ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 206 - WATER BOUND MACADAM BASE WITH COARSE AGGREGATES (CLASS B)
ASSUMED DAILY (8 HOURS) PROGRESS 100 CM

MANPOWER
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Site Engineer 1 2.00 183.00 366.00

2 Foreman Earthwork 1 4.00 66.00 264.00

3 Supervisor 1 4.00 66.00 264.00

4 Surveyor 1 4.00 74.00 296.00

5 Asst. Surveyor 1 4.00 66.00 264.00

6 Helper 4 8.00 58.75 1,880.00

7 Labour 10 8.00 58.75 4,700.00


Total Manpower Charges Rs. 8,034.00

EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Grader (135 H.P.) 1 2.00 2,294.00 4,588.00

2 Combination Roller (18 T) 1 6.00 2,285.00 13,710.00

3 Water Lorry (Local)(12000 L) tow type 1 8.00 616.00 4,928.00

4 Pump 4" Delivery (Diesel) 1 8.00 1,606.00 12,848.00

5 Front End Loader (Cap 1.5 Cum) 1 3.00 1,861.00 5,583.00

6 Dumper Truck (Imported) 18 Ton 2 5.00 1,972.00 19,720.00


Total Equipment Charges Rs. 61,377.00

MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

1 Aggregate (Material at quarry site) Loose Factor=1.25 Cum 125.00 459.10 57,386.88

2 Carriage (220 KM) without profit and overheads Cum 125.00 1,339.75 167,469.08

3
Stone Dust (Material at site) @ 16 % of Agg. Cum 20.00 618.37 12,367.49

4 Water 1000 L 65.00 30.00 1,950.00

Total Material Charges Rs. 239,173.45

SUMMARY
1 Basic cost for 100 CM Rs. 308,584.45
2 Basic cost per CM Rs. 3,085.84
3 Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 771.46
TOTAL COST PER CM Rs. 3,857.31
TOTAL COST PER Cft Rs. 109.23
ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 104 - NATURAL GROUND COMPACTION

ASSUMED PROGRESS 3500 SM

MANPOWER

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Supervisor 1 10.00 66.00 660.00

2 Asst. Surveyor 1 2.00 66.00 132.00

3 Helper 2 2.00 58.75 235.00

4 Labour 2 8.00 58.75 940.00

Total Manpower Charges Rs. 1,967.00

EQUIPMENT

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Grader (135 H.P.) 1 4.00 2,294.00 9,176.00

2 Combination Roller (10-12 T) 1 9.00 2,023.00 18,207.00

3 Water Lorry (Local)(4000 L) tow type 3 8.00 200.00 4,800.00

4 Pump 4" Delivery (Diesel) 1 2.00 106.00 212.00

Total Equipment Charges Rs. 32,395.00

MATERIAL

Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

1 Water 1000 L 105.00 30.00 3,150.00

Total Material Charges Rs. 3,150.00

SUMMARY

Basic cost for 3500 SM Rs. 37,512.00


Basic cost per SM Rs. 10.72
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 2.68
TOTAL COST PER SM Rs. 13.40
ITEM: # 106 a - EXCAVATE UNSUITABLE FOR SURPLUS COMMON MATERIAL

ASSUMED PROGRESS 450 CM

MANPOWER

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Site Engineer 1 2.00 183.00 366.00

2 Supervisor 3 8.00 66.00 1,584.00

3 Surveyor 1 4.00 74.00 296.00

4 Helper 3 8.00 58.75 1,410.00

Total Manpower Charges Rs. 3,656.00

EQUIPMENT

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Bull-Dozer (120 H.P.) 1 6.00 1,210.00 7,260.00

2 Front End Loader (Cap. 2.5 cum) 2 6.00 2,085.00 25,020.00

3 Dumper (Cap. 18 T) 6 6.00 1,972.00 70,992.00

Total Equipment Charges Rs. 103,272.00

MATERIAL

Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

Total Material Charges Rs. -

SUMMARY

Basic cost for 450 CM Rs. 106,928.00


Basic cost per CM Rs. 237.62
Add Contractor's Over Heads @ 7 % & Profits @ 9 % Rs. 38.02

TOTAL COST PER CM Rs. 275.64

TOTAL COST PER Cft Rs. 7.81

Say Rs. 8.00


ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 107 di - GRANULAR BACKFILL WITH SAND


ASSUMED PROGRESS 50 CM

MANPOWER
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Site Engineer 1 2.00 183.00 366.00

2 Foreman Concrete 1 2.00 71.00 142.00

3 Supervisor 1 8.00 66.00 528.00

4 Labour 4 8.00 58.75 1,880.00


Total Manpower Charges Rs. 2,916.00

EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Front End Loader (Cap. 1.5 cum) 1 1.00 1,861.00 1,861.00

2 Tandem Vibratory Roller (Cap. 1.5 T) 1 5.00 564.00 2,820.00

3 Water Lorry (Local)(4000 L) tow type 1 4.00 200.00 800.00

4 Pump 4" Delivery (Diesel) 1 2.00 106.00 212.00

Total Equipment Charges Rs. 5,693.00

MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

1 Sand (Local) Cm 60.00 353.15 21,189.00

2 Water 1000 L 9.00 30.00 270.00


Total Material Charges Rs. 21,459.00

SUMMARY
Basic cost for 50 CM Rs. 30,068.00
Basic cost per CM Rs. 601.36
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 150.34
TOTAL COST PER CM Rs. 751.70
ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 109 a - SUBGRADE PREPARATION


ASSUMED DAILY (8 HOURS) PROGRESS 1450 SM

MANPOWER

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Site Engineer 1 2.00 183.00 366.00

2 Foreman Earthwork 1 4.00 66.00 264.00

3 Supervisor 1 4.00 66.00 264.00

4 Asst. Surveyor 1 4.00 66.00 264.00

5 Helper 2 4.00 58.75 470.00

6 Labour 2 4.00 58.75 470.00

Total Manpower Charges Rs. 0.00

EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
2 Grader (135 H.P.) 1 4.00 3,150.00 12,600.00

3 Combination Roller (Cap. 10-12 T) 1 8.00 2,545.00 20,360.00

5 Water Lorry (Local)(4000 L) tow type 1 4.00 1,290.00 5,160.00

6 Pump 4" Delivery (Diesel) 1 5.00 0.00

Total Equipment Charges Rs. 38,120.00

MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

1 Water 1000 L 4.00 500.00 2,000.00

Total Material Charges Rs. 2,000.00

SUMMARY
Basic cost for 1450 SM Rs. 40,120.00
Basic cost per SM Rs. 50.78
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 12.70

TOTAL COST PER SM Rs. 63.48


ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 201 (a)REUSE OF BROKEN PAVEMENT MATERIAL AS SUBBASE

ASSUMED DAILY (8 HOURS) PROGRESS 480 CM

MANPOWER

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Site Engineer 1 4.00 183.00 732.00

2 Foreman Earthwork 1 8.00 66.00 528.00

3 Supervisor 1 8.00 66.00 528.00

4 Surveyor 1 4.00 74.00 296.00

5 Asst. Surveyor 1 8.00 66.00 528.00

6 Helper 2 8.00 58.75 940.00

7 Labour 4 8.00 58.75 1,880.00

Total Manpower Charges Rs. 5,432.00

EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Grader(135 H.P) 2 6.00 2,294.00 27,528.00

2 Combination Roller (18 T) 2 8.00 2,285.00 36,560.00

3 Water Lorry (Local)(12000 L) tow type 2 6.00 616.00 7,392.00

4 Pump 4" Delivery (Diesel) 1 6.00 106.00 636.00

Total Equipment Charges Rs. 72,116.00

MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

1 Water 1000 L 90.00 30.00 2,700.00

Total Material Charges Rs. 2,700.00

SUMMARY
Basic cost for 480 CM Rs. 80,248.00
Basic cost per CM Rs. 167.18
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 41.80

TOTAL COST PER CM Rs. 209.98


ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 209a - BREAKING OF EXISITING ROAD PAVEMENT STRUCTURE

ASSUMED DAILY (8 HOURS) PROGRESS 187.5 CM

MANPOWER

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Supervisor 1 8.00 66.00 528.00

2 Asst. Surveyor 1 4.00 66.00 264.00

3 Helper 1 8.00 58.75 470.00

Total Manpower Charges Rs. 1,262.00

EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks

1 Bull-Dozer (200 H.P.) 1 8.00 3,315.00 26,520.00

Total Equipment Charges Rs. 26,520.00

MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

Total Material Charges Rs. 0.00

SUMMARY
Basic cost for 187.5 CM Rs. 27,782.00
Basic cost per CM Rs. 148.17
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 37.04

TOTAL COST PER CM Rs. 185.21


ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE

ITEM: # 209b - SCARIFICATION OF EXISTING ROAD PAVEMENT


ASSUMED DAILY (8 HOURS) PROGRESS 1500 SM

MANPOWER

Sr. # Description No. Hours Rate Amount (Rs.) Remarks


1 Supervisor 1 8.00 66.00 528.00

2 Asst. Surveyor 1 8.00 66.00 528.00

3 Helper 2 8.00 58.75 940.00

Total Manpower Charges Rs. 1,996.00

EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks

1 Bull-Dozer (200 H.P.) 1 8.00 3,315.00 26,520.00

Total Equipment Charges Rs. 26,520.00

MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks

Total Material Charges Rs. 0.00

SUMMARY
Basic cost for 1500 SM Rs. 28,516.00
Basic cost per SM Rs. 19.01
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 4.75

TOTAL COST PER SM Rs. 23.76