 Brief Process Analysis of the business

 About Group Companies

 Long and Short term Corporate Objectives

 Land Requirement

 Power and Manpower Requirement

 Financial Requirement

 Locational Advantages

 Marketing Assessment

 Expected Financials (Projections Financial Year 2018-19)

 Coverage under North Eastern Industrial Development

Policies
Brief Process Analysis of the Company…

Procurement of Acacia Wood Logs would then be cut


Catechu. into smaller pieces.

Smaller Wood pieces would then be


cut into wooden chips.

Wood Chips would then be boiled with water in


stainless steel vessels with the help of the steam
generated through boiler.

That extracted liquid will then


undergo the process of evaporation
with the effects of evaporators.

Then the extracted liquid of The finished Output will then


required thickness will be undergo the quality inspection .
produced as a finished output.

Finally, the extracted liquid


would be packed in 50 kg
drums.
Our grOup COmpanies…

Ecoste – A Venture of Asma Traexim Pvt Ltd

About ECOSTE:

Ecoste is a private limited company established in 2012


with its manufacturing unit at Haryana , Sonepat.

 A thought for Environment & durability gave birth to


ECOSTE
 Leading manufacturer of wood polymer composite &
mineral polymer composite boards, doors and door
frames and decorative materials.
 Quality conscious company that strive to provide best
to the customers.
 Chemical free products.
Asma Agro Products

About Asma Agro Products:

Asma Agro Products is a partnership firm well


established in Haryana, Sonepat. In this we are:

 Using agricultural waste of cashew husk to produce


vegetable extract catechu.
 Eco-friendly manufacturing process with minimum
wastage of water.
 Medicinal uses is also there for the same product
Asma Biomass Products

About Asma Biomass Products :


Asma Biomass is an upcoming venture of Asma Group ,
it will be a sole proprietorship firm & will be establish
near it’s group in Haryana, Sonepat. It will :
 Producing renewable source of energy i.e Biomass
pellet using agricultural waste of cashew husk.

 Renewable source thus contributes to sustainable


environment.

 Biofuels leads to low pollution levels & lesser


greenhouse emissions.
Long and Short term Corporate

Objectives…

 Our vision is to grow at a very fast pace , offer optimum

quality and best prices to our customers.

 To generate employment opportunities.

 To perform a viability assessment of the proposed new

business ideas in terms of marketability , technical

feasibility , financing and authorities.

 To be able to prepare a relevant business plan.


Land requirement…
A covered shed of 20,000 square feet along with another 20,000
square feet of land would be required enough for the successful
execution and installation of plant and machinery.
This will undertake the future expansion.

POWER & Manpower


requirement…
The Total Power of about 100 KBA and would be enough to run the
plant.
And as for manpower, approximately;
4 skilled persons will be required for operating boiler,
4 operators required for vessels,
4 operators for evaporators &
20 unskilled workmen.
FinanCe requirement…
A Total projected investment of about 3.5 Crore including land and
building, machinery and its installment, raw materials & operating
cost.
Bifurcation of the total finance required:
For Land Rs 1,00,00,000
For Machinery Rs 1,00,00,000
For Raw Materials Rs 1,00,00,000
For Operations Rs 50,00,000
TOTAL Rs 3,50,00,000

LOCATIONAL
adVantages…
Since, the acacia catechu wood is available in abundance in seven
north eastern states , this specie is grown in this territory from the last
two decades and is being unutilized , thus the locational advantage for
setting up the plant in Guwahati is feasible and a profitable decision.
MARKETING
adVantages…
Since, the group exposure & the exposure of one partner
MR AMRIT LAL HORA in the same industry is almost closed to 38
years.
Thus, there is no need of any marketing team to sell our product.
We plan to achieve 100% utilization and sell the same within 1st
quarter of its installation. And then in the coming quarters we plan to
double the capacity.

expeCted FinanCiaLs…
(Projections f.y 2018-19)
The land will be procured by 30th of September. Thereafter, the process
of ordering raw materials, machinery & its installation will take
another three months. Thus, the plant will commence its production by
1st day of January 2019.
Thus, we’ll get only one quarter in the financial year to showcase the
projections.
By 1st quarter we aim to achieve a sales quarter of about Rs
2,00,00,000.
In the next financial year i.e 2019-20 we project a sales turnover of
about Rs 18,00,00,000.
Coverage
under North
eastern
Industrial
Development
Policies…
Acacia Catechu wood been procured;

Wood Logs would be cut into smaller


pieces:
Smaller wood pieces cut in wood chips:

Boiling Wood chips in Boiler:


Extracted liquid will be evaporated:

Quality Inspection: