Professional Documents
Culture Documents
3
100-mm asphalt overlay on rubblized JRCP 200-mm asphalt overlay on rubblized JRCP
4
Table 1: Concrete Pavement Restoration Techniques
Concrete Pavement
Restoration Technique Used to:
Partial-Depth Repairs Repair joint and crack deterioration and surface distress
Joint and Crack Resealing Minimize infiltration of water and incompressible material into
joint system
Retrofitting Concrete Shoulder Decrease pavement edge stresses and corner deflections
Table 1 shows the CPR techniques. In addition, CPR does not limit future
Each technique is specifically pavement rehabilitations options.
designed to repair or prevent the Once a pavement has been
recurrence of a certain distress or a rubblized, it can only be overlaid.
combination of distresses. While After CPR, all overlay, CPR, and
each technique can be used recycling options are still available
individually, they are more effective when the pavement needs its next
when several are used together. In rehabilitation.
some cases more than one CPR
technique may be applicable.
However, one technique is usually
more suitable than the other because
of the condition of the pavement.
5
Finally, CPR does not have to be In order to ensure that bond
placed over the entire pavement develops, specific steps are taken to
width, as does an asphalt overlay. prepare the surface of the existing
This maintains the existing grade of pavement. This is done with either
the pavement and means features shotblasting and milling. With
such as curbs and gutters, bridge shotblasting, steel shot are hurled at
clearances, and roadside the pavement surface to remove
appurtenances do not need about 3 mm (0.125 in.) from the
adjustment. These advantages pavement surface. This creates a
makes CPR quicker and cause less rough and extremely porous surface
traffic disruption than rubblization and that increases the mechanical
an asphalt overlay. For more interlock and provides a strong bond.
information on CPR, see references Milling is primarily used where deeper
6-11. removal is desired. It typically
removes between 6 and 25 mm (0.25
and 1.0 in). Afterwards, a secondary
Concrete Overlay cleaning is required, which is typically
Alternatives - shotblasting.
Concrete overlays provide two
Surface preparation and cleanliness
important functions. First, they
is the key to long-term bond
improve the surface characteristic of
development and overlay
the pavement (rideability, safety, skid
performance. If the surface is
resistance, cross-section and surface
properly cleaned, and the existing
defects, etc.). Secondly, they
pavement is not too deteriorated,
increase the structural capacity of a
bonded concrete overlays can last for
pavement. There are two basic types
over 15 years without any, or very
concrete overlays for existing
little maintenance work. However,
concrete pavements: bonded
when they are placed on a pavement
concrete overlay and unbonded
in poor condition, they do not perform
concrete overlay. Each overlay 12
well. For more information on
technique has its own unique
Bonded Concrete overlays, see
characteristics.
reference 13.
Bonded Overlays
Bonded concrete overlays consists of
a thin concrete layer (usually 100 mm
or less) bonded to the top of an
existing concrete surface. They are
used on pavements that are in good
condition with little deterioration in
order to increase their structural
capacity. The bond causes the
overlay and existing pavement to act
as one thick slab. A good candidate
for a bonded overlay is a pavement
that has little deterioration, but is too Shotblasting the surface in preparation
thin due to increased truck volumes for a bonded concrete overlay.
(i.e., it is only 150 mm (6.0 in.) when
it should actually be 230 mm (9.0 in)).
6
Unbonded Overlays Another advantage of unbonded
overlays over rubblization and
Ultra-thin An unbonded concrete overlay
Unbonded Overlays – asphalt overlays is that they do not
An Untested Alternate.
consists of thicker concrete layer require that the existing slab be
(125 mm or greater) on top of an broken. Therefore, traffic can be
One of the problems
with traditional
existing concrete pavement. It uses maintained on adjacent lanes and
unbonded overlays is a thin asphalt separation (stress shoulders during construction. This
that they are usually relief) layer, placed between the new is a critical issue in constricted and
fairly thick (150 to 250 and existing concrete, to separate the
mm (6 to 10 in.), congested areas.
depending on traffic two layers so that they act
and sight conditions). independently of each other. The performance of an unbonded
A recent development, Because the two concrete layers are overlay has been very good. Studies
used on existing independent, unbonded overlays
asphalt pavements, is done by the National Cooperative
Ultra-Thin react structurally as if built on a Highway Research Program
Whitetopping (UTW). strong, non-erodable base course. (NCHRP) have shown that unbonded
For this reason, unbonded concrete overlays have performed well for over
One of the reasons overlays are a much better option for 12
that UTW’s work is
20 years. Where there has been
because of their short
deteriorated concrete pavements poor performance, it has usually
joint spacing. The than rubblization and an asphalt been caused by an inadequate
short joint spacing overlay. separation interlayer. The separation
allows the pavement to
act like a cast-in-place interlayer must isolate the overlay
block system. It has
One of the concerns with unbonded from distress and horizontal
been reasoned that a concrete overlays is that the movement in the existing pavement.
thin unbonded overlay, distresses from the lower concrete For more information on Unbonded
with short joint spacing, layer will reflect into the new overlay.
may behave in much Concrete overlays, see reference 14.
the same way and Fortunately, the separation interlayer
provide 8 to 15 years of acts as a cushioning layer that
service. prevents distresses from the WHEN TO RUBBLIZE AN
underlying concrete from reflecting
The Pennsylvania DOT
into the overlay. Additionally,
EXISTING CONCRETE
built a 3.5 inch ultra-
thin unbonded overlay because the pavement is on a strong, PAVEMENT
on a ramp in Hershey, non-erodable foundation, load
PA in 1995. Though it Rubblization should never be used on
induced distresses such as loss of
has not had long-term a pavement that is structurally sound.
monitoring, early support, pumping, faulting and corner
Destroying a structurally sound
investigations show breaks are minimized. Overall, the
pavement in order to minimize
that it is performing structural capacity of the overlay is
well and should be reflective cracking is poor practice
enhanced because of the existing
considered as an and a waste of resources. It is much
alternative for milling better to save and use the structure
and overlaying with Hot
Mix Asphalt. of the existing pavement.
.
.
Furthermore, rubblizing a structurally
. .
.
10
SUMMARY
Rubblization is used to stop reflective
cracking in asphalt overlays of
existing concrete overlays. Though it
is perceived as a rehabilitation
technique, it is actually a destructive
procedure that destroys the structure
of the existing concrete slab and
weakens the entire pavement
system. Its use has been necessary
because asphalt overlays are too
weak to withstand the movements of
the underlying concrete structure,
resulting in reflective cracking and
quick deterioration of the overlay.
11
13. Guidelines for Bonded Concrete
Overlays, TB007P, American
REFERENCES: Concrete Pavement Association,
1. Phone conversations with the South Skokie, IL, 1990.
Carolina DOT, SC I-85 near
Greenville SC. 14. Guidelines for Unbonded Concrete
Overlays, TB005P, American
2. Guide Specifications for Highway Concrete Pavement Association,
Construction, American Association of Skokie, IL, 1990.
State Highway and Transportation
Officials, Washington, DC, 1993 15. Thompson, M.R., et al. HMA Overlay
Construction with One Pass/lane-
3. Michigan PMS data Width with PCCP Rubblization,
Asphalt Paving Technology, Journal
4. Michigan Cost data of the Association of Asphalt Paving
Technologist, Vol. 66, 1997.
5. Rehabilitation of Jointed Portland
Cement Concrete Pavement on I-35 16. Presentation by Phillip Kirk, RMI
(Southbound) in Kay County, given a the Southeastern Pavement
Oklahoma, J.F. Daleiden, D.a. Ooten, Conference, Baton Rouge LA, .June
M.D. Sargernt, Transportation 23, 1998
Research Record 1513, .
17. “AASHTO Guide for Design of
6. The Concrete Pavement Restoration Pavement Structures,” American
Guide: Procedures for Preserving Association of State Highway and
Concrete Pavements, TB020P Transportation Officials, Washington
American Concrete Pavement D.C., 1993.
Association, Skokie, IL, 1997.
18. Structural Coefficients for Fractured
7. Diamond Grinding and CPR 2000, Slabs, Hall, K.T., Proyekta Ingenieria,
TB008P, American Concrete Ltda. paper prepared for the 1999
Pavement Association, Skokie, IL, TRB Annual Meeting.
1990.
12