The above named person confirmed that he/she received the HSE-manual as well as the emergency
response plan TWB and understood the content.
The above named person has been inducted into following contents, amongst others and has been prompted
to ask open questions before the next operation to TWB II.
Safety policy for all operations in the offshore Trianel Windpark Borkum II, regardless of work for the
operation of the wind farm or for research purposes is as follows:
5 Crane work
- Cranes may only be operated by personnel with crane license who are instructed in crane operations.
- Only certified and inspected lifting gears / transport containers may be used. SWL must be considered.
- Prior to use of lifting gears / transport containers visual inspections must be carried out.
- Tug lines must be used. For loads above 500 kg a lift plan must be issued.
- Do not enter the area below floating loads and do not remain within the pivoting range of the crane.
6 Obligation to report
- Work accidents, incidents and near misses must be reported within 24 hours in written form.
- The names of the persons who enter the offshore installations must be communicated to the MCC.
- Other incidents, events or observations which could imply a danger must be promptly reported to the MCC. (Tetra)