You are on page 1of 4

FORM

ACTION PLAN
PROYEK :.................................

KONTRAKTOR xxxxxxxxxxxxxxxxxx
PAKET / PEKERJAAN PENGECORAN
NOMOR xxxxxxxxxxxxxxxxxx
PERIODE s/d FEBRUARI 2018

FEBRUARI
MAN
NO URAIAN PEKERJAAN DURASI MATERIAL Minggu 1 Minggu 2 Ming
POWER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

PENGECORAN
lt Basement
Cor kolom Zona 15,16,17 4 6 Beton FC '35
Cor Retaining Wall As PA/P3-B4 5 6 Beton FC '35
Cor Corelift 3 6 Beton FC '35
Cor Retaining Wall As B6/BA-BC-AsBA/ 4 6 Beton FC '35
Cor Retaining Wall As B9/BA-BI 6 6 Beton FC '35
lt Dasar
Cor kolom zona 3 2 6 Beton FC '35
Cor Zona 4 lt Dasar 6 12 Beton FC '25
Cor Zona 5 lt Dasar 6 12 Beton FC '25
Cor kolom zona 4,dan 5 6 6 Beton FC '35

Lt 2
Cor Zona 1 6 12 Beton FC '25
Cor Corewall Tangga 3 10 Beton FC '35
Cor Kolom Zona 1 2 6 Beton FC '35
Cor Zona 2 6 12 Beton FC '25
Cor Zona 3 6 12 Beton FC '25

Diketahui Oleh Disetujui Oleh

Pemberi Tugas Managemen Konstruksi

PT............... xxxxxxxxxxxxxxxxxxxxxxxxx xxxxxxxxxxxxxxxx

xxxxxxxxxxxxxx

Project Manager Construction Manager Projet Manager


FORM No. Dok : xxxxxxxxxxxxxx
Revisi :
Tanggal : 19 Februari 2018
.... Halaman :

FEBRUARI
Minggu 3 Minggu 4

18 19 20 21 22 23 24 25 26 27 28 1 2 3
Diajukan Oleh

Kontraktor

xxxxxxxxxxxxxxxxxxxxxxxxx

xxxxxxxxxxxxxxxxxxxxxxxxx

Site Manager

You might also like