MS

Project : Tempo Hanoman I - NOV -17


MD : 2344
Subject : SCHEDULE CPC GROUND FLOOR III - JAN - 18
DESEMBER 2017 JANUARI 2018 FEBRUARI 2018
NO KETERANGAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
BASEMANT ELV - 4000
1 COR PILE CAP ( 20 NOS )
2 PEMADATAN DAN URUGAN PASIR
3 COR LANTAI KERJA
4 PASANG BESI LANTAI
5 CONCRETE SLAB FONDATION 1 2 3 4 5 6 7 8 9 10

CONCRETE WALL STAGE 01


1 PASANG BESI DINDING
2 PASANG BEKISTING
3 PENGECORAN DINDING TAHAP 1 1 2 3 4 5 6 7 8 9 10 11 12
4 BONGKAR BEKISTING

CONCRETE WALL STAGE 02


1 PASANG BESI DINDING
2 PASANG BEKISTING
3 PENGECORAN DINDING TAHAP 2
4 BONGKAR BEKISTING

URUGAN DAN PEMADATAN

GROUND FLOOR ELV : 0+-00


ZONE 01 ( AS A~U / 1~4 )
1 COR PILE CAP ( 72 NOS ) @ 10 NOS
2 URUGAN PEMADATAN DAN GALIAN
3 PASANG LOST FW DAN BESI
4 COR GROUD BEAM
ZONE 02 ( AS A~U / 4' ~7 )
1 COR PILE CAP ( 54-49 NOS ) @ 10 NOS
2 URUGAN PEMADATAN DAN GALIAN
3 PASANG LOST FW DAN BESI
4 COR GROUD BEAM
ZONE 03 ( AS A~U / 7~10 )
1 COR PILE CAP ( 44-6 NOS ) @7 NOS
2 URUGAN PEMADATAN DAN GALIAN
3 PASANG LOST FW DAN BESI
4 COR GROUD BEAM
ZONE 04 ( AS A~U / 10~13 )
1 COR PILE CAP ( 49-6 NOS ) @ 7 NOS
2 URUGAN PEMADATAN DAN GALIAN
3 PASANG LOST FW DAN BESI
4 COR GROUD BEAM

DI BUAT
TGL 22 NOVEMBER 2017

NGUSMAN