Professional Documents
Culture Documents
1MW Solar Power Plant-Thermal PDF
1MW Solar Power Plant-Thermal PDF
0% 50 % 100 %
• 1MW Solar Thermal Power Plant
- Design & Development of a 1 MW plant.
- Generation of Electricity for supply to the grid.
Project funded by Ministry of New and Renewable Energy, New Delhi @ Solar Energy Centre (SEC), Gwal Pahari, Haryana
2
Role of IIT Bombay
• Design of solar thermal power plant of 1MWe capacity
– Plant configuration designed by IITB
– Turbine selection, study of its characteristics by IITB
– Storage design and operating strategy conceived by IITB
– Heat exchanger design and operating strategy conceived by IITB
– Design of controls conceived, detailed and executed by IITB
• Engineering of solar thermal power plant
– By IITB with some support from TCE, L and T and other experts
• Procurement for solar thermal power plant
– As per IIT Bombay’s procedure through different vendors
• Design and installation of Testing Facility by IITB
• Development and testing of simulation package by IITB
• Organizational structure
– Consortium under the leadership of IIT Bombay
– Team of engineers and managers at IIT Bombay
– Team of professors from IITB across different departments
3
Consortium under the leadership of IIT Bombay
KGDS
4
Plant configuration design
• Use of widely used thermodynamic cycle
– 40 bar 350°C steam Rankine cycle
– 1 MW (Mega Watt range)
• Combination of low and high cost solar concentrators
– Site and technology specific
– Design DNI 600 W/sqm !! Near Delhi !!
– Minimum temperature requirement, characteristics of
concentrators available, sizing
– Technologies available locally: Advantage of low cost and
local technical support
– Technologies available globally: Advantage of experience
– Procured through open tender process under specifications
prepared by IIT Bombay 5
Super-
Preheater Steam Generator Heater
6
Schematic of process flow for the solar thermal
power plant
High temp short time storage and Hx designed by IIT with L and T
LFR field loop 2 MWth
Direct steam generation
Supplied by KGDS Renewables
9
Attainable Region for Hx at different operating levels
of PTC and LFR
1200
Oil Temperature (Inlet to Superheater ) = 390°C
1100
Turbine Inlet Pressure = 40 bar
1000
900
800
Power (kW)
700
600
500
Oil Flow Rate 2.7 kg/s
400 Oil Flow Rate 3.7 kg/s
Oil Flow Rate 4.7 kg/s
300
Oil Flow Rate 6.2 kg/s
200 Oil Flow Rate 7 kg/s
Oil Flow Rate8.1 kg/s
100 Oil Flow Rate 9.38 kg/s
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2
42
Turbine Deck Foundation
48
49
51
Arial view of
1 MW Solar Thermal Power plant
And Test Facility by IIT Bombay
at Solar Energy Centre (SEC), Gwal Pahari, Dist Gurgaon, Haryana
Solar Thermal Power Plant and Testing Facility Project funded by Ministry of New and Renewable Energy, GoI, New Delhi
52
PARABOLIC TROUGH SOLAR FIELD
53
Parabolic trough solar field
• Mirror
• Receiver Tubes
• Structure
• Tracking mechanism
• Heat Transfer Fluid
• Pressure Vessels
• Piping
54
Erection of Collector
63
Process Flow Diagram
Title
Description
68
Incorporating Storage Vessel
• 30 minutes storage at minimum turbine load
(320 kW) : Designed by IIT B
– Incorporating HT tank pump
• Nitrogen blanketing and pressurization:
– Equalization line between HT and LT vessel
– Novel control strategy to minimize consumption of
Nitrogen
69
Plant Commissioning
Cleaning the lines
Pressure testing
Chemical treatment
Filling Oil
72
Charging into storage tank
76
Expansion vessel piping from Storage vessel
77
Parabolic Trough Solar Field
79
80
LINEAR FRESNEL REFLECTOR
81
An artistic view of LFR system
82
LFR Solar field components by KGDS Renewables
Receiver
Stay wire
A – frame
Reflector
E
484mm
900 mm
93
Fire and raw water tank
94
Soft water and DM water tank
95
Fire water system
96
Demineralisation and water softener
97
Cooling water pumps
98
deaerator
99
Boiler Feed Pumps
100
Chemical Dosing
101
Heat Exchanger
102
Heat Exchanger
103
Steam turbine
104
Condenser
105
Steam Ejector
106
Steam Ejector Condenser
107
Alternator
108
Electrical Panels
109
HT and LT Panels
110
Weather Station
111
DIGNITARIES AT PROJECT SITE
112
Operational Problems
114
Leakages in the superheater – 10/03/2013
Steam Leakage
115
receiver glass window breakage the LFR system
Receiver Window
Glass Breakage
116
Equipment Problems
119
Communication problem between level I and level II
123
Steam System valves
• Problem in complete closing of the valve
• Manual closing of Valve – Not possible
• NRV leakages, allows return flow
• Leakages in control Valve in the Steam Line – problems in regulating the pressure
125
HTF Freezing
15
Ambient Temperature (oC)
14
13
12
11
10
9
12:00 AM
12:30 AM
1:00 AM
1:30 AM
2:00 AM
2:30 AM
3:00 AM
3:30 AM
4:00 AM
4:30 AM
5:00 AM
5:30 AM
6:00 AM
6:30 AM
7:00 AM
7:30 AM
8:00 AM
8:30 AM
Time (hr: min)
126
Pump Seal Failure: February, 2013
129
Mirror Broken by Neel Gai
133
Mirror Breakage in LFR
134
Commissioning and problems in chronological order
139
Site Issues
• Low radiation
• IBR
• Cleaning the steam line for turbine
• Dirt and dust at site:
– Land treatment needed, done
– Problems in mirror cleaning
• Theft and Robbery: Security problems
• No grid power at site for 8 months
– Use of DG sets
140
Comments and status: Performance
141
Solar Thermal Simulator
• Unique features:
o Simulation of user defined plant configurations
o Design point as well as off-design simulations
o Cost analysis
• Simulator predict:
o performance of each equipment of the plant
o annual power generation
o capital cost
o cost of energy
Solar Thermal Simulator
• How Simulator is useful
o preliminary sizing and cost estimation
o heat balance design
o parametric studies
o performance evaluation of a small subset of a
complete plant or a complete plant
o optimize the plant configuration through multiple
simulations
o devise the overall control strategy
• using different control options
o determine the start-up procedures
Features
• Graphical user interface
• Freedom to construct flow sheets using any of the equipment
o Flexibility to simulate user defined small subset of a complete
plant or a complete plant
166
THANK YOU
167