ACTION PLAN
PROYEK :.................................
KONTRAKTOR xxxxxxxxxxxxxxxxxx
PAKET / PEKERJAAN PENGECORAN
NOMOR xxxxxxxxxxxxxxxxxx
PERIODE s/d FEBRUARI 2018
FEBRUARI
MAN
NO URAIAN PEKERJAAN DURASI MATERIAL Minggu 1 Minggu 2 Ming
POWER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
PENGECORAN
lt Basement
Cor kolom Zona 15,16,17 4 6 Beton FC '35
Cor Retaining Wall As PA/P3-B4 5 6 Beton FC '35
Cor Corelift 3 6 Beton FC '35
Cor Retaining Wall As B6/BA-BC-AsBA/ 4 6 Beton FC '35
Cor Retaining Wall As B9/BA-BI 6 6 Beton FC '35
lt Dasar
Cor kolom zona 3 2 6 Beton FC '35
Cor Zona 4 lt Dasar 6 12 Beton FC '25
Cor Zona 5 lt Dasar 6 12 Beton FC '25
Cor kolom zona 4,dan 5 6 6 Beton FC '35
Lt 2
Cor Zona 1 6 12 Beton FC '25
Cor Corewall Tangga 3 10 Beton FC '35
Cor Kolom Zona 1 2 6 Beton FC '35
Cor Zona 2 6 12 Beton FC '25
Cor Zona 3 6 12 Beton FC '25
xxxxxxxxxxxxxx
FEBRUARI
Minggu 3 Minggu 4
18 19 20 21 22 23 24 25 26 27 28 1 2 3
Diajukan Oleh
Kontraktor
xxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxx
Site Manager