Professional Documents
Culture Documents
01 February 2011
FOR
FOR
SECTION NO. 1
PRELIMINARIES
1
Package 3 Lot 3
Amount
SECTION NO. 1
PRELIMINARIES
120 Clause 14.5 - Plant and Materials Intended for the Works
Item
18.0 - INSURANCE
B2 The Site
184 B2.8: Patent Defects in work executed under the previous contract
Item
B3 Management of Contract
The contractor shall provide electricity and lighting for The Works
in accordance with Alternative A
Item
All Prime Cost and Provisional Sums are net and do not include a
cash discount, nor will the Contractor be allowed or entitled to a
cash discount.
Item
216 B7.5: Fuel, power and water for commissioning of mechanical and
other specialised installations
Item
Delete the whole of this clause and replace with the following:
B9: General
The Contractor must allow for and provide all necessary revenue
stamps require.
Item
The Contractor shall take delivery of, handle, store, use, apply
and/or fix all proprietary branded products in strict accordance with
the manufacturers' instructions after consultation with the
manufacturer's authorised representative.
Item
The Contractor shall not cede nor assign his rights or claims to any
monies due or to become due under this contract.
Item
The contractor shall provide for and effect Social Security for all
his/her employees on the works in respect of the Social Security
Act and will also instruct all his sub-contractors to do the same.
Item
SECTION NO. 1
PRELIMINARIES
SECTION SUMMARY
Page
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Carried to Next $
Section No. 1
SECTION SUMMARY
27
Package 3 Lot 3
Amount
Brought from Previous $
26
28
Package 3 Lot 3
SECTION NO. 2
RENOVATIONS
29
Package 3 Lot 3
Rate Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 1
ALTERATIONS
In taking down and removing existing work the utmost care shall be
observed to prevent any structural or other damage to remaining portions of
the building, and the Contractor shall provide all shoring, needling, strutting,
etc. to ensure the stability of all structure during alterations work.
Special care shall be exercised during the progress of the work to ensure
that any electrical installations, water supply pipes, telephone and other
services which may be encountered are not interfered with and notice shall
given to the Architect if any disconnection or alterations becomes necessary.
The Contractor shall take all precautions necessary to prevent any nuisance
from dust whilst carrying out the work.
The Contractor shall make good in all trades to existing work where
damaged or disturbed through the alterations with all necessary new
materails to match the existing.
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
30
Package 3 Lot 3
Rate Amount
The Contractor shall be responsible for the removal from the site all
materials, debris and rubbish resulting from the alterations.
The known services both underground and overhead will be pointed out to
the contractor. The Contractor is hereby expected to include in his tendering
price the cost of exposing of such services where expedient, be the services
known or unknown, as long as it is deemed necessary.
Demolitions, etc:
(2) all external screen and internal walls (clay brick should be set aside,
cleaned, for re-use) steps, ramps, aprons, surface water channels,
rainwater sumps, gulleys, etc. attached to the building to be demolished;
(3) all services, manholes, etc.in ground to a point not less than 1000mm
beyond the perimeter of the building, including plugging of ends of remaing
pipes, drains, etc.,filling in holes where necessary and ramming and
levelling to the ground level.
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
31
Package 3 Lot 3
Rate Amount
2 Steel screen gate and frame 813 x 2,031mm high overall from one
brickwall.
No. 5
3 Timber single door 813 x 2,031mm high overall from one brickwall.
No. 10
4 Steel single door 813 x 2,031mm high overall from one brickwall.
No. 40
Taking out and removing doors, windows, etc from one brickwall
(windows to be set aside for re-use):
5 Glazed steel window 550 x 1,000m high from one brick wall.
No. 2
6 Glazed steel windows 1,000 x 600mm high from one brick wall.
No. 12
7 Glazed steel windows 1,000 x 1,000mm high from one brick wall.
No. 3
8 Glazed steel window 1,470 x 1,000m high from one brick wall.
No. 6
9 Glazed steel window 1,500 x 600m high from one brick wall.
No. 63
10 Glazed steel window 1,500 x 900m high from one brick wall.
No. 70
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
32
Package 3 Lot 3
Rate Amount
12 Vinyl tile floor covering including preparing screed for new ceramic floor tiles.
m² 228
15 Mortice lock and striking plate from steel door and steel frame.
No. 40
16 Mortice lock and striking plate from timber door and steel frame.
No. 9
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
33
Package 3 Lot 3
Rate Amount
Taking out and removing broken glass from windows/door panes and
mirrors:
21 Broken glass from steel windows including cleaning out rebates and
preparing for new glass.
m² 2
22 Allow for removal of learning charts and material ( and putting back
thereafter), from walls and pinning boards so as to expose surfaces to be
painted.
m 27
BUILDING UP OPENINGS
25 Clean ceilings from any organic matters and dirts, apply disinfenctants and
pets poison in the roof space before installing ceiling, make good on
completion, taking utmost care not to damage the ceilings.
m² 1328
26 Floors in patches.
m² 62
27 Walls in patches.
m² 27
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
34
Package 3 Lot 3
Rate Amount
REMEDIAL WORKS
30 Reinforcing the exiting timber tie beam size114 x 38mm wrot softwood
complete with rafter feets, including allowing for lifting up roof sheets and
refixing and including new roofing screws
m 1526
PLASTER REPAIRS
Supplementary preambles:
All plaster repair admixtures are to be applied strictly in accordance with the
"abe Construction Chemicals" or similar approved requirements. Break out
all loose and hollow plaster at least 20 mm wide all around loose plaster
area, brush clean of all loose material, treat exposed area wit "abe
Duralatex" or similar approved adhesive slurry and plaster with an admixture
of 3 to 1 sand/cement and 3 to 1 water / Duralatex.
32 On brick walls
m² 591
33 On narrow widths
m² 33
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
35
Package 3 Lot 3
Rate Amount
CRACK REPAIRS
Supplemantary preamble:
34 On walls
m 55
Supplementary preamble:
Repair crack in screeded floors by hacking off the existing screed to expose
the concrete surface, 200mm width on either side of the crack, wedge crack
with timber wedges at 300mm centres and fill with 'abe epidermix 344' or
similar approved 'wet to dry' epoxy to the crack at rate of 3 sqm/litre, bush
hammer exposed concrete surface, cover with 13mm chicken wire mesh
and applying bonding liquid and finish off with 25Mpa screed including
making good.
35 On concrete floors
m 207
Carried to Collection $
Section No. 2
Bill No. 1
Alterations
36
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 1
ALTERATIONS
COLLECTION
Page No
31
32
33
34
35
36
SECTION NO. 2
RENOVATIONS
BILL NO. 2
EARTHWORKS
Extra over excavations other than bulk in earth for excavation in:
2 Soft rock.
m³ 5
3 Hard rock.
m³ 1
CARTING AWAY.
Extra over all excavations for loading, carting and dumping surplus
excavated material (no allowance made for increase in bulk):
Filling with approved material supplied and carted onto site by the
Contractor, compacted to a density of at least 95% Mod. AASHTO
maximum density:
Carried to Collection $
Section No. 2
Bill No. 2
Earthworks
38
Package 3 Lot 3
Rate Amount
Surface Preparation:
7 Trim and level off surface of natural ground and/or excavated surfaces to
receive concrete surface beds, including ripping and scarifying as necessary
and compacting the whole area for a depth of 150mm to a density of at least
95% Mod. AASHTO maximum density.
m² 259
SOIL POISONING
8 Under floors, etc., including forming and poisoning shallow furrows against
foundation walls, etc., filling in furrows and ramming.
m² 259
Carried to Collection $
Section No. 2
Bill No. 2
Earthworks
39
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 2
EARTHWORKS
COLLECTION
Page No
39
SECTION NO. 2
RENOVATIONS
BILL NO. 3
CONCRETE, FORMWORK AND REINFORCEMENT
REINFORCED CONCRETE
25 MPa/19mm Concrete:
GROOVES, ETC.
4 Edges, risers, ends and reveals not exceeding 300mm high or wide.
m 1036
Fabric reinforcement:
SECTION NO. 2
RENOVATIONS
BILL NO. 4
MASONRY
SUPPLEMENTARY PREAMBLES
BRICKWORK
Brick reinforcements:
Sizes in descriptions:
Where sizes in descriptions are given in brick units, 'one brick' shall
represent the length and 'half brick' the width of a brick.
Pointing:
BRICKWORK SUNDRIES
Brickwork reinforcement:
Cement wash of 1:3 liquid cement and sand mixture applied with a
brush, on previously cement washed surfaces:
Carried to Collection $
Section No. 2
Bill No. 4
Masonry
42
Package 3 Lot 3
Rate Amount
4 On brick surfaces.
m² 223
Carried to Collection $
Section No. 2
Bill No. 4
Masonry
43
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 4
MASONRY
COLLECTION
Page No
43
SECTION NO. 2
RENOVATIONS
BILL NO. 5
CARPENTRY AND JOINERY
1 255 x 6mm Fascias and barge boards including gavanised steel H-profile
jointing strips, screwed on to edges of existing timber trusses, rafters and
purlins.
m 196
3 22 x 75mm cornice.
m 850
SECTION NO. 2
RENOVATIONS
BILL NO. 6
CEILINGS PARTITIONS AND ACCESS FLOORING
2 Extra over ceiling for 1000 x 1000mm trap door of 30 x 30 x 3mm angle
section framing covered with 0.5mm thick IBR profile sheeting fitted flush in
opening.
No. 6
3 Narrow and broad flute closers 150mm girth to suit IBR profile.
m 656
SECTION NO. 2
RENOVATIONS
BILL NO. 7
IRONMONGERY
1 500 x 32mm Satin chrome on brass flush barrel bolt with keep let into
concrete.
No. 20
5 'Blesbok' Art 460/312 four lever lockset complete with a pair of handles.
No. 59
Carried to Collection $
Section No. 2
Bill No. 7
Ironmongery
47
Package 3 Lot 3
Rate Amount
BATHROOM FITTINGS
Approved:
SUNDRIES
13 Vitrex pinning board model 2300 code: 2309, 2,400 x 1,200mm high
plugged.
No. 10
Carried to Collection $
Section No. 2
Bill No. 7
Ironmongery
48
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 7
IRONMONGERY
COLLECTION
Page No
48
SECTION NO. 2
RENOVATIONS
BILL NO. 8
METALWORK
1 Purpose made single security gate 813 x 2,032mm high overall, formed of
38 x 76 x 2.5mm mild steel square hollow section perimeter framing and two
centre transoms forming top and bottom openings, each filled in with 'Mentix
Flattex Code No. 341' expanded metal and mosquito gauze fixed to frame
with flat bar fixing cleats, and fitted with sheet metal lockbox for and
including double cylinder lockset, as 'Solid' 378 narrow style dead lock,
complete with two 100mm heavy duty weld-on lift-off hinges per leaf welded
to steel door frame (frame elsewhere measured).
No. 5
3 10mm Diameter loose bolt type expanding bolt as 'Rawbolt M10 75L',
including mortice in brickwork and bolt up tight.
No. 118
Carried to Collection $
Section No. 2
Bill No. 8
Metalwork
50
Package 3 Lot 3
Rate Amount
Standard ' Wispeco' or similar approved chawl doors with back panel:
7 Door 813 x 2,032mm high complete with back panel with double rebated
frame suitable for one brick wall.
No. 39
8 Door 813 x 2,032mm high complete with back panel, hung to existing door
frame.(Internal)
No. 20
Carried to Collection $
Section No. 2
Bill No. 8
Metalwork
51
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 8
METALWORK
COLLECTION
Page No
51
SECTION NO. 2
RENOVATIONS
BILL NO. 9
PLASTERING
SCREEDS
INTERNAL PLASTER
2 On narrow widths.
m 7
EXTERNAL PLASTER
3 On narrow widths.
m² 7
SECTION NO. 2
RENOVATIONS
BILL NO. 10
TILING
300 x 300 x 6mm 'Dimo Top' full-body ceramic floor tiles fixed with
adhesive on 25mm screed bedding on concrete and flush pointed with
tinted waterproof jointing compound:
4 Circular cutting.
No. 21
SECTION NO. 2
RENOVATIONS
BILL NO. 11
PLUMBING AND DRAINAGE
SUPPLEMENTARY PREAMBLES
Pipes of 40mm diameter and smaller shall be plain ended with solvent
welded uPVC loose sockets and fittings.
Pipes of 50mm diameter and greater shall have sockets and spigots with
push-in type integral rubber ring joints. Bends shall be uPVC and all other
fittings shall be cast iron, all with similar push-in type joints.
Copper pipes:
Pipes shall be hard drawn and half-hard pipes of the class stated. Class 0
(thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half-
hard), class 2 (half-hard) and class 3 (heavy walled half-hard) pipes shall
only be bent with benders with inner and outer formers. Fittings to copper
waste, vent and anti-syphon pipes, capillary solder fittings and compression
fittings shall be 'Cobra Watertech' type. Capillary solder fittings shall comply
with ISO 2016. Only compression fittings shall be used in walls or in ground.
Fixing of pipes:
Reducing fittings:
Flush pans:
Flush pans shall have straight or side outlets and 'P' or 'S' traps as
necessary.
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
55
Package 3 Lot 3
Rate Amount
Excavations:
No claim for rock excavation will be entertained unless the Contractor has
timeously notified the quantity surveyor thereof prior to backfilling.
Pipes shall be laid and bedded and trenches shall be carefully backfilled in
accordance with manufacturers' instructions.
Units shall have standard aprons on all exposed edges and tiling keys
against walls where applicable.
Waste unions:
SANITARY FITTINGS
2 510 x 405mm 'Hibiscus' white vitreous china lavatory basin (product code
7050) with two tapholes including integrated overflow and chainstay hole.
No. 10
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
56
Package 3 Lot 3
Rate Amount
'Franke (t/a Citimetal)' grade 304 (18/10) 1,2mm thick stainless steel
wash hand basins:
3 'Franke Oval A' wash hand basin size 420 x 340mm with pressed bowl , two
tapholes , 100mm radius apron and 50mm high splashback, four times
bolted to wall with M8 expansion bolts.
No. 5
Approved:
4 Polyethylene rotation pedestal and funnel V.I.D.P latrine with heavy duty
seat and cover.
No. 10
TRAPS ETC
6 40mm Rough brass medium seal sink 'P' trap, with FI outlet and cleaning
eye (code VA2.360).
No. 3
7 15mm Star Chrome plated foot operated hose bibtap with 20mm BSP
thread on outlet (code 507-21).
No. 2
WATER SUPPLIES
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
57
Package 3 Lot 3
Rate Amount
11 25mm Fittings.
No. 9
12 32mm Reducer.
No. 3
13 32mm Bend.
No. 2
14 63mm Bend.
No. 5
15 32mm Tee.
No. 4
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
58
Package 3 Lot 3
Rate Amount
23 22mm Pipes.
m 6
25 15mm Fittings.
No. 6
26 22mm Fittings.
No. 6
Sundries:
27 Extra for connecting 22mm Coper pipe to 25mm HDPE pipe including all
neccessary fittings, etc.
No. 12
28 225 x 225mm Cast iron stopcock box including brick chamber below not
exceeding 500mm deep internally.
No. 4
29 Search, locate, excavate and connect the new 32mm HDPE water supply
pipe to existing municipal water line including all labour and materials to
execute the connection.
Item
TESTING
Testing:
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
59
Package 3 Lot 3
Rate Amount
32 'Everyway' hose reel complete with 30m non-kinkable hose 20mm internal
diameter plated stopcock, shut-off nozzle and wall bracket complete with
25mm diameter Saunders type A diaphragm isolated valve.
No. 21
33 9kg Rechargeable dry chemical fire extinguisher complete with initial charge
painted backing board plugged and screwed to plastered or tiled brick wall.
No. 22
36 32mm Fittings
No. 120
Extra over class 10 HDPE Type 4 pressure pipes for solvent welded
pressure fittings:
37 32mm Fittings.
No. 6
39 32mm Pipes
m 32
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
60
Package 3 Lot 3
Rate Amount
40 25mm Fittings
No. 16
41 32mm Fittings
No. 10
SLEEVES
Plastic sleeves for pipes exceeding 100mm and not exceeding 200mm
diameter:
Carried to Collection $
Section No. 2
Bill No. 11
Plumbing And Drainage
61
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 11
PLUMBING AND DRAINAGE
COLLECTION
Page No
56
57
58
59
60
61
SECTION NO. 2
RENOVATIONS
BILL NO. 12
ELECTRICAL WORK (PROVISIONAL)
DISTRIBUTION BOARDS
CONDUCTORS
4 2.5mm2
m 30
5 2.5mm².
m 40
6 4mm².
m 20
Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
63
Package 3 Lot 3
Rate Amount
ELECTRICAL RETICULATION
13 Replace SSO
No. 3
14 Check and repair faulty power circuit including control gear and
isulation,phase rotation,wiring
No. 2
17 Excavation in hard rock conditions for cable trench (for new or existing
cables, to 600mm deep)
m³ 28
Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
64
Package 3 Lot 3
Rate Amount
Distrubution board:
20 Remove and replace door with latch, tray, and blank plates complete with
25mm pad lock
No. 2
22 Flood light, mast / wall mounted, with HID lamp-make good replace lamp
No. 2
28 Replace wall mounted light fitting as 'Lascon' B20 or similar approved and
bulb 2PL9 bulbs (B)
No. 4
Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
65
Package 3 Lot 3
Rate Amount
Carried to Collection $
Section No. 2
Bill No. 12
Electrical Work (provisional)
66
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 12
ELECTRICAL WORK (PROVISIONAL)
COLLECTION
Page No
64
65
66
SECTION NO. 2
RENOVATIONS
BILL NO. 13
GLAZING
SECTION NO. 2
RENOVATIONS
BILL NO. 14
PAINTWORK
SUPPLEMENTARY PREAMBLES
Primers and first coats may be thinned in accordance with the paint
specifications of Plascon Paints (Pty) Ltd to aid the absorption of the paint.
All surfaces must be sound, clean and have a moisture content of less than
8% for walls generally and 3% for slabs/screeds etc.
Where surfaces of plaster etc are sandy / friable, the first coat must be
replaced with 'Plascon Merit' plaster primer thinned 10% with turpentine.
All paints are to bear the SABS mark and are to be applied in strict
accordance with manufacturer's instructions.
Prices for paintwork are to include for masking and protecting of all finished
paintwork and all finished joinery, tiling, floor coverings, etc. during painting.
Any damage to such finished work shall be removed, repaired or replaced at
the Contractor's expenses.
Prices for painting are to include for painting a one square metre sample
panel of all finishing coats and for repeating if required. Only after written
approval from Architect may finishing coats be applied.
Prices for all paintwork are to include all colours which have a value of 8 or
higher on the Munsell system in accordance with the relevant SABS
specification.
The Contractor shall provide all necessary dust sheets, covers, etc. required
during painting. All door handles, locks and other ironmongery, pelmets,
electrical switch and socket covers, etc. are to be removed before
commencing the painting. All paint spots, stains, etc. are to be cleaned off
all floors, walls, glass, doors, frames, fittings, etc. after completion of the
painting
Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
69
Package 3 Lot 3
Rate Amount
ON METAL
2 On corner protectors.
m² 443
Wash down with approved cleaning agent and apply one coat calcium
plumbate primer, one undercoat and two coats enamel paint on
galvanised steel:
Stop, fill, sand down and prepare wood surfaces and apply one coat
'Plascon Oil Wood Primer' or similar approved, one coat 'Plascon Merit
Universal Undercoat' or similar approved and two coats 'Plascon
Velvaglo Polyurethane Enamel' or similar approved paint:
4 On exterior barge and fascia boards, etc not exceeding 300 mm girth.
m 177
ON SMOOTH PLASTER
6 On interior walls.
m² 2805
Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
70
Package 3 Lot 3
Rate Amount
10 On exterior walls.
m² 2391
ON METAL
12 On doors frames
m² 97
Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
71
Package 3 Lot 3
Rate Amount
19 On interior fittings.
m² 74
Carried to Collection $
Section No. 2
Bill No. 14
Paintwork
72
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 14
PAINTWORK
COLLECTION
Page No
70
71
72
SECTION NO. 2
RENOVATIONS
BILL NO. 15
EXTERNAL WORKS
1 Allow for clearing the area of the site to be built upon of all grass, weeds,
shrubs, trees with trunks not exceeding 200mm girth, debris, etc., including
grubbing up all roots, scoffling up as required and cart away all vegetation
and debris.
m² 115
2 Garden kerb 900 x 250 x 75mm high with twice chamfered edges with 150 x
300mm unreinforced concrete haunching at back of each joint including
excavation, formwork, backfilling, etc.
m 18
3 Barrier kerb 900 x 250 x 125mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc.
m 18
4 Barrier kerb 900 x 250 x 125mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc, circular on plan exceeding 4m radius.
m 23
5 Mountable kerb 900 x 125 x 250mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc.
m 77
Carried to Collection $
Section No. 2
Bill No. 15
External Works
74
Package 3 Lot 3
Rate Amount
6 Mountable kerb 900 x 125 x 250mm high with 150 x 300mm unreinforced
concrete haunching at back of each joint including excavation, formwork,
backfilling, etc., circular on plan not exceeding 4m radius.
m 69
7 1,200mm Diameter 300mm high precast concrete ring tree planter including
excavation, backfilling, etc.
No. 8
8 Open face excavation to form platform under parking areas etc and carting
away surplus material from site to a dumping site to be located by the
contractor.
m³ 123
9 Soft rock
m³ 6
10 Hard rock
m³ 3
11 Brickwork.
m³ 5
12 Unreinforced concrete.
m³ 5
13 Reinforced concrete.
m³ 5
Carried to Collection $
Section No. 2
Bill No. 15
External Works
75
Package 3 Lot 3
Rate Amount
Compaction of surfaces:
20 Remove all building rubble and materials to 500mm depth and fill in with
garden soil for grassing, planting, etc (Plant, grass, cost elsewhere
measured).
m² 46
Carried to Collection $
Section No. 2
Bill No. 15
External Works
76
Package 3 Lot 3
Amount
SECTION NO. 2
RENOVATIONS
BILL NO. 15
EXTERNAL WORKS
COLLECTION
Page No
75
76
SECTION NO. 2
RENOVATIONS
SECTION SUMMARY
Bill Page
No.
1 ALTERATIONS 37
2 EARTHWORKS 40
4 MASONRY 44
7 IRONMONGERY 49
8 METALWORK 52
9 PLASTERING 53
10 TILING 54
13 GLAZING 68
14 PAINTWORK 73
15 EXTERNAL WORKS 77
78
Package 3 Lot 3
SECTION NO. 3
NEW BUILDINGS
79
Package 3 Lot 3
Rate Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 1
EARTHWORKS (PROVISIONAL)
NATURE OF GROUND
1 Allow for clearing the area of the site to be built upon of all grass, weeds,
shrubs, trees with trunks not exceeding 200mm girth, debris, etc., including
grubbing up all roots, scoffling up as required and cart away all vegetation
and debris.
m² 948
2 Trenches.
m³ 173
Extra over excavations other than bulk in earth for excavation in:
4 Soft rock.
m³ 18
5 Hard rock.
m³ 8
Carried to Collection $
Section No. 3
Bill No. 1
Earthworks (provisional)
80
Package 3 Lot 3
Rate Amount
Compaction:
CARTING AWAY.
Extra over all excavations for loading, carting and dumping surplus
excavated material (no allowance made for increase in bulk):
Filling with approved material supplied and carted onto site by the
Contractor, compacted to a density of at least 95% Mod. AASHTO
maximum density:
Carried to Collection $
Section No. 3
Bill No. 1
Earthworks (provisional)
81
Package 3 Lot 3
Rate Amount
Surface Preparation:
14 Trim and level off surface of natural ground surfaces to receive concrete
paving, including ripping and scarifying as necessary and compacting the
whole area for a depth of 150mm to a density of at least 95% Mod.
AASHTO maximum density.
m² 243
SOIL POISONING
17 Under floors, etc., including forming and poisoning shallow furrows against
foundation walls, etc., filling in furrows and ramming.
m² 446
Carried to Collection $
Section No. 3
Bill No. 1
Earthworks (provisional)
82
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 1
EARTHWORKS (PROVISIONAL)
COLLECTION
Page No
81
82
SECTION NO. 3
NEW BUILDINGS
BILL NO. 2
CONCRETE, FORMWORK AND REINFORCEMENT
TEST BLOCKS
Test blocks:
1 Making and testing set of six 150 x 150 x 150mm concrete strength test
cubes (Provisional).
Sets 24
UNREINFORCED CONCRETE
25Mpa/19mm Concrete
4 Surface beds.
m3 0.15
25Mpa/19mm Concrete
6 Strip footings.
m³ 40
Carried to Collection $
Section No. 3
Bill No. 2
Concrete, Formwork And Reinforcement
84
Package 3 Lot 3
Rate Amount
8 Paving to falls.
m² 243
GROOVES, ETC.
11 Edges, risers, ends and reveals not exceeding 300mm high or wide.
m 238
Carried to Collection $
Section No. 3
Bill No. 2
Concrete, Formwork And Reinforcement
85
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 2
CONCRETE, FORMWORK AND REINFORCEMENT
COLLECTION
Page No
85
SECTION NO. 3
NEW BUILDINGS
BILL NO. 3
MASONRY
BRICKWORK IN SUPERSTRUCTURE
BRICKWORK SUNDRIES
Brickwork sundries:
Carried to Collection $
Section No. 3
Bill No. 3
Masonry
87
Package 3 Lot 3
Rate Amount
Cement wash of 1:3 liquid cement and sand mixture applied with a
brush:
8 On brick surfaces.
m² 405
9 10mm Bitumen impregnated fibre board built in vertically through brick walls.
m² 5
Brickwork reinforcement:
15 4mm Diameter roof tie 2m girth bent double with one end tied around steel
purlin and other end built into brickwork.
No. 12
Carried to Collection $
Section No. 3
Bill No. 3
Masonry
88
Package 3 Lot 3
Rate Amount
16 30 x 1,6mm Roof tie 2,0m long tied around steel purlin and shot pinned to
both sides of brickwork.
No. 16
BRICK PAVING
Paving of 65mm thick cement paving bricks with open joints on 50mm
thick river sand bed with sand and cement mixture swept into joints,
hosed down and pointed with slightly keyed joints including termite
and soil posioning, preparation of ground or filling and compaction:
Carried to Collection $
Section No. 3
Bill No. 3
Masonry
89
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 3
MASONRY
COLLECTION
Page No
88
89
SECTION NO. 3
NEW BUILDINGS
BILL NO. 4
WATERPROOFING
One layer of 375 micron Consol Plastics Brikgrip DPC embossed damp
proof course:
1 In walls.
m² 24
SECTION NO. 3
NEW BUILDINGS
BILL NO. 5
ROOF COVERINGS
Flashings:
2 Ridge capping 550mm girth, three times bent along girth and notched on
site to suit IBR roof profile.
m 68
Carried to Collection $
Section No. 3
Bill No. 5
Roof Coverings
92
Package 3 Lot 3
Rate Amount
Carried to Collection $
Section No. 3
Bill No. 5
Roof Coverings
93
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 5
ROOF COVERINGS
COLLECTION
Page No
93
SECTION NO. 3
NEW BUILDINGS
BILL NO. 6
CARPENTRY AND JOINERY
FLUSH DOORS
Wrought 'Supawood':
3 22 x 75mm cornice.
m 160
4 Pinboards model 2300 code: '2315', size 1,000 x 1,200mm, with aluminium
frame plugged and screwed to wall with 38mm steel countersunk screws
(Drwng F3).
No. 14
5 Pinboard model 2300 code: '2309', size 2,400 x 1,200mm, with aluminium
frame plugged and screwed to wall with 38mm steel countersunk screws
(Drwng F1).
No. 14
SECTION NO. 3
NEW BUILDINGS
BILL NO. 7
CEILINGS PARTITIONS AND ACCESS FLOORING
NAILED UP CEILINGS
0.5mm Thick light industrial Z275 IBR profiled sheet steel in single
lengths fixed to steel purlins or rails:
1 Ceilings.
m² 454
2 Extra over ceiling for 1000 x 1000mm trap door of 30 x 30 x 2.5mm angle
section framing covered with 'Alu zinc' IBR profiled sheeting and fitted flush
in opening.
No. 3
3 Narrow and broad flute closers 150mm girth to suit IBR profile.
m 114
SECTION NO. 3
NEW BUILDINGS
BILL NO. 8
IRONMONGERY
LOCKS
1 'Blesbok' Art 460/313 four lever lockset with striking plate fixed to metal
complete with a pair of handles.
No. 1
Solid:
BATHROOM FITTINGS
Chairman Industries:
Carried to Collection $
Section No. 3
Bill No. 8
Ironmongery
97
Package 3 Lot 3
Rate Amount
SUNDRIES
Solid:
SHELVING UNITS
11 Single shelving unit 3600 x 312 x 1905mm high in 4 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 2
12 Single shelving unit 7200 x 312 x 1905mm high in 8 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 2
13 Single shelving unit 1800 x 312 x 1905mm high in 2 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 1
14 Single shelving unit 1800 x 450 x 1905mm high in 2 bays with uprights,
each bay 900mm wide with 6 x 450mm shelves.
No. 1
15 Single shelving unit 4500 x 312 x 1905mm high in 5 bays with uprights,
each bay 900mm wide with 6 x 312mm shelves.
No. 1
Carried to Collection $
Section No. 3
Bill No. 8
Ironmongery
98
Package 3 Lot 3
Rate Amount
16 Single shelving unit 4500 x 450 x 1905mm high in 5 bays with uprights,
each bay 900mm wide with 6 x 3450mm shelves.
No. 1
STEEL LOCKERS
17 Teachers cupboard 900 x 450 x 1800mm high with four adjustable shelves.
No. 6
18 System 1000 green writing board 2700 x 1140mm high with chalk rail
plugged.
No. 7
Carried to Collection $
Section No. 3
Bill No. 8
Ironmongery
99
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 8
IRONMONGERY
COLLECTION
Page No
98
99
SECTION NO. 3
NEW BUILDINGS
BILL NO. 9
STRUCTURAL STEELWORK
Welded roof trusses of angle section rails, struts, braces, cleats, etc
and flat section bearer, gusset and connection plates bolted to steel:
SECTION NO. 3
NEW BUILDINGS
BILL NO. 10
METALWORK
SUNDRY STEELWORK
Carried to Collection $
Section No. 3
Bill No. 10
Metalwork
102
Package 3 Lot 3
Rate Amount
9 Door 813 x 2032mm high with double rebated frame suitable for one wall
and with 'Solid' Besbok 460/313 four lever mortice lock complete with a pair
of handles.
No. 9
10 Door 813 x 2032mm high and frame with fixed fanlight 305mm high suitable
for one wall and with 'Solid' Blesbok 460/313 four lever mortice lock
complete with a pair of handles.
No. 2
11 Modified door 713 x 2032mm high with double rebated frame suitable for
813 x 2032mm high door and for half wall and with 'Solid' Besbok 464/364
WC lockset.
No. 7
12 Door 813 x 2032mm high with double rebated frame suitable for one wall
and with 'Solid' Besbok 460/313 four lever mortice lock.
No. 3
13 Door 813 x 2032mm high and frame with fixed fanlight 305mm high suitable
for one wall and with 'Solid' Besbok 460/313 four lever mortice lock.
No. 2
Carried to Collection $
Section No. 3
Bill No. 10
Metalwork
103
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 10
METALWORK
COLLECTION
Page No
103
SECTION NO. 3
NEW BUILDINGS
BILL NO. 11
PLASTERING
SCREEDS
INTERNAL PLASTER
2 On walls.
m² 855
3 On narrow widths.
m² 21
EXTERNAL PLASTER
4 On narrow widths.
m² 14
Carried to Collection $
Section No. 3
Bill No. 11
Plastering
105
Package 3 Lot 3
Rate Amount
Carried to Collection $
Section No. 3
Bill No. 11
Plastering
106
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 11
PLASTERING
COLLECTION
Page No
106
SECTION NO. 3
NEW BUILDINGS
BILL NO. 12
TILING
WALL TILING
300 x 300mm 'Dimo Top' unglazed ceramic tiles fixed with adhesive to
plaster (plaster elsewhere) and flush pointed with tinted jointing
compound:
FLOOR TILING
3 On floors to falls.
m² 5
4 Circular cutting.
No. 9
Carried to Collection $
Section No. 3
Bill No. 12
Tiling
108
Package 3 Lot 3
Rate Amount
SUNDRIES
Sundries:
Carried to Collection $
Section No. 3
Bill No. 12
Tiling
109
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 12
TILING
COLLECTION
Page No
109
SECTION NO. 3
NEW BUILDINGS
BILL NO. 13
PLUMBING AND DRAINAGE (PROVISIONAL)
SOIL DRAINAGE
Sundries:
SANITARY FITTINGS
3 Type TU 101 urinal 1460mm wide with 11 litre 'Shires Lynx' automatic
flushing cistern, flush and sparge pipes and hinged domical grating.
No. 2
Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
111
Package 3 Lot 3
Rate Amount
TRAPS ETC
uPVC:
Brass:
'Cobra Watertech':
SANITARY PLUMBING
uPVC pipes:
10 50mm Pipes.
m 4
11 110mm Pipes.
m 7
Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
112
Package 3 Lot 3
Rate Amount
14 110mm Reducer.
No. 1
15 50mm Bend.
No. 3
16 110mm Bend.
No. 11
22 110mm Stubstack consisting of two x 50mm inlets, necessary pipe and all
fittings.
No. 1
23 110mm Stubstack consisting of two x 110mm inlets, necessary pipe and all
fittings.
No. 1
Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
113
Package 3 Lot 3
Rate Amount
Gulleys:
WATER SUPPLIES
29 15mm Pipes.
m 29
30 28mm Pipes.
m 8
31 15mm Fittings.
No. 38
32 22mm Fittings.
No. 10
33 28mm Fittings.
No. 10
TESTING
Testing:
35 22mm Pipes.
m 18
Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
114
Package 3 Lot 3
Rate Amount
38 40mm Bend.
No. 4
39 40mm Pipes.
m 5
40 50mm Junction.
No. 2
'Chubb':
Carried to Collection $
Section No. 3
Bill No. 13
Plumbing And Drainage (provisional)
115
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 13
PLUMBING AND DRAINAGE (PROVISIONAL)
COLLECTION
Page No
112
113
114
115
SECTION NO. 3
NEW BUILDINGS
BILL NO. 14
ELECTRICAL WORK (PROVISIONAL)
DISTRIBUTION BOARDS
Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
117
Package 3 Lot 3
Rate Amount
CABLES
10 16mm2 2-Core.
m 12
CABLE TERMINATIONS
11 16mm2 2-Core.
No. 3
EARTHING
12 10mm2 Conductor.
m 12
13 10mm2 Conductor.
No. 4
SLEEVES
Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
118
Package 3 Lot 3
Rate Amount
17 20mm Diameter.
m 220
18 20mm Diameter.
m 46
19 20mm Diameter.
m 45
20 25mm Diameter.
m 15
Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
119
Package 3 Lot 3
Rate Amount
CONDUCTORS
29 2.5mm².
m 221
30 2.5mm².
m 430
31 4mm².
m 100
Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
120
Package 3 Lot 3
Rate Amount
39 1200mm Double tube 58W open channel fluorescent light fitting and tubes
(C).
No. 30
EARTHING SYSTEM
Conductors, etc.:
43 Steel core reinforced copper spike (rod) 2000 x 16mm diameter and brass
coupling with driving cap driven into ground.
No. 8
Carried to Collection $
Section No. 3
Bill No. 14
Electrical Work (provisional)
121
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 14
ELECTRICAL WORK (PROVISIONAL)
COLLECTION
Page No
118
119
120
121
SECTION NO. 3
NEW BUILDINGS
BILL NO. 15
GLAZING
4mm Obscure:
6mm Silvered float glass copper backed mirrors with polished edges
holed for and fixed with chromium plated dome capped mirror screws
with rubber buffers to plugs in brickwork or concrete:
SECTION NO. 3
NEW BUILDINGS
BILL NO. 16
PAINTWORK
ON FLOATED PLASTER
One coat primer and two coats exterior quality PVA emulsion paint:
One coat alkali resistant primer, one undercoat and two coats eggshell
enamel paint:
ON METAL
6 On door frames.
m² 1
Carried to Collection $
Section No. 3
Bill No. 16
Paintwork
124
Package 3 Lot 3
Rate Amount
One coat calcium plumbate primer, one undercoat and two coats
enamel paint on steel:
Wash down with approved cleaning agent and apply one coat calcium
plumbate primer, one undercoat and two coats enamel paint on
galvanised steel:
ON WOOD
One coat wood primer, one undercoat and two coats eggshell enamel
paint:
12 On doors.
m² 4
SIGNWRITING
Remove all loose particles and laitance and applu one coat Plascon
Waterbased Plaster Primer and two coats Pure Acrylic PVA(allow
sufficient time or drying between coats):
Carried to Collection $
Section No. 3
Bill No. 16
Paintwork
125
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 16
PAINTWORK
COLLECTION
Page No
125
SECTION NO. 3
NEW BUILDINGS
BILL NO. 17
EXTERNAL WORKS (PROVISIONAL)
1 Holes.
m3 0.3
2 Paving to falls.
m² 3
3 Edges, risers, ends and reveals not exceeding 300mm high or wide.
m 7
Bolts:
Paint one coat calcium plumbate primer, one undercoat and two coats
alkyd enamel paint on galvanised steel:
25Mpa/19mm Concrete
Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
127
Package 3 Lot 3
Rate Amount
7 Flagpole bases.
m3 0.3
Flagpole:
9 100 x 40 x 2.5mm Channel 2000mm long and cast into concrete 500mm
deep.
No. 2
10 6mm Diameter bend eye 35mm girth welded to 50mm diameter flagpole.
No. 1
11 Fixing hook formed with two 6mm Diameter round bar bend to right angles
45mm and welded to upright.
No. 1
One coat calcium plumbate primer, one undercoat and two coats alkyd
enamel paint on steel:
Paint one coat calcium plumbate primer, one undercoat and two coats
alkyd enamel paint on galvanised steel:
SOIL DRAINAGE
uPVC:
Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
128
Package 3 Lot 3
Rate Amount
20 110mm Junction.
No. 6
22 450 x 600mm x 53kg Cast iron single seal manhole cover and frame.
No. 1
Brass:
23 35mm Stopcock.
No. 1
Sundries:
25 350 x 350mm Cast iron stopcock box including brick chamber below not
exceeding 1000mm deep internally.
No. 1
Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
129
Package 3 Lot 3
Rate Amount
WATER RETICULATION
27 35mm Reducer.
No. 1
28 35mm Elbow.
No. 1
French drains:
29 French drain comprising of 700 x 780 x 5000mm long trench including flat
stone placed over slots of agricultural pipes (elsewhere measured) and
trench filled with graded stone.
No. 6
30 Connect to existing water supply including water meter and all necessary
fittings.
Item
ELECTRICAL RETICULATION
31 16mm2 2-Core.
m 40
32 35mm2 4-Core.
m 60
CABLE TERMINATIONS
33 16mm2 2-Core.
No. 4
Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
130
Package 3 Lot 3
Rate Amount
34 35mm2 4-Core.
No. 4
35 10mm2 Conductor.
m 40
36 10mm2 Conductor.
No. 1
Carried to Collection $
Section No. 3
Bill No. 17
External Works (provisional)
131
Package 3 Lot 3
Amount
SECTION NO. 3
NEW BUILDINGS
BILL NO. 17
EXTERNAL WORKS (PROVISIONAL)
COLLECTION
Page No
128
129
130
131
SECTION NO. 3
NEW BUILDINGS
SECTION SUMMARY
Bill Page
No.
1 EARTHWORKS (PROVISIONAL) 83
3 MASONRY 90
4 WATERPROOFING 91
5 ROOF COVERINGS 94
8 IRONMONGERY 100
10 METALWORK 104
11 PLASTERING 107
12 TILING 110
15 GLAZING 123
16 PAINTWORK 126
133
Package 3 Lot 3
SECTION NO. 4
SITE WORKS
134
Package 3 Lot 3
Rate Amount
SECTION NO. 4
SITE WORKS
BILL NO. 1
ALTERATIONS
In taking down and removing existing work the utmost care shall be
observed to prevent any structural or other damage to remaining portions of
the building, and the Contractor shall provide all shoring, needling, strutting,
etc. to ensure the stability of all structure during alterations work.
Special care shall be exercised during the progress of the work to ensure
that any electrical installations, water supply pipes, telephone and other
services which may be encountered are not interfered with and notice shall
given to the Architect if any disconnection or alterations becomes necessary.
The Contractor shall take all precautions necessary to prevent any nuisance
from dust whilst carrying out the work.
The Contractor shall make good in all trades to existing work where
damaged or disturbed through the alterations with all necessary new
materails to match the existing.
Carried to Collection $
Section No. 4
Bill No. 1
Alterations
135
Package 3 Lot 3
Rate Amount
The Contractor shall be responsible for the removal from the site all
materials, debris and rubbish resulting from the alterations.
The known services both underground and overhead will be pointed out to
the contractor. The Contractor is hereby expected to include in his tendering
price the cost of exposing of such services where expedient, be the services
known or unknown, as long as it is deemed necessary.
Demolitions, etc:
(2) all external screen and internal walls (clay brick should be set aside,
cleaned, for re-use) steps, ramps, aprons, surface water channels,
rainwater sumps, gulleys, etc. attached to the building to be demolished;
(3) all services, manholes, etc.in ground to a point not less than 1000mm
beyond the perimeter of the building, including plugging of ends of remaing
pipes, drains, etc.,filling in holes where necessary and ramming and
levelling to the ground level.
1 Steps.
m³ 1
Carried to Collection $
Section No. 4
Bill No. 1
Alterations
136
Package 3 Lot 3
Rate Amount
3 Columns.
m³ 1
4 Mass brickwork.
m³ 1
7 1,800mm High wire mesh security fence complete standard columns, posts,
stays, bracers, etc.
m 464
Carried to Collection $
Section No. 4
Bill No. 1
Alterations
137
Package 3 Lot 3
Amount
SECTION NO. 4
SITE WORKS
BILL NO. 1
ALTERATIONS
COLLECTION
Page No
136
137
SECTION NO. 4
SITE WORKS
BILL NO. 2
EXTERNAL WORKS
1 Allow for clearing the area of the site to be built upon of all rubbish, debris,
vegetation, hedges, shrubs, trees with trunks not exceeding 200mm girth,
including grubbing up all roots, scoffling up as required and cart away all
vegetation and debris.
m² 105
FENCING
4 Horizontal stay 76mm diameter 2000mm long with each end bolted to posts.
No. 46
5 Inclined stay 50mm diameter 2500mm long with one end bolted to post and
other end welded to 200 x 200 x 5mm sole plate and cast into and including
(750 x 400 x 400 mm deep 15Mpa/19) concrete base.
No. 5
Carried to Collection $
Section No. 4
Bill No. 2
External Works
139
Package 3 Lot 3
Rate Amount
6 Straining post 100mm diameter 2,100mm high vertically, with 200 x 200 x
5mm sole plate and cast into and including (500 x 500 x 900mm 15Mpa/19)
concrete base.
No. 9
7 Corner post 100mm diameter 2,100 mm high vertically with 200 x 200x 5
mm sole plate and cast into and including (500 x 500 x 900 mm 15 Mpa/19)
concrete base
No. 46
10 Double gate 5,000 x 2,100mm high in equal leaves, each leave formed of
50mm diameter hollow section perimeter frame and two 35mm diameter
hollow section cross bracers rails filled in with three galvanised wires at
500mm centres horizontally and four barbed wires horizontally at top with a
pair of suitable hinges welded to post and with 'viro heavy duty lock'
complete with three keys, each leaf to bear 8 x 50mm ring around stiles and
100 x 8mm rod pin through stiles and hung to 100mm diameter pressed
steel frame and other leaf to bear 200mm barrel bolt to be anchor on a hole
on 300 x 300 x 300mm concrete anchor block complete with high gloss
enamel paint.
No. 1
Carried to Collection $
Section No. 4
Bill No. 2
External Works
140
Package 3 Lot 3
Rate Amount
11 Trenches
m³ 325
16 Strip footings.
m³ 81
Carried to Collection $
Section No. 4
Bill No. 2
External Works
141
Package 3 Lot 3
Rate Amount
Brickwork reinforcement:
23 On walls.
m² 2041
24 On narrow widths.
m² 102
Remove all loose particles and laitance and apply one coat Plascon
Waterbased Plaster Primer and two coats Plascon Pure Acrylic PVA
(allow sufficient time for drying between coats).:
26 Trenches.
m³ 4
Carried to Collection $
Section No. 4
Bill No. 2
External Works
142
Package 3 Lot 3
Rate Amount
Precast concrete left rough from the mould including bedding, jointing
and pointing:
31 1990mm Diameter concrete ring 465 mm wide x 150mm thick and with 100
x 75mm channel allround including necessary reinforcement.
No. 2
20Mpa/19mm Concrete
32 Strip footings.
m³ 2
25 MPa/19mm Concrete:
Carried to Collection $
Section No. 4
Bill No. 2
External Works
143
Package 3 Lot 3
Rate Amount
36 Paving to falls.
m² 12
37 Edges, risers, ends and reveals not exceeding 300mm high or wide circular
exceeding 1m radius.
m 24
38 Vanity slabs, cupboard slabs, cover slabs, etc. propped up not exceeding
1,5m high.
m² 4
39 365mm Hollow walls of two half brick skins and cavity filled solid with
hardcore filling no wire ties circular on plan in foundations.
m² 3
41 365mm Hollow walls of two half brick grilled skins and cavity filled with
charcoal no wire ties circular on plan.
m² 5
Metalwork Sundries:
42 1.5 x 19mm Flat metal ring 130mm diameter soldered to underside of water
tray (water tray elsewhere measured.
No. 16
Wire Mesh
44 On walls.
m² 7
Carried to Collection $
Section No. 4
Bill No. 2
External Works
144
Package 3 Lot 3
Rate Amount
45 1.2mm Thick 1550mm Diameter tray 150mm deep including 2mm diameter
holes drilled at 150mm centres in base.
No. 2
48 15mm Pipes.
m 12
49 15mm Fittings.
No. 50
Carried to Collection $
Section No. 4
Bill No. 2
External Works
145
Package 3 Lot 3
Amount
SECTION NO. 4
SITE WORKS
BILL NO. 2
EXTERNAL WORKS
COLLECTION
Page No
140
141
142
143
144
145
SECTION NO. 4
SITE WORKS
SECTION SUMMARY
Bill Page
No.
1 ALTERATIONS 138
147
Package 3 Lot 3
SECTION NO. 5
PROVISIONAL SUMS
148
Package 3 Lot 3
Amount
SECTION NO. 5
PROVISIONAL SUMS
JOINERY FITTINGS
Joinery fittings:
1 Provide the amount of N$60, 000. 00 (Sixty Thousand Namibian Dollars) for
the replacement of all damagedJoinery Fittings and the supply and delivery
of new Duracraft or similar approved stainless steel cupboards.
Item 60,000 00
3 Attendance on ditto.
Item
6 Attendance on ditto.
Item
SECTION NO. 5
PROVISIONAL SUMS
SECTION SUMMARY
Page
150
Package 3 Lot 3
1 PRELIMINARIES 28
2 RENOVATIONS 78
ADD: CONTINGENCIES
Allow the Amount of N$350, 000. 00 (Three Hundred and Fifty Thousand 350,000 00
Namibian) for contingencies, to be used by the Engineer in terms of
Clause 3 of the FIDIC [The Federation Internationale des Ingenieurs
Conseils] 'Red Book' Contract 1999 Edition.
FINAL SUMMARY
151
Package 3 Lot 3
Bill No Page No
SECTION NO. 1: PRELIMINARIES 1
SECTION SUMMARY 27
SECTION SUMMARY 28
1 ALTERATIONS 30
Building Up Openings 34
Remedial Works 35
Plaster Repairs 35
Crack Repairs 36
2 EARTHWORKS 38
Carting Away. 38
Soil Poisoning 39
Reinforced Concrete 41
(i)
Package 3 Lot 3
Grooves, Etc. 41
4 MASONRY 42
Supplementary Preambles 42
Brickwork 42
Brickwork Sundries 42
7 IRONMONGERY 47
Bathroom Fittings 48
Sundries 48
8 METALWORK 50
9 PLASTERING 53
Screeds 53
(ii)
Package 3 Lot 3
Internal Plaster 53
External Plaster 53
10 TILING 54
Supplementary Preambles 55
Sanitary Fittings 56
Traps Etc 57
Water Supplies 57
Testing 59
Sleeves 61
Distribution Boards 63
Conductors 63
Electrical Reticulation 64
13 GLAZING 68
(iii)
Package 3 Lot 3
14 PAINTWORK 69
Supplementary Preambles 69
On Metal 70
On Smooth Plaster 70
On Metal 71
15 EXTERNAL WORKS 74
SECTION SUMMARY 78
1 EARTHWORKS (PROVISIONAL) 80
Nature Of Ground 80
Carting Away. 81
Soil Poisoning 82
Test Blocks 84
Unreinforced Concrete 84
(iv)
Package 3 Lot 3
Grooves, Etc. 85
3 MASONRY 87
Brickwork In Superstructure 87
Brickwork Sundries 87
Brick Paving 89
4 WATERPROOFING 91
5 ROOF COVERINGS 92
Flush Doors 95
Nailed Up Ceilings 96
8 IRONMONGERY 97
Locks 97
Bathroom Fittings 97
Sundries 98
(v)
Package 3 Lot 3
Shelving Units 98
Steel Lockers 99
10 METALWORK 102
11 PLASTERING 105
Screeds 105
12 TILING 108
Sundries 109
(vi)
Package 3 Lot 3
Testing 114
Cables 118
Earthing 118
Sleeves 118
Conductors 120
15 GLAZING 123
16 PAINTWORK 124
(vii)
Package 3 Lot 3
On Metal 124
On Wood 125
Signwriting 125
1 ALTERATIONS 135
Fencing 139
(viii)
Package 3 Lot 3
(ix)