technology information sheet, 3 pages, June 2007.

[67] Klementov, “Reliability Investigation of Kilofarad-Size Capacitor Cells”,


Proceeding of 2007 Advanced Capacitor World Summit, July 23-25 2007.

[68] Kozan, E. & Casey, B., “Optimisation of Container Transfers at Multimodal


Terminals”, Journal of the Operational Research Society, 53, pp. 1-11,
2007.

[69] Schneider Electronics, “PowerLogic ION7300 Series – Power & Energy


Meter”, User Guide, Jan 2007.

[70] ZPMC, “Power Calculation for EPA”, Theoretical Power Calculation for
Special quay crane supplied to Esperance Port Authority, 2007.

[71] B. K. Lee, K.H. Kim, “Performance evaluation of yard cranes in container


terminals”, Proceedings of the 2nd International Intelligent Logistics Systems
Conference 2006, pp. 18.1-18.17, 2006.

[72] Bobby Maher, “Ultracapacitors Provide Cost and Energy Savings for Public
Transportation Application”, Battery Power On Line
(www.BatteryPowerOnline.com) Vol. 10 issue 6, 4 pages,
Noverber/December 2006.

[73] Briskorn, D., Drexl, A., & Hartmann, S., “Inventory-based dispatching of
automated guided vehicles on container terminals”, OR Spectrum, 28(4), pp.
611-630, 2006.

[74] Casey, B. and Kozan, E., “A Container Storage Handling Model for High
Tech Automated Multimodal Terminals”, The Second International
Intelligent Logistics Systems Conference 2006, Australia. pp 10.1-10.29,
2006.

[75] Chong Han; Huang, A.Q.; Ding Li; Mamath, H.; Ingram, M.; Atcitty, S.,
“Modeling and design of a transmission Ultracapacitor (TUCAP) integrating
modular voltage source converter with Ultracapacitor energy storage”, 2006
Applied Power Electronics Conference and Exposition (APEC 2006), pp.
1104-1110, 2006.

[76] Degobert, Ph.; Kreuawan, S.; Guillaud, X, “Use of supercapacitors to reduce


the fast fluctuations of power of a hybrid system composed of photovoltaic
and micro turbine”, 2006 International Symposium on Power Electronics,

189
Electrical Drives, Automation and Motion (SPEEDDAM), 2006 , pp. 1223–
1227, 2006.

[77] Grunow, M., Gunther, H.O., & Lehmann, M., “Strategies for dispatching
AGVs at automated seaport container terminals”, OR Spectrum, 28(4), pp.
587-610, 2006.

[78] J. R. Miller, Ilya Goltser, Susannah Butler, “Electrochemical Capacitor Life


Predictions Using Accelerated Test Methods”, Proceedings of the 42nd
Power Sources Conference, Philadelphia, PA, pp. 581-584, June 12-14,
2006

[79] J.R. Miller, A. Klementov, and S. Butler, “Electrochemical Capacitor


Reliability In Heavy Hybrid Vehicles”, paper presented at 16th
International Seminar on Double Layer Capacitors and Hybrid Energy
Storage Devices, December 4-6, 2006

[80] Kim, K.H. & Bae, J.W., “A look-ahead dispatching method for automated
guided vehicles in automated port container terminals”, Transportation
Science, 38(2), pp. 224-234, 2006.

[81] Kim, K. H., & Hong, G-P., “A heuristic rule for relocating blocks”,
Computers & Operations Research, 33(4), pp. 940-954, 2006.

[82] Kozan, E., & Preston, P., “Mathematical modelling of container transfers
and storage locations at seaport terminals”, OR Spectrum, 28(4). Pp. 519-
537, 2006.

[83] Kozan, E., Casey B., “A Container Storage Handling Model for High Tech
Automated Multimodal Terminals”, The Second International Intelligent
Logistics System Conference 2006, Australia. ISBN: 0-9596291-9-X, pp.
10.1-10.29, 2006.

[84] Levinson, M., “The Box”, Princeton University Press., 2006.

[85] M. Steiner, J. Scholten, M. Klohr, Bombardier Transportation “Energy


Storage on Board of Railway Vehicles”, European Conference on Power
Electronics and Application, pp. 1-10, 2006.

[86] Ng. W. C., “Quay crane scheduling in container terminals”, Engineering


Optimization, Vol. 38 Issue 6, pp. 723-737, September 2006.

[87] Ottijes J. A., Veeke H. P. M., Duinkerken M. B., Rijsenbrij J. C., Lodewijks
G, “Simulation of a multiterminal System for Container handling”, OR
Spectrum Vol. 28 issue 4, pp. 447-468, October 2006.

[88] Rong Lu; Jiancheng Zhang, “Active-reactive power compensation based on


SCES in distribution system”, Power System Technology International
Conference, pp. 1-6, 2006.

190
[89] Shushei Kato, Frank Delattre, “Flywheel starting to take off”, Electricity
Storage Association News letter, Jan 2006.

[90] Soriquera F., Robuste F., Juanola R., Lope-Pita A., “Optimization of
handling equipment in the container terminal of the port of Barcelona,
Spain”, Transportation Research Record: Journey of the Transportation
Research Board, issue 1963, pp. 44-51, 2006.

[91] T. D. Hund, D. Johnson, N. Clark and J. Romero, “Abuse Testing Results


From Symmetric Carbon/Carbon Acetonitrile Electrolyte Supercapacitors
Using Over Voltage and Over Temperature Environments”, paper presented
at The 16th International Seminar on Double Layer Capacitors and Hybrid
Energy Storage Devices 12/06, 17 pages, 2006.

[92] T. Hund, N. Clark, D. Johnson, W. Baca, “Testing and Evaluation of Energy


Storage Devices”, DOE Energy Storage Systems Research Program Annual
Peer Review, November 2-3, 2006.

[93] TM GE Automation Systems, “AC versus DC in crane modernisation”, Port


Technology International Edition 30, pp. 1-3, 2006.

[94] Yao, Y.Y.; Zhang, D.L.; Xu, D.G., “A Study of Supercapacitors Parameters
and Characteristics”, 2006 Power System Technology International
Conference , pp.1 – 4, 2006.

[95] YICT, “QC Energy Consumption Study”, Yantian International Container


Terminal Internal Study, 2006.

[96] Yonghua Cheng, Joeri Van Mierlo,Peter Van Den Bossche and Philippe
Lataire, “Using Super Capacitor Based Energy Storage to Improve Power
Quality in Distributed Power Generation”, 2006 European Power
Electronics and Motion Control Conference, pp.537-543, 2006.

[97] Zhongdong Yin; Minxiao Han; Yunlong Du; Zheran Zhang, “A Practical
Approach for Ride Through of Super Capacitor Energy Storage Based ASD
System”, Power and Energy Society Transmission and Distribution
Conference, pp. 744–746, 2006.

[98] ZPMC, “Power Calculation for Post PANAMAX quay crane”, Theoretical
Power Calculation for quay crane supplied to Patrick Stevedores, 2006.

[99] Customer information, “Understanding Electric Demand”, USA National


Grid, Document No. NY0620 Dec 2005, pp 2, 2005.

[100] Dandan Zhang; Man Luo; Jin Li; Junjia He; “Surveying into some aspects
of internal resistance of super capacitor,” Electrical Insulation and
Dielectric Phenomena, 2005, pp. 637 – 640, 2005.

[101] G.E. Canterella, S. de Luca, A. Carteni, “A Simulation model for a container


terminal”, European Transport Conference 2005, 17 pages, 2005.

191
[102] I.El-Samahy and Ehab El-Saadny, “The Effect of DG on Power Quality in a
Deregulated Environment”, Power Engineering Society General Meeting
2005, pp. 1-8, 2005.

[103] Jiang Zhang, “Research on Super Capacitor Energy Storage System for
Power Network”, IEEE PEDS 2005 Conference, pp.1366-1369, 2005.

[104] Ji-Yan Zou; Li Zhang; Jin-Yan Song; “Development of the 40 V hybrid


supercapacitor unit”, Magnetic, IEEE Transactions on Volume 41, Issue 1,
Part 2, Jan. 2005, pp.294-298, 2005.

[105] Johan van Rensburg, Yi He, “A computer simulation model of container


movement by sea”, Proceeding of the 2005 Winter Simulation Conference,
pp. 1559-1566, 2005.

[106] Khatri P.R.; Jape V.S.; Lokhande N.M; Motling B.S., “Improving Power
Quality by Distributed Generation”, Power Engineering Conference 2005,
(IPEC 2005. The 7th International), pp. 675 - 678 Vol. 2, 2005

[107] M.A. Rao, Syed S.H. Rizvu, Ashin K.Datta Taylor and Francis Group,
“Engineering Properties of Foods 3rd edition”, Francis Group, pp. 178, 201,
2005.

[108] Ng, W. C., “Crane scheduling in container yards with inter-crane


interference”, European Journal of Operational Research, 164(1), pp. 64-
78, 2005.

[109] Richard Hunwick, “The economics of electricity storage”, paper presented


at Energy Storage Symposium 1/11/2005 organised by Australian institute of
Energy Sydney branch, 2005.

[110] Robert Reid, “Design, Installation and Electrical Management of Container


Terminals with Large Electrical Demand”, paper presented at 2005
Terminal Operators Conference (TOC), 23 pages, 2005.

[111] Yvo A. Saanen, M. V. Valkengoed, “Comparison of three Automated


Stacking Alternatives by means of Simulation”, Proceeding of the 2005
Winter Simulation Conference, pp. 1567-1576, 2005.

[112] ABS Energy Research, “Electrical Equipment Demand Forecasts”, 2004


Market Research Report Vol. 3, pp. 1-74, 2004.

[113] Christian Godbersen, “Energy storage system based on double layer


capacitor technology - the gateway to high efficient improvement of mass
transit power supply”, Paper presented at 2nd UIC Railway Energy Efficiency
Conference 2004, pp. 1-24, 2004.

[114] EDMI, “MK6 Genius Energy Meter”, User Manual, 2004.

192
[115] Grunow, M., Gunther, H. O., & Lehmann, M., “Dispatching multi-load
AGVs in highly automated seaport container terminals”, OR Spectrum,
26(2), pp. 211-235, 2004.

[116] Guan, Y. P., & Cheung, R. K., “The berth allocation problem: models and
solution methods”, OR Spectrum, 26(1), pp. 75-92, 2004.

[117] J. R. Miller, Susannah M. Butler, “Capacitor Energy Storage For Stationary-


Power Applications”, Final paper for 2004 Battcon conference, 8 pages,
2004.

[118] K.D. Pham, R. Thomas, X. Ramirez, “Traction Power Supply for the
Portland Interstate MAX Light Rail Extension”, Transportation Research
Circular E-C058: 9th National Light Rail Transit Conference, pp. 669-677,
2004.

[119] Kim, K. H., Kang, J. S., & Ryu, K. R., “A beam search algorithm for the
load sequencing of outbound containers in port container terminals”, OR
Spectrum, 26(1), pp. 93-116, 2004.

[120] Kim, K. H., & Park, Y. M., “A crane scheduling method for port container
terminals”, European Journal of Operational Research, 156(3), pp. 752-
768, 2004.

[121] McGraw-Hill, “Electrical Power Systems Quality”, Digital Engineering


Library of McGraw Hill www.digitalengineeringlibrary.com, pp. 389-392,
2004.

[122] N. Clark, T. Hund, G. Nagasubramanian, W. Baca, “Supercapacitor Module


Testing For Energy Storage Devices”, 14th international Seminar on Double
Layer Capacitors and Hybrid Energy Storage Devices, 12/6/2004.

[123] Rufer Alfred; David Hotellier; and Barrade Philippe; “A Supercapacitor-


Based Energy Storage Substation for Voltage Compensation In Weak
transportation Networks”, IEEE transactions on Power Delivery, pp. 629-
636, April 2004.

[124] Steenken, D., Voss, S., & Stahlbock, R., “Container terminal operation and
operations research – a classification and literature review”, OR Spectrum,
26(1), pp. 3-49, 2004.

>@ Steenken, D., S. Voss and R. Stahlbock, “Container terminal operation and
operations research - a classification and literature review”, OR Spectrum,
26 (1), pp. 3–49, 2004.

[126] TM GE Automation Systems, “Crane Factor+ - Active Power Factor


Regulation”, TM GE Automation Systems technical published document, 11
pages, 2004.

193
[127] Bish E. k., “A multiple-crane-constrained scheduling peoblem in a container
terminal”, European Journal of Operation Research issue 144, pp. 82-107,
2003.

[128] Gerhard Fischer, Laurens Franken, “Crane Life Cycle Costs”, Port
Technology International Edition 20, pp. 29-31, 2003.

[129] Imai, A., Nishimura, E., & Papadimitriou, S., “Berth allocation with service
priority”, Transportation Research Part B-Methodological, 37(5), pp. 437-
457, 2003.

[130] Kim, K. H., Lee, K. M., & Hwang, H., “Sequencing delivery and receiving
operations for yard cranes in port container terminals”, International
Journal of Production Economics, 84(3), pp. 283-292, 2003.

[131] Kim, K. H., & Moon, K. C., “Berth scheduling by simulated annealing.
Transportation”, Research Part B-Methodological, 37(6), pp. 541-560,
2003.

[132] Kim, K. H., & Park, K. T., “A note on a dynamic space-allocation method
for outbound containers”, European Journal of Operational Research,
148(1), pp. 92-101, 2003.

[133] P.Barrade, “Energy storage and applications with Super capacitor”,


presented at ANAE (Associazione Nazionale Azionamenti Elettrici), 2003.

[134] T. Shinoda, N. Fukuchi, “Conceptual design and feasibility study of the


floating container terminal with high performance”, paper presented at 8th
International Marine Design Conference, 2003.

[135] Vis, I. F. A., & de Koster, R. “Transshipment of containers at a container


terminal: An overview”, European Journal of Operational Research,
147(1), pp. 1-16, 2003.

[136] ZPMC, “Power Calculation for Post PANAMAX quay crane”, Theoretical
Power Calculation for quay cranes supplied to P&O Stevedores, 2003.

[137] A. Dielinski, K. Amborski, P. Kowslcuk, J. Sukienmik, A. Pawlowski,


“Simulation of operation of a medium sized Seaport. Case study: port of
Gdansk”, 14th European Simulation Symposium and Exhibition, 6 pages,
2002.

[138] Chung, R. K., Li, C. L., & Lin, W. Q., “Interblock crane deployment in
container terminals”, Transportation Science, 36(1), pp. 79-93, 2002.

[139] Kim, K. H., & Kim, H. B., “The optimal sizing of the storage space and
handling facilities for import containers”, Transportation Research Part B-
Methodological, 36(9), pp. 821-835, 2002.

194
[140] Liu, C.-I.; Jula, H.; Ioannou, P.A., “Design, simulation and evaluation of
automated container terminal”, IEEE Transactions on Intelligent
Transportation Systems, Vol. 3, Issue 1, pp. 12-26, 2002.

[141] Nam K.C., Kwak K.S., Yu M.s., “Simulation study of Container Terminal
performance”, Journal of Waterway, Port, Coastal and Ocean Engineering
Vol. 128(3), pp. 126-132, May 2002.

[142] Notteboom Theo E., “Consolidation and contestability in the European


container handling industry”, Maritime Policy and Management Vol. 29
issue 3, pp. 257-269, September 2002.

[143] Palma, L.; Enjeti, P.; Aeloiza, E, “An approach to provide ride-through for
ASD systems with supercapacitors”, Power Electronics Congress 2002, pp.
182 – 187, 2002.

[144] Peter Fraser, “Distributed generation in liberalized electricity Markets”,


International Energy Agency, Paris 2002.

[145] Sels, T.; Dragu, C.; Van Craenenbroeck, T.; Belmans, R, “Overview of new
energy storage systems for an improved power quality and load managing
on distribution level”, CIRED. 16th International Conference and
Exhibition, pp.18-21, 2001.

[146] Singh R. P., D. R. Heldman, “Specific Heat of Food: Introduction to Food


Engineering Four Edition”, Academic Press London, Table A.2.1, 2001.

[147] SP Sgouridis, DC Angelides, “Simulation-based analysis of a port container


terminal”, paper presented at 12th International Offshore and Polar
Conference, 26-31 May 2002.

[148] ABB group, “DC or AC drives? A guide for users of variable speed drives
(VSDs)”, Technical Guide, ABB group document No. 3ADW 000 059
R0201 rev B, Feb 2001.

[149] Bish, E. K., Leong, T. Y., Li, C. L., Ng, J. W. C., & Simchi-Levi, D.,
“Analysis of a new vehicle scheduling and location problem. Naval
Research Logistics, 48(5), pp. 363-385, 2001.

[150] David Roche, “Metering of embedded generators in Australia”, Coelacanth


Consulting prepared for the Australian Greenhouse Office, 41 pages,
October 2001.

[151] Dr. Itsuro Watanabe, “Container Terminal Planning – A Theoretical


Approach”, World Cargo News Publishing, 2001.

[152] Imai, A., Nishimura, E., & Papadimitriou, S., “The dynamic berth allocation
problem for a container port”, Transportation Research Part B-
Methodological, 35(4), pp. 401-417, 2001.

195
[153] Legato, P., & Mazza, R. M., “Berth planning and resources optimisation at a
container terminal via discrete event simulation”, European Journal of
Operational Research, 133(3), pp. 537-547, 2001.

[154] Nishimura, E., Imai, A., & Papadimitriou, S., “Berth allocation planning in
the public berth system by genetic algorithms”, European Journal of
Operational Research, 131(2), pp. 282-292, 2001.

[155] SAIIR, “Small Generator Connections: Technical and Financial Issues”,


South Australia Independent Industry Regulator information paper No.4, 9
pages, February 2001.

[156] Schlumberger Sema, “Quantum Q1000 Multifunction Meter”, Technical


Reference Guide, 2001.

[157] Avriel M., Penn M., Shpirer N., “Conatiner ship stowage planning:
Complexity and connection to the coloring of circle graphs”, Discrete
Applied Mathematics Issue 103, pp. 271-279, 2000.

[158] E.D. Spooner, “A new Australian Standard for small grid-connected


renewable generation systems connected via inverters”, Australian
Corporation Research Centre for Renewable Energy, 6 pages, 2000.

[159] J. Thomas Sholes, James Heron, “Power Quality Part 1”, Port Technology
International Edition , pp. 71-76, 2000.

[160] Kim, K. H., Park, Y. M., & Ryu, K. R., “Deriving decision rules to locate
export containers in container yards”, European Journal of Operational
Research, 124(1), pp. 89-101, 2000.

[161] Massoud Amin, “Modeling and Control of Electric Power Systems and
Markets”, IEEE Control Systems Magazine Aug 2000, pp. 20-24, 2000.

[162] Newman, A. M., & Yano, C. A., “Scheduling direct and indirect trains and
containers in an intermodal setting”, Transportation Science, 34(3), pp. 256-
270, 2000.

[163] Philip P. Barker and R.W. de Mello. “Determining the impact of distributed
generation on power systems. I. Radial distribution systems,” IEEE Power
Engineering Society Summer Meeting, Vol. 3, pp.1645-1656, 2000.

[164] Yang C.H., Kim Y.H., Choi S.H., Bae J.W, Lee J.E, “A Study on the
System Design and Operations of the Automated Container terminal”,
Published by Korea Maritime Institute, 2000.

[165] Averill M. Law, Michael G. McComas, “Simulation of manufacturing


Systems”, Proceeding of the 1999 Winter Simulation Conference, pp. 56-59,
1999.

196
[166] Charles R. Standridge, “A tutorial on simulation in health care: applications
and issues”, Proceeding of the 1999 Winter Simulation Conference, pp. 49-
55, 1999.

[167] Chen T., “Yard operations in the container terminal – a study in the un-
productive moves”, Maritime Policy and Management, 26(1), pp. 27-38,
1999.

[168] Deborah A. Sadowski, Mark R. Grabau, “Tips for successful practice of


simulation”, Proceeding of the 1999 Winter Simulation Conference, pp. 60-
66, 1999.

[169] Farhad Azadivar, “Simulation Optimization Methodologies”, Proceeding of


the 1999 Winter Simulation Conference, pp. 93-100, 1999.

[170] Gerhard L. Fischer, “Comparison of DC and AC Container Crane Drive


Systems”, 1999 IEEE International Conference on Power Electronics and
Drive Systems (PEDS 99), pp. 297-302, 1999.

[171] Jerry Banks, “Introduction to simulation”, Proceeding of the 1999 Winter


Simulation Conference, pp. 7-13, 1999.

[172] Kim, K. H., & Kim, H. B., “Segregating space allocation models for
container inventories in port container terminals”, International Journal of
Production Economics, 59(1-3), pp. 415-423. 1999.

[173] Kim, K. Y., & Kim, K. H., “A routing algorithm for a single straddle carrier
to load export containers onto a containership”, International Journal of
Production Economics, 59(1-3), pp. 425-433, 1999.

[174] Kim, K. H., & Kim, K. Y., “An optimal routing algorithm for a transfer
crane in port container terminals”, Transportation Science, 33(1), pp. 17-33,
1999.

[175] Kim, K. H., & Kim, K. Y., “Routing straddle carriers for the loading
operation of containers using a beam search algorithm”, Computers &
Industrial Engineering, 36(1), pp. 109-136, 1999.

[176] Kozan, E., & Preston, P., “Genetic algorithms to schedule container
transfers at multimodal terminals”, International Transactions in
Operational Research, 6, pp. 311-329, 1999.

[177] Lawrence Leemis, “Simulation input Modeling”, Proceeding of the 1999


Winter Simulation Conference, pp. 14-23, 1999.

[178] Robert G. Sargent, “Validation and Verification of simulation Models”,


Proceeding of the 1999 Winter Simulation Conference, pp. 39-48, 1999.

[179] Susan M. Sanchez, “ABC’s of Output Analysis”, Proceeding of the 1999


Winter Simulation Conference, pp. 24-32, 1999.

197
[180] Thomas A. Ward, “Optimising Quayside productivity Using Computer
Simulation Analysis”, Port Technology International, pp. 65-68, 1999.

[181] Thomas J. Schriber, Daniel T. Brunner, “Inside discrete-event simulation


software: how it works and why it matters”, Proceeding of the 1999 Winter
Simulation Conference, pp. 72-80, 1999.

[182] Wayne J. Davis, “Simulation: Technologies in the new millennium”,


Proceeding of the 1999 Winter Simulation Conference, pp. 141-147, 1999.

[183] W. David Kelton, “Designing simulation experiments”, Proceeding of the


1999 Winter Simulation Conference, pp. 33-38, 1999.

[184] Willard C. Hewitt Jr, Eric E. Miler, “Applying Simulation in a consulting


Environment – Tips from airport planners”, Proceeding of the 1999 Winter
Simulation Conference, pp. 67-71, 1999.

[185] Avriel, M., Penn, M., Shpirer, N., & Witteboon, S. “Stowage planning for
container ships to reduce the number of shifts”, Annals of Operations
Research, 76, pp. 55-71, 1998.

[186] Banks, J., “Handbook of Simulation: Principles, Methodology, Advances,


Applications and practice”, co-published by Engineering & Management
Press, 1998.

[187] Bostel, N., & Dejax, P, “Models and algorithms for container allocation
problems on trains in a rapid transshipment shunting yard”, Transportation
Science, 32(4), pp. 370-379, 1998.

[188] Kim, K. K., & Bae, J. W., “Re-marshaling export containers in port
container terminals”, Computers & Industrial Engineering, 35(3-4), pp. 655-
658, 1998.

[189] Pao-Hsiang His, Shi-Lin Chen, Ray-Jong Li, “Simulating On-Line Dynamic
Voltages of Multiple Trains under Real Operating Conditions for AC
Railways”, IEEE Transactions on Power Systems, Vol. 14 No. 2, pp. 452-
459, 1998.

[190] Kozan, E., “Increasing the Operational Efficiency of Container Terminals in


Australia”, Journal of the Operational Research Society, 48(2), pp. 151-161,
1997.

[191] Evers, J. J. M., & Koppers, S. A. J., “Automated guided vehicle traffic
control at a container terminal”, Transportation Research Part a-Policy and
Practice, 30(1), pp. 21-34., 1996.

[192] Glover, F., “Tabu Search Part I”, ORSA Journal on Computing, 1(3), pp.
190-206, 1996.

198
[193] Kazimierczuk, M.K.; Cravens, R.C, “Application of super capacitors for
voltage regulation in aircraft distributed power systems”, Power Electronics
Specialists Conference, 1996. PESC '96 Record, 27th Annual IEEE, Volume
1, pp. 835 - 841, June 1996.

[194] de Castilho B., Daganzo C.F., “Optimal pricing policies for temporary
storage at ports”, Transportation Research Record 1313, pp. 66-74, 1995.

[195] R. J. Hill, “Electric railway traction Part 1”, Power Engineering Journal
February 1994, pp. 47-56, 1994.

[196] R. J. Hill, “Electric railway traction Part 2”, Power Engineering Journal June
1994, pp. 143-152, 1994.

[197] R. J. Hill, “Electric railway traction Part 3”, Power Engineering Journal
December 1994, pp. 275-286, 1994.

[198] Decastilho, B., & Daganzo, C. F., “Handling Strategies for Import
Containers at Marine Terminals”, Transportation Research Part B-
Methodological, 27(2), pp. 151-166, 1993.

[199] IEEE Std. 519-1992, “Recommended Practices and Requirements for


Harmonics Control in Electric Power Systems”, IEEE Industry Applications
Society, 1993.

[200] P.Kundur, “Power system stability and control”, McGraw –Hill, Inc. pp.1-2,
1993.

[201] Daganzo, C. F., “The crane scheduling problem”, Transportation Research


Part B-Methodological, 23(3), pp. 159-175. 1989.

[202] Chung, Y. G., Randhawa, S. U., & McDowell, E. D., “A simulation analysis
for a transtainer-based container handling facility”, Computers & Industrial
Engineering, 14(2), pp. 113-125, 1988.

[203] MJ Jr Vickerman, R Katims, “Container terminal desin”, 1988 Oceans


Conference, 1988.

[204] Cerny, V., “A thermodynamical approach to the travelling salesman


problem: an efficient simulation algorithm”, Journal of Optimization Theory
and Applications. 45, pp. 41-51, 1985.

[205] J.D. Glover, A. Kusko, S.M. Peeran, “Train Voltage Analysis for AC
Railroad Electrification”, IEEE Transactions on Industry Application Vol.
IA-20, No. 4, pp. 925-934, 1984.

[206] Kirkpatrick, S., Gelatt, C. D. & Vecchi, M. P., “Optimization by Simulated


Annealing. Science, 220 (4589), pp. 671-680, 1983.

199
[207] A E Fitzerald, David E. Higginbotham Arvin Grabel, “Basic Electrical
Engineer”, McGraw-Hill Publisher, pp. 778-787, 1981.

[208] Edmond, E. D., & Maggs, R. P., “How useful are queue models in port
investment decisions for container berths?”, Journal of the Operational
Research Society, 29(8), pp. 741-750, 1978.

[209] Holland, J. H., “Adaptation in natural and artificial systems: An introductory


analysis with applications to biology, control, and artificial intelligence”,
University of Michigan Press, 1975.

[210] Broughton H. H., “Electric cranes: Their Design, Construction and


Application”, The Electrician printing and publishing company ltd, pp. 443-
447, 1911.

200

You might also like