Vertex RMG Division

Vertex wears Ltd.

Plan for January, February & March

1. Reduce the manpower from each & every line minimum one operator.
2. Our efficiency level will not decrease for back to back line feeding.
3. We are setting our bulletin target for more productivity

Example:

Style Bulletin target Plan target


Rbecca 172 185
Victoria 205 230
Ibiza 205 220

4. Our minimum efficiency line will be 70%.


5. Our line average efficiency will be 80%.

According to plan VWL IE team set efficiency for next 3 months. Our average efficiency will be
75%.

Sl No Month Efficiency
1 January 73%
2 February 75%
3 March 77%