JADWAL PERALATAN

Preservasi Jalan dan Jembatan Ruas Tebelian - Sintang - SP. Nanga Silat - Sejiram Dan Jalan Dalam Kota Sintang
MASA PELAKSANAAN : 248 HARI KALENDER
MINGGU KE -
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
NILAI HARI KE -
DIV U R A I A N KET
PEKERJAAN (%) APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER DESEMBER
27/04/21 02/05/21 09/05/21 16/05/21 23/05/21 30/05/21 06/06/21 13/06/21 20/06/21 27/06/21 04/07/21 11/07/21 18/07/21 25/07/21 01/08/21 08/08/21 15/08/21 22/08/21 29/08/21 05/09/21 12/09/21 19/09/21 26/09/21 03/10/21 10/10/21 17/10/21 24/10/21 31/10/21 07/11/21 14/11/21 21/11/21 28/11/21 05/12/21 12/12/21 19/12/21 26/12/21
01/05/21 08/05/21 15/05/21 22/05/21 29/05/21 05/06/21 12/06/21 19/06/21 26/06/21 03/07/21 10/07/21 17/07/21 24/07/21 31/07/21 07/08/21 14/08/21 21/08/21 28/08/21 04/09/21 11/09/21 18/09/21 25/09/21 02/10/21 09/10/21 16/10/21 23/10/21 30/10/21 06/11/21 13/11/21 20/11/21 27/11/21 04/12/21 11/12/21 18/12/21 25/12/21 31/12/21

1 ASPHALT FINISHER 1 Unit 1

2 COMPRESSOR 4000-6500 L/M 1 Unit 1

3 CONCRETE MIXER 0.3-0.6 M3 15 Unit 2 4 3 3 3

4 DUMP TRUCK 3 - 4 M3 3 Unit 3

5 DUMP TRUCK 6-8 M3 1 Unit 1

6 EXCAVATOR 80-140 HP 1 Unit 1

7 GENERATOR SET 1 Unit 1

8 MOTOR GRADER >100 HP 1 Unit 1

9 WHEEL LOADER 1.0-1.6 M3 1 Unit 1

10 TANDEM ROLLER 6-8 T. 1 Unit 1

11 TIRE ROLLER 8-10 T. 1 Unit 1

12 VIBRATORY ROLLER 5-8 T. 1 Unit 1

13 CONCRETE VIBRATOR 6 Unit 3 3

14 WATER TANKER 3000-4500 L. 1 Unit 1

15 ASPHALT DISTRIBUTOR 1 Unit 1

PEKERJAAN RUTIN

1 TAMPER 2 Unit 2

2 ASPHALT CUTTER 1 Unit 1

3 JACK HAMMER 1 Unit 1

4 BABY ROLLER 1 Unit 1

5 FLAT BAD TRUK 3-4 TON 1 Unit 1

6 BOR PILE MACHINE 1 Unit 1