I. GENERAL INFORMATION
The City of Tabuk has invested on science based tool thru the conduct of Tabuk
City Risk Assessment and Vulnerability Analysis last April, 2018. It was found out that
ten (10) barangays are exposed to flood, another ten (10) to landslide while twenty two
(22) barangays are exposed to both flood and landslide. It is in the light of these realities
that a related study must therefore be conducted by targeting the smallest unit, the
barangay. The conduct of community based DRRM provides an in depth analysis of
number of families, vulnerable groups exposed to hazards and at risks to the negative
impact of disaster. Likewise with the identification of capacities and resources present in
the barangay which is an important aspect in barangay disaster management and planning
would somehow make our people more disaster conscious and the barangays more
effective in preparing for and responding to calamities.
Legal basis:
III. OBJECTIVE:
1. To conduct community risk assessment in the 32 barangays.
2. To create an information database system of the barangays.
3. To produce hazard and evacuation route maps of the barangays.
4. To assist in the formulation of Barangay Disaster Risk Reduction and Management
Plan based from the data capture form.
IV. PARTICIPANTS:
CDRRMC data processors, technical working group, GIS mappers and BDRRMCs
of the 32 barangays.
V. PROJECT DESCRIPTION:
The project will be divided into two (2) phases, phase 1 will be the conduct of
community risk assessment by mapping and household survey of the 10 barangays exposed
to rain induced landslide and phase 2 for barangays exposed to both hazards (Flood and
Rain Induced Landslide).
The activity involves ground mapping, GIS mapping and household survey using
the BDRRM template. Data collected during the survey will be processed and validated by
the BDRRMC and CDRRMO. The final output will be stored in the CDRRMO database
system which will serve as reference for planning and operational purposes. In addition,
secondary data will be extracted from CBMS, BDRRM disaster reports and CDRRMC
reports.
VI. METHODOLOGIES:
The outputs will serve as data inputs in the CDRRMO database system and a reference for
Barangay Disaster Risk Reduction and Management Plan formulation that will consists of the