PROJECT PROFILE

AIP Code: 8000-1-02-002-02-03-1-007


I. Project Title : Monitoring on Closure of Open Dump Sites
II. Sectoral Classification : PENRO - Natural Resources Management Program
III. Subsector : Waste and Pollution Management Division
IV. Function : 20% Local Development Fund
V. Program : Priority Development Projects
VI. Special Account : LDP – Economic Development
VII. Rationale/Background Information/Location/Coverage:

Section 37 of Republic Act No. 9003 otherwise known as Ecological Solid Waste Management Act of 2000
provides that no open dumps shall be allowed three (3) years following the effectivity of the Act, further, controlled
dumpsite shall be allowed five (5) years following the effectivity of the Act. Therefore, all open and controlled
dumpsites should have been phased out and closed as of February 16, 2006. This mandate shall be implemented
by this administration under the three pillars of the Provincial Government of Zamboanga del Sur.

Monitoring the open dumpsites is a must in every municipality and the city, expecting to accumulate its volume
of solid waste disposal and will continue beyond its intended solid waste storage (cubic meter or hectare-area)
capacity. It is empirical for the Provincial Government to monitor the formulated Closure and Rehabilitation Plan of
the Municipalities and the City’s Controlled Dumpsite, in order to comply the requirements under RA 9003 and to
attain the zero waste disposal in the Province.

Through monitoring and data gathering, the detailed information will support the assessment and evaluation in
formulating a holistic and harmonious Closure and Rehabilitation Plan.

VIII. Project Description/Methodology:

The Formulation of SCRP is within the context of comprehensive, systematic, and participative solid waste
management approach of the municipality/city. The M/CLGU through the Provincial Environment and Natural
Resources Office (CLENRO) shall facilitate the implementation of closure and rehabilitation activities. But since the
Province has limited resources and equipment, the implementation of the activities stipulated in this Plan shall be
going to be contracted out to a private entity that has the capacity and integrity in the closure of waste disposal
facility.

The closure of the M/CLGU controlled dumpsite would expedite the establishment of Ecological Park with Materials
Recovery Facility. In parallel, a siting of possible areas for Eco- Park shall be done. Likewise, waste reduction and
minimization at source shall be implemented at barangay level.

IX. Project Objectives:

General:
1. To be able to monitor the Formulated Safe Closure and Rehabilitation Plan (SCRP) of the municipality/city which
aims to promote public health and good sanitation in the province-wide of Zamboanga del Sur while attaining
sustainable ecological balance and compliant to RA 9003.

Specific:
1. To provide technical support in establishing workable strategies and parameters for the proper closure and
rehabilitation of the long overdue city dumpsite in compliance to Section 37 of RA 9003 for the province.

2. To ascertain closure requirements and schedule of rehabilitation activities based on the present conditions of
the dumpsite; and

3. To allocate resources in carrying out the safe closure and rehabilitation plan.

X. Output Indicators (Targets):


Description Quantity
1. No. of symposia/seminars conducted. 4 Quarters
2. No. of disposal site must be monitored, and open dumpsite closed with one city. 27 municipalities
3. No. of consultation/dialogues done at specific communities 4 Quarters
4. No. of Monitoring by using the procured equipment support in monitoring 12 months
XI. Time Frame : From January 15, 2020 to December 15, 2020
Major Activities Start Finish
1. Conduct of consultation/dialogues and symposia/seminars January March
2. Formulation of Safe Closure and Rehabilitation Plan March April
3. Project implementation April December
4. Project monitoring activities January December
XII. Venue : Applicable To Training/Seminar Only on how to operate the procured equipment support
XIII. Resource Persons : Applicable To Training/Seminar Only on how to transfer the result in a data based program

Page 1 of 2 PENRO – PLGU ZDS WPM Project profile 03-01-007


XIV. Funding Requirements: By Item
Item 20% LDF (P) PENRO - AIP Account Code
1. Training/Seminar on Safe Closure and Rehabilitation Plan
- - -
Compliance and its importance
2. Logistics, Accommodations and Meals - - -
3. Honorarium for consultant - - -.
-
TOTAL
XV. Implementing Office/s : PENRO – PLGU ZDS
XVI. Participating Office/s : Provincial Planning and Development Office, MPDC and MENROs

Remarks : Gathered Data will be used to formulate the Safe Closure and
XVII.
Rehabilitation Plan

Prepared by:

DEBAH B. WAYCO, MPA, MSci FOR. ROSELLER B. ANDRADES July 20, 2020
SEMS, PENRO – PLGU ZDS SEMS, PENRO – PLGU ZDS Date
Noted by:

EnP RICHARD S. LIGAN, LLB July 20, 2020


PENRO – PLGU ZDS Date
Checked by:

EnP MERILINE B. LOCSON, MPA, MSci July 20, 2020


PPD0 – PLGU ZDS Date
Approved by:

VICTOR J. YU July 20, 2020


Provincial Governor Date

Page 2 of 2 PENRO – PLGU ZDS WPM Project profile 03-01-007