APPENDIX - A

(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX

SITE PROJECTS DEPARTMENT


Project Control
Revision No.: 01 Active Date: September 2016 Review Cycle: 2 Years
This document is digitally signed by all Approval Authorities listed below.
Details of the approval can be audited from Q-Pulse System by opening its Document Details
Card.
Q-Pulse ID (1435)
Prepared by: Reviewed by: Verified by: Approved by:
K.T.Ahmed
Sr. Engineer, Project Control
ID#: 27035;
Date: 21-09-2016 Abdulrahman J Al Khaldi
Luqman Umar
Director-SPD
QA/QC Team Sr. Manager -TAT ID#: 5790
Iqbal Tarwala ID#: 8228
Date: 21-09-2016
Lead Engineer (TAT) / Date: 21-09-2016
DMR - SPD
ID#: 22601
Date: 21-09-2016

PROPRIETARY & CONFIDENTIAL


This document and the information contained herein is SABIC’s proprietary know-how. This document or any
part thereof should not be reproduced, stored in a retrieval system or transmitted by any means, electronic or
otherwise, or divulged without prior written permission of SABIC.
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


Serial No. Activity Site QA/QC CP
Team Team Team
Civil, Architectural & Structure
1 EARTH WORK
1.1 Layout Survey, Establish and protection of Co - Ordinates. X
1.2 Investigation of U/G Facility. X
1.3 Elevation check for existing surface. X
1.4 Suitability for Re- Use of excavated Sand / Soil or Filling
X
Materials.
1.5 Compaction test witness X
1.6 Compaction test of soil for Under ground piping X
1.7 Back filling inspection of U / G piping X
1.8 Fixing of Finished Slope (Location, inclination, Surface finish,
X
Level Fixing)
1.9 Material Approvals for sweet sand, Marl, base course,
X
Aggregate, earth fill materials etc)
2 SOIL IMPROVEMENT WORK
2.1 Procedure Approval X
2.2 Investigation of U/G Facility. X
2.3 Material approval for fill material and gradation X
2.4 Testing of Improved soil X
2.5 Pilot Test X
2.6 Vibroflot test and its compaction X
3 ASPHALT WORK
3.1 Layout Survey, Establish and protection of Co - Ordinated. X
3.2 Compaction test witness X
3.3 Surface/ Sub base finish (Slope and elevation) X
3.4 Approval of Asphalt Materials X
3.5 Apply Prime coat for asphalt X
3.6 Apply tack coat for asphalt. X
3.7 Visual Inspection of surface finish of Asphalt (Ponding, slope
X
and flatness)
3.8 Temperature & other tests of asphalt X
3.9 Asphalt material verification at site X
3.10 Witness for thickness of asphalt. X
4 CONCRETE WORK
4.1 Layout Survey, Establish and protection of Co - Ordinated. X
4.2 Compaction test witness X
4.3 Lean Concrete (Location/Elevation/Thickness) X
4.4 Trial Mix of Concrete X
4.5 Material Approval of Concrete/ Rebar/ Expansion joint/
X
construction joint and form work
4.6 Slump / Temp test of concrete X
4.7 Compressive strength of concrete X
4.8 Line, level, axis of Formwork prior to concrete pour. X
4.9 Water proof coating inspection for all U/G Concrete. X
4.10 Anchor bolt or any structure which is embedded to concrete
X
and box installation Inspection
4.11 Time for removal of Form and support. X

Page 2 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


5 STRUCTURE STEEL
5.1 Dimensional inspection X
5.2 Plumb and elevation Inspection X
5.3 Torque wrench/ Distomat calibration Inspection. X
5.4 Tightening of high strength Bolt. X
5.5 Nuts/ Bolt and anchor bolt approval X
5.6 Inspection of Handrail and ladder fittings. X
5.7 Fire Proofing Materials Approval X
5.8 Wire mesh installation X
5.9 Application of fire proofing X
6 SEWER AND DRAINAGE
6.1 Installation of Pipe (Slope, elevation, co ordinated and
X
alignment of Pipe.)
6.2 Joint/ Tie - in of pipe X
6.3 Water fill test X
6.4 Gravity test X
6.5 Coating wrapping test X
6.6 Holiday test X
6.7 Water proof coating inspection under the man hole. X
6.8 Material approval for oily sewer/ sewer line pipe, coating
X
material for inside manhole.
7 BUILDING CONSTRUCTION
7.1 Layout Survey, Establish and protection of Co - Ordinated. X
7.2 Footing layout/ Elevation including Anchor bolt inspection if
X
any.
7.3 Material receiving and storing X
7.4 Flood test of roofing X
7.5 Water Proofing Activities X
7.6 Weather strip and sealing of Doors / windows. X
7.7 Hydro test of PW and FW Line X
7.8 Ducting Inspection X
7.9 Door, Window & Ceiling installation Inspection. X
7.10 Material Approval all architectural material X
7.11 Material approval all Civil/ Structural material X
7.12 Blockwork X
7.13 Plastering X
7.14 Painting X
8 EQUIPMENT INSTALLATION
8.1 Tightening of Anchor bolts X
8.2 All type of grouting inspection. X

MECHANICAL
9 MATERIALS APPROVAL / VERIFICATION
9.1 Approval of mill test certificates for materials X
9.2 Verification of materials procured by Project Engineer X
9.3 Verification of materials procured by Contractor X
9.4 Approval of mill test certificates for materials Procured by
X
Contractor

Page 3 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


9.5 Alloy verification (PMI & MTC’s) X
9.6 Transfer of identification marks like Heat #, Specifications…etc X
9.7 Positive materials identification ( PMI ) X
10 WELDING:
10.1 WPS / PQR approval X
10.2 Welder certification X
10.3 Dissimilar material approval ( will be covered under WPS )
X
approval
10.4 Welding rods approval X
10.5 Beveling inspection X
10.6 Fit-up X
10.7 Root pass X
10.8 Visual inspection (random) X
10.9 Visual inspection ( All ) X X
10.10 Back chipping X
10.10 PWHT ( Furnace ) X
10.12 PWHT ( Site ) X
10.13 Hardness test of welds X
11 NDT:
11.1 Selection of weld joints for NDT ( RT, DPT, MPI,…etc ) X
11.2 Radiography film interpretation/acceptance X
11.3 DPT witness/acceptance X
11.4 Thickness measurement witness X
11.5 MPI witness/acceptance X
12 FRP/ RTR U/G PIPE
12.1 Material Receiving Inspection X
12.2 Sand Bedding Inspection X
12.3 Dimensional Inspection for Elevation, Slope, Coordinates. X
12.4 Back filling of pipe zone. X
12.5 Hydro test X
12.6 Deflection Check X
12.7 Joining Pipe (Coupling, flange) X
13 EQUIPMENT INSTALLATION
13.1 Performance test for fire fighting system X
13.2 HVAC air balancing X
13.3 Noise and vibration test of structure and foundation X
13.4 Static equipment plumb, elevation inspection. X
14 GENERAL INSPECTION:
14.1 Locations X
14.2 Elevations X
14.3 Slope X
14.4 Dimensional X site X
14.5 All inside and outside Kingdom Equipment -Final Inspection
(Visual , Dimensional , Hydrotest and Performance Test for X
Rotary Equipmemt
14.6 Pre and Final Alignment of rotary equipments X
14.7 Alignment of Static Equipments. X

Page 4 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


14.8 Calibration of Satefy and Relief Valves prior to installation X
14.9 Peaking and Banding for storage tanks X
14.10 Vacuum box test for storage tanks X
14.11 Foundation settlement check for storage tanks X
14.12 Vessels & tanks internal inspection prior to Box up X
14.13 Static Equipment internal component Installation Inspection X
14.14 Visual inspection of foundations prior to installation of
X
Vessels…etc
14.14 Tightening of Flange bolts X
14.16 Supports installation X
14.17 Tie-in Location & Marking X
15 PRESSURE TESTING:
15.1 Test pack approval X
15.2 Review of gauges caliberation X
15.3 Line check prior to pressure testing X
15.4 Witness of Piping system and Isolation Valves Hydrostatic test X
15.5 Witness of Pneumatic test X
15.6 Witness of leak test X
15.7 Cleaning / flushing of tested lines X
15.8 Pigging of lines X
15.9 Plugging & seal welding of high point vents after pressure tests X
15.10 Witness of DPT / MPI of high points vents welding X
16 PAINTING & INSULATION:
16.1 Materials approval X
16.2 Surface preparation X
16.3 Primer coat painting & DFT X
16.4 Intermediate coat painting & DFT X
16.5 Final coat painting & DFT X
16.6 Galvanising X shops X
16.7 Holiday testing of wrappings X
16.8 Inspection of insulation support rings X
16.9 Visual inspection of Insulation X
16.10 Stenciling X
17 RE-INSTATEMENT:
17.1 Line check after re-instatement X
17.2 Valves direction where applicable X
17.3 Proper gaskets installation X
17.4 System punchlist X X
18 PROJECT PROCEDURES:
18.1 Approval of PQP , Inspection test plans, WPS/PQR , WPQT
X
etc.
18.2 Approval of testing procedures X
18.3 Review / Approval of Q.C Dossier X
18.4 Review / Approval of As built drawings X
18.5 Approve of Vendors & Contractors shops X

ELECTRICAL

Page 5 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


19 MATERIALS & EQUIPMENT APPROVAL/VERIFICATION:
19.1 Approve all electrical materials supply by the contractor. X
19.2 Physical verification of materials procured by Contractors. X
19.3 Verification of electrical equipment & materials procured. X
19.4 Verification of approve vendors by the contractor X
20 ELECTRICAL MAIN EQUIPMENT INSTALLATION
(TRANSFORMER, SWITCHGEAR/MOTOR CONTROL
CENTER , ELECTRIC MOTOR & OTHER )
20.1 Verification of final location & orientation. X
20.2 Visual Inspection of Anchoring / Bolting & alignment X
20.3 Conduit Instllation X
20.4 Cable termination X
20.5 Grounding connection X
20.6 Visual Inspection of internal electrical & mechanical connection X
21 ELECRICAL MAIN EQUIPMENT TESTING
COMMISSIONING:
21.1 Insulation Test (Megering,Hi-Potential testing) X
21.2 Functional Check for all Switches (Interlock, Control &
X
operation test)
21.3 Contact resistance test (for Main Circuit Breakers & Bus Bars) X
21.4 Transformer Ratio test X
21.5 Relay setting, testing & calibration X
21.6 Solo run test (electric motor where applied vibration,RPM,
X
directional of rotation. Bearing temperature test)
21.7 Insulation oil test X
21.8 Polarization Index testing X
21.9 Phase sequence test X
21.10 Operation test by Manual & Automatic X X

22 INSTALLATION OF POWER/CONTROL
CABLES:
22.1 Visual inspection for cable tray, conduit & cable routing X
22.2 Visual inspection cable trench & duct bank (deep/dimension) X
22.3 Visual inspection cable laying, termination & splice X
22.4 Hi-Potential,Meggering,loop & continuity test X
23 INSTALLATION OF LIGHTING:
23.1 Verification for approved layout X
23.2 Visual inspection X
23.3 Insulation resistance measurement X
23.4 Lighting circuit test X
23.5 Illumination quality test X
24 INSTALLATION OF WIRING DEVICES:
24.1 Verification for approved layout X
24.2 Visual inspection (wiring termination) X
24.3 Line circuit test X
24.4 Insulation resistance measurement X
24.5 Operation test X
25 INSTALLATION OF GROUNDING & LIGHTNING SYSTEM:

Page 6 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


25.1 Verification of approved layout X
25.2 Visual inspection (cadwelding,cable laying & termination) X
25.3 Grounding resistance measurement X
25.4 Lightning electrode measurement X
25.5 Grounding Continuity test X
26 INSTALLATION OF UPS,BATTERY & BATTERY CHARGER:
26.1 Visual inspection (Panel mounting, Batteries set up with rack) X
26.2 Functional & Operation test by Manual & Automatic mode) X
26.3 Grounding connection X
26.4 Internal electrical & mechanical connection X
27 INSTALLATION OF MISCELLANEOUS EQUIPMENT (FIRE
ALARM, TELEPHONE/ PUBLIC ADDRESS/ PAGING & UHF
RADIO SYSTEM)
27.1 Visual inspection (Panel layout & mounting, Interconnection) X
27.2 Insulation resistance measurement X
27.3 Grounding connection X
27.4 Cable termination & splice X
27.5 Functional & Operation test X

CONTROL SYSTEMS
28 FIELD DEVICES (TRANSMITTERS, GAS DETECTORS,
SWITCHES, CONTROL VALVES, SENSORS, ANALYZERS,
J.B), LOCAL CONTROL PANEL & ANALYZER HOUSE
28.1 Bulk Construction Materials Spec. verification X
28.2 Instrument data sheet verification X
28.3 Physical verification of bulk construction materials procured by
X
contractor
28.4 Physical verification of Instruments, C.Valves, Sensors
X
procured by contractor
28.5 Shell & Seat Leakage test (Control Valves ) X
28.6 Instruments calibration X
28.7 Verification of approved location for Field Devices, L.Panel,
X
Analyzer House
28.8 Field Devices / Local Panel/ Analyzer House Installation X
28.9 Conduit / Cable Tray Installation X
28.10 Cable trench / Duct bank visual inspection X
28.11 Signal & Power Cable laying /pulling X
28.12 Impulse / Pneumatic Tubing Hook-up X
28.13 Tubing Pressure test / Leak test X
28.14 Grounding system installation X
28.15 Grounding system testing X
28.16 Insulation Resistance Test & Continuity check X
28.17 Field terminations X
28.18 Field Devices / Local Control Panel / Analyzers power supply
X
check
28.19 Loop check (Analyzer House / Local Control Panel) X
29 DCS/PLC/ESD/VMS (CONTROL SYSTEMS)
29.1 Received System Cabinet Components Verification X
29.2 Control System Cabinets Installation X

Page 7 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


29.3 Conduit / Cable Entries / Cable Tray Installation X
29.4 Signal & Power Cable laying /pulling X
29.5 Grounding system installation X
29.6 Grounding system testing X
29.7 Insulation Resistance Test & Continuity check X
29.8 Control System Cabinets Terminations X
29.9 Communication / System Cables Routing X
29.10 Communication / System Cables Terminations X
29.11 Fiber Optic (FO) Cable Laying X
29.12 Fiber Optic (FO) Cable Testing (OTDR) & Laser Test X
29.13 Control System Cabinets Power Supply Check X
29.14 Communication Check (System /Subsystems) X
29.15 Loop check X
29.16 Functional Check ( Logic / Interlocks) X

30 CATHODIC PROTECTION SYSTEM


31 REINFORCED CONCRETE CATHODIC PROTECTION
31.1 Materials
I. Material Submittal Approval X
II. Material Delivery and inspection X X
IV. Material Storage X X
31.2 Reference Electrodes Function Test and Encapsulation
I. Manufacturer’s test certificates Approval X
II. Calibration Test Inspection X
III. Encapsulation Test Inspection X
IV. Post Encapsulation Test and Inspection X
31.3 Installation of Conductor Bar , Anode ribbons, positive
connection, system negative, instrument negative and
Positive connection kits
I. Location and Spacing Inspection X
II. Installation and Spot Welding Inspection X
III. Mechanical Integrity inspection for spot welding X
IV. Zones separated inspection according to drawings. X
V. Electrical Continuity test of anode-to-anode, anode to
X
conductor bar and anode feeder cables to anode & CB.
VI. Cad Welding inspection for IN and SN X
VII. Hammer Test for mechanical integrity of IN and SN X
VIII. Electrical Continuity test of IN and SN cables with the steel
X
reinforcement.
31.4 Installation of Reference Electrodes
I. Location inspection as per drawing X
II. Visual Inspection X
31.5 Pre-Concrete Pour Inspections
I. Visual Inspection to ensure area is clean and free of any
X X
possible electrical short circuits
II. Electrical discontinuity testing of anode and cathode X X
III. Electrical Continuity testing of reinforcement and other
X
nearby metallic components

Page 8 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


31.6 Concrete Pour monitoring Inspections
I. Anode to Cathode voltage measurements at every 10mins
X X
interval
31.7 Post Pour monitoring
I. Anode to Cathode voltage measurements test X
II. Native potential of steel w.r.t embedded reference electrodes
X
test.
31.8 Junction Box Installation
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in JB X X
IV. Support post and mounting X X
31.9 Transformer Rectifier Factory Acceptance Test X TR
manufacturer premises
I. DC output ripple factor Test X
II. Temperature rise Test X
III. Efficiency Test X
IV. Dielectric Test X
31.10 Power and Grounding Cable Installation
I. Above ground conduit installation X X
II. Cable tray installation X X
III.Trench inspection (by QA/QC but was recommended earlier
X X
by Mr. Majmal to Site Team)
IV.Construction of duct bank X X
V. Underground duct bank installation X X
VI. Inspection of conduit, cable tray and trench after cable
X X
laying
VII. Insulation resistance test after cable laying X X
VIII. Grounding cable installation, termination and testing X X
31.11 Remote monitoring and control system X TR manufacturer
premises
I. Visual Inspection X
II. Accuracy checks of TR and monitoring values with software
X
values.
III. Remote control checks of TR at various current and voltage
X
outputs.
31.12 Transformer Rectifier Installation
I. Manufacturer’s test certificates approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in TR X X
IV. Concrete foundation or support post and mounting X X
31.13 Pre-Commissioning
CP system circuit verification, continuity and discontinuity tests
X
inspection for positive and negative systems
Native potential test inspection X
Pre-Commissioning forms approval X
31.14 Commissioning
CP system energization inspection X
CP system polarization test inspection after one week of
X
energization

Page 9 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


Initial commissioning report and forms approval X
31.15 Commissioning and 30 day acceptance
CP system performance acceptance inspection X
CP system performance report and forms approval X

32 TANK BOTTOM PLATE CATHODIC PROTECTION


32.1 Materials
I. Material Submittal Approval X
II. Material Delivery and Inspection X X
IV. Material Storage X X
32.2 Reference Electrodes Function Test
I. Manufacturer’s test certificates Approval X
II. Calibration Test Inspection X
32.3 HDPE Liner Installation X
Sweet sand
I. Resistivity Test prior to backfilling X
II. Backfilling (Free of stones and other debris) X X
32.4 Installation of HDPE Liner, Conductor Bar , Anode ribbons
and positive connection kits
I. Location and Spacing Inspection X
II. Installation and Spot Welding Inspection X
III. Mechanical Integrity checks for spot welding X
IV. Electrical Continuity test of anode-to-anode, anode to
X
conductor bar and anode feeder cables to anode & CB.
32.5 Installation of System and Test negative connection kits
I. Location Inspection as per drawing X X
II. Cad Welding Inspection X X
III. Hammer Test for mechanical integrity X X
IV. Electrical Continuity test of System Negative and Test
X X
Negative Cables
32.6 Installation and testing of Reference Electrodes,
Monitoring tubes and Soil access tubes
I. Location inspection X
II. Visual Inspection X
III.Calibration testing of Reference Electrodes X
32.7 Installation of Monitoring tubes, soil access holes and RE
calibration tubes
I. Location inspection X
II. Visual inspection and integrity test of monitoring tubes X
32.8 Junction Box Installation
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in JB X X
IV. Support post and mounting X X
32.9 Transformer Rectifier Factory Acceptance Test X TR
manufacturer premises
I. DC output ripple factor test X
II. Temperature rise test X

Page 10 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


III. Efficiency Test X
IV. Dielectric Test X
32.10 Power and Grounding Cable Installation
I. Above ground conduit installation X X
II. Cable tray installation X X
III. Trench inspection (by QA/QC but was recommended
X X
earlier by Mr. Majmal to Site Team)
IV. Construction of duct bank X X
V. Underground duct bank installation X X
VI. Inspection of conduit, cable tray and trench after cable
X X
laying
VII. Insulation resistance test after cable laying X X
VIII.Grounding cable installation, termination and testing X X
32.11 Remote monitoring and control system X TR manufacturer
premises
I. Visual Inspection X
II. Accuracy checks of TR and monitoring values with software
X
values.
III. Remote control checks of TR at various current and voltage
X
outputs.
32.12 Transformer Rectifier Installation
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in TR X X
IV. Concrete foundation or support post and mounting X X
32.13 Pre-Commissioning
CP system circuit verification, continuity and discontinuity tests
X
inspection for positive and negative systems
Native potential test inspection X
Pre-Commissioning forms approval X
32.14 Commissioning
CP system energization inspection X
CP system polarization test inspection after one week of X
energization
Initial commissioning report and forms approval X
32.15 Commissioning and 30 day acceptance
CP system performance acceptance inspection X
CP system performance report and forms approval X

33 TANK INTERNAL CATHODIC PROTECTION


33.1 Materials
I. Material Submittal Approval X
II. Material Delivery and inspection X X
III. Material Storage X X
33.2 Reference Electrodes Function Test
I. Manufacturer’s test certificates Approval X
II. Function Test Inspection X
33.3 Sacrificial Anodes Function Test
I. Manufacturer’s test certificates Approval X

Page 11 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


II. Function Test Inspection X
33.4 Installation of Sacrificial Anodes
I. Location of Anodes Inspection X
II. Visual Inspection of anodes prior to installation X
III. Elevation and spacing inspection of suspended anodes X
IV. Electrical Continuity test of Anode Tail and Anode body X
33.5 Installation of Impressed Current Anodes
I. Location Inspection of Anode suspension brackets X
II. Visual Inspection of anodes prior to installation X
III. Elevation and spacing inspection of suspended anodes X
IV. Electrical Continuity test of Anode Tail and Anode body X
V. Anode strings inspection secured to tank bottom plate with
X
non-metallic connection
33.6 Installation of System and Test negative connection kits
I. Location inspection as per drawing X X
II. Cad Welding inspection X X
III. Hammer Test for mechanical integrity X X
IV. Electrical Continuity test of System Negative and Test
X X
Negative Cables
33.7 Installation of Reference Electrodes
I. Location inspection X
II. Visual Inspection X
33.8 Junction Box Installation
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in JB X X
IV. Support post and mounting X X
33.9 Transformer Rectifier Factory Acceptance Test X TR
manufacturer premises
I. DC output ripple factor test X
II. Temperature rise test X
III. Efficiency Test X
IV. Dielectric Test X
33.10 Power and Grounding Cable Installation
I. Above ground conduit installation X X
II. Cable tray installation X X
III. Trench inspection (by QA/QC but was recommended
X X
earlier by Mr. Majmal to Site Team)
IV. Construction of duct bank X X
V. Underground duct bank installation X X
VI. Inspection of conduit, cable tray and trench after cable
X X
laying
VII. Insulation resistance test after cable laying X X
VIII. Grounding cable installation, termination and testing X X
33.11 Remote monitoring and control system X TR manufacturer
premises
I. Visual Inspection X
II. Accuracy checks of TR and monitoring values with software
X
values.

Page 12 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


III. Remote control checks of TR at various current and voltage
X
outputs.
33.12 Transformer Rectifier Installation
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in TR X X
IV. Concrete foundation or support post and mounting X X
33.13 Pre-Commissioning
CP system circuit verification, continuity and discontinuity tests
X
inspection for positive and negative systems
Native potential test inspection X
Pre-Commissioning forms approval X
33.14 Commissioning
CP system energization inspection X
CP system polarization test inspection after one week of X
energization
Initial commissioning report and forms approval X
33.15 Commissioning and 30 day acceptance
CP system performance acceptance inspection X
CP system performance report and forms approval X

34 UNDERGROUND PIPELINES CATHODIC PROTECTION


34.1 Materials
I. Material Submittal Approval X
II. Material Delivery and Inspection X X
IV. Material Storage X X
34.2 Reference Electrodes Function Test
I. Manufacturer’s test certificates Approval X
II. Function Test Inspection X
34.3 Sacrificial Anodes Function Test
I. Manufacturer’s test certificates Approval X
II. Function Test Inspection X
34.4 Installation of Sacrificial Anodes
I. Location Inspection of Anode as per approved drawing X
II. Visual Inspection of anodes prior to installation X
III. Anodes soaked in water for 2 hours prior to installation X
34.5 Installation of Impressed Current Anodes
I. Location Inspection of Anode as per approved drawing X
II. Visual Inspection of anodes prior to installation X
III. Elevation and spacing of anodes X
IV. Electrical Continuity test of Anode Tail and Anode body X
V. Anode strings secured to tank bottom plate with non-metallic
X
connection
34.6 Installation of System and Test negative connection
I. Location Inspection as per drawing X X
II. Cad Welding Inspection X X
III. Hammer Test for mechanical integrity X X

Page 13 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


IV. Electrical Continuity test of System Negative and Test
X X
Negative Cables
34.7 Installation of Reference Electrodes
I. Location Inspection as per drawing X
II. Visual Inspection X
34.8 Installation of CP Coupons
I. Location as per drawing X
III. Native potential Test X
34.9 Installation of Test Stations
I. Location Inspection as per drawings X
II. Visual inspection and integrity tests of the terminals X X
III. Accurate termination of cables X X
IV. Installation and integrity of Interrupter Switches. X X
34.10 Junction Box Installation
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in JB X X
IV. Support post and mounting X X
34.11 Transformer Rectifier Factory Acceptance Test X TR
manufacturer premises
I. DC output ripple factor test X
II. Temperature rise test X
III. Efficiency Test X
IV. Dielectric Test X
34.12 Power and Grounding Cable Installation
I. Above ground conduit installation X X
II. Cable tray installation X X
III. Trench inspection (by QA/QC but was recommended
X X
earlier by Mr. Majmal to Site Team)
IV. Construction of duct bank X X
V. Underground duct bank installation X X
VI. Inspection of conduit, cable tray and trench after cable
X X
laying
VII. Insulation resistance test after cable laying X X
VIII. Grounding cable installation, termination and testing X X
34.13 Remote monitoring and control system X TR manufacturer
X
premises
I. Visual Inspection X
II. Accuracy checks of TR and monitoring values with software
X
values.
III. Remote control checks of TR at various current and voltage
X
outputs.
34.14 Transformer Rectifier Installation X
I. Manufacturer’s test certificates Approval X
II. Visual Inspection of enclosures along with all required name
X X
plates
III. Visual inspection and integrity tests of the terminals in TR X X
IV. Concrete foundation or support post and mounting X X
34.15 Pre-Commissioning

Page 14 of 15
APPENDIX - A
(Ref. Doc.: EPM-SPD-PC-P-004 Field Inspection Procedure)

INSPECTION BOUNDARY MATRIX


CP system circuit verification, continuity and discontinuity tests
X
inspection for positive and negative systems
Native potential test inspection X
Pre-Commissioning forms approval X
34.16 Commissioning
CP system energization inspection X
CP system polarization test inspection after one week of X
energization
Initial commissioning report and forms approval X
34.17 Commissioning and 30 day acceptance
CP system performance acceptance inspection X
CP system performance report and forms approval X

Page 15 of 15