ESTIMATE FOR

IMPROVEMENT TO MACNKADCHUAN CHECK DAM (REFILLING OF SCOURED EMBANKMENT) IN


BALANGIR BLOCK OF BALANGIR DISTRICT
Sl. Length Breadth Height
Items Nos. Quantity Unit Amount
No (mtr.) (mtr.) (mtr.)

1 Earth work in oridinary soil within 50m, initial lead and 1.5m, initial lift including
rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not
exceeding 0.3m in depth and as per direction of the Engineer-in-charge
Right Bank
RD 0 TO 90m 1,346.37 cum
RD 90 to 170m 1 x 80.00 x (3+18)/2 x 4.00 = 3,360.00 cum
Total = 4,706.37 cum
₹ 83.60 @ /cum 4,706.37 cum = ₹ 3,93,452.53
₹ 3,93,453.00

Junior Engineer Assistant Executive Engineer Superintending Engineer


M.I.Section,Balangir M.I. Sub-Division,Balangir M.I. Division,Balangir