Professional Documents
Culture Documents
ABSTRACT OF COST FOR SEWAGE PUMPING STATION AND GENERATOR ROOM AT BAH BAZAR AND
APPURTENANT WORKS
Total 2500000.00
Assistant Engineer
ABSTRACT OF COST FOR SEWAGE PUMPING STATION AND GENERATOR ROOM AT SANGAM BAZAR
AND APPURTENANT WORKS
Sl.no. Description Quantity Unit Rate Rs Amount RS.
1 Provision for 3.5 m dia 5.0 m
depth sump cum sewage pump
house including inlet chamber,
grit chamber screen chamber
including all material, labour and
T&P also including excavation,
dewatering etc all complete along
with 3.0m x 4.0m x gererator
room. The
Total 2500000.00
Assistant Engineer
ABSTRACT OF COST FOR SEWAGE PUMPING STATION AND GENERATOR ROOM AT SANTI BAZAR
AND APPURTENANT WORKS
Total 3000000.00
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
FORM 'J'
SUBTOTAL 68647020.00
SUBTOTAL 70706430.60
4 DEPARTMENTAL FEES FOR PROJECT
PREPARATION AND SUPERVISION 70706430.60 12.5 8838303.83
TOTAL 79644734.43
SAY 79645000.00
796.45 Lakh
6 COST TO BE BEARED BY GOVT. OF
INDIA AS PER FORM 'J' 50879500.00
7 COST TO BE BEARED BY GOVT. OF
UTTARANCHAL 28765500.00
PREPARED BY : Recommended By
Computer
(Bhajan Singh)
Chief Engineer (Garhwal)
Uttaranchal Peyjal Nigam
Pauri
DEVPRAYAG SEWERAGE SCHEME
ABATEMENT OF POLLUTION OF RIVER GANGA AT DEVPRAYAG I&D
FORM 'J'
FOR
CENTRAL ASSISTANCE
Sl.NO. DESCRIPTION AMOUNT CENTAGE TOTAL
Rs. % Rs.
TOTAL 72685080.00
Say 72685000.00
726.85 Lakhs
Computer
(Bhajan Singh)
Chief Engineer (Garhwal)
Uttaranchal Peyjal Nigam
Pauri
1 2 3
1 Cost of Laying and jointing of sewer and appurtenant
works including Nala tapping, Gully pit etc. 33270000.00
(a) Cost of Sewage Pumping Station and Generator
2 room at Bah Bazar 2500000.00
(b) Cost of Sewage Pumping Station and Generator
room at Sangam Bazar 2500000.00
(c) Cost of Main Sewage Pumping Station at Santi
Bazar 3000000.00
3 (a) Cost of Rising main from Sewage Pumping
Station at Bah Bazar 210000.00
(b) Cost of Rising main from Sewage Pumping
Station at Sangam Bazar 6321000.00
(c) Cost of Rising main from Main Sewage
Pumping at Santi Bazar 4120000.00
Sub Total 51921000.00
4 Cost of Electrical, Mechnical works 15380000.00
Total 67301000.00
5 Cost of Land Acquisition. 100000.00
Total 67401000.00
Assistant Engineer
Table showing economic size of rising main from Bhajan Ashram Pumping Station for 143.25 lpm discharge
Sl Pipe Loss Cost of Cost of Maintenance Total Capitalised Total cost Remarks
No. size of power pipe per charge of recurring cost col (5+8)
in head col 100m rising main charges (4+6)x7.606
mm per 3xrate including @0.5% of col (4+6)
100m specials col5
M etc
1 2 3 4 5 6 7 8 9 10
1 80 6.36 5959.32 66500 332.50 6291.82 47855.58 114355.58
2 100 2.15 2014.55 84300 421.50 2436.05 18528.60 102828.60 Economical
3 125 0.73 684.01 109600 548.00 1232.01 9370.67 118970.67
4 150 0.30 281.1 136400 682.00 963.10 7325.34 143725.34
Table showing economic size of rising main from Gujrati Ashram Pumping Station for 82.50 lpm
discharge
Sl Pipe Loss Cost of Cost of Maintenance Total Capitalised Total cost Remarks
No. size of power pipe per charge of recurring cost col (5+8)
in head col 100m rising main charges (4+6)x7.606
mm per 3xrate including @0.5% of col (4+6)
100m specials col5
M etc
1 2 3 4 5 6 7 8 9 10
1 80 0.23 124.20 66500 332.50 456.70 3473.66 69973.66 Economical
2 100 0.08 43.20 84300 421.50 464.70 3534.51 87834.51
3 125 0.03 16.20 109600 548.00 564.20 4291.31 113891.31
Note :- As the discharge is very low, the economical size is 80 mm however as per ease in maintenance and
minimum of sewer 100 mm CI rising main is adopted.
Table showing economic size of rising main from Main Pumping Station for 1699.50 lpm discharge
Sl Pipe Loss Cost of Cost of Maintenance Total Capitalised Total cost Remarks
No. size of power pipe per charge of recurring cost col (5+8)
in head col 100m rising main charges (4+6)x7.606
mm per 3xrate including @0.5% of col (4+6)
100m specials col5
M etc
1 2 3 4 5 6 7 8 9 10
1 100 7.07 78575.98 84300 421.50 78997.48 600854.83 685154.83
2 150 2.91 32341.74 136400 682.00 33023.74 251178.57 387578.57
3 200 0.71 7890.94 199100 995.50 8886.44 67590.26 266690.26 Economical
4 250 0.24 2667.36 268400 1342.00 4009.36 30495.19 298895.19
0.60x0.60x6.0
0m
Va
ria
tio
No Depth Variation No Depth Variation No Depth Variation No Depth Variation No Depth Variation No Depth Variation No Depth Variation No Depth n
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
24-25 1 1.38 -0.12
1 1.02 -0.48
1 0.66 -0.84
1 0.85 -0.65
1 1.03 -0.47
1 1.21 -0.29
31-25 1 1.20 -0.30
1 1.46 -0.04
1 1.72 -1.28
25-26 1 1.60 -1.41
1 1.65 -1.35
1 1.70 -1.30
1 2.13 -0.87
1 2.56 -0.44
1 2.46 -0.54
1 1.95 -1.05
1 1.45 -0.05
1 1.49 -0.01
1 1.54 -1.47
1 1.22 -0.29
1 1.80 -1.21
1 2.74 -0.27
32-26 1 1.20 -0.30
1 1.42 -0.08
1 1.64 -1.37
1 1.30 -0.20
1 1.21 -0.29
1 1.55 -1.45
1 1.80 -1.21
1 1.70 -1.30
26-27 1 1.01 -0.49
1 1.01 -0.50
33-34 1 1.20 -0.30
1 1.70 -1.31
1 1.35 -0.15
1 1.02 -0.48
1 1.30 -0.20
1 1.55 -1.46
1 1.78 -1.22
1 1.87 -1.14
1 1.70 -1.30
1 1.54 -1.47
1 1.42 -0.08
1 1.30 -0.20
1 1.68 -1.33
34-35 1 2.79 -0.21
1 3.43 -1.07
1 4.07 -0.44
1 2.68 -0.32
1 1.30 -0.20
1 1.34 -0.16
1 1.61 -1.39
1 1.89 -1.12
1 2.23 -0.77
1 1.95 -1.05
1 1.67 -1.34
1 1.30 -0.20
1 1.04 -0.46
1 1.21 -0.29
1 1.29 -0.21
1 1.37 -0.14
38-39 1 1.20 -0.30
1 1.20 -0.30
39-35 1 1.20 -0.30
1 1.25 -0.25
35-36 1 2.53 -0.48
1 1.86 -1.14
1 1.20 -0.30
1 1.19 -0.31
1 1.18 -0.32
1 1.06 -0.44
36-37 1 0.94 -0.56
1 1.11 -0.39
37-27 1 1.28 -0.22
1 1.18 -0.32
1 1.07 -0.43
1 1.19 -0.31
27-28 1 1.30 -0.20
30-28 1 2.60 -0.40
1 1.89 -1.11
1 1.18 -0.32
1 1.28 -0.22
1 1.39 -0.11
1 1.29 -0.21
1 1.20 -0.30
1 1.20 -0.30
28-29 1 1.30 -0.20
1 1.25 -0.25
29-PS1 1 1.20 -0.30
1 1.00 -0.50
1 1.00 -0.50
1 1.00 -0.50
1 1.00 -0.50
1 3.00 0.00
1 2.64 -0.37
1 1.97 -1.03
1 1.81 -1.20
1 1.41 -0.09
1 1.38 -0.12
1 1.03 -0.47
1 1.06 -0.44
1 1.18 -0.32
1 1.32 -0.18
1 1.28 -0.22
1 1.26 -0.24
1 1.06 -0.44
21-22 1 1.20 -0.30
1 1.39 -0.11
1 1.56 -1.44
1 1.63 -1.37
1 1.48 -0.02
1 1.24 -0.26
1 1.25 -0.25
22-23 1 1.23 -0.27
1 1.25 -0.25
1 1.01 -0.49
1 1.49 -0.01
1 1.78 -1.22
1 2.50 -0.50
1 1.89 -1.11
1 1.89 -1.11
1 1.40 -0.10
1 1.03 -0.48
1 1.08 -0.42
1 1.13 -0.38
1 2.53 -0.48
1-2 1 1.20 -0.30
1 1.30 -0.20
1 2.12 -0.88
1 2.35 -0.65
1 1.27 -0.23
1 3.36 -1.14
1 2.99 -0.01
1 2.73 -0.27
1 2.49 -0.51
1 2.04 -0.96
1 1.91 -1.09
1 1.58 -1.42
1 1.44 -0.06
1 1.30 -0.20
1 1.18 -0.32
1 1.43 -0.07
1 1.38 -0.12
1 1.52 -1.48
1 1.90 -1.11
1 2.08 -0.92
1 1.30 -0.20
1 2.04 -0.96
1 1.30 -0.20
1 1.02 -0.48
1 1.20 -0.30
1 1.40 -0.10
1 1.38 -0.12
1 1.35 -0.15
1 1.30 -0.20
1 1.30 -0.20
1 1.30 -0.20
1 1.64 -1.36
1 1.71 -1.29
1 1.65 -1.35
1 1.30 -0.20
1 1.30 -0.20
1 1.13 -0.37
1 0.96 -0.54
1 1.13 -0.37
1 1.30 -0.20
1 1.25 -0.25
1 1.20 -0.30
1 1.25 -0.25
1 1.30 -0.20
1 1.27 -0.23
1 1.24 -0.27
15-14 1 1.20 -0.30
1 1.91 -1.09
1 1.06 -0.44
1 1.02 -0.48
1 1.12 -0.38
1 1.33 -0.17
1 1.41 -0.09
1 2.34 -0.66
1 1.67 -1.33
1 1.46 -0.04
1 2.10 -0.90
1 1.20 -0.30
1 2.79 -0.21
1 2.06 -0.94
1 1.93 -1.07
1 2.03 -0.97
13-14 1 1.30 -0.20
14-3 1 0.89 -0.61
3-5 1 2.26 -0.74
1 1.43 -0.07
12-5 1 1.20 -0.30
1 2.00 -1.00
1 1.38 -0.12
1 1.13 -0.37
1 2.20 -0.80
1 1.76 -1.24
1 1.83 -1.17
1 1.51 -1.49
1 1.30 -0.20
1 1.48 -0.02
1 1.38 -0.12
1 1.16 -0.34
1 1.30 -0.20
5-7 1 1.30 -0.20
1 1.04 -0.46
1 1.38 -0.12
1 1.65 -1.36
1 1.78 -1.22
1 1.89 -1.11
1 1.35 -0.15
1 1.30 -0.20
1 1.78 -1.23
1 2.02 -0.99
11-7 1 1.20 -0.30
1 1.13 -0.37
1 1.30 -0.20
1 1.30 -0.20
1 1.21 -0.29
1 1.20 -0.30
1 1.30 -0.20
1 1.20 -0.30
7-PS2 1 2.53 -0.48
20-19 1 1.20 -0.30
1 1.66 -1.34
1 1.40 -0.10
1 1.37 -0.13
1 1.03 -0.47
1 1.20 -0.30
1 1.08 -0.42
1 1.30 -0.20
1 1.32 -0.18
1 2.37 -0.63
1 2.68 -0.33
1 2.96 -0.04
1 2.05 -0.95
1 1.38 -0.12
1 1.43 -0.07
1 0.86 -0.64
1 0.66 -0.84
1 0.57 -0.93
1 0.46 -1.05
1 0.72 -0.78
19-19' 1 1.85 -1.15
1 1.30 -0.20
1 1.25 -0.25
1 1.90 -1.11
19'-16 1 1.23 -0.27
1 1.23 -0.27
1 1.25 -0.25
1 1.34 -0.16
1 1.06 -0.44
1 1.05 -0.45
1 1.07 -0.43
1 1.08 -0.42
1 1.07 -0.43
1 1.08 -0.42
1 1.09 -0.41
16-17 1 1.38 -0.12
1 1.25 -0.25
1 1.07 -0.43
18'-18 1 1.00 -0.50
1 2.81 -0.19
1 3.80 -0.71
1 4.78 -1.22
1 3.99 -0.51
18-17 1 3.09 -1.41
1 2.85 -0.16
1 1.15 -0.35
1 1.38 -0.12
1 1.45 -0.05
1 1.35 -0.15
1 2.27 -0.73
1 1.94 -1.06
1 1.32 -0.18
1 1.29 -0.21
1 2.81 -0.19
1 2.59 -0.41
1 1.82 -1.18
1 1.53 -1.47
1 1.64 -1.36
17-PS3 1 1.40 -0.10
0.
0
TOTAL 154 -44.76 85 -80.55 4 -3.50 1 -1.22 27 -7.18 10 -10.78 2 -1.78 0 0
DEVPRAYAG SEWERAGE SCHEME
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
Sl.No
Description No L B H Qty. Unit
1 Excavation for bedding under RCC sewer
along main road.
0-1.50 m BGL
150 mm RCC pipe Section 24-25
1 90 0.6 0.15 8.10
Section 21-22 1 112 0.6 0.15 10.08
Section 19-19' 1 28 0.6 0.15 2.52
150 mm CI pipe Section19-19'
1 35 0.6 0.15 3.15
Total 23.85 Cum
1.50-3.00 m BGL
150 mm RCC pipe Section 19-19'
1 30 0.6 0.15 2.70
200 mm RCC pipe Section 22-23
1 75 0.6 0.15 6.75
250 mm RCC pipe Section 22-23
1 110 0.6 0.15 9.90
Section 18-18' 1 110 0.6 0.15 9.90
200 mm CI pipe Section 22-23
1 128 0.6 0.15 11.52
Total 40.77 Cum
2 PCC 1:2:4 for bedding same as above
0-1.50 m BGL
23.85 Cum
1.50-3.00 m BGL
40.77 Cum
Assistant Engineer
UNIT ESTIMATE FOR NALA TAPPING ARRANGEMENT
Sl.No
Description No L B H Qty. Rate Amount
1 Excavation Side wall
1 3.00 1.26 0.30 1.134
(0.30+1.00) 3.843
1 3.36 1.76 2
4.977 61.65 306.83
2 P.C.C 1:4:8
1 3.00 1.26 0.15 0.567
1 3.36 1.76 0.15 0.887
1.454 1462.70 2126.82
3 Brick Work
2 3.00 0.23 0.50 0.690
(0.50+0.75) 0.575
2 2.00 0.23 2
4 1.10 0.23 1 1.012
2.277 2051.10 4670.35
4 R.C.C 1:2:4
Nala bed 1 3.00 1.26 0.10 0.378
1 3.36 1.76 0.1 0.591
Partition Wall (0.50+0.75) 0.125
1 2 0.1 2
Weir 2 0.6 0.2 0.3 0.072
Slab 2 1.56 0.5 0.1 0.156
1.322 2809.85 3715.63
5
M.S. work in RCC Qtl. 1.600 3940.00 6304.00
6 PCC 1:2:4 1x1/2 (0.3x0.3x1.10) 0.050 2030.55 101.53
7 Supply and fixing of
following:
(i) Coarse bar screen (1x0.5) 2
2 - - - Nos 2000.00 4000.00
(ii) Fine bar screen (1x0.5) 2
2 - - - Nos 4000.00 8000.00
8 Supply and fixing of CI sluce
gate of sixe (0.3x0.3) 2
2 - - - Nos 42000.00 84000.00
9 Fixing of M.H. cover size 1
(0.6x0.45) 1 - - - Nos 1590.55 1590.55
10 2
Fixing of foot step 2 - - - Nos 175.35 350.70
11 Connecting of Sewer line
with RCC pipe Job - - - Job 5780.00 5780.00
12 Diversion of Gadhera
Job - - - Job 5095.00 5095.00
13 Unforeseen Items
Job - - - Job 3958.58 3958.58
Total
130000.00
Assistant Engineer
UNIT ESTIMATE FOR GULLY PIT ARRANGEMENT
Sl.No
Description Unit Qty. Rate Amount
13 Site development and other unforeseen items Job Job 1335.86 1827.85
Total
18000.00
Assistant Engineer
UNIT CONSUMPTION STATEMENT FOR GULLY PIT AND NALA TAPPING ETC .
Sl.No Particulars Unit Qty. Cement Sand Stone Grit Stone Bricks Steel
Bags Cum Nos. Qtl.
Coarse Fine 10-20 20-40
Cum Cum mm Cum mm
Cum
1 2 3 4 5 6 7 8 9 10 11 12
1 Gully pits No 1 5 0.09 0.43 0.03 0.15 885.00 0.20
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
ABSTRACT OF COST FOR RISING MAIN FROM BAH BAZAR PUMPING STATION TO GRAVITY MAN HOLE
AND APPURTENANT WORKS
Assistant Engineer
ABSTRACT OF COST FOR RISING MAIN FROM SANGAM BAZAR PUMPING STATION AND APPURTENANT
WORKS
Sl.no. Description Quantity Unit Rate Rs Amount RS.
1 Excavation in trenches in soil mix with
single,bajri etc in following depths
below ground level including dressing
levelling,refilling of trenches in 15 cm.
Layers and disposal of surplus earth
upto 50 m distance.
(a).0.00to1.50m.BGL
ABSTRACT OF COST FOR RISING MAIN FROM SANTI BAZAR PUMPING STATION AND APPURTENANT
WORKS
Assistant Engineer
UTTARKASHI SEWERAGE SCHEME REVISED PROPOSAL
ABSTRACT OF COST FOR RISING MAIN FROM TILOTH VILLAGE PUMPING STATION TO GRAVITY MAN
HOLE AND APPURTENANT WORKS
ABSTRACT OF COST FOR RISING MAIN FROM KAILASH ASHRAM PUMPING STATION TO GRAVITY MAN
HOLE AND APPURTENANT WORKS
Assistant Engineer
ABSTRACT OF COST FOR RISING MAIN FROM TAMBAKHANI PUMPING STATION TO GRAVITY MAN
HOLE AND APPURTENANT WORKS
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
ABSTRACT OF COST FOR CARTAGE OF MATERIALS FOR RISING MAIN FROM BAH BAZAR TO
GRAVITY MAN HOLE AND APPURTENANT WORKS
Assistant Engineer
ABSTRACT OF COST FOR CARTAGE OF MATERIALS FOR RISING MAIN FROM MAIN PUMPING
STATION TO GRAVITY MAN HOLE AND APPURTENANT WORKS
Assistant Engineer
ABSTRACT OF COST FOR CARTAGE OF MATERIALS FOR RISING MAIN FROM GUJARATI ASHRAM TO
GRAVITY MAN HOLE AND APPURTENANT WORKS
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
Assistant Engineer
Assistant Engineer
Assistant Engineer
UTTARKASHI SEWERAGE SCHEME REVISED PROPOSAL
ABSTRACT OF COST FOR CARTAGE OF MATERIALS FOR RISING MAIN FROM TILOTH VILLAGE SPS
AND APPURTENANT WORKS
Assistant Engineer
Assistant Engineer
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
ABATEMENT OF POLLUTION OF RIVER GANGA AT DEVPRAYAG I&D
CONSUMPTION STATEMENT OF MATERIALS
Sl.No. DESCRIPTION QTY UNIT CEMENT BRICKS STONE COARSE FINE SHINGLE STEEL
BAGS NOS. SAND SAND QTLS.
10- 20-
20MM 40MM
1 2 3 4 5 6 7 8 9 10 11 12
1 Manholes slab
type
1.00x1.20x1.50 1606.
154 Each 22 127204 0 161.7 10.78 95.48 100.1 38.5
1.00x1.20x3.00 85 Each 1547.00 202980 0 178.50 15.3 43.35 105.4 21.25
2 Manholes Arch
type
1.00x1.50x4.50 4 Each 85.60 11424 0 9.60 1.32 2.04 5.16 0.484
1.00x1.50x6.00 1 Each 24.60 3446 0 2.70 0.3 0.58 1.29 0.121
3 Sewer
Connecting
Chamber
0.6x0.6x1.5
27 Each 126.90 15471 0 14.04 1.35 4.32 8.1 0.00
0.60x0.60x3.0 10 Each 72.50 11450 0 8.10 1 1.6 3 0.00
0.60x0.60x4.5 2 Each 25.00 2544 0 3.00 0.32 0.32 1.28 0.00
4 P.C.C. 1:2:4
for beding 64.62 Cum 427.78 0 0 29.08 0 58.16 0 0.00
5 R.R. 1:6 for
protection 320.64 Cum 564.32 0 356.00 0.00 112.22 0 0 0.00
6 P.C.C. 1:4:8
for foundation
of protection
walls 38.89 Cum 134.56 19 0 0.00 0 0 37.33 0.00
7 RCC 1:1.5:3 in
pillar and
foundation 37.68 Cum 302.95 17 0 0.00 0 33.91 0 0.00
8 Flush pointing
in 1:2
83.16 Sqm 9.15 0 0 0.00 0.582 0 0 0.00
9 MS Work 59.16 Qtl 0.00 0 0 0.00 0 0 0 62.12
10 Nala Tapping 7 Each 136.50 7973 0 9.24 3.57 8.68 9.66 11.20
11 Gully Pit 20 Each 100.00 17700 0 1.80 8.6 0.6 3 4.00
DEDUCTIONS
12 Manholes
Shaft variation
1.00x1.20x1.50 -44.76 m -130.25 -27393 0 -16.11 0 0 0 0
1.00x1.20x3.00 -80.55 m -331.06 -81758 0 -45.91 0 0 0 0
1.00x1.50x4.50 -3.50 m -6.265 -1376 0 -0.805 0 0 0 0
1.00x1.50x6.00
-1.22 m -2.18 -479 0 -0.28 0 0 0 0
13 Sewer
Connecting
Chamber shaft
variation
0.6x0.6x1.5
-7.18 m -12.49 -2743 0 -1.58 0 0 0 0
0.60x0.60x3.0 -10.78 m -18.76 -4118 0 -2.37 0 0 0 0
0.60x0.60x4.5 -1.78 m -4.61 -1184 0 -0.64 0 0 0 0
TOTAL 4657.47 281177 356.00 350.07 155.34 249.04 274.32 137.67
SAY 2329 562.35 356.00 350.07 155.34 249.04 274.32 138
qtls cum or cum cum or cum or cum or cum or qtls
8435.30 7120 5601.12 2485.44 4482.72 4937.76
qtl qtl qtl qtl qtl qtl
Assistant Enginner
DEVPRAYAG SEWERAGE SCHEME
271466.09
Total
Say 2715 Qtl
5 RCC Manhole covers and
frames 283 Each 150 42450.00
6 CI Footsteps assuming
average 3 Nos in each
manhole 849 Each 3 2547.00
7 Mis. Items such as sluice
gate, grating for Nala
taping etc. L.S 2400.00
47397.00
Total
Say 474 Qtl
Assistant Engineer
UTTARKASHI SEWERAGE SCHEME REVISED PROPOSAL
ABSTRACT OF COST FOR RISING MAIN FROM TILOTH VILLAGE PUMPING STATION
TO GRAVITY MANHOLE AND APPURTENANT WORKS
J.E A.E.
DEVPRAYAG SEWERAGE SCHEME
1 2 3 4 5 6 7 8
1 Excavation in trenches in soil
mix with shingle,bajri etc in
following depths below
ground level including
dressing levelling,refilling of
trenches in 15 cm. Layers
and disposal of surplus earth
upto 50 m distance.
(a).0.00to1.50m.BGL
1 90 1.00 1.22 109.80 Cum
assuming 50% excavation in
soil mix) and remaning 50%
in hard rock.
(a).Soil Mix
54.90 Cum
(b) Hard Rock 54.90
2 Supply of following size and
type pipes including cartage
upto departmental store.
(a) C.I. Class LA
(i) 100 mm 1 90 90.00 M
(b) C.I. Specials
10% of above
3 Supply amd fixing of
following valves
(a) Air valve double orifice
1x1 1 Nos
(b) C.I. Sluice valve
1x1 1 Nos
4 Cartage from store to site of
works the following dia pipes
lowering it into trenches in
following depths laying true to
alingnment, gradient and
making joints with rubber
gasket including testing etc.
complete (a) C.I. Class LA
1 90 90.00 M
5 Baricating of Sewer trenches 1x2 90 180.00 M
6 Provide all material and
provide following chambers.
(a) Air valve Chamber 1x1 1 Nos
(b) Scour valve Chamber 1x1 1 Nos
7 Provision for disposal of
surplus earth from the site of
2
work 1 90 x 3.14 x 0.11 /4 = 0.85 Cum
8 Provision for Thrust Block
1mx1mx1m RCC 1:2:4 1x5 1 1 1 5.00 Cum
9 Provision for Dismentalling
and reistatement of masonary
work 1 1 job
10 RR 1:6 for protection work. 1 3 0.9 2 5.4 Cum
10 1 0.9 1 9.0 Cum
Sub Total 14.4 Cum
11 Provision for cartage of
material as per attached 1 1 job
12 Unforseen Items 1 1 job
J.E A.E.
J.E A.E.
J.E A.E.
UTTARKASHI SEWERAGE SCHEME REVISED PROPOSAL
J.E A.E.
UTTARKASHI SEWERAGE SCHEME REVISED PROPOSAL
J.E A.E.
CONSUMPTION STATEMENT OF RISING MAIN FROM BAH BAZAR TO GRAVITY MANHOLE AND APPURTENANT WORKS
Total 3.68
148.96 316.80 20.80
37.50 Qtl 3.52 Qtl Cum 93.60 Qtl 22 Qtl
Qtl Qtl Qtl
55.20 Qtl
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
CONSUMPTION STATEMENT OF RISING MAIN FROM SANGAM BAZAR TO GRAVITY MANHOLE AND APPURTENANT WORKS
CONSUMPTION STATEMENT OF RISING MAIN FROM SANTI BAZAR TO GRAVITY MANHOLE AND APPURTENANT WORKS
Total 20.24
469.44 143
156 Qtl 19.36 Qtl Cum 297 Qtl 555.3 Qtl 537 Qtl
Qtl Qtl
303.6 Qtl
Assistant Engineer
UTTARKASHI SEWERAGE SCHEME REVISED PROPOSAL
CONSUMPTION STATEMENT OF RISING MAIN FROM TILOTH VILLAGE TO GRAVITY MANHOLE AND APPURTENANT WORKS
Total 7.36
100.64 Cum 106.20 46.80
33.00 Qtl 7.04 Qtl 108 Qtl
Qtl 110.40 Qtl Qtl
Qtl
Assistant Engineer
Assistant Engineer
CONSUMPTION STATEMENT OF RISING MAIN FROM TAMBAKHANI TO GRAVITY MANHOLE AND APPURTENANT WORKS
Total 9.20
224.80 355.50 58.50
87.00 Qtl 8.80 Qtl Cum 357 Qtl
Qtl Qtl Qtl
138 Qtl
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
ABATEMENT OF POLLUTION OF RIVER GANGA AT DEVPRAYAG I&D
ABSTRACT OF COST FOR LAYING OF SEWER AND APPURTENANT WORKS
1 2 3 4 5 6
1 Excavation in trenches in soil
mix with single,bajri etc in
following depths below
ground level including
dressing levelling,refilling of
trenches in 15 cm. Layers
and disposal of surplus earth
upto 50 m distance. (
assuming 50% excavation in
soil mix) and remaning 50%
in hard rock.
(a).0.00to1.50m.BGL 3227.65 Cum. 61.65 198984.62
(b)1.50 to 3.00 m.BGL 209.57 Cum. 80.35 16838.95
2 Excavation in trenches in
hard work following depths
below ground level including
dressing levelling,refilling of
trenches in 15 cm. Layers
and disposal of surplus earth
upto 50 m distance.
(a).0.00to1.50m.BGL
3227.65 Cum. 330.00 1065124.50
(b) 1.50 to 3.00 m.BGL 209.57 Cum. 363.75 76231.09
3 Provide and fix open
timbering covering 1/3 of area
as per departmental norms.
0-3 m B.G.L.
802.00 Sqm. 222.60 178525.20
4 Dismentling of all types of
road surfaces of pavements
for laying sewers and
appurtenant works including
sorting out serviceable
materials and disposal of
unserviceable materials.
(a) CC road 3215.50 Sqm. 40.15 129102.33
(b) Bitumenious
974.50 Sqm. 40.15 39126.18
5 Provision for payment of road
cutting charges for
dismentalling of roads to be
paid to P.W.D. or
NagarPalika.
(a) CC road 3215.50 Sqm. 1000.00 3215500.00
(b) Bitumenious
974.50 Sqm. 910.00 886795.00
6 Supply of following size and
type pipes including cartage
upto departmental store.
(a) R.C.C. S&S NP3
(i) 150 mm
851.00 M. 115.84 98579.84
(ii) 200 mm
461.00 M. 146.17 67384.37
(ii) 250 mm
237.00 M. 156.00 36972.00
(iii) 300 mm
160.00 M. 240.37 38459.20
(b) C.I. Class LA
(i) 150 mm 1379.00 M. 1240.00 1709960.00
(ii) 200 mm
408.00 M. 1810.00 738480.00
(iii) 250 mm
173.00 M. 2440.00 422120.00
(c) D.I. Class K7
(i) 300 mm 195.00 M. 2230.00 434850.00
8 Cartage from store to site of
works the following dia pipes
lowering it into trenches in
following depths laying true to
alingnment, gradient and
making joints with rubber
gasket including testing etc.
complete
(A) R.C.C. NP3
0.00 to 1.50 m BGL
(i) 150 mm 778 M. 111.12 86451.36
(ii) 200 mm 272 M. 126.36 34369.92
1.50 - 3.00 m BGL
(i) 150 mm
73 M. 118.28 8634.44
(ii) 200 mm 189 M. 134.51 25422.39
(ii) 250 mm 237 M. 150.73 35723.01
(iii) 300 mm 160 M. 187.09 29934.40
(B) C.I. Class LA
0.00-1.50 m BGL
(i) 150 mm 1144 M. 12.87 14723.28
(ii) 200 mm 196 M. 18.82 3688.72
(ii) 250 mm 173 M. 25.38 4390.74
1.50 - 3.00 m BGL
(i) 150 mm 235 M. 13.70 3219.50
(ii) 200 mm 212 M. 20.03 4246.36
(C) D.I. Class K7
0.00-1.50 m BGL
(i) 300mm 195 M. 21.67 4225.65
7 Baricating of Sewer trenches 7728 M. 32.35 250000.80
8 P.C.C 1:2:4 for bedding in
RCC sewer along main Mana
road.
0.00-1.50 m BGL 2385 Cum. 2030.55 4842861.75
1.50-3.00 m BGL 4077 Cum. 2046.04 8341705.08
9 Provide all material, labour
t&p etc and constructslab
type masonary manhole
chambers of following size as
pere type design and
specifications.
(a)1.00*1.20m.1.50m deep 154 Each 10250.00 1578500.00
(b)1.00*1.20m.3.00m deep 85 Each 20400.00 1734000.00
10 Provide all material, labour
t&p etc and construct Arch
type masonary manhole
chambers of following size as
pere type design and
specifications.
(a)1.00*1.50 m.4.50 m deep 4 Each 24550.00 98200.00
(b) 1.00*1.5m. 6.00 m deep 1 Each 31850.00 31850.00
11 Provide all material ,labour
,t&p etc and construct
masonary chamber per m.
shaft for following size
requisting the actual cost of
manhole in above item.
J.E A.E.
DEVPRAYAG SEWERAGE SCHEME
ABATEMENT OF POLLUTION OF RIVER ALAKNANDA AT DEVPRAYAG I&D
ABSTRACT OF COST FOR LAYING OF SEWER AND APPURTENANT WORKS
J.E A.E.
TOTAL 0.00
Assistant Enginner
DEVPRAYAG SEWERAGE SCHEME
Total 1644.83
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
Assistant Engineer
4.DESIGN OF RISING MAINS:
A)FROM BHAJAN ASHRAM SEWAGE PUMPING STATION
Design period 30 Years
a)Average discharge to be pumped 206.28 KLD
Or 143.25 LPM
Or 2.39 LPS
b)Peak discharge to be pumped 618.84 KLD
Or 429.75 LPM
Or 7.16 LPS
1Average Pumping over the years 75% of the theoritical quantity to be
pumped
FOR
EXTENTION OF SEWER IN 56 SUBHASH ROAD
1 2 3
1 Cost of sewer laying 425000
Subtotal 425000
Total 425000
APPROVED LABOUR RATES( S.E./GM 9th circle peyjal nigam,Indiranagar Dehradun
vide letter no. 2308/karyalay aadesh/20 dated 30/05/06)
9 Item Rate Karanprayag
1 Unskilled Labour - --- Beldar, Chaukidar,
Waterman, Majdoor, Helper, Safai Nayak.Bhisti 92.00 92.00
2 Semi Skilled Labour ----- Hole driller, Rock cutter 112.00 112.00
3 Skilled Labour --- Mistri, Mason, Carpanter,
Blacksmith, Plumber,painter,welder. 163.00 163.00
4 Other Labours
Material
Polling boards 7.2
Walers 1.69
Ballies 72
For 5 Times
For 1 Time
Net Cost of Material (Deduct 25% as
salvage value)
a)labour for fixing
Carpenter 5 Each
Mazdoor 10 Each
Spikes
b) labour for Dismentling
Carpenter 2.5 Each
Mazdoor 5 Each
Sundries
Sub Total
Total
Add 10% for CP
Sub Total
Rate/Sqm 27889.97/90=309.8
9
say
16 Closed timbering (3.00-6.00)
Detail for 90 sqm
Material
Polling boards 9
Walers 2.02
Ballies 72
For 5 Times
For 1 Time
Net Cost of Material (Deduct 25% as
salvage value)
a)labour for fixing
Carpenter 7.5 Each
Mazdoor 15 Each
Spikes
b) labour for Dismentling
Carpenter 3.75 Each
Mazdoor 7.5 Each
Sundries
Sub Total
Total
Add 10% for CP
Sub Total
Rate/Sqm 35301.86/90=392.2
4
say
17 Dismentling of all type of road surface
a) Bituminuous
Detail for 10 Sqm
Labour Beldar 4
Sundries job
Total
10% CP
Total
Hence rate per sqm=
b)labour
1 Mistri 0.5
2 Mason 1.5
3 Beldar 14
4 Coolie 14
5 Bhisti 7
6 Black Smith 0.5
7 Sundries job
Total (Labour)
Total
Add 10% CP
Total
Grand total
Hence Rate/Cum
Add Cartage
Cement 6.45x11.05=
sand 0.45x1519.80=
shingle 0.90x771.00=
total
Add 10% CP
total
Hence Rate/Cum
Add 10% CP
Grand total
Hence Rate/Cum
Add Cartage
Cement 3.45x11.05=
sand 0.48x1519.80=
shingle 0.94x771.0=
total
b)labour
1 Mistri 0.5
2 Mason 1.5
3 Beldar 14
4 Coolie 14
5 Bhisti 7
6 Black Smith 0.5
7 Sundries job
Total (Labour)
Cost of Centering Shuttring with Extra
Labour
Black Smith 14
Cost of Binding Wire
Add 10% CP
Total
Hence Rate/Cum
Add Cartage
Cement 8.58x11.05=
sand 0.45x1519.80=
Grit 0.90x1613.40=
total
b)labour
1 Mistri 0.5
2 Mason 1.5
3 Beldar 14
4 Coolie 14
5 Bhisti 7
6 Black Smith 0.5
7 Sundries job
Total (Labour)
Cost of Centering Shuttring with Extra
Labour
Black Smith 14
Cost of Binding Wire
Add 10% CP
Total
Hence Rate/Cum
Add Cartage
Cement 8.58x11.05=
sand 0.45x1519.80=
Grit 0.90x1613.40=
total
CP
TOTAL
RATE/CUM 3465.42/2.83
cement 1.76x11.05=
sand 0.35x771.00=
stone 1.1x771=
total
Total
Total
iv) Bailing out of water etc including
Dismentling &relaying of GI Pipe 15 mm dia
as per site condition job
Total i+ii+iii+iv=
38 MS Work in RCC
Detail for 50Kg
Material
Steel 50
Wastage 2.50%
Total
Add 10% CP
Total
Labour
Blacksmith 1
Coolie 1
T&P Job
Total
Add 10%CP
Total
RATE /QTL (1804.0+342.10)x2=
SAY
add cartage
Steel 1.05x22.10=
Total
Say
39 MS Work in heavy sections
Detail for 50Kg
Material
Steel 50
Wastage 2.50%
Total
Add 10% CP
Total
Labour
Blacksmith 1
Hammerman 1
Coolie 1
Hoisting and welding Job
Coal and t&p Job
Total
Add 10%CP
Total
RATE /QTL (2029.50+624.36)x2
=
SAY
add cartage
Steel 1.05x22.10=
Total
say
40 BW 1:5 in plinth and foundation
Detail for 10 cum
a)Materials
Cement 15
sand 2.5
Bricks 5000
b)labour
Mistri 0.5
Mason 8
Mazdoor 8
Coolie 8
Bhisties 2
T&P etc job
TOTAL
Add 10%CP
Total
Rate/cum=
Add cartage
cement1.50x11.05=
sand0.25x771.0=
Bricks 1x3027.75=
total
say
41 Same as above but 1.50-3.00 m
Rate as above
Add 3% Extra on labour=
total
say
42 Same as above but 3.00-4.50 m
Rate as above
Add 3% Extra on labour=
total
say
43 Same as above but 4.50-6.00 m
Rate as above
Add 3% Extra on labour=
total
say
44 Same as above but 6.00-7.50 m
Rate as above
Add 3% Extra on labour=
total
say
45 BW 1:3 in plinth and foundation
Detail for 10 cum
a)Materials
Cement 22.5
sand 2.25
Bricks 5000
SUBTOTAL
b)labour
Mistri 0.5
Mason 8
Mazdoor 8
Coolie 8
Bhisties 2
T&P etc job
SUBTOTAL
Add 10%CP
Total
Rate/cum=
Add cartage
cement2.25x11.05=
sand0.225x771.0=
Bricks 1x3027.75=
total
say
46 Same as above butr 1.50-3.00 m
Rate as above
Add 3% Extra on labour=
total
say
47 Same as above butr 3.00-4.50 m
Rate as above
Add 3% Extra on labour=
total
say
48 Same as above butr 4.50-6.00 m
Rate as above
Add 3% Extra on labour=
total
say
49 PC Plaster 12 mm thick1:3
Detail for 10sqm
Material
Cement 1.45
Sand 0.15
SUBTOTAL
Labour
Racking and washing surface
Mason 0.25
Coolie 0.25
Bhisties 0.1
Plastering
Mason 0.75
Coolie 0.75
Bhisties 0.25
Scafolding job
Total
10%CP
Total
Rate/SQM
Cartage
cement 0.14x11.05=
sand 0.015x771.0=
Rate/SQM
Say
50 Flush Pointing 1:2
Detail for 10sqm
Material
Cement 0.6
Sand 0.04
SUBTOTAL
Labour
Racking and washing surface
Mason 1.75
Coolie 1.75
Bhisties 0.35
Total
10%CP
Total
Rate/SQM
Deduction
Mason 0.33
Coolie 0.33
Total
10%CP
Total
Deduction/Sqm
Over all Rate/Sqm
Cartage
cement 0.06x11.05=
sand 0.044x771.0=
Rate/SQM
Say
51 Same as above but 1.50-3.00 m BGL
Rate as above
Add 3% Extra on labour=
total
say
52 Same as above but3.00-4.50 m BGL
Rate as above
Add 3% Extra on labour=
total
53 Supply of all material T&P and disilting of
existing drain including disposal of malwa
Labour
Mazdoor 2
For disposal Job
T&P
Total
10%CP
Total
SAY
54 Fixing of steps
For 10 nos
Material
Cement,sand grit Job
Labour
Mason 1
Mazdoor 1
Sundries
Total
10%CP
Total
Rate/footstep=
Say
Cutting of D.I. Pipe 300 mm dia
Detail for 1 Cut for 200 mm dia
Labour
Fitter 0.16666667
Beldar 0.16666667
Sundries
Add 10 % C.P.
Total
Cost for 300 mm dia pipe 300/200*84.18
55
Laying and Jointing 300 mm dia D.I. pipe
Labour
Fitter 0.5
Joinor Fitter 0.5
Beldar 4
Sundries
Add 10 % CP
Add 10 % CP
Rate per M
Add 10 % CP
Rate per Cum
58 Desmentilling of CC Flooring
Details for 10 Sqm
Majdor 1
Coolie 1
Sundries
Add 10 % CP
59 Desmentilling of RCC
Details for 10 Cum
Majdor 14
Coolie 14
Blacksmith 3.33
Sundries
Add 10 % CP
Material
Polling boards 1500 108000.0
7.2 Cum 0 0
Walers 2200
1.69 Cum 0 37180.00
Ballies 72 M 45.00 3240.00
148420.0
For 5 Times 0
For 1 Time 29684.00
Net Cost of Material (Deduct 25% as
salvage value) 22263.00
a)labour for fixing
Carpenter 5 Each 163 815.00
Mazdoor 10 Each 92 920.00
Spikes LS 166.52
b) labour for Dismentling
Carpenter 163.0
2.5 Each 0 407.50
Mazdoor 5 Each 92.00 460.00
Sundries LS 40.78
Sub Total 2809.80
Total 25072.80
Add 10% for CP 2507.28
Sub Total 27580.08
Rate/Sqm 27580.08 /90 = 306.45
say 306.40
1 Closed timbering
2 (3.00-6.00)
Detail for 90 sqm
Material
Polling boards 1500 135000.0
9 Cum 0 0
Walers 2200
2.02 Cum 0 44440.00
Ballies 72 M 45.00 3240.00
182680.0
For 5 Times 0
For 1 Time 36536.00
Net Cost of Material (Deduct 25% as
salvage value) 27402.00
a)labour for fixing
Carpenter 7.5 Each 163 1222.50
Mazdoor 15 Each 92 1380.00
Spikes LS 237.04
b) labour for Dismentling
Carpenter 163.0
3.75 Each 0 611.25
Mazdoor 7.5 Each 92.00 690.00
Sundries LS 118.94
Sub Total 4259.73
Total 31661.73
Add 10% for CP 3166.17
Sub Total 34827.91
Rate/Sqm 34827.91 /90 = 386.98
collars 16 nos@0.07q=1.12qtl
b) Materials
cement 0.704 bag 180 126.72
Coarse sand 0.05 cum 285 14.25
Spun Yarn 1.6 kg 20 32.00
c)Labour
Mistri 1 Each 154 154.00
Mason 3 Each 154 462.00
Mazdoor 6 Each 84 504.00
Bhisties 1 Each 84 84.00
Watchmen 3 Each 84 252.00
d)Miscellaneous
i)Excavation
below invert job LS 184.80
ii) Testing job LS 134.40
iii) Sundries job LS 235.20
Total 2183.37
Add 10% for CP 205.67
Total 2389.04
Rate /m= 2389.04/32 74.66
say 74.65
site rate add cartage
cement 0.704 bag/32 @29.49/bag=
0.65
sand0.05cum/32x957.80/cum=
1.49
pipe etc0.33x90.96= 30.02
Site rate 106.81
say 106.80
1 Same as above but 1.50-3.00 m BGL
6
Rate as above 106.80
add 6.45% extra on labour
4.46
total 111.26
say 111.25
1 Carting of DI PipeS&S LA from site
7 store to site of work,lowering true to
alignment ,laying jointing and testing
but excluding the cost of trenches and
cutting of pipes etc for making up
lengths and making joints
job LS 203.90
Total i+ii+iii+iv = 672.90
say 672.90
3
3 MS Work in RCC
Detail for 50Kg
Material
Steel 50 KG 37 1850.00
Wastage 2.50
% 46.25
Total 1896.25
Add 10% CP 189.63
Total 2085.88
Labour
Blacksmith 1 Each 163 163.00
Coolie 1 Each 92 92.00
T&P Job LS 25.49
Total 280.49
Add 10%CP 28.05
Total 308.54
RATE /QTL 2085.88 + 308.54 )x 2 = 4788.82
SAY say 4788.80
add cartage
Steel = 1.05 x 104.70 109.94
Total 4898.74
Say say 4898.70
3
4 MS Work in heavy sections
Detail for 50Kg
Material
Steel 50 KG 37 1850.00
Wastage 2.50
% 46.25
Total 1896.25
Add 10% CP 189.63
Total 2085.88
Labour
Blacksmith 1 Each 163 163.00
Hammerman 1 Each 92 92.00
Coolie 1 Each 92 92.00
Hoisting and welding Job LS 135.94
Coal and t&p Job LS 25.49
Total 508.42
Add 10%CP 50.84
Total 559.27
RATE /QTL 2085.88 + 559.27 )x 2 = 5290.28
say 5290.30
add cartage
Steel = 1.05 X 43.63 )x 2 = 91.61
Total 5381.91
say 5381.90
3
5 BW 1:5 in plinth and foundation
Detail for 10 cum
a)Materials
Cement 15 bag 180 2700.00
sand 2.5 cum 250 625.00
Bricks 5000 nos 2.3 11500.00
14825.00
b)labour
Mistri 0.5 each 163 81.50
Mason 8 163 1304.00
Mazdoor 8 92 736.00
Coolie 8 92 736.00
Bhisties 2 92 184.00
T&P etc job LS 84.96
TOTAL 3126.46
Add 10%CP 1525.15
Total 19476.61
Rate/cum= 1947.66
Add cartage
cement = 1.5 X 43.63 = 65.44
sand = 0.25 1800.4
X 0 = 450.10
Bricks = 1 1323.0
X 0 = 1323.00
total 3786.20
say 3786.20
3 Same as above but
6 1.50-3.00 m
Rate as above 3786.20
Add 3% Extra on labour= 9.38
total 3795.58
say 3795.60
3 Same as above but
7 3.00-4.50 m
Rate as above 3795.60
Add 3% Extra on labour= 9.38
total 3804.98
say say 3805.00
3 Same as above but 4.50-
8 6.00 m
Rate as above 3805.00
Add 3% Extra on labour= 9.38
total 3814.38
say say 3814.40
3 Same as above but
9 6.00-7.50 m
Rate as above 3814.40
Add 3% Extra on labour= 9.38
total 3823.78
say 3823.80
4
0 BW 1:3 in plinth and foundation
Detail for 10 cum
a)Materials
Cement 22.5 bag 250 5625.00
sand 2.25 cum 250 562.50
Bricks 5000 nos 2.2 11000.00
SUBTOTAL 17187.50
b)labour
Mistri 0.5 each 163 81.50
Mason 8 each 163 1304.00
Mazdoor 8 each 92 736.00
Coolie 8 each 92 736.00
Bhisties 2 each 92 184.00
T&P etc job LS 84.96
SUBTOTAL 3126.46
Add 10%CP 1468.90
Total 21782.86
Rate/cum= 2178.29
Add cartage
cement2.25x11.05= 2.25 X 43.63 = 98.16
sand0.225x771.0= 0.225 1800.4
X 0 = 405.09
Bricks 1x3027.75= 1 1323.0
X 0 = 1323.00
total 4004.53
say 4004.50
4 Same as above butr
1 1.50-3.00 m
Rate as above 4004.50
Add 3% Extra on labour= 9.38
total 4013.88
say say 4013.90
4 Same as above but in
2 3.00-4.50 m
Rate as above 4013.90
Add 3% Extra on labour= 9.38
total 4023.28
say say 4023.30
4 Same as above but in 4.50-6.00 m
3
Rate as above 4023.30
Add 3% Extra on labour= 9.38
total 4032.68
say say 4032.70
4 PC Plaster 12 mm
4 thick 1:3
Detail for 10 sqm
a)Material
Cement 250.0
1.45 bag 0 362.50
Sand 0.15 cum 250 37.50
SUBTOTAL 400.00
b)Labour
Racking and washing surface
Cartage
cement = 0.14 x 43.63 = 6.11
sand = 1800.4
0.015 x 0 = 27.01
Rate/SQM 106.02
say 106.00
4 Same as above but
5 1.50-3.00 m BGL
Rate as above 106.00
Add 3% Extra on labour= 0.89
total 106.89
Labour
Fitter 0.5 Each 163 81.50
Joinor Fitter 0.5 Each 112 56.00
Beldar 4 Each 92 368.00
Sundries L.S 62.02
567.52
Add 10 % CP
56.75
624.27
Rate/qtl 43.14
Rate per M for DI pipe 300 mm Dia (56
kg/M) 43.14 X 0.56 = 24.16
5 Desmentilling of 150 mm dia RCC
6 sewer line
Details for 30 m
Mason 2 Each 163 326.00
Majdor 4 Each 92 368.00
Sundries L.S. 211.55
905.55
Add 10 % CP
90.56
996.11
Rate per M 33.20
Shaft Variation
(1.0x1.20x1.50)
1 Excavation
Depth (0-1.5 m) 3.45 Cum 58.30 201.14
Brick work 1:5
Depth (0-1.5 m) 1.22 Cum 3786.20 4619.16
2 Plaster 1:3 4.4 Sqm 106.00 466.40
3 Footsteps 2 No 43.80 87.60
Total 5374.30
Say 6300.00
Shaft Variation
(1.0x1.20x3.0)
1 Excavation
Depth (1.5-3.0 m) 4.40 Cum 73.30 322.52
Brick work 1:5
Depth (1.5-3.0 m) 2.03 Cum 3795.60 7705.07
2 Plaster 1:3 (1.5-3.0 m) 4.4 Sqm 106.89 470.30
3 Footsteps 2 No 43.80 87.60
Total 8585.49
Say 10200.00
Shaft Variation
(1.0x1.20x4.5) Arch type
1 Excavation
Depth (3.0-4.5 m) 4.56 Cum 92.10 419.98
Brick work 1:5
Depth (3.0-4.5 m) 0.79 Cum 3805.00 2990.73
2 Plaster 1:3 (3.0-4.5 m) 2.5 Sqm 107.77 269.44
3 Footsteps 2 No 43.80 87.60
3767.74
Shaft Variation
(1.0x1.20x6.0) Arch type
1 Excavation
Depth (4.5-6.0 m) 4.56 Cum 134.20 611.95
Brick work 1:5
Depth (4.5-6.0 m) 0.79 Cum 3814.40 2998.12
2 Plaster 1:3 (4.5-6.0 m) 2.5 Sqm 108.66 271.65
3 Footsteps 2 No 43.80 87.60
3969.32
Prepared by: Lead varified and Checked: Approved:
recommended for
approval:
Connecting Chamber
(0.6x0.6x4.5)
1(i) Excavation in mixed soil
Depth (0-1.5 m) 9.38 Cum 58.30 546.85
(1.5-3.0) 6.00 Cum 73.30 439.80
(3.0-4.5) 3.38 Cum 92.10 311.30
(4.5-6.0) 0.90 Cum 134.20 120.78
Connecting Chamber
(0.6x0.6x3.0)
1(i) Excavation in mixed soil
Depth (0-1.5 m) 3.20 Cum 58.30 186.56
(1.5-3.0) 2.38 Cum 73.30 174.45
(3.0-4.5) 0.48 Cum 92.10 44.21
(ii) PCC 1:4:8 with 40 mm stone
ballast (3.0-4.5m) 0.32 Cum 1888.70 604.38
(iii) PCC 1:2:4 with 20 mm gauge
stone ballast
Depth (0-1.5 m) 0.10 Cum 4301.60 408.65
(1.5-3.0) 0.04 Cum 4313.60 172.54
(3.0-4.5) 0.04 Cum 4325.60 173.02
(iv) Brick work 1:3 for arch(1.5-3.0) 0.01 Cum 106.89 1.07
(v) Brick work 1:5
Depth (0-1.5 m) 1.07 Cum 3786.20 4051.23
(1.5-3.0) 1.12 Cum 3795.60 4251.07
(3.0-4.5) 0.08 Cum 3805.00 304.40
(vi) 12 mm thick plaster 1:3
Depth (0-1.5 m) 3.36 Cum 106.00 356.16
(1.5-3.0) 3.12 Cum 106.89 333.49
(ix) Fixing 56x56 cm MH cover and
frame 1.00 No L.S. 238.38
(x) Provide and fix CI footsteps 8.00 No 43.80 350.40
(xi) Unforseen items 345.3x 92 /99 320.88
Total 11970.92
Say 13400.00
Connecting Chamber
(0.6x0.6x1.5)
1(i) Excavation in mixed soil
Depth (0-1.5 m) 2.38 Cum 58.30 138.75
(1.5-3.0) 0.48 Cum 73.30 35.18
(ii) PCC 1:4:8 with 40 mm stone
ballast (1.5-3.0m) 0.32 Cum 1888.70 604.38
(iii) PCC 1:2:4 with 20 mm gauge
stone ballast
Depth (0-1.5 m) 0.04 Cum 4301.60 154.86
(1.5-3.0) 0.14 Cum 4313.60 603.90
(iv) Brick work 1:3 for arch(1.5-3.0) 0.01 Cum 106.89 1.28
(v) Brick work 1:5
Depth (0-1.5 m) 1.06 Cum 3786.20 4013.37
(1.5-3.0) 0.08 Cum 3795.60 303.65
(vi) 12 mm thick plaster 1:3
Depth (0-1.5 m) 2.88 Cum 106.00 305.28
(ix) Fixing 56x56 cm MH cover and
frame 1.00 No L.S. 238.38
(x) Provide and fix CI footsteps 3.00 No 43.80 131.40
(xi) Unforseen items 206.45x 92 /99 191.85
Total 6722.30
Say 7300.00
Shaft Variation
(0.6x0.6x3.0)
1 Excavation
Depth (1.5-3.0 m) 1.59 Cum 58.30 92.70
Brick work 1:5
Depth (1.5-3.0 m) 0.76 Cum 3795.60 2884.66
2 Plaster 1:3 (1.5-3.0 m) 2.4 Sqm 106.89 256.53
3 Footsteps 2 No 43.80 87.60
Total 3321.48
Say 3900.00
Shaft Variation
(0.6x0.6x1.5)
1 Excavation
Depth (0.0-1.5 m) 1.59 Cum 58.30 92.70
Brick work 1:5
Depth (0.0-1.5 m) 0.76 Cum 3786.20 2877.51
2 Plaster 1:3 (0.0-1.5 m) 2.4 Sqm 106.00 254.40
3 Footsteps 2 No 43.80 87.60
Total 3312.21
Say 3900.00
Prepared by: Lead varified and Checked: Approved:
recommended for
approval:
TECHNICAL NOTES
1.0 POPULATION FORECAST :-
The Census for Deoprayag town in district Tehri Garhwal in different years
are given as below:-
Year Census
1951 1535
1961 1819
1971 2107
1981 2230
1991 2703
2001 2769
The base, mid and design years for this project are adopted as 2011, 2026 and 2041
respectively. Based on the above census various methods are used to forecast the
population of the town for base, mid and design years.
P n = P + ni
n = no of decades.
here P = 2769
Say i = 247
P n = P(1+i/100)n
Population for the year 2026 = 2769+247 x 2.5 + 2.5(1+2.5)/2 x (-54) = 3150
Bhagirathi and as well as holy Ganga. Previously due to absence of any motor road
bridge in Devprayag over Ganga and as well as on Alaknanda, the only way to Bah
bazaar was through the suspension bridges. However during the last five years a motor
bridge was constructed over holy river Ganga due to which the whole of the town is
now connected by motor road and due to the fact the town is growing very fast. Hence
geometrical increase method is considered best suited in this situation and thus
adopted
adjoining Devprayag. The work is expected to start by April 2006 by NHPC. Due to
this reason , nearly 7000 people will also be added to the population of Devprayag
town as persons related with construction of Dams will stay in the town for nearly
next 16 years. This fact is also verified by Executive Officer, Nagar Panchayad
also considered.
Moreover Devprayag is situated on Rishikesh- Badrinath motor road. It
is also an important town due to its situation at the conjunction of Alaknanda and
Bhagirathi . After the conjunction the river becomes holy Ganga. Thus it is the starting
point of holy Ganga. A large number of people visit the town throughout the year.
population.
Thus the total base, mid and design year population forecast adopted is as
follows:-
The rate of water supply has been adopted as 135 lpcd plus 15% provision for
wastages. The other factors are adopted as per CPHEEO Manual on Sewerage and
Sewage Treatment.
3. DESIGN OF SEWERS:-
The Sewers are proposed to intercepted all the drains polluting the rivers as
possible . The Sewers are design for 30 years design period . The factors are taken
as follows :-
6. DESIGN OF SUMP
A. AT BAH BAZAR PUMPING STATION:-
Sump is design for the year 2041 for storage of 3.75 min of peak discharge as per
design criteria = 1762.56 kld
1. Storage capacity for 3.75 min = 1762.56x3.75 = 4.59 KL
24x60
However as the site is situated in hilly region and flow is very less hence sump of
capacity for 30 min storage of peak discharge has been adopted
Thus Storage capacity for 30 min = 1762.56x30 = 36.72 KL
24x60
Adopting 3.50 M dia sump depth of storage = 36.72/(3.502 x3.14/4) = 3.81 M
Say 4.00 M
Minimum depth required for submersible pumping plants = 1 M
Say 4.00 M
Minimum depth required for submersible pumping plants = 1 M
Say 4.00 M
Minimum depth required for submersible pumping plants = 1 M
Assistant Engineer
DEVPRAYAG SEWERAGE SCHEME
PROJECT REPORT
1. AUTHORITY :
This scheme has been prepared under Ganga Action Plan as per instructions
of Managing Director, Uttaranchal Peyjal Nigam, Dehradun vide his letter
no.1796/Ganga karya Yojona dated 20-12-2005 (Annexure no.1).
Devprayag is a town of District Tehri situated in the valley adjoining the river
Alaknanda and Bhagirathi on Rishkesh – Badrinath motor road at a distance of 70 Km
from Rishkesh. It has a great pilgrimage importance due to Sangam of Alaknanda and
Bhagirati and formation of river the Ganga downstream. Devprayag town has been
divided into three areas which are separated from each other by the holy rivers. The
first part is towards Srinagar and enclosed by Bhagirathi and Alaknanda, in this area
Teshil and main Deoprayag town is situated. The second part is enclosed by
Alaknanda and Ganga and is know as Bah bazaar area. The third part is enclosed
between Bhagirathi and Ganga, this area is known as Santi Bazar area. All these areas
are marked on index plan. These areas are connected with each other only by means of
two suspension bridges on which only pedestrians can pass through.
3. INTRODUCTION :-
2. STP - 11.34
3. LCS - 56.70
4. Crematoria - 3.40
5. RFD - 5.67
6. Aforestation - 2.29
TOTAL - 354.94
As per the above schemes of I&D and STP the various drains which are
flowing towards and thus polluting the river were proposed to be tapped near river by
constructing 6 nala tapping arrangements and laying 100 mm CI class LA 915 metre
sewer upto six no. localized sewage treatment plants consisting of septic tank
followed by upflow filter as well as chlorinated chambers. Moreover as no land is
available for these STPs, thus these STPs were proposed in the bank of river below I
flood level. This project was not found feasible because of the availability of land as
well as the possibility of over flowing, leaking of septic tank and again polluting the
river ever after construction of these septic tanks.
The proposals of I&D and STP were also inspected by Additional Director,
National River conservation Directorate, Ministry of Environment and Forest Govt. of
India, New Delhi, who after inspection suggested that in this town there is a possibility
of using waste stabilization ponds. But this will require at least three pumping station
and extra I&D works. The best option seems to be using combination of imhoff tanks
and ever clean tanks which are claimed to be suitable for small communities and
working efficiently by Dr. I.C. Agarwal, Ex. Professor M N L R college Allahabad.
This suggestion was confirmed by his letter No. J-39011/1/2001 NRCD- II (Vol.-II)
dated 8.12.04. (Annexure -4)
The concept of ever clean tanks was examined for Deoprayag and the expert
Dr. I.C. Agarwal visited the town. However due to the very narrow streets in the town
as well as no other land availability for construction of ever clean tanks this proposal
was also not found feasible.
In continuation of efforts for finding most suitable proposals for I&D and STP
works for abatement of pollution of rivers Ganga at Deoprayag the General Manager
Ganga Pollution Control Unit Uttaranchal Peyjal Nigam, Srinagar camp Dehradun
also visited the town on 19.04.05. He also found that the proposals taken up in the
already submitted projects are not suitable as well as not fully sufficient. He
suggested that :
1. After tapping the drains in the area of Santi Bazar the flow is to be taken on right
bank of Ganga upto proposed STP site which is proposed near new Pauri road
bridge In this proposal a bridge for crossing of sewer over Ganga will be required
2. After tapping the drains of Main Bazar the flow is taken to a point from where it
can be connected to the sewer laid as above on the right bank. In this proposal a
bridge for crossing of sewer over Bhagirathi will be required.
3. Similarly after tapping the drains of Bah bazaar the flow can be diverted to
proposed sewage treatment plant site.
4. PROPOSALS :
Considering the above facts the only solution to above problems is to adopt
pumping in I&D works. Thus the following proposals were found best suitable and
adopted.
1. For Bah bazaar area the flow from drains after tapping is to be diverted to a
sewage pumping station downstream from where the sewage will be pumped to a
manhole on Bah Bazar-Pauri motor road from where the sewage will be taken to
proposed sewage treatment plant site near Pauri motor bridge.
2. For Main Bazaar or Beech Bazaar area the flow from drains after tapping is to be
diverted to a sewage pumping station near Sangam (Samsan Ghat) from where
the sewage will be pumped to the pumping station of Santi Bazaar . The
alignment of rising main is such that it will cross the Bhagirathi river along the
bridge on Srinagar- Rishikesh motor road. Thus no additional bridge for crossing
the sewer will be required.
3. For Santi Bazaar area the flow from drains after tapping is to be diverted to a
sewage pumping station near suspension bridge from where the sewage will be
pumped to the proposed STP site. In this proposal the alignment of rising main is
along motor road near the right bank of Ganga and it will cross the Ganga
through motor bridge on Deoprayag – Pauri motor road. Thus no additional
bridge for crossing the sewer will be required.
4. As the topography of the town is such that it is located on a very steep gradient
towards rivers, this causes pollution of river due to over flowing of drains due to
any hindrance and the over flow of waste water easily finds its way directly to the
river. Thus to check the pollution of river it is necessary that the waste water of
the town is to be tapped from the point of generation as much as possible. Thus
complete sewer system in all the main streets is proposed. These proposals were
also discussed with Nagar Panchayat Deoprayag officials who also found these
proposals best suitable as confirmed by letter No. 201/2005-06 Deoprayag dated
28-3-06 (Annexure -7 )
These discharge were measured in the month of March/April, 1996. it may vary
depending upon seasonal variation and floating population. These drains are
discharging sewage directly into the river. Drains No. 1 to 3 discharge into river
Alaknanda and drains 4 to 6 discharge into river Bhagirath. Thus the sewage of the
city is either polluting river or creating health hazard to the community directly.
Hence proper sewage and sanitation facilities must be provided to this town and only
after treatment, the sewage can be allowed to discharge into the river. As per the test
report of raw sewage BOD the results are as follows: (Annexure -8 )
Parameter Maximum Minimum
BOD mg/l 520 12
Suspended Solids mg/l 1020.30 74
The drainage system of the town is quite poor and cover part of town. The
system is inadequate to carry the storm water resulting flooding the streets. The
condition worsens during the dry weather flow. When sewage flows into the open
drains. During storms the rain water flows along the roads causing inconvenience to
the public. Newly developing areas do not have disposal dranins and presently water
seems to be soaked by the land.
6. POPULATION :
The Census for Deoprayag town in district Tehri Garhwal in different years
are given as below:-
Year Census
1951 1535
1961 1819
1971 2107
1981 2230
1991 2703
2001 2769
The base, mid and design years for this project are adopted as 2011, 2026 and
2041 respectively. Based on the above census various methods are used to forecast
the population of the town for base, mid and design years.
As the town is situated on all the banks of the river Alaknanda, Bhagirathi and
as well as holy Ganga. Previously due to absence of any motor road bridge in
Devprayag over Ganga and as well as on Alaknanda, the only way to Bah bazaar was
through the suspension bridges. However during the last five years a motor bridge was
constructed over holy river Ganga due to which the whole of the town is now
connected by motor road and due to the fact the town is growing very fast. Hence
geometrical increase method is considered best suited in this situation and thus
adopted.
Devprayag. The work is expected to start by April 2006 by NHPC. Due to this reason
nearly 7000 people will also be added to the population of Devprayag town as
persons related with construction of Dams will stay in the town for nearly next 16
years. This fact is also verified by Executive Officer, Nagar Panchayad Devprayag,
an important town due to its situation at the conjunction of Alaknanda and Bhagirathi .
After the conjunction the river becomes holy Ganga. Thus it is the starting point of
holy Ganga. A large number of people visit the town throughout the year. Thus a
follows:-
7. DESIGN CRITERIA :
The design criteria for design of sewerage schemes has been adopted as
circulated by UP Jal Nigam head quarter circular No. 1067/PPRD/ Design Criteria
dated 25.07.2002 and as modified by Managing Director, Uttaranchal Peyjal
Nigam,Dehradun
i) INTERCEPTING FACTOR :
It has been taken that 80% of the theoretical average daily water supply will
find its way into the sewers. The rate of water supply is taken as 135 lpcd plus 15%
provision for losses.
The ratio between peak and average quantity of the flow passing through the
sewer are to be taken as 3.0for population upto 20000, 2.50 population more than
20000 and upto 50000, 2.25 for population more than 50000 and upto 7.5 lacs and for
population above 7.50lacs it is taken as 2.00. The value of peak factor shall depend
upon the contributory population and not upon the total designed population of the
town.
V = 1/n R2/3 S ½
Where V = Velocity in m/ sec.
S = Slope
n = 0.011 for RCC S&S and DI pipes as per CPHEEO Manual on sewerage
and sewage treatment.
The depth of flow is sewers upto 400 mm dia is kept as half full, for sewers
above 400 to 900 mm as two third full and for larger than 900 mm dia three forth full
at peak flow.
Velocity of flow in sewers at peak flow during dry weather for the ultimate
condition is to be taken as 0.80 meter per second subject to the condition that the
velocity shall not be less than 0.60 meter per second for present peak flow, otherwise
flushing is to be done. Maximum velocity in the sewers shall not be allowed to exceed
2.40 meters per second.
Minimum size of 150 mm dia sewer has been used. The RCC NP3, C.I S&S
class LA and D.I.S&S class K-7 pipes have been used as sewers based on topography
and strata of soil.
Sewer have been designed to lay with crown meeting crown and necessary
drop to be provided accordingly however is should be ascertained that the flow line
for sewer at the meeting point is such that back flow does not occur in them. A
minimum drop of 30 mm be assured at each sewer transition. Sewer transition, change
in size, shape and alignment.
Sewers as far as possible should be laid one meter below ground level,. In case
laying of sewers at depth less than one meter is necessary, proper concrete encasing be
provided to avoid any damage to the sewer. It should also be ensured that houses near
about it should be tapped into it.
viii) MANHOLE :
Timbering has been proposed for trench having depth more than 2.00 m and it
is proposed as open timbering upto 3.00 m depth whereas it is adopted as close
timbering below 3.00 m depth.
Lump sump provision has been made for dismantling and restatement of stone
masonry which will be required for laying of sewer.Lump sump provision for
diversion of path, shifting of water mains, which may come in the manholes has also
been made in the estimate.
12. GODOWNS :
Provision of Rs. 72000.00 for godown has been made for 24 months at the rate
of Rs.3000.00 Per Month.
The provision for work charged staff and contingencies has been made @2%
and 3% respectively as per prevailing norms. Provision for supervision @12.5% have
also been made in the estimate to be submitted to Govt. of Uttaranchal. The cost
worked out to be Rs. 796.45 Lakhs.
However as the project is proposed to be submitted to NRCD Govt. of India
and as per present policy the cost sharing basis between State Govt. Versus Central
Govt. is 30:70. Considering this the project cost has been worked out on 8% centage
on cost of work which works out to be Rs. 726.85 Lakhs. Out of this Rs. 508.795
Lakhs will be beared by Govt. of India and balance Rs. 796.45 – Rs. 508.795 =
Rs. 287.655 Lakhs will be beared by Govt. of Uttaranchal.
14. MAINTENANCE:
16. INFLATION :
No provision has been made in the DPR for escalation as per NRCD
Guidelines However revised estimate will be prepared, if required, depending upon
the actual price escalation at the time of completion of the project.
17. ECONOMICS :
18. CONCLUSION :
(V.C.Purohit)
Executive Engineer
Counter Signed
(R.N. Verma)
General Manager