You are on page 1of 6

The Role of Mass Concrete in Soft Rock Block Cave Mines

R J Butcher1

ABSTRACT undercutting (advanced undercutting) can reduce this


problem. Lacasse et al (1981) and Gallagher and Loftus,
Concrete has been used for many years in block caving, principally for
drift and drawpoint linings. This paper describes the requirements for (1960) indicate that concrete lining damage due to undercut
concrete in this application, the required properties, the mix design, and stresses becomes unacceptable when operational depths
transportation and placement systems. In addition a concrete mix design exceed ±450 m (when post undercutting is used). Under such
rationale is also proposed. conditions in excess of 50 per cent of the concrete will
require replacing.
INTRODUCTION • the time and hazards associated with the removal of damaged
concrete linings;
Concrete has been used in block caving for many years, mainly
as linings for slusher drifts and drawpoint mouth support in • the high-cost of lining installation;
trackless caving operations. This paper describes the application • high capital and labour costs associated with batching plant
of concrete in slusher, panel and inclined drawpoint caves. installation and operation;
Technical aspects such as strength, workability, transport and
placement of underground concrete are also discussed. • quality control difficulties and problems in achieving
concrete linings of the required strength, thickness and
homogeneity; and
APPLICATION OF CONCRETE IN
BLOCK CAVING • material supply problems, which mainly affects mines in
remote areas where mix designs necessitate the use of
Gallagher and Loftus (1960) showed that concrete has been used specific cement and aggregate types. An example of this, is
in block caving for over 40 years. However, in recent years, with the difficulty in the supply of river sand for drawpoint
the increased application of panel caves, deeper operational concrete in parts of the Free State Province of South Africa.
depths and larger tunnel sizes, concrete usage has decreased
(possibly because of the costs associated with concrete lining of BLOCK CAVE CONCRETE APPLICATIONS
large tunnels and longer lining commissioning times). In this
regard it is important to understand the advantages and A description is given of the main applications of concrete in
disadvantages of mass concrete in block caving. In block caving, block caving in the following sections.
concrete has the following advantages:
• Concrete can be cast into most shapes provided that suitable Slusher block cave drift linings
moulds (shutters) can be constructed. In practice this means Figure 1 shows a typical concrete lining in a slusher drift block
that different drift profiles can be cast. cave. Mass concrete is used in slusher drifts to provide cave
• Concrete has a high impact and abrasion resistance. This foundation support, which has a high blast, abrasion, and
means that the structural stability of linings is only affected weathering resistance. Table 1 shows the typical characteristics
to a limited extent by ore flowing through drawpoints, by of mass concrete slusher drift linings (Lacasse et al, 1981;
scrapers operating in drifts and by LHD body and bucket Gallagher and Loftus, 1960).
impacts. Taking cognisance of standard concrete mix design methods
• Concrete is relatively resistant to the effects of blasting (Fulton, 1994) and the author’s experience, the following
emissions and peak air over pressures. This means that the concrete mix specifications can be determined. These
material can be used in drawpoint mouths where secondary specifications are a general guide to the quantities used per cubic
blasting is carried out. metre of concrete.
• Concrete is waterproof and weather resistant, meaning that
Aspect Quantity Remarks
drifts and drawpoint linings remain intact even after the host
rock comprising the draw horizon has been eroded or Cement 480 - 650 kg Up to 75 per cent fly ash OPC
weathered away. This is a common situation in diamond replacement used.
mines, where kimberlites weather rapidly due to water Sand 715 - 800 kg River sand preferred, crusher dust used.
inflows from the muckpile. Stone 1000 - 1200 kg 19 mm diameter stone normally used.
• Concrete structures are capable of supporting fractured Water 150 - 2001 Plasticisers/super-plasticiser used.
drawpoint brows and cave foundations (draw horizons). Accelerators and retarders rarely used.
The main disadvantages with the use of concrete and possible Fibre 60 kg Rarely added due to cost.
reasons for the decline in the quantities poured underground are:
• Concrete is stiff and inflexible and cannot sustain the
deformations that accompany undercutting. This results in Concrete is usually batched and mixed near drifts in a typical
failure of tunnel linings and the need for drift repairs. slusher mine. In the case of shallower operations a surface
Installing linings after undercutting (pre-undercut) or batching and mixing plant is used. The concrete is then gravity
reducing the percentage of draw horizon development before fed to a re-mixing station before pumping to the drift shutters.
Drift concrete is placed into steel shutters at the construction site.
Trepannier and Underwood (1981) indicate that at King Beaver
1. Senior Mining Engineer, SRK Consulting, 265 Oxford Road, Illovo, mine no vibrators were used to aid compaction. It would appear
Johannesburg, South Africa. that no curing aids were used after pouring. Ready-mixed

MassMin 2000 Brisbane, Qld, 29 October - 2 November 2000 423


R J BUTCHER

FIG 1 - Typical slusher concreted drift arrangement.

TABLE 1
Slusher drift block cave concrete characteristics.

Lining thickness Uniaxial compressive Water/cement ratio Slump Mining depth


strength @ 28 days
180 - 1000 mm 30 - 50 MPa 0.31:0.65 100 - 230 mm 400 - 1000 m

TABLE 2
Panel cave drawpoint mass concrete characteristics.

Lining thickness Uniaxial compressive Water/cement ratio Slump Mining depth


strength @ 28 days
±450 mm ±24 MPa ±0.44 ±100 mm 300 - 1200 m

concrete is used for drift construction, the ready mix being Using the standard Henderson mix design (Watson and
transported underground to a re-mix plant before it is pumped to Keskumaki, 1992), the following concrete mix specifications are
the drifts. Pumping equipment consists of Schwing pumps, with given below.
pumping distances being between 75 and 400 m. Concrete is
transported via 150 mm diameter steel pipes. Experience from Aspect Quantity Remarks
both King Beaver and Kimberley indicates that pump Cement 318 kg Up to 60 per cent fly ash/OPC replacement.
performance decreases significantly with an increase in line
Sand 603 kg Crusher dust or river sand used.
bends.
Stone 767 kg 19 mm diameter stone normally used
Trackless drawpoint mouths Water 140 l

Figure 2 shows a typical trackless drawpoint concrete lining.


Mass concrete is used in drawpoint mouths to provide support to
fractured or weathered drawpoint brows, protect support Concrete batching and mixing is conducted at the drawpoint
measures from secondary blasting, LHD damage and also to construction site. However current concrete technology does
withstand abrasion from the rilling ore. Table 2 shows the typical preclude the use of concrete mix at a central batching plant and
characteristics of a trackless drawpoint mouth mass concrete. delivered to site in agitator trucks. Materials are bulk delivered

424 Brisbane, Qld, 29 October - 2 November 2000 MassMin 2000


THE ROLE OF MASS CONCRETE IN SOFT ROCK BLOCK CAVE MINES

FIG 2 - Typical panel cave concrete drawpoint mouth lining.

FIG 3 - Incline drawpoint cave. Drawpoint mouth (modified after Gaths Mine visitors handbook).

MassMin 2000 Brisbane, Qld, 29 October - 2 November 2000 425


R J BUTCHER

and mixed at site by small mobile plant. The concrete is placed respect it is important to recognise the different roles and
in the shutters by means of a concrete placer. No curing aids are applications of mass concrete in a civil engineering environment
used (Watson and Keskimaki, 1992). and in a block caving application. These differences are given
below:
Trackless drawpoints - inclined drawpoint/front cave • From the author’s experience, quality control in all
drawpoints underground concrete practices tends to be lower in block
Figure 3 shows a typical drawpoint arrangement. Published caving, resulting in the need for simpler mix designs.
literature on concrete specifications is limited (Gaths Mine • Concrete in block caving is subject to variable loading
visitors handbook). The role of concrete in this type of drawpoint conditions - high compressive stresses during undercutting to
is similar to the panel cave situation however due to the fact that tensile stresses during the production phase of the cave. In
drawpoints will be subjected to cave abutment stresses longer civil engineering, concrete structures are normally subjected
(drawpoints are not de-stressed by undercutting, Jakubec, 1992) to more or less static loading conditions.
concrete compressive strengths would have to be higher. Figure 3
shows the reinforcing used in the lining. In this respect it can be • The loads imposed on block cave linings are generally higher
expected that a concrete mix should have higher workability than than in civil engineering. This results in a higher demand, not
that used for panel cave drawpoints (slumps). This is due to the only for uniaxial compressive strengths, but also for tensile
fact that a limited clearance, exists between the drawpoint shutter and shear strengths.
and the heavy drift support measures. This makes the use of • Owing to the undercut abutment stresses, secondary blasting
vibrators difficult. Higher slumps are necessary to prevent the and muckpile point load damage, concrete replacement and
formation of voids in the concrete. Table 3 gives the drawpoint rehabilitation is more frequent in block caving operations,
concrete characteristics. whereas, in civil engineering, lining replacement is not
Using the information given in Table 3 the following concrete generally undertaken.
mix specifications are to be determined using standard concrete • The limited clearance (±350 mm) between the shutter and the
mix design principals (Fulton, 1994). supported rockwall in trackless blockcaves may make the use
of poker vibrators difficult. This results in a need for a
Aspect Quantity Remarks concrete with a higher workability (sloppy concrete). In
Cement 451 kg OPC cases where a damaged slusher drift concrete lining has to be
Sand 624 kg Crusher dust totally removed during drift repair (resulting in the fact that
concrete installation is conducted under a highly fractured
Stone 1240 kg 19 mm diameter stone
back where concrete vibration cannot be conducted safely)
Water 220 l higher concrete workability is also required. In civil
engineering it common practice for vibrators to be used to
aid concrete mobility.
The comments regarding batching and mixing of concrete are
similar to those made for the trackless panel cave situation. From the above information it is evident that block cave
conditions are different to civil engineering practice resulting in
the need for a different rational to set to set concrete mix design
Concrete design rationale parameters. In this regard the ‘3S’ rationale is advocated. This
From a review of literature, it appears that the selection of simple, strong and sloppy criterion provides guidelines for input
concrete strengths, mixes, material and lining thickness have parameters (for standard civil engineering concrete mix design
been based on local experience. In the case of slusher caves, procedures) by taking note of the block caving environment. A
concrete drift linings were designed on the experiences gained in discussion of the ‘3S’ rationale is given below.
North America. Little is written regarding the rationale on which
the actual mixes were designed. From the information Simple
summarised in Tables 1, 2 and 3 it would appear that mixes were
based on the need to produce a standard structural-grade to high Owing to the fact that concrete practice standards in block caving
strength concrete (+20 MPa UCS @ 28 days - Cement and are much more difficult to achieve than in civil engineering
Concrete, 1991) with a high to very high degree of workability practice, mixes should be as simple as possible. In this regard
(+100 mm slump). It can be assumed that the high concrete concrete should be made from basic materials such as Ordinary
strength was required to prevent failure during undercut Portland Cement, crusher or river sand and 19 mm stone. The use
abutment loading. The high degree of workability is required for of concrete additives such as plasticisers, accelerators and
pumping and self-compaction in congested shutters. retarders should only be considered if the required concrete
properties cannot be achieved with standard materials. The use of
site blended cement extenders should also be avoided if possible.
BLOCK CAVE CONCRETE MIX DESIGN By keeping mixes simple, quality control problems are reduced.
RATIONALE In the case where concrete is required to be highly workable for
pumping or shutter placement purposes, the following should be
From the above discussion it is clear that underground block cave
considered before using plasticisers or super plasticisers in
concrete has been designed according to local experience and
mixes:
probably on basic civil engineering mix design principles. In this

TABLE 3
Characteristics of inclined drawpoint/front cave block cave drawpoint mass concrete.

Lining thickness Uniaxial compressive Water/cement ratio Slump Mining depth


strength @ 28 days
± 300 mm ± 30 MPa 0.48 - 0.67 ±150 mm <1000 m

426 Brisbane, Qld, 29 October - 2 November 2000 MassMin 2000


THE ROLE OF MASS CONCRETE IN SOFT ROCK BLOCK CAVE MINES

• the replacement of crusher dust with river sand to improve The above assumes that concrete would fail in compression. It
workability; is well known that concrete will fail in tension or shear before
compressional failure occurs. Since tensile and shear strengths
• increasing the coarse aggregate content or size in mixes are considerably lower (10 - 15 per cent of UCS), this would
(stone); mean that concrete linings could only be installed at shallower
• allowing a target mean strength reduction to improve depths without failure occurring. This would seem to conflict
workability: this can be achieved by a reduced design with historical observations. A possible explanation for the lack
margin, assuming that higher quality control standard can be of damage could be:
implement, without affecting the required characteristics • lining damage may be limited to the extent that it is
strength of the concrete; unnoticeable; and
• the use of fly ash in cement; and • concrete linings are installed after rock mass deformations
• increasing the proportion of fly ash in existing fly ash/cement due to development of the drifts have occurred and hence are
blends. subject to limited loading at that time;
Table 4 shows the effect of fly ash/cement replacement on Taking cognisance of the above arguments and the need to
28-day uniaxial compressive concrete strength. specify a 28-day uniaxial compressive strength under static stress
It can be seen that fly ash replacement levels of 20 per cent conditions, it is advocated that, for slusher drift and trackless
reduce the 28-day compressive strength by 11 per cent. In terms caves, minimum 28-day uniaxial compressive specified strengths
of pumpable/highly workable concrete, 20 to 30 per cent of 30 and 27 MPa are used. These figures have been based on
ash/cement replacement levels are normally required. Tables 1, 2 and 3. In this respect two specified strengths are given
due to the fact that slusher linings are normally subject to higher
levels of secondary blasting, point load and abrasion damage.
Strong
A common mistake made in underground concrete practice is
The strong aspect of the ‘3 S’ principle relates to the uniaxial to take the specified concrete strength as the mean cube strength
compressive strength selection for the concrete. Gallagher and to be achieved by underground construction teams. This will
Loftus (1961) have indicated that once post-undercut cave result in 50 per cent of the concrete produced being below the
operational depths exceed 450 m, severe damage occurs to block specified strengths. In civil engineering, it is common practice to
cave linings. From closed-form equations, the tangential stresses design concrete mixes with a design margin. This ensures that a
acting on block cave drifts at this depth would be in the region of 95 per cent of all concrete produced will be above the specified
26 MPa. From Tables 1, 2 and 3 the uniaxial compressive 28-day uniaxial compressive strength. Concrete mixes are
strength of lining concrete ranges from 30 to 50 MPa. Therefore, normally designed to a target mean strength (ie specified 28-day
if compressional lining failure is considered to be dominant, then uniaxial compressive strength plus a design margin). It should be
concrete linings should not fail. Brumleve and Maier (1981) have
noted that 28-day concrete strength tests are referred to due to
shown that during undercutting the magnitudes of stresses can
the fact that most basic concrete materials and mix design charts
increase by a factor of 2 to 3. Therefore, if a post-undercut is
used (at about 450 m depth), then linings could be subject to refer to the above period. Table 5 shows the required target mean
stress magnitudes of 52 to 78 MPa, a stress change of 26 to 52 strengths for block cave concrete.
MPa. Under these conditions lining failure would be expected.
According to Salamon (1970) the main disadvantage of using
TABLE 5
concrete as an underground support system is that, due to its
limited stiffness, it cannot restrain the dilatation of the rock mass 28-day target mean strengths for block cave concrete.
that accompanies an underground stress change and subsequently
fails. It is therefore evident that concrete cannot be used in a Block cave Specified Design margin Target mean
changing stress environment (ie with post-undercutting). strength strength
Salamon further indicates that increasing the concrete strength or Slusher 30 MPa 11.5 MPa 41.5 MPa
the lining thickness does little to inhibit dilatation of the rock Trackless caves 27 MPa 11.5 MPa 38.5 MPa
mass directly. It enhances failure due to the fact that concrete
stiffness is increased to the point that larger reaction stresses are
generated in the concrete (ie concrete is not stiff enough to
prevent rock mass dilatation, but has sufficient stiffness to
generate stresses great enough to cause its failure). Block cave concrete should be designed for a 28-day uniaxial
The main point arising from the above is that below depths of compressive strength of 41.5 and 38.5 MPa for slusher and
about 450 m, block cave concrete will fail during post trackless operations respectively. This assumes a concrete failure
undercutting. Increasing concrete strengths or lining thicknesses rate of five per cent and poor quality control conditions (Fulton,
will simply add to the failure. 1994).

TABLE 4
28 day uniaxial compressive strength difference for different level of cement/ fly ash replacement (Ash Resources, 1985).

Uniaxial compressive Ash % Difference in uniaxial W/C ratio


strength @ 28 days compressive strength %
30.0 MPa 0 0 0.67
27.6 MPa 15 8 0.67
26.6 MPa 20 11 0.67
24.6 MPa 30 18 0.67

MassMin 2000 Brisbane, Qld, 29 October - 2 November 2000 427


R J BUTCHER

TABLE 6
Typical concrete slumps and applications (Fulton, 1994).

Degree of workability Compaction Slump (mm) Use


Very low Heavy compaction required 0 - 25 Concrete roads
Low Compaction by vibration equipment 25 - 50 Prestressed concrete/slabs
Medium Normal compaction required. 50 - 100 Reinforced concrete
Hand compaction can be used.
High Hand compaction and 100 - 150 Heavily reinforced concrete
light vibratuioin required
Very high Flowing concrete 150+ Pumpable concrete

Sloppy (high workability) REFERENCES


In the design of blockcave concrete, high levels of workability Ash Resources, 1985. Technical Information Bulletin, Issue Number 5
(normally defined by concrete slump) are essential. If this is not (Alpha curves), November.
achieved the following can occur: Brumleve, C B and Maier, M M, 1981. Applied investigations of rock
mass response to panel caving, Henderson Mine, Colorado, USA, in
• Water may be added to the concrete mix to increase Design and Operation of Caving and Sublevel Stoping Mines (Ed:
workability. This in turn reduces the strength of the concrete. D R Stewart) pp 223-249 (SME of AIME).
• Pumping of concrete becomes difficult. This results in the Cement and Concrete, 1991. Ninth edition (Portland Cement Institute).
blocking of steel pipes used to convey concrete. Gallagher, W S and Loftus, W K B, 1961. Yielding arch support for
block cave scraper drifts at Kimberley Mine, Association of Mine
• Air voids are created in the poured concrete. This in turn Managers of South Africa, Papers and Discussions, 1960-1961.
results in concrete strengths being reduced. Gaths Mine Visitor’s Handbook, undated. (African Associated Mines Ltd,
Table 6 shows typical concrete slumps for different Zimbabwe).
applications. Fultons Concrete Technology, 1994. 7th Edition (Portland Cement
In the selection of the concrete workability, cognisance has to Institute).
be taken of the fact that, in most cases during underground drift Jakubec, J, 1992. Support at Cassiar underground mine, in Proceedings
MassMin 92, pp l l l - 123 (SAIMM: Johannesburg).
and drawpoint construction, vibration and compaction equipment
cannot be used or is difficult to use. Taking into account the Laccasse, M and Legast, P, 1981. Change from grizzly to LHD extraction
systems, in Design and Operation of Caving and Sublevel Stoping
information in Table 6, it is therefore evident that concrete Mines (Ed: D R Stewart) pp 107- 118 (SME of AIME).
slumps should be in excess of 100 mm if problems are to be
Salamon, M D G, 1970. A note on the design of tunnel linings, The
avoided. Technology and Potential of Tunnelling, in Proceedings South
African Tunnelling Conference TUNCON 70, pp 115- l l 9.
CONCLUSIONS Trepanier, M L S and Underwood, A H (1981) Block Caving at King
Beaver Mine, in Design and Operation of Caving and Sublevel
Traditionally in block caving, concrete is used mainly for drift Stoping Mines, (Ed: D R Stewart) pp 229-319 (SME of AIME).
and drawpoint linings. Concrete linings vary from 180 mm to Watson, D and Keskumaki, K, 1992. Shotcreting, Concreting at Climax
1000 mm thick. Concrete 28-day strengths range from 24 to 50 Molybdenum’s Henderson Mine, Mining Engineering, November, pp
MPa. Workabilities, when measured as concrete slumps, are 1330-1332.
between 100 and 230 mm. Drift and drawpoint lining parameters
have been designed according to local experience. Experience BIBLIOGRAPHY
from North America and South Africa has shown that concrete
linings will suffer damage when exposed to changing stress Concrete Technology and Construction, 1994. Part l, General Principles.
regimes at operational depths greater than 450 m, regardless of Course notes, City and Guilds of London, Institute examination, Portland
strength or lining thickness. Therefore, for lining failure to be Cement Institute.
avoided, concrete must be installed in static stress conditions. Grobbelaar, C, 1992. The degradation and failure of concrete linings
around water conveyance tunnels, in Proceedings Design and
Owing to the differing stress regime, challenging quality
Construction of Tunnels, Maseru, Lesotho, pp 45-51 (S Afr National
control and safety requirements, the direct application of a civil Council on Tunnelling).
engineering concrete mix design rationale is difficult. In this Laubscher, D H, 1984. Design aspects and effectiveness of support
respect the ‘3S’ (simple, strong and sloppy) rationale for block systems in different mining conditions, Trans Inst Min Metall,
cave concrete mix is advocated. Concrete should have 28-day London, Section A, Vol 93, April.
strengths in excess of 38 MPa. Block cave concrete should have Peel, R, 1941. Mining Engineering Handbook, Tunnelling, 3rd Edition,
slumps greater than 100 mm for workability purposes. (Eds: L Parkinson and H T Dickson) Ch 6, p 24.

428 Brisbane, Qld, 29 October - 2 November 2000 MassMin 2000

You might also like