ACTIVITIES- SUB-TASKS PERSONNELS MATERIALS EQUIPMENTS/TOOLS EXPECTED EXPECTED

MAIN TASKS START DATE FINISHED


DATE
Emergency 8/8/2019 8/8/2019
Assembly point -Installation of sign post -1masons -Cement Wheelbarrow
-1heper -Aggregate Spades
-Sand Trowel
-Water
Construction of -Excavation -2 masons -Cement 8/8/2019 8/8/2019
Generator shed -Casting of slab -2 helpers -Aggregate Wheelbarrow
-Installing Pols -Sand Back hoe Excavator
-Fixing iron sheets -Pols Spades
-Roofing -Roofing nails Trowel
-5inch nail
-Water
Installation of -Purchase and Transportation 2 Operators -10trips of Tipper truck 8/8/2019 9/8/2019
Boulders to -Installation boulders Excavator
protect the
diversion drift.
Improvement -Laying of Marram 1mason -1Trip of Plate Compactor 8/9/2019 8/8/2019
of Kitchen floor -Applying Moisture 2helpers Marram
and seat -Levelling and compaction -Water
Installation -Installation of seats -6pcs of 8’’x1’’
-8pcs of poles
Installation of -Installation of base footings 1 Operator -Belt for the High up crane 10/8/2019 11/8/2019
Containers for -Carrying and lifting from Nalakasi 1 Mason High up crane
workshop and camp to Secondary camp
store -Transporting to site
Installation of -Gathering and assembling from 2Carpenters -Rivet gun -Tipper truck 9/8/2019 12/8/2019
prefabricated elements and fittings from the 3Helpers -Tape Measure
office primary camp. -Strings
-Fixing and Installation.
Construction of -Excavation of Foundation 2Masons -Cement Wheelbarrow 8/8/2019 12/8/2019
Ablution for -Blinding and backfill 2helpers -Aggregate Back hoe Excavator
Senior staffs -Floor slab -Sand Spades
-Superstructure wall(Timber poles -Roofing nails Trowel
and Iron sheet) -5inch nail Harmer
-Roofings -Water
-Plumbing works -Iron sheet
-Timber(4x2)
-Iron sheets
-timber poles

Construction of -Substructure wall construction 2masons -Cement Wheelbarrow 8/8/2019 17/8/2019


Huts For Senior -Superstructure wall construction 2helpers -Sand Back hoe Excavator
Staffs. -Roofing -Bricks Spades
-Plumbing works -Grass Trowel
-Plastering -Poles
-Purlins
-Rebar
-Links
Dismantling -Measurements and taking -Rigor Team -will be Moverble crane 15th/8/2019 25th/8/2019
Bailey Bridge dimension requested by
-Greasing and removing primary the Rigor head
member
-Unbolting and lifting using a moval
crane
-Storage for use in the next repair
Steel Cutting, -Request and deliverance of Rebar Steel Gloves Welding machine 15th/8/2019 15th/10/019
Bending and T16,Links for the abutment Fixtures Eye protection Grinding machine
formwork footings team wears Torque Wretch
preparation Safty boots
Bending table
Hollow pipe
Excavation of -Taking levels 3operators Total station 25th/8/2019 5th/9/2019
Foundation -Excavation 1 Surveyor Staff
Abutment -Compaction 1Helper Tipper Truck
Laboratory test
Equipment
Ground -Request and Delivery of materials 2 operator CRR Tipper truck 6th/9/2019 14th/9/2019
Improvement at site. Masons Geogrid Jumper
-Storage and usage for backfill on Blinding Excavator
the subgrade of the foundation Hardcore Back hoe
abutment.

Critical Activities:

-Dismantling the Existing Bailey Bridge

-Excavation of Foundation Abutment

-Ground Improvement