Professional Documents
Culture Documents
Pert Notes PDF
Pert Notes PDF
1. Bar chart
2. Linked bar chart
3. Critical path method (AOA method-Activity on arrows)
4. Precedence Diagramming method (AON method- Activity on
nodes)
5. PERT method(program Evaluation and review Technique
method)
6. Probabilistic method (Based on simulation/ models)
The first four methods use a single estimate for the activity
durations (task durations) and obtain single estimate for the
project duration. Hence these methods are called deterministic
models of project scheduling. These methods do not consider
uncertainty in the activity time estimates and hence use single
values for activity durations.
PERT(Program evaluation and review technique) method
x is from mean
z is the probability score or number of standard deviation in
normal distribution (obtained from standard normal distribution
table )
x- Target project duration for which probability is to be
determined
- Project mean expected duration (TE ) as calculated from PERT
analysis with expected activity durations (te).
Steps involved in PERT analysis
1) Identify project activities (tasks) through WBS.
Square of σi2=
PROBABILITY
z (probability score) =
z=
z= = =2
z= = -1
SOLUTION-
Expected Activity Durations te= to+4tm+tp /6
Expected Standard Deviation of Activity /6
2
Activity Variance =( )2
2 2 2 2
Total project Variance =( 1 + 2 + 3 +……….)
2
Project standard deviation = =
ACTIVITY THREE TIME ESTIMATES
VARIANCE
ACTIVITY OPTIMISTIC PESSIMISTIC MOST LIKELY te σ
σ2
to tp tm
A 3 21 12 12 3 9
B 1 7 4 4 1 1
C 5 17 14 13 2 4
D 2 14 5 6 2 4
E 6 30 15 16 4 16
√29
TE = 41 DAYS
= = 5.4 5 DAYS
Probability Score Z = TX – TE /
TX = Target Project Duration
TE = Project Expected Duration
= Standard Deviation
For 48 days
Z = TX – TE / = 48 – 41 / 5 = + 1.4
The probability of completing this project in 45 days is 91.9%
For 45 days
Z = TX – TE / = 45 – 41 / 5 = + 0.8
The probability of completing this project in 45 days is 78.8%
For 38 days
Z = TX – TE / = 38 – 41 / 5 = - 0.6
The probability of completing this project in 38 days is 27.4%
CUMULATIVE PROBABILITY UP TO Z FOR STANDARD NORMAL
DISTRIBUTION
Z CUMULATIVE PROBABILITY
-3.0 0.001
-2.8 0.003
-2.6 0.005
-2.4 0.008
-2.2 0.014
-2.0 0.023
-1.8 0.036
-1.6 0.055
-1.4 0.081
-1.2 0.115
-1.0 0.159
-0.8 0.212
-0.6 0.274
-0.4 0.345
-0.2 0.421
0.0 0.500
0.2 0.579
0.4 0.655
0.6 0.726
0.8 0.788
1.0 0.841
1.2 0.885
1.4 0.919
1.6 0.945
1.8 0.964
2.0 0.977
2.2 0.986
2.4 0.992
2.6 0.995
2.8 0.997
3.0 0.999