You are on page 1of 12

Technical Information

Concrete Pavement Engineering and Research

Rubblizing of Concrete Pavements:


INCLUDES: A Discussion of its Use
Public agencies have been misusing rubblization and an asphalt
Discussion on the overlay of concrete slabs as a rehabilitation technique for the last 10
theory for rubblizing a to 15 years. It has been misused because most of the pavements
pavement’s structure that have been rubblized did not need rubblization. In most
situations, either concrete pavement restoration (CPR) or a concrete
overlay is a more appropriate and economical rehabilitation
Performance of procedure. These procedures directly address why a concrete
rubblized concrete pavement is deteriorating and minimize further deterioration.
and asphalt overlay
Rubblization is a destructive procedure that breaks an existing
concrete slab into small fragments. This destroys the structural
Alternatives to integrity of the pavement and reduces its load carrying capacity.
Rubblization Unlike CPR or concrete overlays, rubblization does not address the
cause of the existing pavement deterioration and sometimes it can
• CPR exacerbate the problem. For example, many concrete distresses are
• Bonded Overlays a result of poor support conditions. Rubblizing a pavement destroys
the concrete slab’s natural bridging action, causing the problems to
• Unbonded Overlays become more pronounced. This can and has caused early failure of
1
the asphalt overlay.
Recommendations on
when to rubblize a The only appropriate time to rubblize an existing concrete pavement
concrete pavement is when it has severe material durability problems, such as alkali-silica
reactivity (ASR), D-cracking, or freeze-thaw damage. These material
problems cause the concrete pavement to deteriorate and lose its
Improved Design structural integrity.
Procedures for
Asphalt Overlays of THE THEORY BEHIND RUBBLIZATION
Rubblized Concrete
Rubblization∗ breaks the existing concrete pavement into small
Pavement fragments that range from sand size pieces to pieces approximately
100 mm (4 in.) to 200 mm (8 in.) in width. It was developed as an
Proposed Design attempt to control the reflective cracking that occurs in an asphalt
Procedures for overlay of concrete. Reflective cracking is the cracking that occurs
above a concrete pavement’s joints. It happens because the asphalt
Concrete Overlays of overlay is too weak to withstand the daily and seasonal temperature
Rubblized Concrete movements of the underlying concrete.
Pavement
* Rubblization is just one type of fracturing procedure that destroys the concrete pavement.
Crack and Seat (C/S) and Break and Seat (B/S) are two other types. C/S is used on JPCP and
has a crack spacing from 300 to 1500 mm (12 to 60 in.). B/S is used on JRCP or CRCP and has
a crack spacing from 150 to 600 mm (6 to 24 in.).
© American Concrete Pavement Association 1998
completely destroys the concrete’s
When an asphalt overlay is placed on
slab action by breaking it down into
an unrubblized concrete pavement,
crushed-stone sized fragments. It is
the concrete remains the main
an attempt to turn the existing
structural component of the
pavement into base course.
pavement system. The asphalt layer
However, there is one notable
acts mainly as a riding surface.
shortcoming to this analogy: a
When the concrete slabs expand and
rubblized pavement has no gradation
contract because of temperature
or density control. Specifications for
changes, the joints open and close.
base courses require both gradation
However, the asphalt layer is too 2
and density control.
weak to withstand these movements.
This sets up shear stresses in the
In conclusion, rubblization (as well as
asphalt-riding layer and it cracks.
Crack & Seat and Break & Seat) and
an asphalt overlay does not address
To stop the reflective cracking, two
why an asphalt overlay cracks.
fracturing procedures (Crack & Seat
Instead, these procedures destroy
and Break & Seat) were developed to
the concrete slabs so that the asphalt
decrease the slab length. It was
does not crack. However, this also
believed that if the slabs were
destroys the main structural
shorter, the movements at the joints
component of the pavement system
and cracks would be reduced and
and reduces its load carrying
there would no reflective cracking.
capacity.
However, these initial fracturing
processes were not successful.
Even with the reduced movements of PERFORMANCE AND COST
the smaller slabs, cracks eventually
reflected through the asphalt overlay. The performance of rubblization and
asphalt overlay has varied from good
Rubblization is the reduction of the to very poor. The key to good
slab length to the extreme. It performance is properly assessing
the conditions under the concrete
slabs and the
uniformity of the
rubblized layer.
However, this is very
difficult, if not
impossible, to do. As
such, many asphalt
overlays are severely
under designed.

One example of this is


Interstate 85 (I-85)
near Greenville, South
1
Carolina. This
overlay was built in
1998 and designed as
a 200 mm (8 in.)
Rubblized concrete pavement.
Note the lack of uniformity in the rubblized material.
16 asphalt overlay on a
rubblized concrete
pavement. During
2
construction, normal traffic caused rehabilitation. For concrete
severe rutting problems in the asphalt pavements, the state requires that
overlay. Upon investigation, it was they be restored when the DI is
found that the underlying soils were greater than four. If that criterion
much weaker than determined before were used, then between 67-87% of
rubblization (before rubblization, the the rubblized projects would need
concrete was bridging over the weak rehabilitation. Finally, it is important
soil). to note that approximately 28% of all
the 5-year-old rubblized overlay
To strengthen the pavement, the projects have a DI greater than 15,
state needed to add 100-mm (4.0-in.) indicating substantial distress.
of asphalt to the 200-mm (8.0 in.)
design. This supplemental asphalt In addition to poor performance,
added approximately $2.5 million Michigan has seen that the costs of
dollars to a $15 million dollar rubblization and asphalt overlays can
1
contract. be higher than concrete overlays. An
example is a set of rehabilitation
4
The state of Michigan has also had projects constructed on I-96.
less than desired performance of
their rubblized and asphalt overlaid The first project, in Clinton County, is
pavements. The accompanying chart a 190-mm (7.5 in.) concrete overlay
is from the Michigan Pavement built in 1991. The second project, in
Management System. It shows the Ingham County, is a 152-mm (6 in.)
5-year distress index (DI) for 65.8 Km asphalt overlay on rubblized concrete
(40.9 miles) of rubblized and asphalt done in 1992. The cost of the
overlaid pavements. Note: a higher concrete overlay was $1,034,000 per
3
DI means poorer performance. mile. The cost for the rubblization
and asphalt overlay was $1,437,500
The state requires that asphalt per mile. This is 39% difference in
pavements with DI greater than eight the initial costs of the projects.
be rehabilitated. Using this criteria,
between 47-67% of the 5-year-old Even with the most controlled
asphalt overlays on rubblized experiments, rubblized concrete and
concrete pavements need asphalt overlays have had poor
performance. The photos on
the next page are from a
30 rubblization project in the
25 Strategic Highway Research
Program (SHRP) constructed
20
in 1992.
15
10
The project is in the
southbound lanes of I-35 in
5 Kay County, OK. The first
0 photo shows a 100-mm (4-in.)
asphalt overlay on a rubblized
228-mm (9-in.) jointed
Distress Index
reinforced concrete pavement.
The second photo shows an 8-
Distress index distribution for rubblized concrete inch asphalt overlay on the
pavements and asphalt overlays in Michigan same pavement.

3
100-mm asphalt overlay on rubblized JRCP 200-mm asphalt overlay on rubblized JRCP

5 Therefore, they are much more


A 1994 report stated that both these
appropriate and viable solutions.
projects were controlling the
reflective cracking. However, since
that time, both have developed a Concrete Pavement
considerable amount of longitudinal
Restoration
and fatigue cracking in the
wheelpaths. Though the 200-mm (8- CPR is a series of engineered
in.) overlay is outperforming the 100- techniques that repairs isolated areas
mm (4-in.) overlay, it still has a of deterioration in a concrete
considerable amount of distress pavement. Appropriate and timely
considering it has only been in CPR maintains the pavement in a
service for 6 years. smooth, safe, and quiet condition and
extends its service life on average by
Overall, the performance and cost 9-10 years. This is about the same
data shows that an asphalt overlay of life expected of an asphalt overlay of
a rubblized concrete pavement is a a rubblized concrete pavement.
short-term solution that lasts between Some CPR projects have performed
6
8 and 12 years. Because of its short for more than 17 years.
life, a rubblized concrete pavement
with an asphalt overlay requires more
repairs and is more costly when CPR
compared to other concrete
Pavement Condition

pavement rehabilitation options. Bonded Concrete Overlay


Unbonded Concrete Overlay
ALTERNATIVES TO Reconstruction
RUBBLIZING AND ASPHALT
OVERLAY
Concrete pavement restoration Min. Acceptable Rating
(CPR) and concrete overlays are
procedures that keep and use the
intact structural integrity of an Age or Traffic
existing concrete slab. Unlike
rubblization, CPR and concrete Life Cycle diagram showing appropriate pavement
overlays directly address the cause of rehabilitation strategies and where they relate to
the problems in the pavement. pavement condition

4
Table 1: Concrete Pavement Restoration Techniques

Concrete Pavement
Restoration Technique Used to:

Full-Depth Repairs Repair cracked slabs and joint deterioration

Partial-Depth Repairs Repair joint and crack deterioration and surface distress

Diamond Grinding Extend serviceability; improve ride and skid resistance;


reduce noise

Dowel-Bar Retrofit Restore load transfer at joints and cracks

Joint and Crack Resealing Minimize infiltration of water and incompressible material into
joint system

Slab Stabilization Fill small voids underneath the concrete slab

Cross-Stitching Repair low and medium severity longitudinal cracks

Grooving Reduce wet weather accidents and prevent hydroplaning

Retrofitting Edge Drains Add a longitudinal drainage system

Retrofitting Concrete Shoulder Decrease pavement edge stresses and corner deflections

Table 1 shows the CPR techniques. In addition, CPR does not limit future
Each technique is specifically pavement rehabilitations options.
designed to repair or prevent the Once a pavement has been
recurrence of a certain distress or a rubblized, it can only be overlaid.
combination of distresses. While After CPR, all overlay, CPR, and
each technique can be used recycling options are still available
individually, they are more effective when the pavement needs its next
when several are used together. In rehabilitation.
some cases more than one CPR
technique may be applicable.
However, one technique is usually
more suitable than the other because
of the condition of the pavement.

CPR has several advantages over


rubblizing. First, it repairs the
isolated areas of distress that need
repaired without destroying the
structural integrity of the slab. This
fundamental difference makes CPR Diamond Grinding of an old concrete
more effective and less costly than pavement to restore smoothness
rubblization and asphalt overlays.

5
Finally, CPR does not have to be In order to ensure that bond
placed over the entire pavement develops, specific steps are taken to
width, as does an asphalt overlay. prepare the surface of the existing
This maintains the existing grade of pavement. This is done with either
the pavement and means features shotblasting and milling. With
such as curbs and gutters, bridge shotblasting, steel shot are hurled at
clearances, and roadside the pavement surface to remove
appurtenances do not need about 3 mm (0.125 in.) from the
adjustment. These advantages pavement surface. This creates a
makes CPR quicker and cause less rough and extremely porous surface
traffic disruption than rubblization and that increases the mechanical
an asphalt overlay. For more interlock and provides a strong bond.
information on CPR, see references Milling is primarily used where deeper
6-11. removal is desired. It typically
removes between 6 and 25 mm (0.25
and 1.0 in). Afterwards, a secondary
Concrete Overlay cleaning is required, which is typically
Alternatives - shotblasting.
Concrete overlays provide two
Surface preparation and cleanliness
important functions. First, they
is the key to long-term bond
improve the surface characteristic of
development and overlay
the pavement (rideability, safety, skid
performance. If the surface is
resistance, cross-section and surface
properly cleaned, and the existing
defects, etc.). Secondly, they
pavement is not too deteriorated,
increase the structural capacity of a
bonded concrete overlays can last for
pavement. There are two basic types
over 15 years without any, or very
concrete overlays for existing
little maintenance work. However,
concrete pavements: bonded
when they are placed on a pavement
concrete overlay and unbonded
in poor condition, they do not perform
concrete overlay. Each overlay 12
well. For more information on
technique has its own unique
Bonded Concrete overlays, see
characteristics.
reference 13.

Bonded Overlays
Bonded concrete overlays consists of
a thin concrete layer (usually 100 mm
or less) bonded to the top of an
existing concrete surface. They are
used on pavements that are in good
condition with little deterioration in
order to increase their structural
capacity. The bond causes the
overlay and existing pavement to act
as one thick slab. A good candidate
for a bonded overlay is a pavement
that has little deterioration, but is too Shotblasting the surface in preparation
thin due to increased truck volumes for a bonded concrete overlay.
(i.e., it is only 150 mm (6.0 in.) when
it should actually be 230 mm (9.0 in)).

6
Unbonded Overlays Another advantage of unbonded
overlays over rubblization and
Ultra-thin An unbonded concrete overlay
Unbonded Overlays – asphalt overlays is that they do not
An Untested Alternate.
consists of thicker concrete layer require that the existing slab be
(125 mm or greater) on top of an broken. Therefore, traffic can be
One of the problems
with traditional
existing concrete pavement. It uses maintained on adjacent lanes and
unbonded overlays is a thin asphalt separation (stress shoulders during construction. This
that they are usually relief) layer, placed between the new is a critical issue in constricted and
fairly thick (150 to 250 and existing concrete, to separate the
mm (6 to 10 in.), congested areas.
depending on traffic two layers so that they act
and sight conditions). independently of each other. The performance of an unbonded
A recent development, Because the two concrete layers are overlay has been very good. Studies
used on existing independent, unbonded overlays
asphalt pavements, is done by the National Cooperative
Ultra-Thin react structurally as if built on a Highway Research Program
Whitetopping (UTW). strong, non-erodable base course. (NCHRP) have shown that unbonded
For this reason, unbonded concrete overlays have performed well for over
One of the reasons overlays are a much better option for 12
that UTW’s work is
20 years. Where there has been
because of their short
deteriorated concrete pavements poor performance, it has usually
joint spacing. The than rubblization and an asphalt been caused by an inadequate
short joint spacing overlay. separation interlayer. The separation
allows the pavement to
act like a cast-in-place interlayer must isolate the overlay
block system. It has
One of the concerns with unbonded from distress and horizontal
been reasoned that a concrete overlays is that the movement in the existing pavement.
thin unbonded overlay, distresses from the lower concrete For more information on Unbonded
with short joint spacing, layer will reflect into the new overlay.
may behave in much Concrete overlays, see reference 14.
the same way and Fortunately, the separation interlayer
provide 8 to 15 years of acts as a cushioning layer that
service. prevents distresses from the WHEN TO RUBBLIZE AN
underlying concrete from reflecting
The Pennsylvania DOT
into the overlay. Additionally,
EXISTING CONCRETE
built a 3.5 inch ultra-
thin unbonded overlay because the pavement is on a strong, PAVEMENT
on a ramp in Hershey, non-erodable foundation, load
PA in 1995. Though it Rubblization should never be used on
induced distresses such as loss of
has not had long-term a pavement that is structurally sound.
monitoring, early support, pumping, faulting and corner
Destroying a structurally sound
investigations show breaks are minimized. Overall, the
pavement in order to minimize
that it is performing structural capacity of the overlay is
well and should be reflective cracking is poor practice
enhanced because of the existing
considered as an and a waste of resources. It is much
alternative for milling better to save and use the structure
and overlaying with Hot
Mix Asphalt. of the existing pavement.
.

.
Furthermore, rubblizing a structurally
. .
.

sound pavement eliminates all other


.. .
. . .
..
.
.
.
. current and future pavement
rehabilitation options. Once a
pavement is rubblized, the only thing
Schematic of an unbonded overlay. that an agency can do with it is
Note how the Asphalt layer separates overlay it. Later, this could cause
the two concrete layers so that they act problems with elevated crowns and
independently. raised grades for future
rehabilitations. Keeping the
intact pavement.
7
pavement intact keeps all options sand size particles to fragments that The importance of
subgrade support.
open for future rehabilitations. are approximately 150 to 200 mm (6
to 8 in.) in width, with no gradation or Eventually, the
Rubblization is an appropriate density control. subgrade carries the
load of any pavement.
solution when the existing concrete Therefore, it is very
slab exhibits material problems such The resonant breaker has a 150-mm important that it be
as alkali-silica reactivity (ASR), D- (6-in.) wide head that vibrates at a characterized correctly.
cracking, or freeze-thaw damage. low amplitude and high frequency.
The main deficiency
These material problems cause the As it vibrates, it impacts and shatters with rubblization is that
concrete pavement to deteriorate and the slab. However, this small head it is difficult to predict
lose its structural integrity. can only break a small, longitudinal the subgrade
strip at a time. Thus, it requires conditions until after
rubblization.
ASR reduces the durability of about 50 passes to completely break
concrete by creating a gel that may a 7.3 m (24 foot) wide pavement. Testing on top of the
absorb water, expand, and crack the intact concrete does
concrete. Once cracked, the The multihead breaker (MHB) not guarantee correct
concrete loses it strength and pulverizes an entire lane in a single characterization of the
subgrade. In many
deteriorates. D-cracking occurs pass. However, it uses high cases, the concrete’s
when certain aggregates in a amplitude drop hammers that impact natural bridging action
concrete mixture become saturated, the concrete and crushes or breaks it will cover up a weak
subgrade and masks
freeze, and expand. This expansion in flexure. As such, it is not its true strength.
causes the surrounding concrete to rubblization, it is pulverization.
crack. A good rule for judging
Besides not providing a uniform how a rubblized
Freeze-thaw damage occurs in base, both pieces of equipment can pavement will perform
is to look at the
concrete that has a poor entrained-air damage and introduce variability into performance of the
system. Entrained air is a system of the subgrade support. With the existing concrete. If
microscopic air bubbles in the resonant breaker, the subgrade can the existing concrete is
concrete that protects it as it freezes. be damaged because two of its deteriorating due to
poor support, then
If the volume and spacing of the air wheels, which are around 20,000 lbs. rubblization will also
bubbles is not adequate, the concrete each, must ride on the broken have problems due to
cracks when it freezes. All three of concrete, which can push the broken poor support.
these material problems typically concrete into the underlying subbase
15
takes several years to occur and the or subgrade. The MHB damages
degree of deterioration depends upon the subgrade when its forceful
the amount of poor materials in the crushing procedure impacts the
concrete. concrete and pushes it into the
16
subbase or subgrade.
The Rubblization Once the subgrade and subbase is
Procedure damaged, it no longer provides
uniform support. This must be taken
There are two pieces of machinery
into account in the design procedure
used to rubblize concrete pavement:
or it must be removed and repaired
the resonant breaker and the
during the construction procedure.
multihead breaker (MHB). Though
both machines break the slab into
smaller pieces, neither one breaks
the concrete into the uniform high
quality base course that they claim.
Instead, rubblization produces a
broken concrete that ranges from
8
DESIGNING AN OVERLAY done until construction, this is a
difficult procedure.
ON A RUBBLIZED
CONCRETE PAVEMENT Complicating the problem is the fact
that the rubblized material is not
Once it has been determined that a uniform and difficult to characterize.
pavement has a materials problem The AASHTO Guide for Design of
and is good candidate for Pavement Structures states that
rubblization, the pavement engineers there is “a wide range of
must properly select the overlay backcalculated modulus values
thickness. Though most overlays among different projects, from
have been asphalt, it is possible to 100,000 psi (690 MPa) to several
place a concrete overlay on the hundred thousand psi, and within
rubblized concrete pavement. In project coefficient of variation of as
17
either case, the most important much as 40 percent.”
aspect of the design procedure is the
characterization of the rubblized In a recent research project,
concrete layer. Structural Coefficients for Fractured
Concrete Slabs,18 an attempt to
develop realistic values was
Asphalt Overlay undertaken. In this research, the
Structural coefficients
describe the strength The most recognized design structural coefficients were
of the layer. The procedure for asphalt overlays of developed by relating the overlay
higher the value, the rubblized concrete is the AASHTO thicknesses from both the rigid and
stronger the layer. Overlay Design of Fractured slabs.
17
flexible asphalt overlay models used
This procedure uses the concept of in the AASHTO Guide.
AASHTO recommends
the following structural structural numbers (SN) and layer
coefficient values for coefficients (a) to determine the The AASHTO Guide uses two
the design of an thickness of the overlay. The basic models to design asphalt overlays of
asphalt overlay on concrete. One is used for asphalt
rubblized slabs: equation to determine the asphalt
overlay thickness is: overlays of intact concrete and is
New Asphalt Concrete based on rigid pavement modeling.
0.20 – 0.44 tasph = SNreq-(arub conc*trub conc+abase*tbase) The second is based on flexible
aasphalt pavement modeling and is used for
Rubblized Slab
0.14 - 0.30 asphalt overlays of asphalt
Where pavements and fractured slabs.
Base Course SNreq = required structural
0.0 - 0.14 For a given traffic volume, these two
number to carry the future
These values are
traffic models should give the same
reasonable, except for structural capacity. Using this
the rubblized slab. An ai = structural coefficient of the
stabilized material has asphalt, rubblized concrete, or premise, the research related the
a structural coefficient
base course overlay thicknesses from both the
value of 0.20. The rigid and flexible asphalt overlay
upper values for ti = thickness of the asphalt,
rubblized slabs are rubblized concrete, or base models and developed the structural
higher than for the course coefficients so that the structural
stabilized materials. capacity from the two methods were
This indicates that the as close as possible to each other.
broken slabs are The key to the AASHTO design
stronger than an intact procedure is correctly quantifying the
stabilized material. contribution of the rubblized layer. Rubblized slab thicknesses from 180
However, because rubblization is not to 280 mm (7 to 11 in.) were
investigated. It found that no single
value for the structural coefficient of a
9
rubblized slab yielded equivalent pumping are lost when the existing
ACPA recommended
overlay designs for the full range of structure is rubblized. layer coefficients values:
the existing slab thicknesses. The
structural coefficient value varied Concrete Overlay Rubblized Slab
based on the expected traffic values. 0.14 - 0.25
Though there is no established
procedure to design a concrete Value depends on the
Overall, the structural coefficient overlay of rubblized pavement, it is future thickness or traffic
range was between 0.149 to 0.245, possible to use concepts from the requirements.
with an average value of 0.197. The AASHTO new concrete pavement
values at the low end of this range and overlay design procedures to Lower values are
are appropriate for larger future appropriate for high
determine an overlay thickness. traffic volumes, where
thickness requirements (high traffic thicknesses will be
volumes), while values at the high The proposed procedure consists of greater.
end are more appropriate for smaller designing the overlay as a new
future thickness requirements (low Higher values are
concrete pavement on an improved appropriate for low traffic
traffic volumes). granular base with a higher k-value. volumes, where
This is the procedure used with thicknesses will be
Based on the results of this analysis, concrete pavements on bases thinner.
ACPA recommends that a range of courses and concrete overlays of
0.14 to 0.25, with a midrange of 0.20 Degradation or intrusion
asphalt pavements (whitetopping). It of fines into base course
be used in the current AASHTO also characterizes the rubblized should also be taken into
design procedure for asphalt overlays pavement in the same manner as an account. If there is
of rubblized pavements. For high asphalt overlay of a rubblized degradation or intrusion
volumes of traffic, the lower structural of fines, then the lower
pavement. values are appropriate.
coefficient values should be used and
for low volumes of traffic, the higher Similar to the asphalt overlay, the key
values should be used. in the design procedure is to
characterize the rubblized slab with
Rubblizing and Concrete an appropriate k-value. The following
procedure is recommended:
Overlay
Though not used as often, it is 1. Determine the rubblized slab
possible to place a concrete overlay modulus value (use the same
on a rubblized concrete pavement. procedure as used in the overlay
This technique has been extremely design procedure for an asphalt
successful in both Pennsylvania and overlay of a rubblized pavement). Because of the wide
variation of the modulus
Iowa. Furthermore, because value, and because an
concrete overlays last 25 years or 2. Convert the rubblized slab exact value for a given
more while asphalt overlays typically modulus value to k-value using project is impossible to
last only 10 to 15 years, the concrete the procedures outlined in determine until
AASHTO Overlay Procedure for construction, it is
option is a better long-term solution. recommended to use low
Concrete Overlays of Asphalt values (i.e. 100,000 psi)
Still, particular care should be used in Pavements (whitetopping). until actual field and
the decision to rubblize the existing performance data
concrete pavement because it will 3. Design the overlay as a new provide better
pavement using the improved k- information.
reduce the structural capacity and
likely warrant a thicker concrete value determined in Step 2.
overlay. The benefits of improved
load transfer from sleeper-slab
action, and decreased potential for

10
SUMMARY
Rubblization is used to stop reflective
cracking in asphalt overlays of
existing concrete overlays. Though it
is perceived as a rehabilitation
technique, it is actually a destructive
procedure that destroys the structure
of the existing concrete slab and
weakens the entire pavement
system. Its use has been necessary
because asphalt overlays are too
weak to withstand the movements of
the underlying concrete structure,
resulting in reflective cracking and
quick deterioration of the overlay.

Better alternatives to rubblization and


asphalt overlays are concrete
pavement restoration (CPR) and
concrete overlays. These
procedures directly address the
cause of the pavement distress and
keep the structural integrity of the
pavement system intact.

Still, there are times when


rubblization is an option for an
existing concrete pavement. This
occurs when the concrete slabs
exhibit material problems such as
alkali silica reactivity (ASR), D-
cracking, or freeze-thaw damage.
These materials problems cause the
concrete pavement to deteriorate and
lose its structural integrity.

Once a pavement is rubblized, it is


viable to place either a concrete or an
asphalt overlay. The advantage of
the concrete overlay is that it is a
long-term solution that will not need
to be rehabilitated again for many,
many years.

11
13. Guidelines for Bonded Concrete
Overlays, TB007P, American
REFERENCES: Concrete Pavement Association,
1. Phone conversations with the South Skokie, IL, 1990.
Carolina DOT, SC I-85 near
Greenville SC. 14. Guidelines for Unbonded Concrete
Overlays, TB005P, American
2. Guide Specifications for Highway Concrete Pavement Association,
Construction, American Association of Skokie, IL, 1990.
State Highway and Transportation
Officials, Washington, DC, 1993 15. Thompson, M.R., et al. HMA Overlay
Construction with One Pass/lane-
3. Michigan PMS data Width with PCCP Rubblization,
Asphalt Paving Technology, Journal
4. Michigan Cost data of the Association of Asphalt Paving
Technologist, Vol. 66, 1997.
5. Rehabilitation of Jointed Portland
Cement Concrete Pavement on I-35 16. Presentation by Phillip Kirk, RMI
(Southbound) in Kay County, given a the Southeastern Pavement
Oklahoma, J.F. Daleiden, D.a. Ooten, Conference, Baton Rouge LA, .June
M.D. Sargernt, Transportation 23, 1998
Research Record 1513, .
17. “AASHTO Guide for Design of
6. The Concrete Pavement Restoration Pavement Structures,” American
Guide: Procedures for Preserving Association of State Highway and
Concrete Pavements, TB020P Transportation Officials, Washington
American Concrete Pavement D.C., 1993.
Association, Skokie, IL, 1997.
18. Structural Coefficients for Fractured
7. Diamond Grinding and CPR 2000, Slabs, Hall, K.T., Proyekta Ingenieria,
TB008P, American Concrete Ltda. paper prepared for the 1999
Pavement Association, Skokie, IL, TRB Annual Meeting.
1990.

8. Guidelines for Full-Depth Repair,


TB002P, American Concrete
Pavement Association, Skokie, IL,
1995.

9. Guidelines for Partial-Depth Repair,


TB003P, American Concrete
Pavement Association, Skokie, IL,
1989.

10. Joint and Crack Sealing and Repair


for Concrete Pavements, TB012P,
American Concrete Pavement
Association, Skokie, IL, 1993.

11. Slab Stabilization Guidelines for


Concrete Pavements, TB018P
American Concrete Pavement
Association, Skokie, IL, 1994.

12. NCHRP 204, Performance of


Concrete Overlays

12

You might also like