TIME FRAME

SG/GA AIR RECEIVER TANK + Foundation Tank

Project Name SG/GA AIR RECEIVER TANK + Foundation Tank


Customer PT. INDOKORSA Tbk.
No. Doc 017/CME/TF/07/2017
DRAWING NO 46-C-730

REMAKS
Aug-17 Sep-17
NO DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 5 6 7 8 9 10 11 12 13 14 15 16
NEW AIR RECEIVER TANK
1 APRROVAL DRAWING
2 Shop Drawing
3 INCOMING MATERIAL
4 INCOMING MATERIAL KHUSUS PLATE A516 Gr 70
5 FABRIKASI
CUTTING PLATE
ROLL PLATE
BODEM HEAD(RIGHT & LEFT)
MACHINING FLANGE
ASSEMBLING
WELDING FULL
FINISHING
6 NDT TEST
PENETRAN TEST 100%
PNEUMATIC TEST
HYDRO TEST
X-RAY 30%
7 INSPECTION
8 SANDBLASTING
9 PAINTING PRIMER
10 PAINTING SECOND COAT
11 PAINTING FINISH COAT
12 DELIVERY
SIPIL WORK NEW AIR RECEIVER TANK
1 PENGUKURAN ACTUAL PENEMPATAN TANKI
2 LEVELING
3 PENGALIAN TANAH
4 COMPACTED SOIL
5 RIVER STONES

FINISH
6 LEAN CONNCRETE
7 SLOP STEEL/PEMBESIAN
8 BEKISTING FLOOR
9 REDY MIX K-300 TAHAP 1
10 BAKISTING FOUNDATION TANK + Anchor
11 REDY MIX K-300 TAHAP 2
12 SALURAN AIR
13 PAINTING
14 FINISING
INSTALLASI NEW AIR RECEIVER TANK
1 INSTALLASI TANK FOR FOUNDATION
2 LEVELING
3 INSTALLASI PIPING
4 INSULLATION
5 CLEANING AREA