1 Continuous heavy air exhaust observed in air regulator exhaust point & same to be cleared (241-XV-508C). METERING SKID RAGHAVAN Completed
2 Continuous heavy air exhaust observed in air regulator exhaust point & same to be cleared (241-XV-80). METERING SKID RAGHAVAN Completed
3 Continuous heavy air exhaust observed in air regulator exhaust point & same to be cleared (241-XV-81). METERING SKID RAGHAVAN Completed
4 MOV(241-MOV-530) not operating from Remote mode(DCS) & found modbus issue,but in local mode operating normally. METERING SKID RAGHAVAN Completed
RAGHAVAN
5 MOV(241-MOV-520) not operating from Remote mode(DCS) & found PCB card issue,but in local mode operating normally. METERING SKID Need vendor support on this issue
Metering skid Flow transmitter(241-FT-530) in C stream found D- transducer gain value found abnormal,so vendor recommended to flush the line for particular time
6 period (or) need to remove the transducer from line for find out the sensor status. METERING SKID RAGHAVAN Shutdown of line (C-stream) required for attending problem.
7 On/Off valve's (241-XV-508 A /B/C) open/close soft button not enable in DCS valve face plate & ABB person is working for same issue. METERING SKID RAGHAVAN Completed
RAGHAVAN
8 XV-034 valve operation to be checked. TERMINAL Process clearence required
RAGHAVAN
9 XV-701E valve passing to be observed @ closed condition and same to be cleared. TERMINAL Mechanical support is required for attending this issue
RAGHAVAN
10 Flare page iginition off from DCS button acknowledge status to be provided. TERMINAL ABB support required
11 MOV (218-MOV-008A) was not operated from DCS & same to checked and cleared. TERMINAL RAGHAVAN Completed
RAGHAVAN
12 Flare flame sensor(DI) not in line same to be checked and cleared. TERMINAL ABB support required
RAGHAVAN
13 Shore to ship/ship to shore activated alarm to be provided as (FIFO) Concept. TERMINAL ABB support required
14 All ESD interlock & tripping points alarm/events to be provided. TERMINAL RAGHAVAN Already available in C&E graphics "Flare & Fire Water Pump"
15 All area local indicators like(LI,FI & PI) AO signals to be taken into line. TERMINAL RAGHAVAN Please provide specific tag numbers.
RAGHAVAN
16 Jockey pump five conditions to be checked. TERMINAL ABB support required
RAGHAVAN For Jockey pump only status feedback are available in DCS and there is no
17 Jockey pump Remote start/stop to be checked from DCS with as per the logics & also to be checked with main/stand-by selection. TERMINAL start/ stop command from DCS and the same to be check with ABB
RAGHAVAN Most of the electrical driven pumps running status are already checked and
18 All electrical driven pump running status to be implemented from MCC to DCS. TERMINAL feedbacks are available in DCS
20 All Diesel tank LT signal to be hooked upto DCS. TERMINAL RAGHAVAN Already available in C&E graphics "Flare & Fire Water Pump"
21 Pressure recorder to be configured upto 7 days as per the document. TERMINAL RAGHAVAN Please provide specific tag numbers.
Please provide specific tag numbers. Some Tags were aleady attended in
22 AFR issues to be cleared for all valves. TERMINAL RAGHAVAN Metering Skid. Work in progress.
23 FT-32 LP side root valve leakge was observed & same to be cleared. TERMINAL RAGHAVAN Same point as 39
Please provide specific tag numbers. Some Tags were already attended in
24 All area transmitter impluse tubing ferrule punching & manifold tightness to be done. TERMINAL RAGHAVAN Metering Skid. Work in progress.
25 242-PT-069 single way manifold not avaliable & same to be cleared. TERMINAL RAGHAVAN Completed
Venkat: RAGHAVAN
26 In jetty CA to HVAC panel one signal was balance & same to be cleared. JETTY
226-LT-520
RAGHAVAN
27 On/Off (XV) valve's LCP Operation to be implemented. JETTY ABB support required
RAGHAVAN
28 211-XV-101 & 211-XV-102 valve did not closed fully & same to be cleared. JETTY Completed
29 De-luge valve (DV-15) PS was operated even DV not operated. JETTY RAGHAVAN Completed
30 DV-13 & 14 leakage was observed at pressure relief valve. JETTY RAGHAVAN Completed
RAGHAVAN
31 Jetty DCS panel cable dressing to be done and extra cable to be removed. JETTY
RAGHAVAN
32 Jetty DCS Panel room false floor inside FO cable was rolled & kept & same to be clarify. JETTY
RAGHAVAN
33 Jetty DCS panel & Console room false floor inside cleaning to be done. JETTY
34 211-XV-008 valve leakage to be arrested. JETTY RAGHAVAN Mechanical discipline will attend valve flange leakage
35 Tide & wave sensor working normally but value description to be confirmed by vendor. JETTY RAGHAVAN Marine Contractor's scope.
36 Local indicators like (LI,FI & PI) AO signals to be taken into line. JETTY RAGHAVAN Same as point15
37 LT Flare stack -511 found cable not connected Flare stack SAMIRAN Completed
SAMIRAN
38 TT 101-16 Near BOG found RTD mounting not proper BOG By KSS. Work in progress.
Nipple thread is not proper.
39 FT 227-032 Leakage found near LP line tapping point RECONDENSOR SAMIRAN Nipple to be replaced by Piping.
40 FV 227-XV-058 solenoid coil not working so replacement need to be done RECONDENSOR SAMIRAN Completed
SAMIRAN
41 FT-227-034 found sensor cable not connected with transmitter as missing RECONDENSOR Special cable to be laid and to be checked with KSS
SAMIRAN
42 All are like BOG, Recondensor, HP,LP line main tank area housekeeping need to be require ALL AREA Not a commissioning punch point
This is already part of Construction Punch Lists (C).
43 In RIO & DCS panel cable glanding plate hole to be packed by M-seal MCR SAMIRAN Please delete from commissioning Punch list
44 In RIO & DCS panel tube light, cooling fan supply to be provided in Raw power not in UPS MCR SAMIRAN Completed
45 241-MOV-510 found inside motor terminal cover huge water or moisture found that’s why tripped , need to be check METERING SKID SAMIRAN Completed
47 241-CV-508 B leakage from AFR , need to be arrrested METERING SKID SAMIRAN Completed
48 Between 241-XV- 508 A&B staircase welding required as hanging . METERING SKID SAMIRAN Part of Mechanical work.
SAMIRAN
49 Found GC one heleium cylinder vent tubing not connected , tubing mismatch METERING SKID Completed
50 Found cable layed with out cable tray of 241-XV-080 , need to be proper cable tray required METERING SKID SAMIRAN Completed
Please provide specific tag numbers. Some Tags were aleady attended in
51 All Instruments spare gland entries to be blinded ALL AREA NAGENDRA Metering Skid. Work in progress.
This is already part of Construction Punch Lists (C).
52 Sharp edges of cable trays should be covered with some sleeves ALL AREA NAGENDRA Please delete from commissioning Punch list
NAGENDRA
53 Some control valves were not having vent port breathers.(239-FV-053F,238-FV-53E,237-FV-53D) ALL AREA
This is already part of Construction Punch Lists (C).
54 BOG MMS RTD’s and vibration probes should be provided with conduits BOG NAGENDRA Please delete from commissioning Punch list
This is already part of Construction Punch Lists (C).
55 FDV cable dressing at JBs was not properly done FDAV NAGENDRA Please delete from commissioning Punch list
This is already part of Construction Punch Lists (C).
56 Battery limit area branch cable trays were not provided with supports, some of the trays got twisted. ALL AREA NAGENDRA Please delete from commissioning Punch list
Related punch point already in Construction punch (C ), Please delete from
57 All STV skin temperature transmitters near to the grating proper cable dressing to be done by extending trays. (tied to the grating with ties). ALL AREA NAGENDRA commissioning Punch list
NAGENDRA
58 226-LT-520 BOG cooling skid LT tapping was taken from top. BOG LT HP tapping impulse line modification to be carried out.
This is already part of Construction Punch Lists (C).
59 Multi pair cables dressing was not done properly near FDAV jbs. FDAV NAGENDRA Please delete from commissioning Punch list
Please provide specific tag numbers. Some Tags were aleady attended in
60 PT and LT ranges should be verified with datasheet. some of the tags were not matching ALL AREA NAGENDRA Metering Skid. Work in progress.
NAGENDRA
61 223-FT-026 orifice to be inspected when opportunity comes. No DP was generating during existence of process flow TANK pending due to process clearance
62 241-XV-508A/B/C valve enable option in faceplate is not provided METERING SKID NAGENDRA Completed
63 245-XV-097 valve was not operating properly TRUCK LOADING NAGENDRA Completed
64 All differential pressure level transmitters are to be configured according to the datasheet.Wet/Dry leg calibration to be checked. ALL AREA MADHU Please provide specific tag numbers.
MADHU
65 All pumps operating through IRP panels shall be checked and to be taken in the interlock. ALL AREA Most of the pumps IRP trip interlocks are checked and taken inline
MADHU
66 Flare system temperature element shall be checked as it was showing less temperature. FLARE Temp. transmitter is faulty and vendor support is needed.
MADHU
67 Flare flow transmitter configuration shall be confirmed with data sheet as operation expecting more flow through line. FLARE
MADHU
most of the pumps IEC protocol tesing are completed and 415V Switchgear
68 IEC protocol related pumps shall be checked. ALL AREA IEC protocol testing is pending due Vendor non availability at site
69 Fire water pumps related pending points shall be mitigated. FIRE WATER SYSTEM MADHU Please provide specific tag numbers.
70 Fire and gas related pending points shall be completed. ALL AREA MADHU Please provide specific tag numbers.
Please provide specific tag numbers. Valves are being attended in shifts as
71 All valves shall be checked physically for any leakages as well as damaged parts. ALL AREA MADHU problems are reported.
Please provide specific tag numbers. Valves are being attended in shifts as
72 All leakages related impulse tubing shall be attended. ALL AREA MADHU problems are reported.
73 All ESD and FSGDS controller healthiness checking and redundancy checking shall be done. MCR/JCR MADHU Part of ESD SAT.
74 DCS panel utility power not avaliable at JCR. MCR/JCR RAGHAVAN Completed
RAGHAVAN
75 AAH-A(246-TI-401) not showing value in DCS & same was found normal in local. MCR/JCR Completed
AAH vibration switch (246-VAH-506) not healthy in DCS & same to be checked.Other fan vibration switch also checked and found switch are connected NO contact,there is no RAGHAVAN
76 fail safe condition. MCR/JCR Completed
77 BOG Knock out drum level transmitter (224-LT-010 & 224-LT-011 ) unit to be changed as per datasheet.(data sheet-0-399.5 mmH2O)(field 0-399 inchH2O). MCR/JCR RAGHAVAN Completed
RAGHAVAN
78 HP LNG pump (228-TI-074AA) FF configuration to be done in DCS & same was found normal in local. MCR/JCR Completed
RAGHAVAN
79 Level transmitter(251-LI-049) unit was interchanged as per datasheet & same to be rectified. Level transmitter is faulty and vendor is attending the fault
RAGHAVAN
80 Bently vibration controller reached high temperature at MCR panel room(MCR-MMS-01 & 02) and found utility power supply not avaliable & same to be rectified. to be checked with Electrical for utility power supply
RAGHAVAN
81 HP LNG pump sump RTD (228-TI-074AB & AC ) was interchanged and same to rectified. HP LNG PUMP Completed
RAGHAVAN
82 LNG storage tank(101-T01) level showing full percentage & same to be cleared. TANK Completed
OPERATION
83 Air compressor -A & B (101-K02A & 2B) running indication to be provided in DCS. NITROGEN PACKAGE Completed
84 XV-49 open feedback is not receiving & same was forced in DCS. TANK OPERATION Completed
OPERATION
85 In MCR annunciator panel UPS fault alarm(009-XA-001 & 009-XA-002) was activated when main(EB) power was fails & same to be cleared. MCR/JCR to be check with ABB
OPERATION
86 Pressure valve(223-PV-019A) feedback showing 5 % @valve fully closed condition. Valve diaphragm issue
87 Flow transmitter (246-FT-076A & 246-FT-075A )to be taken into the line. OPERATION This is not counted as a punch point.
88 Hot water expansion drum Level Gauge(LG-006G) to be taken into the line. STV OPERATION Flange mismatch. Working with Piping Discipline.
OPERATION
89 Latching switch was missing in (XV-73).
OPERATION
90 LNG tank-1 inter transfer flow transmitter(223-FT-025) value is showing (67689 kg/hr),even valve(FV-025) closed condition. TANK Flow element (Orifice direction) is wrongly installed
91 LNG tank - 1 to recondenser line flow transmitter(223-FT-026) value is not showing even valve open condition. TANK OPERATION Same as point 61.
92 LNG tank - 1 LP pump(P01D) discharge MOV-008A not working in remote mode. TANK OPERATION Completed
93 LNG tank - 1 all LP pump vent valve feedback problem to be rectified. TANK OPERATION Completed
OPERATION
94 LNG tank - 1 all LP pump (Ampere & KW) value not showing in DCS & same to be cleared. TANK Completed
OPERATION
95 STV- A(E-01A) ON/OFF valve(234-XV-065A) observed heavy noise during opening time of (80-100 %). STV Completed
99 Temperature transmitter(233-TI-83 A/B/C and 233-TI-82 A) faceplate & DCS tag plate showing double cross indication & same to be rectified. OPERATION Completed
OPERATION
100 LP LNG pump -D discharge MOV not operated from Local & remote mode. LP LNG PUMP Completed
101 Road tanker instruments to be configured in DCS side(TI-151,TI-517A,TI-517B & PI-512 A & B). TRUCK LOADING OPERATION Completed
OPERATION
102 Drain purge line Flow transmitter( FT-159) to be checked. Process clearence required
OPERATION
103 LNG tank-1 protection interlock (IZ 2.2) effect healthy indication to be changed. TANK Completed
OPERATION
104 ON/OFF valve(218-XV-25A) not closing after 90 sec when pump is running. Completed
OPERATION
105 FDAV- A(MT-4) & AAH (05A- MT-09) pump is automatically started even stop command executed. FDAV Completed
106 MCR-MBD -10(R)- cable dressing to be done MCR/JCR NEELAKANDAN Part of Construction Punch Points
NEELAKANDAN
107 MCR-MBD-09(R),MBD 1(R), MBE 1(F), ESD 1 (F),MBD 4(F), MBD 2(F),MBD 1(F), MBE 7(R), MBE 5(F)- light is not glowing MCR/JCR ABB support required
NEELAKANDAN
108 MCR-MBD-06(R) - TB group ferruling is pending and light is not glowing MCR/JCR ABB support required
NEELAKANDAN
109 ESD 01 FFTDU is not working properly. MCR/JCR ABB support required
110 Found in electrical panel inside room smoke detector tag no- 010-ICJC-009 found not in field only showing in P&ID drawaing JCR SAMIRAN Completed
111 In JCR building first floor 01 ECP , but no connection JCR SAMIRAN Completed
Found in JCR control room first floor the following smoke detector showing in client page or trial taken through modbus but in mention drawing or P&ID it has been not found . SAMIRAN
112 ( 010-ICJC-004,014,015) JCR
Location Not clear.
113 Near entry gate of panel one MCP canopy , tag plate missing . NEAR ECR SAMIRAN Please clarify location.
114 Near track loading section one flame dector B002 supply wire disconnected from panel end as spare not available TRUCK LOADING SAMIRAN Detector in maintenance.
SAMIRAN
115 In BOG area one BCON hooter unhealthy , but in field it is ok , need to be checked by ABB person in logix. BOG ABB support required
116 224-TV-056:No approach for valve FDAV SUBHASISH GHOSH Not an Instrumentation issue. Informed PFM (B&V)
117 240-XV-073:Latching valve wheel missing and PG damaged FDAV SUBHASISH GHOSH Same as 89
SUBHASISH GHOSH
118 240-FT-063:Manifold mounted downwards.To be rectified FDAV Completed
This is already part of Construction Punch Lists (C).
119 240-TT-128:Thimble not there at transmitter FDAV SUBHASISH GHOSH Please delete from commissioning Punch list
This is already part of Construction Punch Lists (C).
120 240-TT-063:Thimble not there at transmitter FDAV SUBHASISH GHOSH Please delete from commissioning Punch list
This is already part of Construction Punch Lists (C).
121 240-TT-130:Thimble not there at transmitter FDAV SUBHASISH GHOSH Please delete from commissioning Punch list
This is already part of Construction Punch Lists (C).
122 240-TE-135:Tags were interchanged at field.Both are FF tag.No ferrule and no thimble at element head. FDAV SUBHASISH GHOSH Please delete from commissioning Punch list