PROJECT NAME: Widening to two lane from km 212/700 to 253/700 km and km

281/700 to 311/700 of NH326 (erstwhile km from km 0/0 to 30/0


km and km 58/0 to 99/0) of SH-4 under V-R corridor in the state
of Odisha. –Koraput-Raygada
REVIEW MEETING
BY
Shri. Rakesh Kumar
Regional Officer, MoRTH,
Bhubaneswar

On dated
28th August 2019
Authority’s Reresentative Authority’s Engineer EPC Contractor
Chief Engineer, M/s Chaitanya Projects M/s ARSS Infrastructure
NHs, Consultancy Pvt. Ltd. Projects Limited
ODISHA Ghaziabad Bhubaneswar
PROJECT SYNOPSYS

Chief Engineer,
Name of Authority
Public Works Department (NH), Bhubaneswar, Odisha
M/s Chaitanya Projects Consultancy Pvt. Ltd.,
Name of Authority Engineer
Ghaziabad, New Delhi
Name of EPC Contractor M/s ARSS Infrastructure Project Limited, Bhubaneswar

Type of Contract Engineering, Procurement and Construction (EPC)

Agreement No and Date CENH-EPC-07/15-16, Dt. - 30th September 2015

Project Cost Rs. 148, 00, 00, 000 /- ( One Hundred Forty Eight Crores Only)
Date of Appointment of
2nd November 2015
EPC

Project Duration 24 Months (730 Days) from the date of Appointment

1st November 2017 (Extended till 15th January 2018)


Date of Project Completion (Extended till 17th April 2018)
(Further EOT recommended till 15.01.2019)
MILESTONE SUMMERY
Target
Milestone Value of Duration Last date of
Amount Remarks
No. Work (In Days) Milestone
( In Rs. )

1st 10% of the 31st March 2016 Milestone achieved on


150th Day (Extended upto 14th June Rs. 14,80,00,000
Milestone Contract Value 2016) dated 31st May 2016

27th September 2016 Milestone achieved on


2nd 30% of the
330th Day (Extended upto 11th Rs. 44,40,00,000 27th November 2016
Milestone Contract Value December 2016)

3rd 60% of the 24th February 2017


Milestone achieved on
480th Day (Extended upto 10th May Rs. 88,80,00,000
Milestone Contract Value 2017) 15th May 2017

1st November 2017 Till 27.08.2019 the


(Extended to 15th Jan 2018) Physical Progress is
4th 100% of the (Extended till 17th April 100%
730th Day Rs. 148,00,00,000
Milestone Contract Value 2018) Financial Progress is
(Further EOT recommended Rs. 147.4 Crs. i.e.
till 15.01.2019) 99.59%
PHYSICAL PROGRESS
PROGRESS TILL
BALANCE WORK
Description of Scope of 27.08.2019
Sl. No. Unit
Items work In Length In In Length In
/Nos. Percentage /Nos. Percentage
1 C&G km 71 71 100% 0 0%
2 SUB GRADE km 71 71 100% 0 0%
3 GSB km 71 71 100% 0 0%
4 WMM km 71 71 100% 0 0%
5 DBM km 71 71 100% 0 0%
6 BC km 71 71 100% 0 0%
7 HP Culverts nos. 101 101 100% 0 0%
8 Box Culverts nos. 135 135 100% 0 0%
9 Road side Drain m 9740 9740 100% 0 0%
10 Guard wall m 3500 3500 100% 0 0%
11 Toe Wall m 7745 7745 100% 0 0%
12 Breast Wall (COS) m 970 970 100% 0 0%
Road Safety and
13 km 71 71 100% 0 0%
Signage
Improvement of
14 nos. 3 3 100% 0 0%
Major Junction

Miscellaneous Work
15 m 2240 2240 100% 0 0%
(CC Shoulder)

16 Metal crash barrier m 2210 2210 100% 0 0%


STATUS OF UTILITY SHIFTING

Date of Date of
Progress of
Utility Length Approval of deposit of Estimate Issue/
Name Status Department physical
Category Affected estimate by supervision amount Comments
shifting
RO/Authority charges

Electric
Koraput Estimate 42.60
Line 9.190 Km. SOUTHCO 09-10-2015 Deposited Completed Completed
District Approved Lakh
Shifting

EE,
Koraput Estimate 51.44
0.900 Km. RWS&S 09-10-2015 N.A. Completed
Shifting District Approved Lakh
Koraput
of
Completed
RWS&S
Pipelines EE,
Rayagada Estimate 20.14
2.650 Km. RWS&S 11-03-2016 N.A. Completed
District Approved Lakh
Rayagada

Shifting of
Koraput Estimate EE, PHD 114.00
PHD 3.420 Km. 09-10-2015 N.A. Completed Completed
District Approved Koraput Lakh
Pipelines