Tools details:
1. Fitter -6
2. GL-01
3. Helper -1
4. Supervisor- 02
5. Engineer – GE & SPGVL
6. Safety –
Step -01
Shut down –
1. Lay the cut conductor between tower span using existing tower beam, Bamboo support
and Manlift.
2. Assemble the composite/polymer insulator as per the drawing.
3. Fix the string hardware and corona ring / turn buckle / sag compensating spring to the
conductor. Fix the same to the insulator string.
4. Fix one end of the conductor span with string to one of the beams, with the help of lifting
tools(PP Rope & Pulley) manually by fixing it on enough strengthening material.
5. Lift other end of the conductor along with string by pulleys After achieving required
tension/sag, fix it on the beam.
6. After fixing of both the ends of span, recheck the sag and ensure the same is as per sag
tension chart. If required, adjust the sag by turn buckle.
7. Fix the spacers as per the approved drawing.
Stringing work would be completed and returning of shut down would be done.