Education Infrastructure “47 Schools” within the

Education Quality Activity


Bills of Quantities (Provisional) – Package 3 – LOT 3
e
(Kunene Region) at:
Jack Francis JSS

01 February 2011

commissioned by the Millennium Challenge Account Namibia


with funding from the Millennium Challenge Corporation
PROVISIONAL BILLS OF QUANTITIES

FOR

Education Infrastructure "47 School" within the Education Quality Activity

FOR

Millennium Challenge Account Namibia

ARCHITECTS QUANTITY SURVEYORS


Omugongo J V Omugongo J V
Joint Venture
47 Nelson Mandela Avenue 47 Nelson Mandela Avenue
Klein Windhoek Klein Windhoek
Windhoek
9000
Tel. +264 61 220081 Tel. +264(61) 220081
Fax: +264 61 221333 Fax: +264(61) 221333
e Mail: hugo@hugosarc.com e Mail: iyaloo@jonqs.com
Package 3 Lot 3

SECTION NO. 1

PRELIMINARIES

1
Package 3 Lot 3
Amount

SECTION NO. 1
PRELIMINARIES

The Tenderer is referred to the relevant Clauses in the separate


document Model Preambles for Trades (2008 Edition) and to the
Supplementary Preambles which are incorporated in this Bill.

PREAMBLES FOR TRADES

The Model Preambles for Trades (2008 edition) as published by


the Association of South African Quantity Surveyors shall be
deemed to be incorporated in these bills of quantities and no
claims arising from brevity of description of items fully described in
the said Model Preambles will be entertained

Supplementary preambles are incorporated in these bills of


quantities to satisfy the requirements of this project. Such
supplementary preambles shall take precedence over the
provisions of the said Model Preambles

The contractor's prices for all items throughout these bills of


quantities must take account of and include for all of the
obligations, requirements and specifications given in the said
Model Preambles and in any supplementary preambles

SECTION A - GENERAL CONDITIONS

1.0 - GENERAL PROVISIONS

1 Clause 1.1 - Definitions


Item

2 Clause 1.2 - Interpretation


Item

3 Clause 1.3 - Communications


Item

4 Clause 1.4 - Law and Language


Item

5 Clause 1.5 - Priority of Documents


Item

6 Clause 1.6 - Contract Agreement


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
2
Package 3 Lot 3
Amount

7 Clause 1.7 - Assigment


Item

8 Clause 1.8 - Care and Supply of Documents


Item

9 Clause 1.9 - Delayed Drawings or Instructions


Item

10 Clause 1.10 - Employer's Use of Contractor's Documents


Item

11 Clause 1.11 - Contractor's Use of Employer's Documents


Item

12 Clause 1.12 - Confidential Details


Item

13 Clause 1.13 - Compliance with Laws


Item

14 Clause 1.13 - Compliance with Laws

[a]Contractor to comply with the Namibia Environmental


Management Act No.7 of year 2007 as well as the Environmental
Assessment Policy of year 1995 by implementing the
Environmental Management Plans (EMP) documented separately
as part of this contract. Bidders are compelled to price this line
item in accordance with the total cost derived as per requirements
and instruction in Form: Environmental and Social Documents
accompanying these Bills.
Item

15 Clause 1.13 - Compliance with Laws

[b]Contractor to comply with the Namibia Public Health and Safety


Management Policy under Act No. 11 of year 2007 by
implementing the Public Health and Safety Awareness Plan
(PHSAP) documented separately as part of this contract.Bidders
are compelled to price this line item in accordance with the total
cost derived as per requirements and instruction in Form: Health
and Safety Documents accompanying these Bills.
Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
3
Package 3 Lot 3
Amount

16 Clause 1.14 - Joint and Several Liability


Item

2.0 - THE EMPLOYER

17 Clause 2.1 - Right of Access to the Site


Item

18 Clause 2.2 - Permits, Licences or Approvals


Item

19 Clause 2.3 - Employer's Personnel


Item

20 Clause 2.4 - Employer's Financial Arrangement


Item

2.0 - THE ENGINEER

21 Clause 3.1 - Engineer's Duties and Authority


Item

22 Clause 3.2 - Delegation by the Engineer


Item

23 Clause 3.3 - Instructions of the Engineer


Item

24 Clause 3.4 - Replacement of the Engineer


Item

25 Clause 3.5 - Determinations


Item

4.0 - THE CONTRACTOR

26 Clause 4.1 - Contractor's General Obligations


Item

27 Clause 4.2 - Performance Security


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
4
Package 3 Lot 3
Amount

28 Clause 4.3 - Contactor's Security


Item

29 Clause 4.4 - Subcontractors


Item

30 Clause 4.5 - Assignment of Bennefit of Subcontract


Item

31 Clause 4.6 - Co-operation


Item

32 Clause 4.7 - Setting Out


Item

33 Clause 4.8 - Safety Procedures


Item

34 Clause 4.9 - Quality Assurance


Item

35 Clause 4.10 - Site Data


Item

36 Clause 4.11 - Sufficiency of the Accepted Contract Amount


Item

37 Clause 4.12 - Unforseeable Physical Conditions


Item

38 Clause 4.13 - Rights of Way and Facilities


Item

39 Clause 4.14 - Avoidance of Interference


Item

40 Clause 4.15 - Access Route


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
5
Package 3 Lot 3
Amount

41 Clause 4.16 - Transport of Goods


Item

42 Clause 4.17 - Contractor's Equipment


Item

43 Clause 4.18 - Protection of the Enviroment


Item

44 Clause 4.19 - Electricity, Water and Gas


Item

45 Clause 4.20 - Employer's Equipment and Free-Issue Material


Item

46 Clause 4.21 - Progress Reports


Item

47 Clause 4.22 - Security of the Site


Item

48 Clause 4.23 - Contractor's Operations on Site


Item

49 Clause 4.24 - Fossils


Item

5.0 - NOMINATED SUBCONTRACTORS

50 Clause 5.1 - Definition of "nominated Subcontractor"


Item

51 Clause 5.2 - Objection to Nomination


Item

52 Clause 5.3 - Payments to nominated Subcontractors


Item

53 Clause 5.4 - Evidence of Payments


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
6
Package 3 Lot 3
Amount

6.0 - STAFF AND LABOUR

54 Clause 6.1 - Engagement of Staff and Labour


Item

55 Clause 6.2 - Rates of Wages and Conditions of Labour


Item

56 Clause 6.3 - Persons in the Service of Employer


Item

57 Clause 6.4 - Labour Laws


Item

58 Clause 6.5 - Working Hours


Item

59 Clause 6.6 - Facilities for Staff and Labour


Item

60 Clause 6.7 - Health and Safety


Item

61 Clause 6.8 - Contractor's Superintendence


Item

62 Clause 6.9 - Contractor's Personnel


Item

63 Clause 6.10 - Records of Contractor's Personnel and Equipment


Item

64 Clause 6.11 - Disorderly Conduct


Item

7.0 - PLANT, MATERIALS AND WORKMANSHIP

65 Clause 7.1 - Manner of Execution


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
7
Package 3 Lot 3
Amount

66 Clause 7.2 - Samples


Item

67 Clause 7.3 - Inspection


Item

68 Clause 7.4 - Testing


Item

69 Clause 7.5 - Rejection


Item

70 Clause 7.6 - Remedial Work


Item

71 Clause 7.7 - Ownership of Plant and Material


Item

72 Clause 7.8 - Royalties


Item

8.0 - COMMENCEMENT, DELAYS AND SUSPENSION

73 Clause 8.1 - Commencement of Works


Item

74 Clause 8.2 - Time for Completion


Item

75 Clause 8.3 - Programme


Item

76 Clause 8.4 - Extension of Time for Completion


Item

77 Clause 8.5 - Delays cuased by Authorities


Item

78 Clause 8.6 - Rate of Progress


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
8
Package 3 Lot 3
Amount

79 Clause 8.7 - Delay Damages


Item

80 Clause 8.8 - Suspension of Work


Item

81 Clause 8.9 - Consequences of Suspension


Item

82 Clause 8.10 - Payment for Plant and Materials in Event of


Suspension
Item

83 Clause 8.11 - Prolonged Suspension


Item

84 Clause 8.12 - Resumption of Work


Item

9.0 - TESTS ON COMPLETION

85 Clause 9.1 - Contractor's Obligation


Item

86 Clause 9.2 - Delayed Tests


Item

87 Clause 9.3 - Retesting


Item

88 Clause 9.4 - Failure to Pass Tests on Completion


Item

10.0 - EMPLOYER'S TAKING OVER

89 Clause 10.1 - Taking Over of the Works and Sections


Item

90 Clause 10.2 - Taking Over of Parts of the Works


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
9
Package 3 Lot 3
Amount

91 Clause 10.3 - Interference with Tests on Completion


Item

92 Clause 10.4 - Surfaces Requiring Reinstatement


Item

11.0 - DEFECTS LIABILITY

93 Clause 11.1 - Completion of Outstandin g Work and Remedying


Defects
Item

94 Clause 11.2 - Cost of Remedying Defects


Item

95 Clause 11.3 - Extension of Defects Notification Period


Item

96 Clause 11.4 - Failure to Remedy Defects


Item

97 Clause 11.5 - Removal of Defective Work


Item

98 Clause 11.6 - Further Tests


Item

99 Clause 11.7 - Right of Access


Item

100 Clause 11.8 - Contractor to Search


Item

101 Clause 11.9 - Performance Certificate


Item

102 Clause 11.10 - Unfulfilled Obligations


Item

103 Clause 11.11 - Clearance of Site


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
10
Package 3 Lot 3
Amount

12.0 - MEASUREMENT AND EVALUATION LIABILITY

104 Clause 12.1 - Works to be Measured


Item

105 Clause 12.2 - Method of Measurement


Item

106 Clause 12.3 - Evaluation


Item

107 Clause 12.4 - Ommisions


Item

13.0 - VARIATIONS AND ADJUSTMENTS

108 Clause 13.1 - Right to Vary


Item

109 Clause 13.2 - Value Engineering


Item

110 Clause 13.3 - Variation Procedure


Item

111 Clause 13.4 - Payment in Applicable Currencies


Item

112 Clause 13.5 - Provisional Sums


Item

113 Clause 13.6 - Daywork


Item

114 Clause 13.7 - Adjustments for Changes in Legislation


Item

115 Clause 13.8 - Adjustments for Changes in Cost


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
11
Package 3 Lot 3
Amount

14.0 - CONTRACT PRICE AND PAYMENTS

116 Clause 14.1 - The Contract Price


Item

117 Clause 14.2 - Advance Payment


Item

118 Clause 14.3 - Application for Iterim Payment Certificates


Item

119 Clause 14.4 - Schedule of Payments


Item

120 Clause 14.5 - Plant and Materials Intended for the Works
Item

121 Clause 14.6 - Issue of Interim Payment Certificates


Item

122 Clause 14.7 - Payment


Item

123 Clause 14.8 - Delayed Payment


Item

124 Clause 14.9 - Payment of Retention Money


Item

125 Clause 14.10 - Statement at Completion


Item

126 Clause 14.11 - Application for Final Payment Certificate


Item

127 Clause 14.12 - Discharge


Item

128 Clause 14.13 - Issue of Final Payment Certificate


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
12
Package 3 Lot 3
Amount

129 Clause 14.14 - Cessation of Employer's Liability


Item

130 Clause 14.15 - Currencies of Payment


Item

15.0 - TERMINATION BY EMPLOYER

131 Clause 15.1 - Notice to Correct


Item

132 Clause 15.2 - Termination by Employer


Item

133 Clause 15.3 - Valuation at Date of Termination


Item

134 Clause 15.4 - Payment after Termination


Item

135 Clause 15.5 - Empoyer's Entitlement to Termination


Item

16.0 - SUPSENSION AND TERMINATION BY CONTRACTOR

136 Clause 16.1 - Contractor's Entitlement to Suspend Work


Item

137 Clause 16.2 - Termination by Contractor


Item

138 Clause 16.3 - Cessasion of Work and Removal of Contractor's


Equipment
Item

139 Clause 16.4 - Payment on Termination


Item

17.0 - RISK AND RESPONSIBILITY

140 Clause 17.1 - Indemnities


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
13
Package 3 Lot 3
Amount

141 Clause 17.2 - Contractor's Care of the Works


Item

142 Clause 17.3 - Employer's Risks


Item

143 Clause 17.4 - Consequences of Employer's Risks


Item

144 Clause 17.5 - Intellectual and Industrial Property Rights


Item

145 Clause 17.6 - Limitation of Liability


Item

18.0 - INSURANCE

146 Clause 18.1 - General Requierments for Insurances


Item

147 Clause 18.2 - Insurance for Works and Contractor's Equipment


Item

148 Clause 18.3 - Insurance against Injury to Persons and Damage to


Property
Item

149 Clause 18.4 - Insurance for Contractor's Personnel


Item

19.0 - FORCE MAJEURE

150 Clause 19.1 - Definition of Force Majuere


Item

151 Clause 19.2 - Notice of Force Majuere


Item

152 Clause 19.3 - Duty to Minimise Delay


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
14
Package 3 Lot 3
Amount

153 Clause 19.4 - Consequences of Force Majuere


Item

154 Clause 19.5 - Force Majuere Affecting Subcontractor


Item

155 Clause 19.6 - Optional Termination, Payment and Release


Item

156 Clause 19.7 - Release from Performance under the Law


Item

20.0 - CLAIMS, DISPUTES AND ARBITRATION

157 Clause 20.1 - Contractors Claim


Item

158 Clause 20.2 - Appointment of the Dispute Adjudication Board


Item

159 Clause 20.3 - Failire to Agree Dispute Adjudication Board


Item

160 Clause 20.4 - Obtaining Dispute Adjudication Board's Decision


Item

161 Clause 20.5 - Amicable Settlement


Item

162 Clause 20.6 - Arbitration


Item

163 Clause 20.7 - Failure to Comply Dispute Adjudication Board's


Decision
Item

164 Clause 20.8 - Expiry of Dispute Adjudication Board's Appointment


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
15
Package 3 Lot 3
Amount

SECTION B - MODEL PRELIMINARIES

Model Preliminary Document can be purchased from the Institute


of Namibian Quantity Surveyor's offices situated at c/o Hugo Hahn
St and Nelson Mandela Ave, Klein Windhoek, Windhoek during
week days from 8H00 to 12H00.

All references in this document made to "the Architect" will mean


Engineer, except where the profession is meant.

B1: Supplementary Documentation

165 B1.1: Bills of Quantities

These Bills of Quantities contain pages and annexures as indexed


on the flyleaf.

These Bills of Quantities are consecutively numbered and the


Tenderer is required to check the number of pages and should any
be found missing or in duplicate or the figures or typing indistinct
or there be any doubt, obscurity or ambiguity as to the meaning or
intent of the descriptions, particulars, etc. He must inform the
Quantity Surveyor at once in writing and have the same rectified or
explained as the case may be. No claim whatsoever will be
afterwards admitted due to the Contractor having failed to comply
with any of the above conditions.

No alterations, erasure, omission or addition is to be made in the


text and conditions of these Bills of Quantities and should any
such alteration, amendment, note or addition be made, the same
will not be recognised, but the reading of these Bills of Quantities,
as prepared by the Quantity Surveyor will be adhered to.

The items in these Bills of Quantities are to be read and priced in


conjunction with and the descriptions regarded as amplified by the
Model Preambles for Trades as recommended and published by
the Institute of Namibian Quantity Surveyors, 2008 Edition, and no
claim arising from brevity of description of items fully described in
the said Model Preambles for Trades will be entertained.
Item

166 B1.2: Provisional Bills of Quantities


Item

167 B1.3: Availability of Construction Documentation for contracts


based on Provisional Bills of Quantities
Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
16
Package 3 Lot 3
Amount

168 B1.4: Name of Architect, Quantity Surveyor and Specialist


Consultants

Refer to the Appedix To Tender


Item

169 B1.5: Lodging and Scrutiny of priced Bills of Quantities.

These Bills of Quantities must be extended in black ink.


Item

170 B1.6: Meaning of Words


Item

171 B1.7: Performance Guarantee by Contractor


Item

172 B1.8: Payment Guarantee by Employer


Item

173 B1.9: Waiver of Contractor's Lien


Item

174 B1.10: Signing powers


Item

175 B1.11: Tenders

Notwithstanding anything contained in this clause, tenders shall be


valid for a period as stipulated in the separate Bid Invitation
Documents, from the closing date of tenders.

The Employer reserves the right to correct any arithmetical or


other errors in the extension of the rates and totals in the tender
and/or to adjust any rates that are considered by him to be
unbalanced and unacceptable. Such adjustments will be done
without affecting the Tender Sum.
Item

176 B1.12: Inspection of Documents


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
17
Package 3 Lot 3
Amount

B2 The Site

177 B2.1: Site and Bounderies

The sites will be as indicated on the site plans in the Bidding


Documents.
Item

178 B2.2: Area of the Works

The Area of the Works to be occupied by the Contractor, any


restriction on the area and the limit of access or exit will be pointed
out to the Contractor by the Engineer on handing over of the Site.
Item

179 B2.3: Boundary Beacons, setting-out pegs and master datum

The Contractor shall notify the Engineer if any encroachments of


adjoining foundations, buildings, structures, pavements, etc., exist
so that the necessary arrangements can be made for the
rectification of any such encroachments
Item

180 B2.4: Site soil investigation

No site soil investigation report is available and the Tenderer is


advised to inspect the site to ascertain the exact nature of the
ground and report to the Engineer.
Item

181 B2.5 : Viewing of the Site

No claims for extras arising from the Contractor having failed to


comply with this Clause will be entertained.
Item

182 B2.6: Existing premises occupied


Item

183 B2.7: Dimensional accuracy of work executed under the previous


contract
Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
18
Package 3 Lot 3
Amount

184 B2.8: Patent Defects in work executed under the previous contract
Item

185 B2.9: Existing known services

Existing services and points of connection are shown on the Site


plan or will be pointed out on the Site by the Engineer.
Item

186 B2.10: Unknown Services


Item

187 B2.11: Protection of trees


Item

188 B2.12: Articles of Value


Item

189 B2.13: Inspection of nearby properties etc.


Item

B3 Management of Contract

190 B3.1: Management of Works


Item

191 B3.2: Programming of The Works

The Contract shall be programmed by the Contractor in


accordance with Alternative A
Item

192 B3.3: Progress Meetings


Item

193 B3.4: Technical Meetings


Item

B4: Materials and Workmanship

194 B4.1: Samples of materials


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
19
Package 3 Lot 3
Amount

195 B4.2: Samples of workmanship and mockups


Item

196 B4.3: Ordering of materials


Item

B5: Temporary Works and Plant

197 B5.1: Deposits and Fees


Item

198 B5.2: Enclosure of Works


Item

199 B5.3: Pavement crossings and parking meters


Item

200 B5.4: Advertising


Item

201 B5.5: Plant and Equipment


Item

202 B5.6: Special Scaffolding

No special scaffolding is measured as these Bills of Quantities are


based on the Sixth edition of the Standard System for Measuring
Building Work.
Item

203 B5.7: Contractor's Offices and Sheds

Under NO circumstances may any of the buildings at any stage be


used for temporary accommodation for workers, contractor's
offices or the storage of materials.
Item

204 B5.8: Offices


Item

205 B5.9: Office of the Clerk of Works


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
20
Package 3 Lot 3
Amount

206 B5.10: Main Noticeboard


Item

207 B5.11: Subcontractors' Noticeboard


Item

B6: Temporary Services

208 B6.1: Water

The contractor shall provide water for The Works in accordance


with Alternative A
Item

209 B6.2: Electricity and Lighting

The contractor shall provide electricity and lighting for The Works
in accordance with Alternative A
Item

210 B6.3: Telephones

The contractor shall provide telephones for the Works in


accordance with Alternative A
Item

211 B6.4: Toilets

The contractor shall provide toilets for The Works in accordance


with Alternative A
Item

B7: Prime Cost and Provisional Amounts

212 B7.1: Cash Discount

All Prime Cost and Provisional Sums are net and do not include a
cash discount, nor will the Contractor be allowed or entitled to a
cash discount.
Item

213 B7.2: Taking delivery and fixing of prime cost items


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
21
Package 3 Lot 3
Amount

214 B7.3: Nominated or Selected Subcontract Documents


Item

215 B7.4: Attendance on Nominated or Selected Subcontractors


Item

216 B7.5: Fuel, power and water for commissioning of mechanical and
other specialised installations
Item

B8: Financial Aspects

217 B8.1: Sales Taxes

Delete the whole of this clause and replace with the following:

B8.1: Taxes, etc.

Provision is made in the separate Bid Invitation Documents for the


inclusion of Value Added Tax (VAT) at 15%. The Contractor shall
price these Bills of Quanties excluding Value added Tax (VAT).
Item

218 B8.2: Contract price adjusment provisions


N/A

219 B8.3: Payment of Preliminaries

Payment of Preliminaries will be calculated from the priced items


within the Preliminaries in accordance with Alternative B

In addition to the exclusions mentioned in the third paragraph of


this clause it shall be deemedd that "day works" be added as a
fourth exclusion.
Item

220 B8.4: Adjustment of Preliminaries

The Adjustment of Preliminaries will be on the basis of fixed price,


value related and time related items in accordance with Method 3.

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
22
Package 3 Lot 3
Amount

In addition to the exclusions mentioned in the this paragraph of


this clause it shall be deemed that day works be added as a fourth
exclusion.
Item

221 B8.5: Certificate payment projection


Item

222 B8.6: Dayworks


N/A

223 B8.7: Information supplied by Contractor


Item

B9: General

224 B9.1: Protection


Item

225 B9.2: Protection of existing and/or partially occupied works.


Item

226 B9.3: Safety


Item

227 B9.4: Site security


Item

228 B9.5: Notice before covering work


Item

229 B9.6: Disturbance


Item

230 B9.7: Clearing and cleaning


Item

231 B9.8: Vermin


Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
23
Package 3 Lot 3
Amount

232 B9.9: Overhand Work


Item

233 B9.10: Jobbing


Item

SECTION C - SPECIFIC PRELIMINARIES

234 Site instructions

Instructions issued on site are to be recorded in triplicate in a site


instruction book which is to be maintained on site by the contractor
Item

235 Warranties for material and workmanship

Where warranties for materials and/or workmanship are called for,


the contractor shall obtain a written warranty, addressed to the
employer, from the firm supplying the materials and/or doing the
work and shall deliver same to the engineer on the certified
completion of the contract. The warranty shall state that
workmanship, materials and installation are warranted for a
specified period from the date of final completion and that any
defects that may arise during the specified period shall be made
good at the expense of the firm supplying the materials and/or
doing the work, upon written notice to do so. The warranty will not
be enforced if the work is damaged by defects in the construction
of the building in which case the responsibility for replacement
shall rest entirely with the contractor
Item

236 Co-operation of contractor for cost management

It is specifically agreed that the contractor accepts the obligation of


assisting the engineer in implementing proper cost management.
The contractor will be advised by the engineer of all cost
management procedures which will be implemented to ensure that
the final building cost does not exceed the budget. The engineer
undertakes to make available to the contractor all budgetary
allowances and cost assessments/reports to enable the proper
procedure to be implemented and the contractor shall attend all
cost plan review and cost management meetings. The contractor
undertakes to extend these procedures, as necessary, to all
subcontractors
Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
24
Package 3 Lot 3
Amount

237 Testing of windows for watertightness

Each window shall be tested for watertightness with water sprayed


on using adequate pressure. If in the opinion of the engineer, the
pressure proves to be inadequate, then the pressure shall be
boosted by means of compressed air or other approved means
Item

238 Revenue Stamps

The Contractor must allow for and provide all necessary revenue
stamps require.
Item

239 Proprietary Branded Products.

The Contractor shall take delivery of, handle, store, use, apply
and/or fix all proprietary branded products in strict accordance with
the manufacturers' instructions after consultation with the
manufacturer's authorised representative.
Item

240 Non-Cession of Monies

The Contractor shall not cede nor assign his rights or claims to any
monies due or to become due under this contract.
Item

241 As Built Drawings

The position of construction breaks and the extent of individual


concrete pours are to be recorded by the Contractor on the
Structural Engineer's drawings and are to be submitted to the
Architect and the Structural Engineer for their records.

The Contractor shall furnish the Architect with a set of marked up


drawings indicating the positions of all plumbing and drainage
pipework as actually built.
Item

242 Social Security

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
25
Package 3 Lot 3
Amount

The contractor shall provide for and effect Social Security for all
his/her employees on the works in respect of the Social Security
Act and will also instruct all his sub-contractors to do the same.
Item

243 Employment of Namibian People

The contractor is encouraged to employ Namibian citizens for


skilled and semi skilled artisans and employ unskilled labour from
the area of interventions.

All Namibian skilled artisans and Namibian unskilled employees


are to be registered according to the Social Security Act of 1994
(Act No. 34 of 1994), and the Tenderer must submit Certificates of
Good Standing with the Social Security Commission, which are
obtainable from the Commission.
Item

Carried To Section Summary $


Section No. 1
Bill No. 1
Preliminaries
26
Package 3 Lot 3
Amount

SECTION NO. 1
PRELIMINARIES

SECTION SUMMARY
Page

Brought forward from page 2

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

Carried to Next $
Section No. 1
SECTION SUMMARY

27
Package 3 Lot 3
Amount
Brought from Previous $

26

Carried to Final Summary $


Section No. 1
SECTION SUMMARY

28
Package 3 Lot 3

SECTION NO. 2

RENOVATIONS

29
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 1
ALTERATIONS

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SUPPLEMENTARY PREAMBLES, ETC.

Materials from the alterations, credit, etc:

Materials recovered from the alterations (except where described as to be


re-used or to be handed over to the client) will become the property of the
Contractor, who may allow credit in respect thereof where provided for in the
bills of quantities. Such materials shall not be re-used in new work without
written permission from the Architect.

Materials described as "removed" shall be removed from the site


immediately.

Materials described as "handed over to the client" shall be carefully


dismantled where necessary, neatly stored under cover on site where
directed and protected from damage, until required.

Materials described as "set aside for re-use" shall be carefully dismantled


where necessary, neatly stored under cover on protected from damage until
required for re-use. Any damage caused to such materials during removal,
storage or refixing shall be made good at the Contractor's expense.

In taking down and removing existing work the utmost care shall be
observed to prevent any structural or other damage to remaining portions of
the building, and the Contractor shall provide all shoring, needling, strutting,
etc. to ensure the stability of all structure during alterations work.

Special care shall be exercised during the progress of the work to ensure
that any electrical installations, water supply pipes, telephone and other
services which may be encountered are not interfered with and notice shall
given to the Architect if any disconnection or alterations becomes necessary.

The Contractor shall take all precautions necessary to prevent any nuisance
from dust whilst carrying out the work.

Making good damaged work:

The Contractor shall make good in all trades to existing work where
damaged or disturbed through the alterations with all necessary new
materails to match the existing.

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
30
Package 3 Lot 3
Rate Amount

Disposal of debris, etc:

The Contractor shall be responsible for the removal from the site all
materials, debris and rubbish resulting from the alterations.

Exposing of underground services:

The known services both underground and overhead will be pointed out to
the contractor. The Contractor is hereby expected to include in his tendering
price the cost of exposing of such services where expedient, be the services
known or unknown, as long as it is deemed necessary.

Demolitions, etc:

Descriptions of demolitions give a rough guide only as to the scope of the


work. Tenderers are therefore advised to visit the site before submitting a
tender and to acquaint themselves with the nature and extent of the work to
be done and the value of recoverable materials which are to be re-used or
handed over to the Client and those which are neither to be re-used nor
handed over to the Client. Unless otherwise stated, loose furniture, kitchen
and other equipment, apparatus, machinery, etc. shall remain the property
of the Client and the removal thereof does not fall within the scope of this
Contract.

The Contractor shall completely demolish the buildings, etc. in a careful,


skillful, practical and safe manner down to 150mm below ground level.

Description of demolitions shall be deemed to include breaking up and


removing:

(1) all floors and surface beds

(2) all external screen and internal walls (clay brick should be set aside,
cleaned, for re-use) steps, ramps, aprons, surface water channels,
rainwater sumps, gulleys, etc. attached to the building to be demolished;

(3) all services, manholes, etc.in ground to a point not less than 1000mm
beyond the perimeter of the building, including plugging of ends of remaing
pipes, drains, etc.,filling in holes where necessary and ramming and
levelling to the ground level.

REMOVAL OF EXISTING WORK

Breaking up and removing mass concrete:

1 Steps and pavers


m³ 65

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
31
Package 3 Lot 3
Rate Amount

Taking out and removing doors, screen gates, etc including


thresholds, sills, etc in one brick walls including making good cement
plaster and paintwork on both sides:

2 Steel screen gate and frame 813 x 2,031mm high overall from one
brickwall.
No. 5

3 Timber single door 813 x 2,031mm high overall from one brickwall.
No. 10

4 Steel single door 813 x 2,031mm high overall from one brickwall.
No. 40

Taking out and removing doors, windows, etc from one brickwall
(windows to be set aside for re-use):

5 Glazed steel window 550 x 1,000m high from one brick wall.
No. 2

6 Glazed steel windows 1,000 x 600mm high from one brick wall.
No. 12

7 Glazed steel windows 1,000 x 1,000mm high from one brick wall.
No. 3

8 Glazed steel window 1,470 x 1,000m high from one brick wall.
No. 6

9 Glazed steel window 1,500 x 600m high from one brick wall.
No. 63

10 Glazed steel window 1,500 x 900m high from one brick wall.
No. 70

Taking down and removing roofs, floors, panelling, ceilings, partitions,


etc:

11 Nailed up Celotex ceilings.


m² 316

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
32
Package 3 Lot 3
Rate Amount

Taking out and removing sundry joinery work:

12 Vinyl tile floor covering including preparing screed for new ceramic floor tiles.
m² 228

13 Timber cornices from brickwork.


m 656

14 Timber skirtings from brickwork.


m 656

Taking out and removing ironmongery:

15 Mortice lock and striking plate from steel door and steel frame.
No. 40

16 Mortice lock and striking plate from timber door and steel frame.
No. 9

Hacking up/off and removing granolithic, screeds, plaster, etc from


concrete or brickwork and preparing surfaces for new screeds,
plaster, etc:

17 Plasters from walls or columns in patches.


m² 55

Hacking up/off and removing granolithic, screeds, plaster, etc from


concrete or brickwork and bush hummering surfaces to receive new
screeds, plaster, etc:

18 50mm Screed from floors (internal and external).


m² 1036

Taking out and removing piping, sanitary fittings, etc including


disconnecting piping from fittings and making good floor and wall
finishes (making good tiling and paintwork elsewhere):

19 Broken polyethylene rotation pedestal WC pot.


No. 10

20 Broken viteous china WHB


No. 10

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
33
Package 3 Lot 3
Rate Amount

Taking out and removing broken glass from windows/door panes and
mirrors:

21 Broken glass from steel windows including cleaning out rebates and
preparing for new glass.
m² 2

Charts and learning material on walls

22 Allow for removal of learning charts and material ( and putting back
thereafter), from walls and pinning boards so as to expose surfaces to be
painted.
m 27

BUILDING UP OPENINGS

Brickwork in cement bricks [7 Mpa] in class I mortar in building up:

23 Half brick walls.


m² 10

24 One brick walls.


m² 30

MAKING GOOD OF FINISHES, ETC.

Making good existing metal ceilings:

25 Clean ceilings from any organic matters and dirts, apply disinfenctants and
pets poison in the roof space before installing ceiling, make good on
completion, taking utmost care not to damage the ceilings.
m² 1328

Making good 300 x 300mm ceramic floor tiles:

26 Floors in patches.
m² 62

Making good external bagged finish to cement plaster:

27 Walls in patches.
m² 27

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
34
Package 3 Lot 3
Rate Amount

Making good pinning board surface, clean and re-glue:

28 'Flortime' pinning boardmodel 2300 code: '2309', size 2,400 x 1,200mm.


m² 74

REMEDIAL WORKS

Roof timber rafters:

29 Replace broken or missing eaves purlin with 50 x 76mm wrot softwood


purlin, including allowing for lifting up roof sheets and refixing and including
new roofing screws
m 332

30 Reinforcing the exiting timber tie beam size114 x 38mm wrot softwood
complete with rafter feets, including allowing for lifting up roof sheets and
refixing and including new roofing screws
m 1526

ROOF LEAKS REPAIRS AND SEALING

Inspect, re-fastened, replace missing screws, and seal roof screws,


gaps, overlaps, holes, flashings, etc with 'Klodek Glass fibre fabric
with two coats of sealant' where necessary to leave in perfect
waterproof condition on completion:

31 On existing IBR roof covering.


m² 1328

PLASTER REPAIRS

Supplementary preambles:

All plaster repair admixtures are to be applied strictly in accordance with the
"abe Construction Chemicals" or similar approved requirements. Break out
all loose and hollow plaster at least 20 mm wide all around loose plaster
area, brush clean of all loose material, treat exposed area wit "abe
Duralatex" or similar approved adhesive slurry and plaster with an admixture
of 3 to 1 sand/cement and 3 to 1 water / Duralatex.

Prepare and apply 3 to 1 plaster admixture as described:

32 On brick walls
m² 591

33 On narrow widths
m² 33

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
35
Package 3 Lot 3
Rate Amount

CRACK REPAIRS

Supplemantary preamble:

Repair crack in plastered walls by hacking off existing plaster to 300mm


width on either side of the crack, wedge crack with timber wedges at
300mm centres and fill with 'epidermix'/ 'mendell 90' or similar approved
crack repair product, cover with 13mm chicken wire mesh and applying
bonding liquid and finish off with 3:1 cement plaster including making good.

Repairs cracked plaster/ concrete surfaces as noted above:

34 On walls
m 55

Supplementary preamble:

Repair crack in screeded floors by hacking off the existing screed to expose
the concrete surface, 200mm width on either side of the crack, wedge crack
with timber wedges at 300mm centres and fill with 'abe epidermix 344' or
similar approved 'wet to dry' epoxy to the crack at rate of 3 sqm/litre, bush
hammer exposed concrete surface, cover with 13mm chicken wire mesh
and applying bonding liquid and finish off with 25Mpa screed including
making good.

35 On concrete floors
m 207

Carried to Collection $
Section No. 2
Bill No. 1
Alterations
36
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 1
ALTERATIONS
COLLECTION
Page No

Brought Forward from Page 30

31

32

33

34

35

36

Carried To Section Summary $


Section No. 2
Bill No. 1
Alterations
37
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 2
EARTHWORKS

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

EXCAVATION OTHER THAN BULK

Excavation in earth not exceeding 2m deep:

1 Trenches and holes for thickening under paving edge.


m³ 78

Extra over excavations other than bulk in earth for excavation in:

2 Soft rock.
m³ 5

3 Hard rock.
m³ 1

Risk of collapse of excavations other than bulk:

4 Sides of trench and hole excavations not exceeding 1,5m deep.


m² 49

CARTING AWAY.

Extra over all excavations for loading, carting and dumping surplus
excavated material (no allowance made for increase in bulk):

5 Off site to a dumping site to be found by the Contractor.


m³ 78

EARTH FILLING, ETC.

Filling with approved material supplied and carted onto site by the
Contractor, compacted to a density of at least 95% Mod. AASHTO
maximum density:

6 Under floors, pavings, etc.


m³ 89

Carried to Collection $
Section No. 2
Bill No. 2
Earthworks
38
Package 3 Lot 3
Rate Amount

Surface Preparation:

7 Trim and level off surface of natural ground and/or excavated surfaces to
receive concrete surface beds, including ripping and scarifying as necessary
and compacting the whole area for a depth of 150mm to a density of at least
95% Mod. AASHTO maximum density.
m² 259

SOIL POISONING

Approved brand of anti-termite soil poison mixed with weedkiller


applied by a Registered Pest Control company and guaranteed against
termite infestation for ten years, strictly according to manufacturer's
instructions:

8 Under floors, etc., including forming and poisoning shallow furrows against
foundation walls, etc., filling in furrows and ramming.
m² 259

Carried to Collection $
Section No. 2
Bill No. 2
Earthworks
39
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 2
EARTHWORKS
COLLECTION
Page No

Brought Forward from Page 38

39

Carried To Section Summary $


Section No. 2
Bill No. 2
Earthworks
40
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 3
CONCRETE, FORMWORK AND REINFORCEMENT

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

REINFORCED CONCRETE

25 MPa/19mm Concrete:

1 Pavings cast in panels.


m³ 213

FINISHING TOP SURFACE OF CONCRETE

Finishing top surfaces of concrete smooth with a power float:

2 Paving to falls and currents.


m² 1417

GROOVES, ETC.

Grooves, channels, mortices, sinkings, etc in concrete:

3 40 x 40mm Chamfer to exposed concrete edges.


m 1036

ROUGH FORMWORK (DEGREE OF ACCURACY II) (CPAP Work Group


No 111)

Rough Formwork to Sides:

4 Edges, risers, ends and reveals not exceeding 300mm high or wide.
m 1036

REINFORCEMENT (PROVISIONAL) (CPAP Work Group No 114)

Fabric reinforcement:

5 Type 245 fabric reinforcement in concrete surface beds, slabs, etc.


m² 1771

Carried To Section Summary $


Section No. 2
Bill No. 3
Concrete, Formwork And Reinforcement
41
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 4
MASONRY

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SUPPLEMENTARY PREAMBLES

BRICKWORK

Brick reinforcements:

The brickwork reinforcements have been measured on every course in


foundations brickworks, every third course in superstructure brickwork, and
every course in the beamfilling brickwork.

Sizes in descriptions:

Where sizes in descriptions are given in brick units, 'one brick' shall
represent the length and 'half brick' the width of a brick.

Hollow walls etc:

Descriptions of hollow walls shall be deemed to include leaving every fifth


perpend of the bottom course of the external skin open as a weep hole.

Pointing:

Descriptions of recessed pointing to fair face brickwork and face brickwork


shall be deemed to include square recessed, hollow recessed, weathered
pointing, etc.

BRICKWORK SUNDRIES

Brickwork reinforcement:

1 75mm Wide reinforcement built in horizontally.


m 60

2 150mm Wide reinforcement built in horizontally.


m 109

Cement wash of 1:3 liquid cement and sand mixture applied with a
brush, on previously cement washed surfaces:

3 On concrete surfaces including removing fins, irregularities,etc.


m² 23

Carried to Collection $
Section No. 2
Bill No. 4
Masonry
42
Package 3 Lot 3
Rate Amount

4 On brick surfaces.
m² 223

Prestressed fabricated lintels:

5 110 x 75mm Lintels in lengths not exceeding 3m.


m 16

Carried to Collection $
Section No. 2
Bill No. 4
Masonry
43
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 4
MASONRY
COLLECTION
Page No

Brought Forward from Page 42

43

Carried To Section Summary $


Section No. 2
Bill No. 4
Masonry
44
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 5
CARPENTRY AND JOINERY

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

EAVES, VERGES, ETC

Everite FC77 pressed fibre-cement:

1 255 x 6mm Fascias and barge boards including gavanised steel H-profile
jointing strips, screwed on to edges of existing timber trusses, rafters and
purlins.
m 196

BEADS, ARCHITRAVES, ETC

Wrought ' supawood':

2 22 x 150mm Angle rounded bumper rail.


m 787

3 22 x 75mm cornice.
m 850

Carried To Section Summary $


Section No. 2
Bill No. 5
Carpentry And Joinery
45
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 6
CEILINGS PARTITIONS AND ACCESS FLOORING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

METAL NAILED UP AND SCREW UP CEILINGS (CPAP Work Group No


126)

0.5mm IBR profile metal ceiling in single lengths fixed to steel


purlins/branderings or rails:

1 Ceilings including 30 x 30 x 3mm angle iron brandering at 1250mm centres


running both ways.
m² 316

2 Extra over ceiling for 1000 x 1000mm trap door of 30 x 30 x 3mm angle
section framing covered with 0.5mm thick IBR profile sheeting fitted flush in
opening.
No. 6

0.8mm Thick galvanised sheet flashings:

3 Narrow and broad flute closers 150mm girth to suit IBR profile.
m 656

4 Angle flashing once bend 300mm girth.


m 850

Carried To Section Summary $


Section No. 2
Bill No. 6
Ceilings Partitions And Access Flooring
46
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 7
IRONMONGERY

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

HINGES, FLOOR SPRING HINGES, BOLTS, PANIC BOLTS, ETC

Flush barrel bolts in Solid or similar approved:

1 500 x 32mm Satin chrome on brass flush barrel bolt with keep let into
concrete.
No. 20

CATCHES, CABIN HOOKS, ETC

Solid or similar approved:

2 Approved standard window catch.


No. 6

3 Approved standard window stay.


No. 25

4 Approved standard window handle.


No. 26

LOCKS, HANDLES, ETC

Solid or similar approved:

5 'Blesbok' Art 460/312 four lever lockset complete with a pair of handles.
No. 59

LETTERS, NAMEPLATES, ETC.

Solid or similar approved:

6 20mm High letter or numeral.


No. 20

7 Anodised aluminium plate with male or female symbol.


No. 20

Carried to Collection $
Section No. 2
Bill No. 7
Ironmongery
47
Package 3 Lot 3
Rate Amount

BATHROOM FITTINGS

Chairman Industries or simmilar approved:

8 DL2 Stainless steel side grab rail.


No. 4

9 SR2 Stainless steel backgrab rail.


No. 4

Solid or similar approved:

10 Approved chromium plated toilet roll holder plugged


No. 20

Approved:

11 Chromium plated toilet roll holder plugged.


No. 2

SUNDRIES

Dclsa or similar approved:

12 Code 140/83 satin chrome plated floor mounted door stop.


No. 59

PINNING BOARDS, WRITING BOARDS, PROJECTION SCREENS, ETC

Vitrex or other approved:

13 Vitrex pinning board model 2300 code: 2309, 2,400 x 1,200mm high
plugged.
No. 10

Carried to Collection $
Section No. 2
Bill No. 7
Ironmongery
48
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 7
IRONMONGERY
COLLECTION
Page No

Brought Forward from Page 47

48

Carried To Section Summary $


Section No. 2
Bill No. 7
Ironmongery
49
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 8
METALWORK

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

WELDED SCREENS, GATES, ETC.

The following in purpose made screens, frames, and gates, etc:

1 Purpose made single security gate 813 x 2,032mm high overall, formed of
38 x 76 x 2.5mm mild steel square hollow section perimeter framing and two
centre transoms forming top and bottom openings, each filled in with 'Mentix
Flattex Code No. 341' expanded metal and mosquito gauze fixed to frame
with flat bar fixing cleats, and fitted with sheet metal lockbox for and
including double cylinder lockset, as 'Solid' 378 narrow style dead lock,
complete with two 100mm heavy duty weld-on lift-off hinges per leaf welded
to steel door frame (frame elsewhere measured).
No. 5

2 Extra on 40 x 76 x 3mm hollow section framing for mitred angle intersection.


No. 47

3 10mm Diameter loose bolt type expanding bolt as 'Rawbolt M10 75L',
including mortice in brickwork and bolt up tight.
No. 118

4 Purpose made gate frame consisting of 40 x 76 x 3mm square hollow


section bolted to brickwork with bolts (bolts elsewhere measured).
m 23

5 10mm M10 Bolts.


Kg 31

Carried to Collection $
Section No. 2
Bill No. 8
Metalwork
50
Package 3 Lot 3
Rate Amount

Screens and gates:

6 Single burglar gate 813 x 2032mm high of 40 x 40 x 2mm hollow section


frame and two x 40 x 40 x 2mm hollow section horizontal middle rails filled
in with 900mm long 12 x 12 x 2mm hollow section vertical rails at the bottom
section and 862mm long 12 x 12 x 2mm hollow section vertical rails at the
top section at approximately 120mm centres and fitted with one and a half
pairs of suitable hinges welded to door frame and lock box with and
including 'Solid' 378 narrow style cylinder dead lock and 3mm steel cover
plate 120 x 813 cover plate welded middel rails.
No. 5

PRESSED STEEL COMBINATION DOORS AND FRAMES

Standard ' Wispeco' or similar approved chawl doors with back panel:

7 Door 813 x 2,032mm high complete with back panel with double rebated
frame suitable for one brick wall.
No. 39

8 Door 813 x 2,032mm high complete with back panel, hung to existing door
frame.(Internal)
No. 20

1,2mm Double rebated frames suitable for half brick walls:

9 Frame for door 813 x 2,032mm high.


No. 20

Carried to Collection $
Section No. 2
Bill No. 8
Metalwork
51
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 8
METALWORK
COLLECTION
Page No

Brought Forward from Page 50

51

Carried To Section Summary $


Section No. 2
Bill No. 8
Metalwork
52
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 9
PLASTERING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SCREEDS

Screeds with compressive strength of 25 Mpa steel trowelled on


exposed concrete complete with Durashake or similar approved floor
harderner applied to the manufacturer's specifications:

1 50mm Thick on floors and landings.(internal and external)


m² 1036

INTERNAL PLASTER

Cement plaster on brickwork:

2 On narrow widths.
m 7

EXTERNAL PLASTER

Cement plaster on brickwork:

3 On narrow widths.
m² 7

Carried To Section Summary $


Section No. 2
Bill No. 9
Plastering
53
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 10
TILING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

NOSING, JOINT COVERS, PROTECTORS, ETC.

Wall edge protectors:

1 'Schluter Schiene Type AE 80' or similar approved brushed aluminium tile


edge trim cut to lengths and bedded in tile adhesive.
m 350

CERAMIC WALL TILING

Allow a PC sum of N$ 100.00 per m2 for purchasing and delivery of


wall tiles fixed with adhesive to and including 20mm plaster bedding
on walls and flush pointed with tinted waterproof jointing compound:

2 On walls in isolated panels, splashbacks, etc.


m² 27

CERAMIC FLOOR TILING

300 x 300 x 6mm 'Dimo Top' full-body ceramic floor tiles fixed with
adhesive on 25mm screed bedding on concrete and flush pointed with
tinted waterproof jointing compound:

3 On floors and landings.


m² 228

4 Circular cutting.
No. 21

5 100mm high cut tile skirting.


m 530

Carried To Section Summary $


Section No. 2
Bill No. 10
Tiling
54
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 11
PLUMBING AND DRAINAGE

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SUPPLEMENTARY PREAMBLES

uPVC pressure pipes and fittings:

Pipes for water supply shall be of the class stated.

Pipes of 40mm diameter and smaller shall be plain ended with solvent
welded uPVC loose sockets and fittings.

Pipes of 50mm diameter and greater shall have sockets and spigots with
push-in type integral rubber ring joints. Bends shall be uPVC and all other
fittings shall be cast iron, all with similar push-in type joints.

Copper pipes:

Pipes shall be hard drawn and half-hard pipes of the class stated. Class 0
(thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half-
hard), class 2 (half-hard) and class 3 (heavy walled half-hard) pipes shall
only be bent with benders with inner and outer formers. Fittings to copper
waste, vent and anti-syphon pipes, capillary solder fittings and compression
fittings shall be 'Cobra Watertech' type. Capillary solder fittings shall comply
with ISO 2016. Only compression fittings shall be used in walls or in ground.

Fixing of pipes:

Unless specifically otherwise stated, descriptions of pipes shall be deemed


to include for fixing to walls etc. casting in, building in or suspending not
exceeding 1m below suspension level

Reducing fittings:

Where fittings have reducing ends or branches they are described as


'reducing'. In the case of pipes with diameters not exceeding 60mm only the
largest end or branch size is given. Should the Contractor wish to use other
fittings and bushes or reducers he may do so on the understanding that no
claim in this regard will be entertained. In the case of pipes with diameters
exceeding 60mm all sizes are given and no claim for extra bushes,
reducers, etc will be entertained.

Flush pans:

Flush pans shall have straight or side outlets and 'P' or 'S' traps as
necessary.

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
55
Package 3 Lot 3
Rate Amount

Exposed concrete surfaces:

Where no manufacturers' instructions exist pipes shall be laid in accordance


with clauses 5.1 and 5.2 of each of the following: SABS 1200 L : Medium
pressure pipelines LD : Sewers LE : Stormwater drainage Pipe trenches
etc shall be backfilled in accordance with clause 3, 5.5, 5.6, 5.7 and 7 of
SAB.

Exposed surfaces of concrete stormwater channels, cover slabs, inspection


eye marker slabs, gulley tops, cleaning eye tops, catchpits, inspection
chambers, etc shall be finished smooth with plaster.

Excavations:

No claim for rock excavation will be entertained unless the Contractor has
timeously notified the quantity surveyor thereof prior to backfilling.

Laying, backfilling, bedding, etc of pipes:

Pipes shall be laid and bedded and trenches shall be carefully backfilled in
accordance with manufacturers' instructions.

Stainless steel basins, sinks, wash troughs, urinals, etc:

Units shall have standard aprons on all exposed edges and tiling keys
against walls where applicable.

Waste unions:

Descriptions of waste unions shall be deemed to include rubber or vulcanite


plugs and chains fixed to fittings.

SANITARY FITTINGS

'Ballam' Waterslot or similar approved:

1 Low level water-saving WC suit comprising of Polyethylene bowl with heavy


duty double flap seat and cover and 6l 'Shires Lynx' duranite cistern.
No. 10

'Vaal Sanitaryware' vitreous china wash hand basins and pedestals:

2 510 x 405mm 'Hibiscus' white vitreous china lavatory basin (product code
7050) with two tapholes including integrated overflow and chainstay hole.
No. 10

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
56
Package 3 Lot 3
Rate Amount

'Franke (t/a Citimetal)' grade 304 (18/10) 1,2mm thick stainless steel
wash hand basins:

3 'Franke Oval A' wash hand basin size 420 x 340mm with pressed bowl , two
tapholes , 100mm radius apron and 50mm high splashback, four times
bolted to wall with M8 expansion bolts.
No. 5

Approved:

4 Polyethylene rotation pedestal and funnel V.I.D.P latrine with heavy duty
seat and cover.
No. 10

WASTE UNIONS ETC

'Cobra Watertech' or similar approved waste unions etc:

5 75mm diameter Chrome plated shower/fountain grating (code 323).


No. 2

TRAPS ETC

'Cobra Watertech' or similar approved traps etc:

6 40mm Rough brass medium seal sink 'P' trap, with FI outlet and cleaning
eye (code VA2.360).
No. 3

TAPS, VALVES, ETC

'Cobra Watertech' crutch handle, elbow action and lockshield bibtaps:

7 15mm Star Chrome plated foot operated hose bibtap with 20mm BSP
thread on outlet (code 507-21).
No. 2

WATER SUPPLIES

Class 10 HDPE pipes:

8 25mm Pipes laid in and including trenches.


m 12

9 32mm Pipes laid in and including trenches.


m 7

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
57
Package 3 Lot 3
Rate Amount

10 63mm Pipes laid in and including trenches.


m 7

Extra over HDPE pipes for solvent welded pressure fittings:

11 25mm Fittings.
No. 9

12 32mm Reducer.
No. 3

13 32mm Bend.
No. 2

14 63mm Bend.
No. 5

15 32mm Tee.
No. 4

16 32 x 32 x 25mm Reducing tee.


No. 2

17 63 x 32 x 25mm Reducing tee.


No. 1

18 63 x 63 x 32mm Reducing tee.


No. 2

19 32mm Adaptor coupling.


No. 3

20 63mm Adaptor coupling.


No. 1

Class O copper pipes:

21 15mm Pipes chased into brick walls.


m 12

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
58
Package 3 Lot 3
Rate Amount

22 22mm Pipes chased into brick walls.


m 3

23 22mm Pipes.
m 6

24 22mm Pipes laid in and including trenches.


m 9

Extra over class O copper pipes for capillary fittings:

25 15mm Fittings.
No. 6

26 22mm Fittings.
No. 6

Sundries:

27 Extra for connecting 22mm Coper pipe to 25mm HDPE pipe including all
neccessary fittings, etc.
No. 12

28 225 x 225mm Cast iron stopcock box including brick chamber below not
exceeding 500mm deep internally.
No. 4

29 Search, locate, excavate and connect the new 32mm HDPE water supply
pipe to existing municipal water line including all labour and materials to
execute the connection.
Item

TESTING

Testing:

30 Testing water pipe system.


Item

31 Testing drainage pipe system.


Item

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
59
Package 3 Lot 3
Rate Amount

FIRE APPLIANCES ETC.

'Chubb'or similar approved:

32 'Everyway' hose reel complete with 30m non-kinkable hose 20mm internal
diameter plated stopcock, shut-off nozzle and wall bracket complete with
25mm diameter Saunders type A diaphragm isolated valve.
No. 21

33 9kg Rechargeable dry chemical fire extinguisher complete with initial charge
painted backing board plugged and screwed to plastered or tiled brick wall.
No. 22

34 80 x 65mm Brass hydrant booster connection with cap and chain.


No. 10

Fire hydrant pedestals:

35 Unreinforced concrete hydrant pedestals 900mm high cast around vertical


pipe with bottom 300mm below ground, 300 x 300mm square at base and
tapering to octagonal shaped top 200 x 200mm overall including necessary
excavation, formwork and two coats of paint to exposed surfaces supplied
complete with instantaneous or bayonet outlet with cover sleeve over valve
and standpipe.
No. 1

WATER SUPPLIES TO FIRE APPLIANCES

Class 10 HDPE Type 4 pressure pipes:

36 32mm Fittings
No. 120

Extra over class 10 HDPE Type 4 pressure pipes for solvent welded
pressure fittings:

37 32mm Fittings.
No. 6

Galvanised steel pipes:

38 25mm Pipes laid in and including trenches not exceeding 1m.


m 48

39 32mm Pipes
m 32

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
60
Package 3 Lot 3
Rate Amount

Extra over galvanised steel pipes for steel Fittings:

40 25mm Fittings
No. 16

41 32mm Fittings
No. 10

FLUE PIPES ETC

1.2mm Galvanised sheet iron pipes etc:

42 200mm Diameter pipe 3450mm long fixed with holderbats to wall.


No. 2

STORM WATER, SOIL WATER, AND WATER SYSTEMS REPAIRS

Clean, unblock, seal leakages and where applicable repair or replace


part of or entire system or sub-systems to restore service:

43 Soilwater system, including inspection chambers, rodding eyes, vents, etc.


m 55

44 Water reticulation system, including fire protection sub-system, valves,


connections, pipe replacement, etc
m 135

SLEEVES

Plastic sleeves for pipes not exceeding 100mm diameter:

45 Sleeve exceeding 250mm and not exceeding 500mm long.


No. 35

Plastic sleeves for pipes exceeding 100mm and not exceeding 200mm
diameter:

46 Sleeve exceeding 250mm and not exceeding 500mm long.


No. 35

Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
61
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 11
PLUMBING AND DRAINAGE
COLLECTION
Page No

Brought Forward from Page 55

56

57

58

59

60

61

Carried To Section Summary $


Section No. 2
Bill No. 11
Plumbing And Drainage
62
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 12
ELECTRICAL WORK (PROVISIONAL)

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

DISTRIBUTION BOARDS

Distribution board complete with sheetmetal tray, frames, sub-frames,


busbars, provision for four future circuit breakers, legend card, circuit
breakers, fuses, relay, volt-meter, ammeter, transformer, earth leakage
unit, time switch, etc.

1 10A Single pole circuit breaker.


No. 1

2 15A Earth leakage and circuit breaker combination..


No. 1

3 20A Double pole main switch isolator.


No. 1

CONDUCTORS

Bare stranded copper earth conductor drawn into wireways.

4 2.5mm2
m 30

PVC insulated stranded copper conductor drawn into wireways.

5 2.5mm².
m 40

6 4mm².
m 20

Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
63
Package 3 Lot 3
Rate Amount

LIGHT SWITCHES, SWITCHED SOCKET OUTLETS, ETC.

Switches, etc. complete with cover plate fixed in flush box.

7 16A One-lever one-way switch.


No. 1

8 16A Three-pin switched socket outlet.


No. 2

ELECTRICAL RETICULATION

Termination for bare and PVC insulated copper conductors including


lugs and connections.

9 Install bird cage on siren


No. 1

10 Decommission Electricity and make safe


Item

11 Replace 1G1/2W switches weatherproof


No. 1

12 Replace 1G1/2W switches


No. 3

13 Replace SSO
No. 3

14 Check and repair faulty power circuit including control gear and
isulation,phase rotation,wiring
No. 2

15 Rewire fitting or circuit to distribution board, excluding existing wiring or


control gear
No. 1

16 Application for electrical power supply to local supply Authority

17 Excavation in hard rock conditions for cable trench (for new or existing
cables, to 600mm deep)
m³ 28

Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
64
Package 3 Lot 3
Rate Amount

18 Termination / make safe / remove existing cabling or wires not in use


Item

19 Conceal / make good existing cabling or wires on surface by grouping


multiple wires and tying down, conceal using metal trunking or conduits

Distrubution board:

20 Remove and replace door with latch, tray, and blank plates complete with
25mm pad lock
No. 2

21 Clean kiosk(s) complete, remove cobwebs and dust, check mechanical


connections, latch mechanisms gaskets, replace if needed
Item

Take delivery and install luminaries or equipment supplied by others


complete with lamps, connections, etc:

22 Flood light, mast / wall mounted, with HID lamp-make good replace lamp
No. 2

23 Replace 36W flourescent tubes


No. 34

24 Replace 58W flourescent tubes


No. 17

25 Replace 100W flourescent tubes


No. 6

26 Replace external CFL's on external lights


No. 12

27 Replace damaged 1500/1800mm with standard type C with 2 x 1200mm


fittings complete with tubes
No. 10

28 Replace wall mounted light fitting as 'Lascon' B20 or similar approved and
bulb 2PL9 bulbs (B)
No. 4

Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
65
Package 3 Lot 3
Rate Amount

29 Make good 36/58/100W fluorescent light fitting, including re-fitting, replace


starter and / or transformer
No. 18

Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
66
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 12
ELECTRICAL WORK (PROVISIONAL)
COLLECTION
Page No

Brought Forward from Page 63

64

65

66

Carried To Section Summary $


Section No. 2
Bill No. 12
Electrical Work (provisional)
67
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 13
GLAZING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

GLAZING TO STEEL WITH PUTTY

4mm Clear float glass:

1 Panes exceeding 0,1m2 and not exceeding 0,5m2.


m² 2

Carried To Section Summary $


Section No. 2
Bill No. 13
Glazing
68
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 14
PAINTWORK

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SUPPLEMENTARY PREAMBLES

All work to be executed in strict accordance with the specifications of


Plascon Paints (Pty) Ltd. The coating systems are as per Plascon's 'List of
Decorative Paint Products' unless otherwise specified. Full specifications
are available on request from Plascon approved suppliers.

Primers and first coats may be thinned in accordance with the paint
specifications of Plascon Paints (Pty) Ltd to aid the absorption of the paint.

All surfaces must be sound, clean and have a moisture content of less than
8% for walls generally and 3% for slabs/screeds etc.

Where surfaces of plaster etc are sandy / friable, the first coat must be
replaced with 'Plascon Merit' plaster primer thinned 10% with turpentine.

All paints are to bear the SABS mark and are to be applied in strict
accordance with manufacturer's instructions.

Prices for paintwork are to include for masking and protecting of all finished
paintwork and all finished joinery, tiling, floor coverings, etc. during painting.
Any damage to such finished work shall be removed, repaired or replaced at
the Contractor's expenses.

Prices for painting are to include for painting a one square metre sample
panel of all finishing coats and for repeating if required. Only after written
approval from Architect may finishing coats be applied.

Prices for all paintwork are to include all colours which have a value of 8 or
higher on the Munsell system in accordance with the relevant SABS
specification.

The Contractor shall provide all necessary dust sheets, covers, etc. required
during painting. All door handles, locks and other ironmongery, pelmets,
electrical switch and socket covers, etc. are to be removed before
commencing the painting. All paint spots, stains, etc. are to be cleaned off
all floors, walls, glass, doors, frames, fittings, etc. after completion of the
painting

Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
69
Package 3 Lot 3
Rate Amount

PAINTWORK ETC TO NEW WORK

ON METAL

Spot priming defects in pre-primed surfaces with zinc chromate primer


and applying one undercoat and two coats enamel paint on steel:

1 On doors, gates, grilles, burglar screens, balustrades, etc (both sides


measured over the full flat area).
m² 112

2 On corner protectors.
m² 443

Wash down with approved cleaning agent and apply one coat calcium
plumbate primer, one undercoat and two coats enamel paint on
galvanised steel:

3 On IBR metal ceilings (measured flat)


m² 1085

ON WOOD, WOOD BOARD

Stop, fill, sand down and prepare wood surfaces and apply one coat
'Plascon Oil Wood Primer' or similar approved, one coat 'Plascon Merit
Universal Undercoat' or similar approved and two coats 'Plascon
Velvaglo Polyurethane Enamel' or similar approved paint:

4 On exterior barge and fascia boards, etc not exceeding 300 mm girth.
m 177

5 On interior skirtings, rails, etc not exceeding 300 mm girth.


m 1638

PAINTWORK, ETC TO PREVIOUSLY PAINTED WORK

ON SMOOTH PLASTER

Remove any loose and flaking residue by means of wire brushing,


wash with 'Polycell Sugar Soap' or weak spirits of salts, open up
cracks and make good with 'Polycell Mendall 90' or 'Polycell Polyfilla
Exterior' filler sanded smooth, apply one coat 'Plascon Masonry Paint'
and two coats 'Plascon Polvin Super Acrylic' paint on existing water
based paint surfaces:

6 On interior walls.
m² 2805

Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
70
Package 3 Lot 3
Rate Amount

7 On interior walls in patterned multi-colours.


m² 148

8 On narrow widths, (internal & external)


m² 435

9 On interior walls in bands not exceeding 300mm girth.


m 1094

Remove any loose and flaking residue by means of wire brushing,


wash with 'Polycell Sugar Soap' or weak spirits of salts, open up
cracks and make good with 'Polycell Mendall 90' or 'Polycell Polyfilla
Exterior' filler sanded smooth, apply one coat 'Plascon Masonry Paint'
and one coat 'Plascon Wall and All Pure Acrylic' paint on existing
water based paint surfaces:

10 On exterior walls.
m² 2391

11 On exterior mouldings and bands not exceeding 300mm wide or girth in


colours differing form surrounding work.
m 266

ON METAL

Remove any loose and flaking residue by means of wire brushing,


sand down, wash with 'Polycell Sugar Soap' or weak spirits of salts,
rinse, spot priming with 'Plascon Namelcote Synthetic Metal Primer'
and apply one coat 'Plascon Merit Universal Undercoat' and two coats
'Plascon Super Univeral Enamel' paint on existing steel:

12 On doors frames
m² 97

13 On exterior steel roof members at eaves and verges.


m² 177

14 On windows, gates, grilles, burglar screens, balustrades, etc (both sides


measured over the full flat area).
m² 16

15 On IBR metal ceilings.(measured flat)


m² 1019

Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
71
Package 3 Lot 3
Rate Amount

16 On mesh window covers (both sides measured).


m² 44

17 On metal members supporting walkway covers and overhangs.


m² 89

18 On rails, bars, pipes, etc not exceeding 300 mm girth.


m 44

ON WOOD, WOOD BOARD

Remove any loose and flaking residue by means of wire brushing,


sand down, wash with 'Polycell Sugar Soap' or weak spirits of salts,
rinse and apply one coat 'Plascon Oil Wood Primer', one coat 'Plascon
Merit Universal Undercoat' and two coats' Plascon Super Universal
Enamel' paint on existing enamel surfaces:

19 On interior fittings.
m² 74

20 On exterior roof timbers at eaves and verges.


m² 177

Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
72
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 14
PAINTWORK
COLLECTION
Page No

Brought Forward from Page 69

70

71

72

Carried To Section Summary $


Section No. 2
Bill No. 14
Paintwork
73
Package 3 Lot 3
Rate Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 15
EXTERNAL WORKS

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SITE CLEARANCE, ETC.

Site clearance, etc:

1 Allow for clearing the area of the site to be built upon of all grass, weeds,
shrubs, trees with trunks not exceeding 200mm girth, debris, etc., including
grubbing up all roots, scoffling up as required and cart away all vegetation
and debris.
m² 115

ROADWORK, PAVING, ETC

Precast concrete kerbs (30 Mpa) finished smooth on exposed surfaces


including bedding, cutting, pointing and pointing and 20/19mm Mpa
unreinforced concrete haunching at junctions:

2 Garden kerb 900 x 250 x 75mm high with twice chamfered edges with 150 x
300mm unreinforced concrete haunching at back of each joint including
excavation, formwork, backfilling, etc.
m 18

3 Barrier kerb 900 x 250 x 125mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc.
m 18

4 Barrier kerb 900 x 250 x 125mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc, circular on plan exceeding 4m radius.
m 23

5 Mountable kerb 900 x 125 x 250mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc.
m 77

Carried to Collection $
Section No. 2
Bill No. 15
External Works
74
Package 3 Lot 3
Rate Amount

6 Mountable kerb 900 x 125 x 250mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc., circular on plan not exceeding 4m radius.
m 69

7 1,200mm Diameter 300mm high precast concrete ring tree planter including
excavation, backfilling, etc.
No. 8

Open face excavation over sloping site:

8 Open face excavation to form platform under parking areas etc and carting
away surplus material from site to a dumping site to be located by the
contractor.
m³ 123

Extra over bulk excavation in earth for excavation in:

9 Soft rock
m³ 6

10 Hard rock
m³ 3

Extra over bulk excavation in earth for breaking up and removing:

11 Brickwork.
m³ 5

12 Unreinforced concrete.
m³ 5

13 Reinforced concrete.
m³ 5

Earth filling supplied by the contractor under pavings etc:

14 Over site of G5 material in accordance with SABS 1200ME, stabilised to


attain UCS > 1,0 MPa after seven days and compacted to 98% Mod
AASHTO density.
m³ 88

Carried to Collection $
Section No. 2
Bill No. 15
External Works
75
Package 3 Lot 3
Rate Amount

15 Over site of G6 material in accordance with SABS 1200ME, stabilised to


attain UCS > 1,0 MPa after seven days and compacted to 98% Mod
AASHTO density.
m³ 49

Compaction of surfaces:

16 Compaction of ground surface under pavings etc. including scarifying for a


depth of 150mm, breaking down oversize material, adding suitable material
where necessary and compacting to 95 % Mod AASHTO density (materials
to comply with CBR >25%)
m² 215

Anti-termite soil poison and weedkiller:

17 Approved brands of weedkiller and termite poisoning mixed and applied in


accordance with the manufacturer's instructions under pavings, etc.
m² 215

65mm Thick 35Mpa standard grey double zig zag interlocking


roadstone paving with open joints on and including 25mm thick river
sand bed with sand and cement mixture swept into joints, hose down
including bedding, jointing and pointing:

18 Paving in herring borne pattern bond with butt joints to falls.


m² 215

25Mpa/19mm Reinforced Concrete:

19 Toes and walls of walkways


m³ 6

Garden soil to planter:

20 Remove all building rubble and materials to 500mm depth and fill in with
garden soil for grassing, planting, etc (Plant, grass, cost elsewhere
measured).
m² 46

Carried to Collection $
Section No. 2
Bill No. 15
External Works
76
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS
BILL NO. 15
EXTERNAL WORKS
COLLECTION
Page No

Brought Forward from Page 74

75

76

Carried To Section Summary $


Section No. 2
Bill No. 15
External Works
77
Package 3 Lot 3
Amount

SECTION NO. 2
RENOVATIONS

SECTION SUMMARY
Bill Page
No.

1 ALTERATIONS 37

2 EARTHWORKS 40

3 CONCRETE, FORMWORK AND REINFORCEMENT 41

4 MASONRY 44

5 CARPENTRY AND JOINERY 45

6 CEILINGS PARTITIONS AND ACCESS FLOORING 46

7 IRONMONGERY 49

8 METALWORK 52

9 PLASTERING 53

10 TILING 54

11 PLUMBING AND DRAINAGE 62

12 ELECTRICAL WORK (PROVISIONAL) 67

13 GLAZING 68

14 PAINTWORK 73

15 EXTERNAL WORKS 77

Carried to Final Summary $


Section No. 2
SECTION SUMMARY

78
Package 3 Lot 3

SECTION NO. 3

NEW BUILDINGS

79
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 1
EARTHWORKS (PROVISIONAL)

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

NATURE OF GROUND

The nature of the ground is assumed to be loose sandy material,


therefore "earth", but possibly interspersed with "hard rock" or "soft
rock"

SITE CLEARANCE, ETC.

Site clearance, etc.:

1 Allow for clearing the area of the site to be built upon of all grass, weeds,
shrubs, trees with trunks not exceeding 200mm girth, debris, etc., including
grubbing up all roots, scoffling up as required and cart away all vegetation
and debris.
m² 948

EXCAVATION OTHER THAN BULK

Excavation in earth not exceeding 2m deep:

2 Trenches.
m³ 173

3 Trenches and holes for thickening under paving edge.


m³ 6

Extra over excavations other than bulk in earth for excavation in:

4 Soft rock.
m³ 18

5 Hard rock.
m³ 8

Carried to Collection $
Section No. 3
Bill No. 1
Earthworks (provisional)
80
Package 3 Lot 3
Rate Amount

Compaction:

6 Trim and level off surface of excavated surfaces to receive concrete


footings, including ripping and scarifying as necessary and compacting the
whole area for a depth of 150mm to a density of at least 95% Mod.
AASHTO maximum density.
m² 173

Risk of collapse of excavations other than bulk:

7 Sides of trench and hole excavations not exceeding 1,5m deep.


m² 520

Soilcrete filling from selected earthfilling mixed with 5% cement by


volume compacted to 95% Mod. AASHTO maximum density and
mechanically Vibrated:

8 In trenches, holes etc under strip foundations.


m³ 49

CARTING AWAY.

Extra over all excavations for loading, carting and dumping surplus
excavated material (no allowance made for increase in bulk):

9 Off site to a dumping site to be found by the Contractor.


m³ 55

EARTH FILLING, ETC.

Filling with material from the excavations compacted to a density of at


least 95% Mod. AASHTO maximum density:

10 Under floors, pavings, etc.


m³ 75

11 Backfilling to trenches, holes, etc.


m³ 44

Filling with approved material supplied and carted onto site by the
Contractor, compacted to a density of at least 95% Mod. AASHTO
maximum density:

12 Under floors, pavings, etc.


m³ 40

Carried to Collection $
Section No. 3
Bill No. 1
Earthworks (provisional)
81
Package 3 Lot 3
Rate Amount

Coarse river sand filling compacted to 95% Mod. AASHTO maximum


density:

13 Under floors, etc.


m³ 22

Surface Preparation:

14 Trim and level off surface of natural ground surfaces to receive concrete
paving, including ripping and scarifying as necessary and compacting the
whole area for a depth of 150mm to a density of at least 95% Mod.
AASHTO maximum density.
m² 243

KEEPING EXCAVATIONS FREE OF WATER

Keeping excavations free of water:

15 Allow for keeping excavations free of water by hand or machinery.


Item

SOIL POISONING

Approved brands of weedkiller mixed with termite poison and applied


in accordance with the manufacturer's instructions:

16 To bottoms of trenches, etc.


m² 173

17 Under floors, etc., including forming and poisoning shallow furrows against
foundation walls, etc., filling in furrows and ramming.
m² 446

Carried to Collection $
Section No. 3
Bill No. 1
Earthworks (provisional)
82
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 1
EARTHWORKS (PROVISIONAL)
COLLECTION
Page No

Brought Forward from Page 80

81

82

Carried To Section Summary $


Section No. 3
Bill No. 1
Earthworks (provisional)
83
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 2
CONCRETE, FORMWORK AND REINFORCEMENT

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

TEST BLOCKS

Test blocks:

1 Making and testing set of six 150 x 150 x 150mm concrete strength test
cubes (Provisional).
Sets 24

UNREINFORCED CONCRETE

25Mpa/19mm Concrete

2 Surface beds cast in panels on waterproofing.


m³ 44

3 Pavings cast in panels.


m³ 31

4 Surface beds.
m3 0.15

5 Truss anchor block.


m3 1.8

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

25Mpa/19mm Concrete

6 Strip footings.
m³ 40

Carried to Collection $
Section No. 3
Bill No. 2
Concrete, Formwork And Reinforcement
84
Package 3 Lot 3
Rate Amount

FINISHING TOP SURFACE OF CONCRETE

Finishing top surfaces of concrete smooth with a power float:

7 Surface beds, slabs, etc.


m² 443

8 Paving to falls.
m² 243

GROOVES, ETC.

Grooves, channels, mortices, sinkings, etc in concrete:

9 40 x 40mm Chamfer to exposed concrete edges.


m 210

ROUGH FORMWORK (DEGREE OF ACCURACY II)

Rough Formwork to Sides:

10 Truss anchor block.


m² 16

11 Edges, risers, ends and reveals not exceeding 300mm high or wide.
m 238

Carried to Collection $
Section No. 3
Bill No. 2
Concrete, Formwork And Reinforcement
85
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 2
CONCRETE, FORMWORK AND REINFORCEMENT
COLLECTION
Page No

Brought Forward from Page 84

85

Carried To Section Summary $


Section No. 3
Bill No. 2
Concrete, Formwork And Reinforcement
86
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 3
MASONRY

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

BRICKWORK IN FOUNDATIONS (PROVISIONAL)

Brickwork of concrete bricks [14Mpa] in Class I mortar:

1 Half brick walls.


m² 89

2 One brick walls.


m² 204

BRICKWORK IN SUPERSTRUCTURE

Brickwork of concrete bricks [7Mpa] in Class I mortar:

3 Half brick walls.


m² 205

4 Half brick walls in beamfilling.


m² 32

5 One brick walls.


m² 472

BRICKWORK SUNDRIES

Brickwork sundries:

6 Brick-on-edge cill set sloping and projecting.


m 59

Carried to Collection $
Section No. 3
Bill No. 3
Masonry
87
Package 3 Lot 3
Rate Amount

Fair face to brickwork in horizontal stretcher bond pointed with


recessed horizontal and flush vertical joints:

7 Extra for fair face.


m² 405

Cement wash of 1:3 liquid cement and sand mixture applied with a
brush:

8 On brick surfaces.
m² 405

Joint forming material in movement joints:

9 10mm Bitumen impregnated fibre board built in vertically through brick walls.
m² 5

Brickwork reinforcement:

10 75mm Wide reinforcement built in horizontally in foundations.


m 1090

11 75mm Wide reinforcement built in horizontally.


m 1025

12 150mm Wide reinforcement built in horizontally in foundations.


m 2518

13 150mm Wide reinforcement built in horizontally.


m 2471

Approved prestressed fabricated lintels:

14 110 x 75mm Lintels in lengths not exceeding 3m.


m 159

Galvanised wire ties etc:

15 4mm Diameter roof tie 2m girth bent double with one end tied around steel
purlin and other end built into brickwork.
No. 12

Carried to Collection $
Section No. 3
Bill No. 3
Masonry
88
Package 3 Lot 3
Rate Amount

Galvanised hoop iron cramps, ties, etc:

16 30 x 1,6mm Roof tie 2,0m long tied around steel purlin and shot pinned to
both sides of brickwork.
No. 16

Air bricks etc:

17 230 x 160mm Galvanised air brick.


No. 24

BRICK PAVING

Paving of 65mm thick cement paving bricks with open joints on 50mm
thick river sand bed with sand and cement mixture swept into joints,
hosed down and pointed with slightly keyed joints including termite
and soil posioning, preparation of ground or filling and compaction:

18 Paving in fish bone patern.


m² 5

19 110mm Wide brick-on-end edging on 100mm thick concrete bed.


m 1

Carried to Collection $
Section No. 3
Bill No. 3
Masonry
89
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 3
MASONRY
COLLECTION
Page No

Brought Forward from Page 87

88

89

Carried To Section Summary $


Section No. 3
Bill No. 3
Masonry
90
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 4
WATERPROOFING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

DAMPPROOFING OF WALLS AND FLOORS

One layer of 375 micron Consol Plastics Brikgrip DPC embossed damp
proof course:

1 In walls.
m² 24

One layer of 250 micron Consol Plastics Gunplas Black waterproof


sheeting sealed at laps with Gunplas Pressure Sensitive Tape:

2 Under surface beds.


m² 521

JOINT SEALANTS ETC

'Expandite' or other approved two-part grey polysulphide sealing


compound including backing cord, bond breaker, primer, etc:

3 10 x 15mm In vertical expansion joints.


m 22

'Sikaflex' PRO-3 WF multi-use, one component, polyurethane sealant


in colour Concrete Grey applied in accordance with the manufacturer's
instructions:

4 10 x 15mm elastic joint on floor tiling.


m 25

Carried To Section Summary $


Section No. 3
Bill No. 4
Waterproofing
91
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 5
ROOF COVERINGS

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

TROUGHED METAL SHEETING AND ACCESSORIES

0.5mm Thick industrial Z275 IBR profiled or similar approved sheet


steel in single lengths fixed to steel purlins or rails and sheet steel
accessories:

1 Roof covering with pitch not exceeding 25 degrees, in transportable lengths


not exceeding 20m.
m² 756

Flashings:

2 Ridge capping 550mm girth, three times bent along girth and notched on
site to suit IBR roof profile.
m 68

3 Serrated eaves closers.


m 130

4 Narrow and broad flute closers.


m 134

5 Ridge cape and closures to suit IBR profile


No. 6

Carried to Collection $
Section No. 3
Bill No. 5
Roof Coverings
92
Package 3 Lot 3
Rate Amount

ROOF AND WALL INSULATION

Sisalation 400 housing grade glass fibre reinforced aluminium foil


bonded insulation:

6 Insulation laid taut over purlins on galvanised straining wires (at


approximately 300mm centres).
m² 604

Carried to Collection $
Section No. 3
Bill No. 5
Roof Coverings
93
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 5
ROOF COVERINGS
COLLECTION
Page No

Brought Forward from Page 92

93

Carried To Section Summary $


Section No. 3
Bill No. 5
Roof Coverings
94
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 6
CARPENTRY AND JOINERY

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

FLUSH DOORS

Semi-solid flush doors with commercial veneer:

1 40mm Door 813 x 2032mm high.


No. 1

BEADS, ARCHITRAVES, ETC

Wrought 'Supawood':

2 22 x 150mm Angle rounded bumper rail.


m 139

3 22 x 75mm cornice.
m 160

NOTICE BOARDS, PINNING BOARDS, KEYBOARDS, DUCKBOARDS,


ETC

Vitrex or similar approved:

4 Pinboards model 2300 code: '2315', size 1,000 x 1,200mm, with aluminium
frame plugged and screwed to wall with 38mm steel countersunk screws
(Drwng F3).
No. 14

5 Pinboard model 2300 code: '2309', size 2,400 x 1,200mm, with aluminium
frame plugged and screwed to wall with 38mm steel countersunk screws
(Drwng F1).
No. 14

Carried To Section Summary $


Section No. 3
Bill No. 6
Carpentry And Joinery
95
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 7
CEILINGS PARTITIONS AND ACCESS FLOORING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

NAILED UP CEILINGS

0.5mm Thick light industrial Z275 IBR profiled sheet steel in single
lengths fixed to steel purlins or rails:

1 Ceilings.
m² 454

2 Extra over ceiling for 1000 x 1000mm trap door of 30 x 30 x 2.5mm angle
section framing covered with 'Alu zinc' IBR profiled sheeting and fitted flush
in opening.
No. 3

0.8mm Thick galvanised sheet flashings:

3 Narrow and broad flute closers 150mm girth to suit IBR profile.
m 114

4 Angle flashing once bend 300mm girth.


m 160

Carried To Section Summary $


Section No. 3
Bill No. 7
Ceilings Partitions And Access Flooring
96
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 8
IRONMONGERY

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

LOCKS

Solid or similar approved:

1 'Blesbok' Art 460/313 four lever lockset with striking plate fixed to metal
complete with a pair of handles.
No. 1

LETTERS, NAMEPLATES, ETC.

Solid or similar approved:

2 20mm High letter or numeral.


No. 30

Solid:

3 20mm High letter or numeral.


No. 15

4 150 x 150mm Anodised aluminium plate with male or female symbol.


No. 4

5 150 x 150mm Natural anodised aluminium plate with paraplegic symbol.


No. 1

BATHROOM FITTINGS

Chairman Industries:

6 32mm Type DL2 back grab rail plugged.


No. 1

Carried to Collection $
Section No. 3
Bill No. 8
Ironmongery
97
Package 3 Lot 3
Rate Amount

7 32mm Type SR2 side grab rail plugged.


No. 1

SUNDRIES

Solid or similar approved:

8 38mm Diameter rubber door stop floor mounted.


No. 13

Solid:

9 38mm Diameter rubber door stop.


No. 4

10 38mm Diameter rubber door stop plugged to wall.


No. 8

SHELVING UNITS

Approved industrial steel shelving units with standard epoxy powder


coated finish including uprights, open base foot pieces, shelf
brackets, shelves, spacers, top rails, top finishing plates and
adjustable book clips:

11 Single shelving unit 3600 x 312 x 1905mm high in 4 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 2

12 Single shelving unit 7200 x 312 x 1905mm high in 8 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 2

13 Single shelving unit 1800 x 312 x 1905mm high in 2 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 1

14 Single shelving unit 1800 x 450 x 1905mm high in 2 bays with uprights,
each bay 900mm wide with 6 x 450mm shelves.
No. 1

15 Single shelving unit 4500 x 312 x 1905mm high in 5 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 1

Carried to Collection $
Section No. 3
Bill No. 8
Ironmongery
98
Package 3 Lot 3
Rate Amount

16 Single shelving unit 4500 x 450 x 1905mm high in 5 bays with uprights,
each bay 900mm wide with 6 x 3450mm shelves.
No. 1

STEEL LOCKERS

Approved steel lockers with standard baked enamel finish:

17 Teachers cupboard 900 x 450 x 1800mm high with four adjustable shelves.
No. 6

PINNING BOARDS, WRITING BOARDS, PROJECTION SCREENS, ETC

Vitrex or similar approved:

18 System 1000 green writing board 2700 x 1140mm high with chalk rail
plugged.
No. 7

Carried to Collection $
Section No. 3
Bill No. 8
Ironmongery
99
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 8
IRONMONGERY
COLLECTION
Page No

Brought Forward from Page 97

98

99

Carried To Section Summary $


Section No. 3
Bill No. 8
Ironmongery
100
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 9
STRUCTURAL STEELWORK

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

STEEL TRUSSES ETC

Welded roof trusses of angle section rails, struts, braces, cleats, etc
and flat section bearer, gusset and connection plates bolted to steel:

1 Seventeen double pitched trusses 10440 x 1024mm high extreme.


Kg 2450

Bolts to trusses etc:

2 High tensile bolts.


Kg 6

3 M8 x 100mm Expansion bolt.


No. 176

4 12mm Diameter U-shaped anchor bolt 800mm girth.


No. 44

PURLINS, GIRTS, BRACING, ETC

Purlins and girts bolted to steel:

5 Lipped channel section purlins.


Kg 2560

6 Lipped channel section brandering.


Kg 1517

Carried To Section Summary $


Section No. 3
Bill No. 9
Structural Steelwork
101
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 10
METALWORK

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

SUNDRY STEELWORK

Welded bearers and framing to ceiling trapdoor:

1 30 x 30 x 2.5mm Angle section framing.


Kg 24

2 Extra over 30 x 30 x 2.5mm angle section for welded T-intersection.


No. 32

WELDED SCREENS, GATES, ETC.

Screens and gates:

3 Single burglar gate 813 x 2337mm high of 40 x 40 x 2mm hollow section


frame and two x 40 x 40 x 2mm hollow section horizontal middle rails filled
in with 900mm long 12 x 12 x 2mm hollow section vertical rails at the bottom
section and 1167mm long 12 x 12 x 2mm hollow section vertical rails at the
top section at approximately 120mm centres and fitted with one and a half
pairs of suitable hinges welded to door frame and lock box with and
including 'Solid' 378 narrow style cylinder dead lock and 3mm steel cover
plate 120 x 813 cover plate welded middel rails.
No. 3

PRESSED STEEL DOOR FRAMES

1,2mm Double rebated frames suitable for half brick walls:

4 Frame for door 813 x 2032mm high.


No. 1

Carried to Collection $
Section No. 3
Bill No. 10
Metalwork
102
Package 3 Lot 3
Rate Amount

STEEL WINDOWS, DOORS, ETC.

Standard residential windows with NBP2 burglar bars to all sections:

5 Window type NG2, 1022 x 359mm high (W3).


No. 3

6 Window type E2H, 1022 x 654mm high.


No. 6

7 Window type E4H, 1511 x 654mm high (W2).


No. 13

8 Window type D4H, 1511 x 1245mm high (W1).


No. 20

PRESSED STEEL COMBINATION DOORS AND FRAMES

Standard 'Wispeco' chawl door with back panel:

9 Door 813 x 2032mm high with double rebated frame suitable for one wall
and with 'Solid' Besbok 460/313 four lever mortice lock complete with a pair
of handles.
No. 9

10 Door 813 x 2032mm high and frame with fixed fanlight 305mm high suitable
for one wall and with 'Solid' Blesbok 460/313 four lever mortice lock
complete with a pair of handles.
No. 2

11 Modified door 713 x 2032mm high with double rebated frame suitable for
813 x 2032mm high door and for half wall and with 'Solid' Besbok 464/364
WC lockset.
No. 7

12 Door 813 x 2032mm high with double rebated frame suitable for one wall
and with 'Solid' Besbok 460/313 four lever mortice lock.
No. 3

13 Door 813 x 2032mm high and frame with fixed fanlight 305mm high suitable
for one wall and with 'Solid' Besbok 460/313 four lever mortice lock.
No. 2

Carried to Collection $
Section No. 3
Bill No. 10
Metalwork
103
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 10
METALWORK
COLLECTION
Page No

Brought Forward from Page 102

103

Carried To Section Summary $


Section No. 3
Bill No. 10
Metalwork
104
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 11
PLASTERING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

SCREEDS

Screeds with compressive strength of 25 Mpa steel trowelled on


exposed concrete complete with Durashake or similar approved floor
harderner or similar approved applied to the manufacturer's
specifications:

1 50mm Thick on floors and landings.


m² 458

INTERNAL PLASTER

Cement plaster on brickwork:

2 On walls.
m² 855

3 On narrow widths.
m² 21

EXTERNAL PLASTER

Cement plaster on brickwork:

4 On narrow widths.
m² 14

5 On 200mm wide band.


m 450

6 On sloping top, edge and projecting soffits of sills 505mm girth.


m 59

Carried to Collection $
Section No. 3
Bill No. 11
Plastering
105
Package 3 Lot 3
Rate Amount

CORNER PROTECTORS, DIVIDING STRIPS, ETC

Corner protectors, dividing strips, etc:

7 3 x 35mm Flat section steel weather bar.


m 13

Carried to Collection $
Section No. 3
Bill No. 11
Plastering
106
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 11
PLASTERING
COLLECTION
Page No

Brought Forward from Page 105

106

Carried To Section Summary $


Section No. 3
Bill No. 11
Plastering
107
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 12
TILING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

NOSING, JOINT COVERS, PROTECTORS, ETC.

Wall edge protectors:

1 'Schluter Schiene Type AE 80' or similar approved brushed aluminium tile


edge trim cut to lengths and bedded in tile adhesive.
m 350

WALL TILING

300 x 300mm 'Dimo Top' unglazed ceramic tiles fixed with adhesive to
plaster (plaster elsewhere) and flush pointed with tinted jointing
compound:

2 On walls as splash backs.


m² 1

FLOOR TILING

300 x 300mm 'Dimo Top' unglazed floor tiles on average 35mm


bedding on concrete and flush pointed with tinted waterproof jointing
compound:

3 On floors to falls.
m² 5

4 Circular cutting.
No. 9

5 100mm high cut tile skirting.


m 350

Carried to Collection $
Section No. 3
Bill No. 12
Tiling
108
Package 3 Lot 3
Rate Amount

SUNDRIES

Sundries:

6 'Schluter Rondec' aluminium tile edging.


m 3

Carried to Collection $
Section No. 3
Bill No. 12
Tiling
109
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 12
TILING
COLLECTION
Page No

Brought Forward from Page 108

109

Carried To Section Summary $


Section No. 3
Bill No. 12
Tiling
110
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 13
PLUMBING AND DRAINAGE (PROVISIONAL)

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

SOIL DRAINAGE

Sundries:

1 Testing waste pipe system.


Item

SANITARY FITTINGS

Approved stainless steel:

2 506 x 450mm Wash hand basins.


No. 6

'Citimetal' stainless steel:

3 Type TU 101 urinal 1460mm wide with 11 litre 'Shires Lynx' automatic
flushing cistern, flush and sparge pipes and hinged domical grating.
No. 2

'Ballam' Waterslot or similar approved:

4 High level water-saving WC suit comprising of Polyethylene toilet bowl with


heavy duty double flap seat and cover, 'Shires' remote flushing control and
9l 'Shires Lynx' duranite cistern.
No. 7

5 Low level water-saving WC suit comprising of Polyethylene bowl with heavy


duty double flap seat and cover 9l 'Shires Lynx' duranite cistern.
No. 2

Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
111
Package 3 Lot 3
Rate Amount

WASTE UNIONS ETC

Waste unions etc:

6 40mm 'Cobra' 310 sink waste outlet.


No. 6

TRAPS ETC

uPVC:

7 40mm Deep seal 'P' or 'S' trap.


No. 6

Brass:

TAPS, VALVES, ETC

'Cobra Watertech':

8 15mm Star 232/350CP angle regulating valve.


No. 15

9 15mm Star 214CP bibtap.


No. 6

SANITARY PLUMBING

uPVC pipes:

10 50mm Pipes.
m 4

11 110mm Pipes.
m 7

12 40mm Pipes under floors laid in and including trenches.


m 7

13 110mm Pipes laid in and including trenches not exceeding 1m deep.


m 15

Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
112
Package 3 Lot 3
Rate Amount

Extra over uPVC pipes for fittings:

14 110mm Reducer.
No. 1

15 50mm Bend.
No. 3

16 110mm Bend.
No. 11

17 110mm Reducing junction.


No. 5

18 110mm Pan connector.


No. 8

19 110mm Bent pan connector.


No. 2

20 40mm Access bend.


No. 1

21 110mm Access bend.


No. 8

22 110mm Stubstack consisting of two x 50mm inlets, necessary pipe and all
fittings.
No. 1

23 110mm Stubstack consisting of two x 110mm inlets, necessary pipe and all
fittings.
No. 1

24 110mm Stubstack consisting of three x 110mm, necessary pipe and all


fittings.
No. 1

25 110mm Stubstack consisting of two x 110mm, one x 50mm inlets,


necessary pipe and all fittings.
No. 1

Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
113
Package 3 Lot 3
Rate Amount

26 110mm Stubstack consisting of two x 110mm, two x 40mm inlets,


necessary pipe and all fittings.
No. 1

Gulleys:

27 110mm Overflow gulley not exceeding 1m deep.


No. 4

FLUE PIPES ETC

28 110mm Access junction.


No. 10

WATER SUPPLIES

Class O copper pipes:

29 15mm Pipes.
m 29

30 28mm Pipes.
m 8

Extra over class 10 copper pipes for capillary fittings:

31 15mm Fittings.
No. 38

32 22mm Fittings.
No. 10

33 28mm Fittings.
No. 10

34 Connection of 28mm pipe to 35mm HDPE pipe.


No. 1

TESTING

Testing:

35 22mm Pipes.
m 18

Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
114
Package 3 Lot 3
Rate Amount

36 Testing water pipe system.


Item

37 50mm Pipes under floors laid in and including trenches.


m 2

38 40mm Bend.
No. 4

39 40mm Pipes.
m 5

40 50mm Junction.
No. 2

41 50mm 'GI Two-way' vent valve.


No. 5

42 50mm Reseal 'P' trap.


No. 2

43 50mm Access bend.


No. 1

FIRE APPLIANCES ETC.

'Chubb':

44 9kg Dry chemical fire extinguisher with backing board.


No. 5

Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
115
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 13
PLUMBING AND DRAINAGE (PROVISIONAL)
COLLECTION
Page No

Brought Forward from Page 111

112

113

114

115

Carried To Section Summary $


Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
116
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 14
ELECTRICAL WORK (PROVISIONAL)

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

DISTRIBUTION BOARDS

Lockable distribution board complete with sheetmetal tray, frames,


sub-frames, busbars, provision for two future circuit breakers, legend
card and 25mm pad lock.

1 Distribution board build into wall.


No. 4

2 20A Double pole main switch isolator.


No. 1

3 40A Single pole circuit breaker.


No. 1

4 10A Single pole circuit breaker.


No. 7

5 15A Earth leakage and circuit breaker combination.


No. 2

6 20A Single pole circuit breaker.


No. 2

7 16A Single pole circuit breaker.


No. 1

8 16A Earth leakage and circuit breaker combination.


No. 1

Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
117
Package 3 Lot 3
Rate Amount

9 40A Single pole earth leakage.


No. 1

CABLES

600/1000 V PVC/SWA/PVC copper cable pulled in cable sleeves


(sleeves measured elsewhere).

10 16mm2 2-Core.
m 12

CABLE TERMINATIONS

Termination for 600/1000 V PVC/PVC/SWA/PVC copper cables.

11 16mm2 2-Core.
No. 3

EARTHING

Bare copper earth conductor installed with cable (cable measured


elsewhere).

12 10mm2 Conductor.
m 12

EARTH CONDUCTOR TERMINATION

Termination for bare and PVC insulated copper conductors including


lugs and connections.

13 10mm2 Conductor.
No. 4

SLEEVES

PVC sleeve chased or built into wall:

14 50mm Diameter pipe.


m 7

PVC sleeve in ground including excavations, backfilling, etc.:

15 50mm Diameter pipe.


m 11

Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
118
Package 3 Lot 3
Rate Amount

Extra on UPVC piping for:

16 50mm Diameter long radius bend.


No. 4

BLACK ENAMELLED CONDUIT

Suspended from steel trusses or concrete slab with and including


hangers not exceeding 1000mm long and not exceeding 3000mm
above floor level.

17 20mm Diameter.
m 220

RIGID PVC CONDUIT

Cast in concrete, surface bed or screed.

18 20mm Diameter.
m 46

Chased and/or fixed in brickwork not exceeding 3000mm above floor


level.

19 20mm Diameter.
m 45

20 25mm Diameter.
m 15

CONDUIT BOXES AND FITTINGS

Black enameled fixed onto conduit.

21 Round conduit box for 20mm diameter conduit.


No. 44

22 Round conduit box cover.


No. 14

Metal type fixed onto PVC conduit.

23 Round conduit box for 20mm diameter conduit.


No. 1

Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
119
Package 3 Lot 3
Rate Amount

24 100 x 50 x 50mm Deep box.


No. 10

25 100 x 100 x 50mm Deep box.


No. 8

26 Round conduit box cover.


No. 1

27 Cover plate for 100mm x 50mm box.


No. 2

28 Cover plate for 100mm x 100mm box.


No. 3

CONDUCTORS

Bare stranded copper earth conductor drawn into wireways.

29 2.5mm².
m 221

PVC insulated stranded copper conductor drawn into wireways.

30 2.5mm².
m 430

31 4mm².
m 100

LIGHT SWITCHES, SWITCHED SOCKET OUTLETS, ETC.

Switches, etc. complete with cover plate fixed in flush box.

32 16A Water proof light switch.


No. 2

33 16A Two-lever one-way switch.


No. 2

34 10A Day light switch.


No. 2

Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
120
Package 3 Lot 3
Rate Amount

35 16A One-lever one-way switch.


No. 10

36 16A Three-pin switched socket outlet.


No. 8

LUMINARIES AND EQUIPMENT

Luminaries or equipment complete with lamps, connections, etc.,


mounted in position

37 'Lascon B10' ceiling mounted light fitting and bulb. (Type A)


No. 2

38 'Lascon B10' wall mounted light fitting and bulb. (Type B)


No. 8

39 1200mm Double tube 58W open channel fluorescent light fitting and tubes
(C).
No. 30

RIGID PVC CONDUIT

Chased and/or fixed in brickwork not exceeding 3000mm above floor


level:

40 100 x 100 x 50mm Deep box.


No. 3

EARTHING SYSTEM

Conductors, etc.:

41 6mm² Bare stranded copper conductor drawn into conduiting (conduiting


measured elsewhere).
m 90

42 70mm² Bare stranded copper conductor drawn into conduiting (conduiting


measured elsewhere).
m 16

43 Steel core reinforced copper spike (rod) 2000 x 16mm diameter and brass
coupling with driving cap driven into ground.
No. 8

Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
121
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 14
ELECTRICAL WORK (PROVISIONAL)
COLLECTION
Page No

Brought Forward from Page 117

118

119

120

121

Carried To Section Summary $


Section No. 3
Bill No. 14
Electrical Work (provisional)
122
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 15
GLAZING

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

GLAZING TO STEEL WITH PUTTY

4mm Clear float glass:

1 Panes exceeding 0,1m2 and not exceeding 0,5m2.


m² 41

4mm Obscure:

2 Panes exceeding 0,1m2 and not exceeding 0,5m2.


m² 4

TOPS, SHELVES, DOORS, MIRRORS, ETC.

6mm Silvered float glass copper backed mirrors with polished edges
holed for and fixed with chromium plated dome capped mirror screws
with rubber buffers to plugs in brickwork or concrete:

3 Mirror 450 x 600 mm high with four screws.


No. 6

Carried To Section Summary $


Section No. 3
Bill No. 15
Glazing
123
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 16
PAINTWORK

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

ON FLOATED PLASTER

One coat primer and two coats exterior quality PVA emulsion paint:

1 On external floated plaster walls.


m² 48

2 On external mouldings and bands not exceeding 300mm wide or girth in


colours differing form surrounding work.
m 530

One coat alkali resistant primer, one undercoat and two coats eggshell
enamel paint:

3 On internal floated plaster walls.


m² 1061

4 On internal mouldings and bands not exceeding 300 mm wide or girth in


colours differing from surrounding work.
m 420

ON METAL

Spot priming defects in pre-primed surfaces with zinc chromate primer


and applying one undercoat and two coats enamel paint on steel:

5 On combination doors and frames.


m² 207

6 On door frames.
m² 1

Carried to Collection $
Section No. 3
Bill No. 16
Paintwork
124
Package 3 Lot 3
Rate Amount

7 On windows with burglar bars.


m² 119

One coat calcium plumbate primer, one undercoat and two coats
enamel paint on steel:

8 On gates, grilles, burglar screens, balustrades, etc (both sides measured


over the full flat area).
m² 12

9 On members of roof trusses.


m² 188

Wash down with approved cleaning agent and apply one coat calcium
plumbate primer, one undercoat and two coats enamel paint on
galvanised steel:

10 On IBR profiled sheeting ceiling (measured on flat).


m² 494

ON WOOD

One coat wood primer, one undercoat and two coats eggshell enamel
paint:

11 On skirtings, rails, etc not exceeding 300 mm girth.


m 139

12 On doors.
m² 4

Three coats clear varnish:

13 On skirtings, rails, etc not exceeding 300 mm girth.


m 155

SIGNWRITING

Remove all loose particles and laitance and applu one coat Plascon
Waterbased Plaster Primer and two coats Pure Acrylic PVA(allow
sufficient time or drying between coats):

14 Numeral or letter 500mm high.


No. 12

Carried to Collection $
Section No. 3
Bill No. 16
Paintwork
125
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 16
PAINTWORK
COLLECTION
Page No

Brought Forward from Page 124

125

Carried To Section Summary $


Section No. 3
Bill No. 16
Paintwork
126
Package 3 Lot 3
Rate Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 17
EXTERNAL WORKS (PROVISIONAL)

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

The Following bills cater for:

A:2 x 3 Classroom Blocks

B:1 x Waterborne Toilet Blocks

THE FOLLOWING IN FLAG POLE

Excavation in earth not exceeding 2m deep:

1 Holes.
m3 0.3

Finishing top surfaces of concrete smooth with a steel trowel:

2 Paving to falls.
m² 3

Rough Formwork to Sides:

3 Edges, risers, ends and reveals not exceeding 300mm high or wide.
m 7

Bolts:

4 M10 x 75mm Bolts.


No. 2

Paint one coat calcium plumbate primer, one undercoat and two coats
alkyd enamel paint on galvanised steel:

5 On rails, bars, pipes, etc not exceeding 300 mm girth.


m 5

25Mpa/19mm Concrete

6 Pavings cast in panels.


m3 0.37

Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
127
Package 3 Lot 3
Rate Amount

7 Flagpole bases.
m3 0.3

Flagpole:

8 50mm Diameter galvanised pipe.


m 5

9 100 x 40 x 2.5mm Channel 2000mm long and cast into concrete 500mm
deep.
No. 2

10 6mm Diameter bend eye 35mm girth welded to 50mm diameter flagpole.
No. 1

11 Fixing hook formed with two 6mm Diameter round bar bend to right angles
45mm and welded to upright.
No. 1

One coat calcium plumbate primer, one undercoat and two coats alkyd
enamel paint on steel:

12 Extra over 50mm diameter pipe for closed end.


No. 1

13 On rails, bars, pipes, etc.


m² 1

Paint one coat calcium plumbate primer, one undercoat and two coats
alkyd enamel paint on galvanised steel:

14 On rails, bars, pipes, etc not exceeding 300 mm girth.


m 10

15 On rails, bars, pipes, etc.


m² 2

SOIL DRAINAGE

uPVC:

16 Connection to existing water supply including all necessary fittings.


Item

Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
128
Package 3 Lot 3
Rate Amount

17 110mm Slotted uPVC agriculture pipes laid in trenches (elsewhere


measured).
m 30

18 110mm Pipes laid in and including trenches not exceeding 1m deep.


m 20

Extra over uPVC pipes for fittings:

19 110mm End cap.


No. 1

20 110mm Junction.
No. 6

Inspection chambers (covers elsewhere):

21 Inspection chamber 450 x 600mm and not exceeding 750mm deep


internally.
No. 1

Gratings, covers, etc:

22 450 x 600mm x 53kg Cast iron single seal manhole cover and frame.
No. 1

TAPS, VALVES, ETC

Brass:

23 35mm Stopcock.
No. 1

24 Type 395 fabric reinforcement in concrete surface beds, slabs, etc.


m² 9

Sundries:

25 350 x 350mm Cast iron stopcock box including brick chamber below not
exceeding 1000mm deep internally.
No. 1

Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
129
Package 3 Lot 3
Rate Amount

WATER RETICULATION

Class 10 HDPE pipes:

26 35mm Pipes laid in and including trenches.


m 40

Extra over HDPE pipes for solvent welded pressure fittings:

27 35mm Reducer.
No. 1

28 35mm Elbow.
No. 1

EXTERNAL WATER SUPPLIES

French drains:

29 French drain comprising of 700 x 780 x 5000mm long trench including flat
stone placed over slots of agricultural pipes (elsewhere measured) and
trench filled with graded stone.
No. 6

30 Connect to existing water supply including water meter and all necessary
fittings.
Item

ELECTRICAL RETICULATION

600/1000 V PVC/PVC/SWA/PVC copper cable laid in and including


trenches and backfilling.

31 16mm2 2-Core.
m 40

32 35mm2 4-Core.
m 60

CABLE TERMINATIONS

Termination for 600/1000 V PVC/PVC/SWA/PVC copper cables.

33 16mm2 2-Core.
No. 4

Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
130
Package 3 Lot 3
Rate Amount

34 35mm2 4-Core.
No. 4

EARTH CONDUCTOR TERMINATION

Bare copper earth conductor installed with cable (cable measured


elsewhere).

35 10mm2 Conductor.
m 40

Termination for bare and PVC insulated copper conductors including


lugs and connections.

36 10mm2 Conductor.
No. 1

Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
131
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS
BILL NO. 17
EXTERNAL WORKS (PROVISIONAL)
COLLECTION
Page No

Brought Forward from Page 127

128

129

130

131

Carried To Section Summary $


Section No. 3
Bill No. 17
External Works (provisional)
132
Package 3 Lot 3
Amount

SECTION NO. 3
NEW BUILDINGS

SECTION SUMMARY
Bill Page
No.

1 EARTHWORKS (PROVISIONAL) 83

2 CONCRETE, FORMWORK AND REINFORCEMENT 86

3 MASONRY 90

4 WATERPROOFING 91

5 ROOF COVERINGS 94

6 CARPENTRY AND JOINERY 95

7 CEILINGS PARTITIONS AND ACCESS FLOORING 96

8 IRONMONGERY 100

9 STRUCTURAL STEELWORK 101

10 METALWORK 104

11 PLASTERING 107

12 TILING 110

13 PLUMBING AND DRAINAGE (PROVISIONAL) 116

14 ELECTRICAL WORK (PROVISIONAL) 122

15 GLAZING 123

16 PAINTWORK 126

17 EXTERNAL WORKS (PROVISIONAL) 132

Carried to Final Summary $


Section No. 3
SECTION SUMMARY

133
Package 3 Lot 3

SECTION NO. 4

SITE WORKS

134
Package 3 Lot 3
Rate Amount

SECTION NO. 4
SITE WORKS
BILL NO. 1
ALTERATIONS

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
Preambles which are incorporated in this Bill.

SUPPLEMENTARY PREAMBLES, ETC.

Materials from the alterations, credit, etc:

Materials recovered from the alterations (except where described as to be


re-used or to be handed over to the client) will become the property of the
Contractor, who may allow credit in respect thereof where provided for in the
bills of quantities. Such materials shall not be re-used in new work without
written permission from the Architect.

Materials described as "removed" shall be removed from the site


immediately.

Materials described as "handed over to the client" shall be carefully


dismantled where necessary, neatly stored under cover on site where
directed and protected from damage, until required.

Materials described as "set aside for re-use" shall be carefully dismantled


where necessary, neatly stored under cover on protected from damage until
required for re-use. Any damage caused to such materials during removal,
storage or refixing shall be made good at the Contractor's expense.

Making good damaged work, etc:

In taking down and removing existing work the utmost care shall be
observed to prevent any structural or other damage to remaining portions of
the building, and the Contractor shall provide all shoring, needling, strutting,
etc. to ensure the stability of all structure during alterations work.

Special care shall be exercised during the progress of the work to ensure
that any electrical installations, water supply pipes, telephone and other
services which may be encountered are not interfered with and notice shall
given to the Architect if any disconnection or alterations becomes necessary.

The Contractor shall take all precautions necessary to prevent any nuisance
from dust whilst carrying out the work.

The Contractor shall make good in all trades to existing work where
damaged or disturbed through the alterations with all necessary new
materails to match the existing.

Carried to Collection $
Section No. 4
Bill No. 1
Alterations
135
Package 3 Lot 3
Rate Amount

Disposal of debris, etc:

The Contractor shall be responsible for the removal from the site all
materials, debris and rubbish resulting from the alterations.

Exposing of underground services:

The known services both underground and overhead will be pointed out to
the contractor. The Contractor is hereby expected to include in his tendering
price the cost of exposing of such services where expedient, be the services
known or unknown, as long as it is deemed necessary.

Demolitions, etc:

Descriptions of demolitions give a rough guide only as to the scope of the


work. Tenderers are therefore advised to visit the site before submitting a
tender and to acquaint themselves with the nature and extent of the work to
be done and the value of recoverable materials which are to be re-used or
handed over to the Client and those which are neither to be re-used nor
handed over to the Client. Unless otherwise stated, loose furniture, kitchen
and other equipment, apparatus, machinery, etc. shall remain the property
of the Client and the removal thereof does not fall within the scope of this
Contract.

The Contractor shall completely demolish the buildings, etc. in a careful,


skillful, practical and safe manner down to 150mm below ground level.

Description of demolitions shall be deemed to include breaking up and


removing:

(1) all floors and surface beds

(2) all external screen and internal walls (clay brick should be set aside,
cleaned, for re-use) steps, ramps, aprons, surface water channels,
rainwater sumps, gulleys, etc. attached to the building to be demolished;

(3) all services, manholes, etc.in ground to a point not less than 1000mm
beyond the perimeter of the building, including plugging of ends of remaing
pipes, drains, etc.,filling in holes where necessary and ramming and
levelling to the ground level.

REMOVAL OF EXISTING WORK

Breaking up and removing mass concrete:

1 Steps.
m³ 1

Carried to Collection $
Section No. 4
Bill No. 1
Alterations
136
Package 3 Lot 3
Rate Amount

Breaking up and removing reinforced concrete including cutting off


and removing reinforcement:

2 Stairs and landings.


m³ 1

3 Columns.
m³ 1

Breaking down and removing brickwork etc:

4 Mass brickwork.
m³ 1

5 Half brick wall.


m² 1

6 One brick wall.


m² 1

Taking out/off and removing sundry metalwork:

7 1,800mm High wire mesh security fence complete standard columns, posts,
stays, bracers, etc.
m 464

Carried to Collection $
Section No. 4
Bill No. 1
Alterations
137
Package 3 Lot 3
Amount

SECTION NO. 4
SITE WORKS
BILL NO. 1
ALTERATIONS
COLLECTION
Page No

Brought Forward from Page 135

136

137

Carried To Section Summary $


Section No. 4
Bill No. 1
Alterations
138
Package 3 Lot 3
Rate Amount

SECTION NO. 4
SITE WORKS
BILL NO. 2
EXTERNAL WORKS

The Tenderer is referred to the relevant Clauses in the separate document


Model Preambles for Trades (2008 Edition) and to the Supplementary
preambles which are incorporated in this Bill

SITE CLEARANCE, ETC.

Site clearance, etc:

1 Allow for clearing the area of the site to be built upon of all rubbish, debris,
vegetation, hedges, shrubs, trees with trunks not exceeding 200mm girth,
including grubbing up all roots, scoffling up as required and cart away all
vegetation and debris.
m² 105

FENCING

Security fencing, gates, etc including two coats bitumious aluminium


paint on metal stays, framing, etc:

2 Security fencing 2,100mm high vertically formed of 50mm diameter


standards cast into and including concrete base (base size 450 x 450 x
900mm deep 15 Mpa/19) at average 3,000mm centres, five galvanised
straining wires and four galvanised razor wires ' barbed' tied to standards,
posts and eye bolts, the 2,100mm vertical height covered with 3mm
galvanised razor mesh fixed at 500mm centres to each straining wire.
m 464

3 Mass concrete 20Mpa/19mm ground beam 150 x 350mm deep including


necessary excavation, formwork, backfilling, etc,.
m 464

4 Horizontal stay 76mm diameter 2000mm long with each end bolted to posts.
No. 46

5 Inclined stay 50mm diameter 2500mm long with one end bolted to post and
other end welded to 200 x 200 x 5mm sole plate and cast into and including
(750 x 400 x 400 mm deep 15Mpa/19) concrete base.
No. 5

Carried to Collection $
Section No. 4
Bill No. 2
External Works
139
Package 3 Lot 3
Rate Amount

6 Straining post 100mm diameter 2,100mm high vertically, with 200 x 200 x
5mm sole plate and cast into and including (500 x 500 x 900mm 15Mpa/19)
concrete base.
No. 9

7 Corner post 100mm diameter 2,100 mm high vertically with 200 x 200x 5
mm sole plate and cast into and including (500 x 500 x 900 mm 15 Mpa/19)
concrete base
No. 46

8 Single gate 1,000 x 2,100mm high overall, consisting of 50mm diameter


hollow section perimeter frame and two 35mm diameter hollow section
cross bracers rails filled in with three galvanised wires at 500mm centres
horizontally and four barbed wires horizontally at top with a pair of suitable
hinges welded to post and with 'viro heavy duty lock' complete with three
keys, each leaf to bear 8 x 50mm ring around stiles and 100 x 8mm rod pin
through stiles and hung to 100mm diameter pressed steel frame and a
200mm barrel bolt to be anchor on a hole on 300 x 300 x 300mm concrete
anchor block complete with high gloss enamel paint.
No. 3

9 Single gate 1,500 x 2,100mm high overall, consisting of 50mm diameter


hollow section perimeter frame and two 35mm diameter hollow section
cross bracers rails filled in with three galvanised wires at 500mm centres
horizontally and four barbed wires horizontally at top with a pair of suitable
hinges welded to post and with 'viro heavy duty lock' complete with three
keys, each leaf to bear 8 x 50mm ring around stiles and 100 x 8mm rod pin
through stiles and hung to 100mm diameter pressed steel frame and a
200mm barrel bolt to be anchor on a hole on 300 x 300 x 300mm concrete
anchor block complete with high gloss enamel paint.
No. 1

10 Double gate 5,000 x 2,100mm high in equal leaves, each leave formed of
50mm diameter hollow section perimeter frame and two 35mm diameter
hollow section cross bracers rails filled in with three galvanised wires at
500mm centres horizontally and four barbed wires horizontally at top with a
pair of suitable hinges welded to post and with 'viro heavy duty lock'
complete with three keys, each leaf to bear 8 x 50mm ring around stiles and
100 x 8mm rod pin through stiles and hung to 100mm diameter pressed
steel frame and other leaf to bear 200mm barrel bolt to be anchor on a hole
on 300 x 300 x 300mm concrete anchor block complete with high gloss
enamel paint.
No. 1

Carried to Collection $
Section No. 4
Bill No. 2
External Works
140
Package 3 Lot 3
Rate Amount

THE FOLLOWING IN YARD WALL.

Excavation not exceeding 2m deep:

11 Trenches
m³ 325

Risk of collapse of excavations:

12 Sides of trench and hole excavations not exceeding 1,5m deep


m² 928

Soilcrete filling from selected earthfilling mixed with 5% cement by


volume compacted to 95% Mod. AASHTO maximum density and
mechanically vibrated:

13 In trenches, holes, etc under strip footings.


m³ 32

Selected earth filling supplied by the contractor under floor, etc


(material to comply with CBR>40%) in layers and compacted to 98%
Mod AASHTO density:

14 Backfilling to trenches, holes, etc.


m³ 167

Keeping excavations free of water:

15 Keeping excavations free of all water other than subterranean water


Item

25 MPa/19mm Unreinforced concrete:

16 Strip footings.
m³ 81

Brickwork of cement bricks (7 MPa nominal compressive strength) in


Class I mortar:

17 One brick walls in foundations.


m² 464

18 One brick wall.


m² 557

Carried to Collection $
Section No. 4
Bill No. 2
External Works
141
Package 3 Lot 3
Rate Amount

19 Two brick walls batress in foundations.


m² 102

Brickwork reinforcement:

20 150mm Wide reinforcement built in horizontally.


m 4639

21 150mm Wide reinforcement built in horizontally in foundations.


m 5567

Joint forming material in movement joints:

22 10mm Bitumen impregnated fibre board built in vertically between brick


skins.
m² 102

External cement plaster on brickwalls:

23 On walls.
m² 2041

24 On narrow widths.
m² 102

Remove all loose particles and laitance and apply one coat Plascon
Waterbased Plaster Primer and two coats Plascon Pure Acrylic PVA
(allow sufficient time for drying between coats).:

25 On external textured plaster walls.


m² 2134

THE FOLLOWING IN DRINKING FOUNTAIN

Excavation in earth not exceeding 2m deep:

26 Trenches.
m³ 4

Risk of collapse of excavations other than bulk:

27 Sides of trench and hole excavations not exceeding 1,5m deep.


m² 18

Carried to Collection $
Section No. 4
Bill No. 2
External Works
142
Package 3 Lot 3
Rate Amount

Filling with material from the excavations compacted to a density of at


least 95% Mod. AASHTO maximum density:

28 Backfilling to trenches, holes, etc


m³ 2

Filling with material supplied by the Contractor compacted to a


density of at least 95% Mod. AASHTO maximum density:

29 Under floors, pavings, etc.


m³ 2

Approved brand of weedkiller mixed with proved brand of anti-termite


soil poison and applied in accordance with the manufacturer's
instructions:

30 To bottoms and sides of trenches, etc.


m² 4

Precast concrete left rough from the mould including bedding, jointing
and pointing:

31 1990mm Diameter concrete ring 465 mm wide x 150mm thick and with 100
x 75mm channel allround including necessary reinforcement.
No. 2

20Mpa/19mm Concrete

32 Strip footings.
m³ 2

33 Pavings cast in panels.


m³ 1

25 MPa/19mm Concrete:

34 Vanity slabs, cupboard slabs, cover slabs, etc.


m³ 2

100mm Diameter fibre cement pipe filled solid with 25 MPa/19mm


Concrete:

35 Column 1340mm long.


No. 16

Carried to Collection $
Section No. 4
Bill No. 2
External Works
143
Package 3 Lot 3
Rate Amount

Finishing top surfaces of concrete smooth with a wood float:

36 Paving to falls.
m² 12

Smooth Formwork to Sides:

37 Edges, risers, ends and reveals not exceeding 300mm high or wide circular
exceeding 1m radius.
m 24

Permanent formwork to Soffits left in place:

38 Vanity slabs, cupboard slabs, cover slabs, etc. propped up not exceeding
1,5m high.
m² 4

Brickwork of concrete bricks in Class I mortar:

39 365mm Hollow walls of two half brick skins and cavity filled solid with
hardcore filling no wire ties circular on plan in foundations.
m² 3

40 One brick wall circular on plan.


m² 2

41 365mm Hollow walls of two half brick grilled skins and cavity filled with
charcoal no wire ties circular on plan.
m² 5

Metalwork Sundries:

42 1.5 x 19mm Flat metal ring 130mm diameter soldered to underside of water
tray (water tray elsewhere measured.
No. 16

Wire Mesh

43 Galvanised wire mesh with 6 x 6mm screen opening.


m² 13

Cement plaster on brickwork:

44 On walls.
m² 7

Carried to Collection $
Section No. 4
Bill No. 2
External Works
144
Package 3 Lot 3
Rate Amount

Galvanised sheet iron:

45 1.2mm Thick 1550mm Diameter tray 150mm deep including 2mm diameter
holes drilled at 150mm centres in base.
No. 2

Cobra Watertech' crutch handle and lockshield stopcocks:

46 15mm Rough brass F x F stoptap (code 121-15).


No. 2

'Cobra Watertech' 'Demand' 'Mastermatic, etc. bibtaps:

47 15mm Rough brass 'Demand' bibtap (code KM2.203-15).


No. 16

Class O copper pipes:

48 15mm Pipes.
m 12

Extra over class O copper pipes for capillary fittings:

49 15mm Fittings.
No. 50

"Namibian Roto Mould" Plastic water tank:

50 1000l Water tank.


No. 2

Carried to Collection $
Section No. 4
Bill No. 2
External Works
145
Package 3 Lot 3
Amount

SECTION NO. 4
SITE WORKS
BILL NO. 2
EXTERNAL WORKS
COLLECTION
Page No

Brought Forward from Page 139

140

141

142

143

144

145

Carried To Section Summary $


Section No. 4
Bill No. 2
External Works
146
Package 3 Lot 3
Amount

SECTION NO. 4
SITE WORKS

SECTION SUMMARY
Bill Page
No.

1 ALTERATIONS 138

2 EXTERNAL WORKS 146

Carried to Final Summary $


Section No. 4
SECTION SUMMARY

147
Package 3 Lot 3

SECTION NO. 5

PROVISIONAL SUMS

148
Package 3 Lot 3
Amount

SECTION NO. 5
PROVISIONAL SUMS

JOINERY FITTINGS

Joinery fittings:

1 Provide the amount of N$60, 000. 00 (Sixty Thousand Namibian Dollars) for
the replacement of all damagedJoinery Fittings and the supply and delivery
of new Duracraft or similar approved stainless steel cupboards.
Item 60,000 00

2 Profit on above item.


Item

3 Attendance on ditto.
Item

WATER RETICULATION SYSTEM:

Upgrading Of Water Reticultion:

4 Provide the amount of N$ 100,000.00 (One Hundred Thousand Namibian


Dollars) for the upgrade of the water reticulation system.
Item 100,000 00

5 Profit on above item.


Item

6 Attendance on ditto.
Item

Carried To Section Summary $


Section No. 5
Bill No. 1
Provisional Sums
149
Package 3 Lot 3
Amount

SECTION NO. 5
PROVISIONAL SUMS

SECTION SUMMARY
Page

Brought Forward from Page 149

Carried to Final Summary $


Section No. 5
SECTION SUMMARY

150
Package 3 Lot 3

Section FINAL SUMMARY


No.
Page

1 PRELIMINARIES 28

2 RENOVATIONS 78

3 NEW BUILDINGS 133

4 SITE WORKS 147

5 PROVISIONAL SUMS 150

ADD: CONTINGENCIES

Allow the Amount of N$350, 000. 00 (Three Hundred and Fifty Thousand 350,000 00
Namibian) for contingencies, to be used by the Engineer in terms of
Clause 3 of the FIDIC [The Federation Internationale des Ingenieurs
Conseils] 'Red Book' Contract 1999 Edition.

Carried to Tender Form $

FINAL SUMMARY

151
Package 3 Lot 3

INDEX TO BILLS OF QUANTITIES

Bill No Page No
SECTION NO. 1: PRELIMINARIES 1

Preambles For Trades 2

Section A - General Conditions 2

Section B - Model Preliminaries 16

Section C - Specific Preliminaries 24

SECTION SUMMARY 27

SECTION SUMMARY 28

SECTION NO. 2: RENOVATIONS 29

1 ALTERATIONS 30

Supplementary Preambles, Etc. 30

Removal Of Existing Work 31

Building Up Openings 34

Making Good Of Finishes, Etc. 34

Remedial Works 35

Roof Leaks Repairs And Sealing 35

Plaster Repairs 35

Crack Repairs 36

2 EARTHWORKS 38

Excavation Other Than Bulk 38

Carting Away. 38

Earth Filling, Etc. 38

Soil Poisoning 39

3 CONCRETE, FORMWORK AND REINFORCEMENT 41

Reinforced Concrete 41

(i)
Package 3 Lot 3

Finishing Top Surface Of Concrete 41

Grooves, Etc. 41

Rough Formwork (Degree Of Accuracy ii) (Cpap Work Group No 111) 41

Reinforcement (Provisional) (Cpap Work Group No 114) 41

4 MASONRY 42

Supplementary Preambles 42

Brickwork 42

Brickwork Sundries 42

5 CARPENTRY AND JOINERY 45

Eaves, Verges, Etc 45

Beads, Architraves, Etc 45

6 CEILINGS PARTITIONS AND ACCESS FLOORING 46

Metal Nailed Up And Screw Up Ceilings (Cpap Work Group No 126) 46

7 IRONMONGERY 47

Hinges, Floor Spring Hinges, Bolts, Panic Bolts, Etc 47

Catches, Cabin Hooks, Etc 47

Locks, Handles, Etc 47

Letters, Nameplates, Etc. 47

Bathroom Fittings 48

Sundries 48

Pinning Boards, Writing Boards, Projection Screens, Etc 48

8 METALWORK 50

Welded Screens, Gates, Etc. 50

Pressed Steel Combination Doors And Frames 51

9 PLASTERING 53

Screeds 53

(ii)
Package 3 Lot 3

Internal Plaster 53

External Plaster 53

10 TILING 54

Nosing, Joint Covers, Protectors, Etc. 54

Ceramic Wall Tiling 54

Ceramic Floor Tiling 54

11 PLUMBING AND DRAINAGE 55

Supplementary Preambles 55

Sanitary Fittings 56

Waste Unions Etc 57

Traps Etc 57

Taps, Valves, Etc 57

Water Supplies 57

Testing 59

Fire Appliances Etc. 60

Water Supplies To Fire Appliances 60

Flue Pipes Etc 61

Storm Water, Soil Water, And Water Systems Repairs 61

Sleeves 61

12 ELECTRICAL WORK (PROVISIONAL) 63

Distribution Boards 63

Conductors 63

Light Switches, Switched Socket Outlets, Etc. 64

Electrical Reticulation 64

13 GLAZING 68

Glazing To Steel With Putty 68

(iii)
Package 3 Lot 3

14 PAINTWORK 69

Supplementary Preambles 69

Paintwork Etc To New Work 70

On Metal 70

On Wood, Wood Board 70

Paintwork, Etc To Previously Painted Work 70

On Smooth Plaster 70

On Metal 71

On Wood, Wood Board 72

15 EXTERNAL WORKS 74

Site Clearance, Etc. 74

Roadwork, Paving, Etc 74

25Mpa/19mm Reinforced Concrete: 76

SECTION SUMMARY 78

SECTION NO. 3: NEW BUILDINGS 79

1 EARTHWORKS (PROVISIONAL) 80

Nature Of Ground 80

Site Clearance, Etc. 80

Excavation Other Than Bulk 80

Carting Away. 81

Earth Filling, Etc. 81

Keeping Excavations Free Of Water 82

Soil Poisoning 82

2 CONCRETE, FORMWORK AND REINFORCEMENT 84

Test Blocks 84

Unreinforced Concrete 84

(iv)
Package 3 Lot 3

Unreinforced Concrete Cast Against Excavated Surfaces 84

Finishing Top Surface Of Concrete 85

Grooves, Etc. 85

Rough Formwork (Degree Of Accuracy ii) 85

3 MASONRY 87

Brickwork In Foundations (Provisional) 87

Brickwork In Superstructure 87

Brickwork Sundries 87

Brick Paving 89

4 WATERPROOFING 91

Dampproofing Of Walls And Floors 91

Joint Sealants Etc 91

5 ROOF COVERINGS 92

Troughed Metal Sheeting And Accessories 92

Roof And Wall Insulation 93

6 CARPENTRY AND JOINERY 95

Flush Doors 95

Beads, Architraves, Etc 95

Notice Boards, Pinning Boards, Keyboards, Duckboards, Etc 95

7 CEILINGS PARTITIONS AND ACCESS FLOORING 96

Nailed Up Ceilings 96

8 IRONMONGERY 97

Locks 97

Letters, Nameplates, Etc. 97

Bathroom Fittings 97

Sundries 98

(v)
Package 3 Lot 3

Shelving Units 98

Steel Lockers 99

Pinning Boards, Writing Boards, Projection Screens, Etc 99

9 STRUCTURAL STEELWORK 101

Steel Trusses Etc 101

Purlins, Girts, Bracing, Etc 101

10 METALWORK 102

Sundry Steelwork 102

Welded Screens, Gates, Etc. 102

Pressed Steel Door Frames 102

Steel Windows, Doors, Etc. 103

Pressed Steel Combination Doors And Frames 103

11 PLASTERING 105

Screeds 105

Internal Plaster 105

External Plaster 105

Corner Protectors, Dividing Strips, Etc 106

12 TILING 108

Nosing, Joint Covers, Protectors, Etc. 108

Wall Tiling 108

Floor Tiling 108

Sundries 109

13 PLUMBING AND DRAINAGE (PROVISIONAL) 111

Soil Drainage 111

Sanitary Fittings 111

Waste Unions Etc 112

(vi)
Package 3 Lot 3

Traps Etc 112

Taps, Valves, Etc 112

Sanitary Plumbing 112

Flue Pipes Etc 114

Water Supplies 114

Testing 114

Fire Appliances Etc. 115

14 ELECTRICAL WORK (PROVISIONAL) 117

Distribution Boards 117

Cables 118

Cable Terminations 118

Earthing 118

Earth Conductor Termination 118

Sleeves 118

Black Enamelled Conduit 119

Rigid Pvc Conduit 119

Conduit Boxes And Fittings 119

Conductors 120

Light Switches, Switched Socket Outlets, Etc. 120

Luminaries And Equipment 121

Rigid Pvc Conduit 121

Earthing System 121

15 GLAZING 123

Glazing To Steel With Putty 123

Tops, Shelves, Doors, Mirrors, Etc. 123

16 PAINTWORK 124

(vii)
Package 3 Lot 3

On Floated Plaster 124

On Metal 124

On Wood 125

Signwriting 125

17 EXTERNAL WORKS (PROVISIONAL) 127

The Following In Flag Pole 127

Soil Drainage 128

Taps, Valves, Etc 129

Water Reticulation 130

External Water Supplies 130

Electrical Reticulation 130

Cable Terminations 130

Earth Conductor Termination 131

SECTION SUMMARY 133

SECTION NO. 4: SITE WORKS 134

1 ALTERATIONS 135

Supplementary Preambles, Etc. 135

Removal Of Existing Work 136

2 EXTERNAL WORKS 139

Site Clearance, Etc. 139

Fencing 139

The Following In Yard Wall. 141

The Following In Drinking Fountain 142

SECTION SUMMARY 147

SECTION NO. 5: PROVISIONAL SUMS 148

Joinery Fittings 149

(viii)
Package 3 Lot 3

Water Reticulation System: 149

SECTION SUMMARY 150

(ix)