ITEM: # 206 - WATER BOUND MACADAM BASE WITH COARSE AGGREGATES (CLASS B)
ASSUMED DAILY (8 HOURS) PROGRESS 100 CM
MANPOWER
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Site Engineer 1 2.00 183.00 366.00
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Grader (135 H.P.) 1 2.00 2,294.00 4,588.00
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
1 Aggregate (Material at quarry site) Loose Factor=1.25 Cum 125.00 459.10 57,386.88
2 Carriage (220 KM) without profit and overheads Cum 125.00 1,339.75 167,469.08
3
Stone Dust (Material at site) @ 16 % of Agg. Cum 20.00 618.37 12,367.49
SUMMARY
1 Basic cost for 100 CM Rs. 308,584.45
2 Basic cost per CM Rs. 3,085.84
3 Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 771.46
TOTAL COST PER CM Rs. 3,857.31
TOTAL COST PER Cft Rs. 109.23
ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE
MANPOWER
EQUIPMENT
MATERIAL
SUMMARY
MANPOWER
EQUIPMENT
MATERIAL
SUMMARY
MANPOWER
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Site Engineer 1 2.00 183.00 366.00
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Front End Loader (Cap. 1.5 cum) 1 1.00 1,861.00 1,861.00
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
SUMMARY
Basic cost for 50 CM Rs. 30,068.00
Basic cost per CM Rs. 601.36
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 150.34
TOTAL COST PER CM Rs. 751.70
ROAD WORKS AT FAZAIA HOUSING SCHEME PHASE-1 RAIWAND ROAD LAHORE
MANPOWER
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
2 Grader (135 H.P.) 1 4.00 3,150.00 12,600.00
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
SUMMARY
Basic cost for 1450 SM Rs. 40,120.00
Basic cost per SM Rs. 50.78
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 12.70
MANPOWER
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
1 Grader(135 H.P) 2 6.00 2,294.00 27,528.00
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
SUMMARY
Basic cost for 480 CM Rs. 80,248.00
Basic cost per CM Rs. 167.18
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 41.80
MANPOWER
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
SUMMARY
Basic cost for 187.5 CM Rs. 27,782.00
Basic cost per CM Rs. 148.17
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 37.04
MANPOWER
EQUIPMENT
Sr. # Description No. Hours Rate Amount (Rs.) Remarks
MATERIAL
Sr. # Description Unit Qty. Rate Amount (Rs.) Remarks
SUMMARY
Basic cost for 1500 SM Rs. 28,516.00
Basic cost per SM Rs. 19.01
Add Contractor's Over Heads @ 15 % & Profits @ 10 % Rs. 4.75