Professional Documents
Culture Documents
HERON RESOURCES
LIMITED
www.heronresources.com.au
Heron Resources Limited ©
heron@heronresources.com.au 1
Woodlawn Project PEA – 29 May 2015
Heron Resources Limited Title & Contents
This report has been prepared and signed for by the following “Qualified Persons”
(within the meaning of National Instrument 43-101). The effective date of this report
is 29 May 2015.
Signed the 29th May 2015
________________
Anne-Marie Ebbels
Principal Consultant (Mining)
SRK Consulting (Australasia)
________________
Pty Ltd
Daniel Guibal
Principal Consultant (Geology)
SRK Consulting (Australasia)
Pty Ltd
________________
Rodney Brown
Principal Consultant (Geology)
SRK Consulting (Australasia) ________________
Pty Ltd
Peter Allen
Manager – Process & Technical
Services
GR Engineering Services
Limited
Table of Contents
1 Summary ............................................................................................................................ 14
1.1 Introduction and Scope ................................................................................................................. 14
1.2 Economic Modelling Outcomes ..................................................................................................... 15
1.3 Property Description and Ownership ............................................................................................ 15
1.4 History and Exploration................................................................................................................. 18
1.5 Geology and Mineralisation .......................................................................................................... 18
1.6 Mineral Resource and Mineral Reserves Estimates ....................................................................... 19
1.6.1 Current Mineral Resource ............................................................................................................... 20
1.6.2 Current Mineral Reserve ................................................................................................................. 21
1.7 Mining........................................................................................................................................... 22
1.8 Metallurgy & Processing ............................................................................................................... 26
1.9 Infrastructure ................................................................................................................................ 28
1.9.1 Access and Site Roads ...................................................................................................................... 28
1.9.2 Power Supply ................................................................................................................................... 28
1.9.3 Water Supply ................................................................................................................................... 28
1.9.4 Tailings Storage Facility ................................................................................................................... 28
1.10 Environmental, Permitting & Social .............................................................................................. 29
1.10.1 Environmental Permits ................................................................................................................ 29
1.10.2 Permitting Requirements ............................................................................................................ 29
1.10.3 Social and Community Aspects, Stakeholder Consultation ......................................................... 29
1.10.4 Closure ........................................................................................................................................ 30
1.11 Capital and Operating Costs .......................................................................................................... 30
1.11.1 Capital Costs ................................................................................................................................ 30
1.11.2 Operating Costs ........................................................................................................................... 32
1.12 Economic Analysis ......................................................................................................................... 33
1.12.1 Basis of Evaluation ...................................................................................................................... 33
1.12.2 Summary Economics ................................................................................................................... 33
1.12.3 Macroeconomic Assumptions ..................................................................................................... 34
1.12.4 Technical Assumptions ................................................................................................................ 35
1.12.5 Sensitivity Study .......................................................................................................................... 37
1.13 Conclusions ................................................................................................................................... 38
1.14 Recommendations ........................................................................................................................ 39
2 Introduction ........................................................................................................................ 40
2.1 Terms of Reference ....................................................................................................................... 40
2.2 Purpose of Report ......................................................................................................................... 40
2.3 Report Preparation ....................................................................................................................... 40
2.4 Cautionary Notes .......................................................................................................................... 40
2.5 CIM Code Reconciliation ............................................................................................................... 41
2.6 Sources of Information.................................................................................................................. 41
2.7 Units and Currency ........................................................................................................................ 41
2.8 Site Visits ...................................................................................................................................... 42
3 Reliance on Other Experts ................................................................................................... 43
3.1 Report Authors ............................................................................................................................. 43
3.2 External Reports Incorporated ...................................................................................................... 44
4 Property Description and Location ....................................................................................... 45
4.1 Location ........................................................................................................................................ 45
4.2 Property Description ..................................................................................................................... 45
4.3 Location of Mineralised Zones ...................................................................................................... 48
4.4 Survey Coordinate System and Conversions.................................................................................. 48
4.5 Tenure........................................................................................................................................... 49
4.5.1 Mining License – SML 20 ................................................................................................................. 49
List of Figures
Figure 1.1 : Woodlawn location map with relative population sizes ....................................................................... 16
Figure 1.2: Woodlawn site layout ........................................................................................................................... 17
Figure 1.3: Woodlawn Project Mineral Resource Block Model (ZnEq coloured) .................................................... 19
Figure 1.4: PEA Stope Design (SRK) .................................................................................................................... 23
Figure 1.5: Plant Feed Sources and Grades Delivered to the Mil .......................................................................... 24
Figure 1.6: Underground Production by Mining Type............................................................................................. 25
Figure 1.7: Underground Production by Domain .................................................................................................... 25
Figure 4.1 : Woodlawn location map with relative population sizes ....................................................................... 46
Figure 4.2: Woodlawn Site Layout ......................................................................................................................... 47
Figure 4.3: Grid conversion calculations at Woodlawn .......................................................................................... 48
Figure 4.4: Demarcation of the Veolia and Heron Activities ................................................................................... 51
Figure 7.1: Regional Geological Setting of the Woodlawn Project, within the Goulburn Basin. ............................. 62
Figure 7.2: Interpreted solid geology for the Woodlawn area. ................................................................................ 64
Figure 7.3: Interbedded volcanic mudstone and quartz-crystal-rich sandstone. Arrow indicates the local younging
direction ........................................................................................................................................................ 66
Figure 7.4: Monomictic quartz-phyric rhyolite breccia viewed on a surface parallel to cleavage ........................... 67
Figure 7.5: Equant rhyolite clast with curviplanar margins, in the monomictic quartz-phyric rhyolite breccia; viewed
on a surface parallel to cleavage................................................................................................................... 67
Figure 7.6: Interbed of graded quartz-crystal-rich sandstone in the monomictic quartz-phyric rhyolite breccia.
Arrow indicates the local younging direction ................................................................................................. 68
Figure 7.7: Strongly chlorite-altered quartz-phyric rhyolite ..................................................................................... 68
Figure 7.8: Massive amygdaloidal basalt / dolerite (amygdales are filled by dark green chlorite). ......................... 69
Figure 7.9: Schematic section based on the Woodlawn Pit traverse. The section was not measured but the
approximate thickness is in the range of several tens of metres to possibly 150 m. The younging direction is
not confidently known but is generally considered to be younging up the section. ....................................... 70
Figure 7.10: Copper stringer and polymetallic massive sulphide mineralisation from WLTD015 Kate Lens
“discovery hole”, 396 to 409m with assay results .......................................................................................... 72
Figure 8.1: Cross section through typical Palaeozoic VMS system of Eastern Australia (after Gemmell et al 1998).
...................................................................................................................................................................... 75
Figure 9.1 Woodlawn Oblique Cross-Section looking north (top) and Figure 9.2 Woodlawn Long-section looking
east in the plane of the Kate Lens (bottom). ................................................................................................. 81
Figure 9.3: Woodlawn lens plan view..................................................................................................................... 82
Figure 9.4: G Lens long section looking east ......................................................................................................... 83
Figure 9.5: Woodlawn Prospects Location Plan..................................................................................................... 84
Figure 10.1: WNDD0018 comparison of Pathfinder vs Keeper Gyro down hole survey readings .......................... 89
Figure 11.1: Control standard plot BLANK_SS Zn Analysis ................................................................................... 98
Figure 11.2: Control standard plot BLANK_SS Cu Analysis .................................................................................. 98
Figure 11.3: Control standard plot BLANK_SS Pb Analysis .................................................................................. 99
Figure 11.4: Control standard plot BLANK_SS Au Analysis .................................................................................. 99
Figure 11.5: Control standard plot BLANK_SS Ag Analysis .................................................................................. 99
Figure 11.6: Control standard plot GBM309-15 Zn Analysis ................................................................................ 101
Figure 11.7: Control standard plot GBM309-15 Cu Analysis ............................................................................... 101
Figure 11.8: Control standard plot GBM309-15 Pb Analysis ................................................................................ 101
Figure 11.9: Control standard plot GBM309-15 Ag Analysis ................................................................................ 102
Figure 11.10: Control standard plot GBM911-11 Zn Analysis .............................................................................. 102
Figure 11.11: Control standard plot GBM911-11 Cu Analysis ............................................................................. 102
Figure 11.12: Control standard plot GBM911-11 Pb Analysis .............................................................................. 103
Figure 11.13: Control standard plot GBM911-11 Ag Analysis .............................................................................. 103
Figure 11.14: Control standard plot G901-7 Au Analysis ..................................................................................... 103
Figure 11.15: Correlation Plot for Zn TriAusMin (Original) vs Heron (Duplicate) Analysis ................................... 104
Figure 11.16: Correlation Plot for Cu TriAusMin (Original) vs Heron (Duplicate) Analysis ................................... 104
Figure 11.17: Correlation Plot for Pb TriAusMin (Original) vs Heron (Duplicate) Analysis ................................... 105
Figure 11.18: Correlation Plot for Au TriAusMin (Original) vs Heron (Duplicate) Analysis ................................... 105
Figure 11.19: Correlation Plot for Ag TriAusMin (Original) vs Heron (Duplicate) Analysis ................................... 106
Figure 11.20: Correlation Plot for Zn Original vs Lab Duplicate Check Analysis .................................................. 106
Figure 11.21: Correlation Plot for Cu Original vs Lab Duplicate Check Analysis ................................................. 107
Figure 11.22: Correlation Plot for Pb Original vs Lab Duplicate Check Analysis.................................................. 107
Figure 11.23: Correlation Plot for Ag Original vs Lab Duplicate Check Analysis.................................................. 108
Figure 11.24: Correlation Plot for Zn Original vs Field Duplicate Analysis ........................................................... 108
Figure 13.1: FEED Study – Plant Flowsheet ........................................................................................................ 116
List of Tables
1 Summary
1.1 Introduction and Scope
Heron Resources Limited (Heron) (ASX:HRR / TSX:HER) presents the results of a
Preliminary Economic Assessment (PEA or the Study) of its 100%-owned
Woodlawn Zinc-Copper Project (Woodlawn Project or simply the Project) in the
Goulburn district, New South Wales, Australia.
The Study was overseen by Anne-Marie Ebbels of SRK, with contributions from
other consultants discussed in Section 2.3. The Report has been prepared in
accordance with the requirements of National Instruments 43-101 (NI 43-101),
“Standards of Disclosure for Mineral Projects”, of the Canadian Securities
Administrators (CSA) for lodgment on the CSA’s “System for Electronic Document
Analysis and Retrieval” (SEDAR). The opinions contained herein and effective 29
May 2015, are based on information collected by the various consultants and
employees of Heron.
The Study considers the design and construction of an integrated processing
facility for the Woodlawn Underground Project (WUP) and the Woodlawn Tailings
Retreatment Project (WRP). It encompasses geology, resource definition, mine
design, metallurgical testing and process design, infrastructure requirements, and
associated capital and operating cost estimation, leading to a preliminary
assessment of the economic potential of the Project.
The base case “UG Starter Case” development scenario for the WUP Resource
considers the treatment of 3.8 million tonnes, representing 58% of the updated
JORC Mineral Resource. In addition, 11.2 million tonnes of Mineral Resources
from the WRP are treated, for a total Plant Feed Estimate of 15 million tonnes.
The UG Starter Case scenario reflects an initial design life of approximately 11
years based on co-treatment of WUP and WRP material through a 1.5Mtpa plant.
The UG Starter Case is a starting point for the now-commenced Feasibility Study,
which will be based on achieving attractive project returns whilst minimising
development time and cost. However, there is very strong potential for the Project
to deliver significantly greater tonnages from underground based on both the
Resource and on the exploration potential of the Woodlawn mineralised system.
Cautionary statements
The purpose of this technical report (Report) is to present the PEA findings of the
Project. The contents of this Report reflect various technical and economic
conditions at the time of writing. Given the nature of the mining business, these
conditions can change significantly over relatively short periods of time.
Consequently, actual results may be significantly more or less favourable.
The reader is cautioned that the PEA summarised in this Report is preliminary in
nature and is only intended to provide an initial, high-level review of the Project.
Further studies are required with regards to the resource, infrastructure and
operational methodologies, particularly as they relate to the WUP. The PEA
production schedule and economic model include the use of a significant portion
(29%) of Inferred Mineral Resources that are considered to be too speculative
geologically to have economic considerations applied to them that would enable
them to be characterised as Mineral Reserves. There is no guarantee that Inferred
Figure 1.2 below shows the layout of the site, highlighting the three existing tailings
dams, the location of the open pit where Veolia has established a bioreactor, and
the adjacent underground mineralised zones, and the proposed location for the box
cut and the plant site. The site is highly disturbed, and reprocessing activities
associated with the existing tailings dams are expected to contribute significantly to
the ongoing rehabilitation of the site.
Figure 1.2: Woodlawn site layout
Figure 1.3: Woodlawn Project Mineral Resource Block Model (ZnEq coloured)
500m of the system, deferring the need to drill deeper targets. While considerable
resource potential exists in deeper parts of the system, the PEA focus has been
only on the shallower, up-dip lens positions, with the result that the underground
Mineral Resource used in the production schedule for the PEA extends the depth
of the mine only 80m below previous workings.
Heron has taken a deliberately cautious approach to areas that would be
considered remnant, which has reduced the underground Mineral Resource
compared with the previously published estimate. There are numerous areas
adjacent to historical mining which have been excluded from the new resource
estimate, and there is considerable potential to re-incorporate these zones into the
mine plan once operations are under way and underground access facilitates
closer and more detailed assessment.
The Mineral Resource has been reported undiluted to a lower cut-off grade of 7%
zinc equivalent (ZnEq – refer to section 14.6.3 for calculation details), a value that
approximates the estimated lower cut-off grade for the mining methods considered
by the PEA Study.
The tailings or Woodlawn Retreatment Project Mineral Resource estimate, detailed
in Table 1.2 below is a re-statement of the previously released estimate.
Grades
Resource Category Quantity ZnEq (%) Zn Cu Pb Au Ag
(Mt) (%) (%) (%) (g/t) (g/t)
Measured + Indicated Mineral Resources
North Dam
Measured 0.83 6.2 2.35 0.43 1.43 0.29 35
Indicated 1.38 6.7 2.68 0.45 1.44 0.29 40
Sub-Total 2.21 6.5 2.56 0.44 1.44 0.29 38
South Dam
Measured 2.43 6.0 2.60 0.48 1.19 0.22 25
Indicated 1.17 5.8 2.44 0.48 1.19 0.22 23
Sub-Total 3.60 5.9 2.55 0.48 1.19 0.22 24
West Dam
Measured 2.05 6.5 2.00 0.60 1.46 0.39 36
Indicated 1.54 6.5 1.93 0.60 1.51 0.39 37
Sub-Total 3.59 6.5 1.97 0.60 1.48 0.39 36
All Dams
Measured 5.31 6.2 2.33 0.52 1.33 0.30 31
Indicated 4.09 6.4 2.33 0.52 1.40 0.31 34
Total Measured + 9.40 6.3 2.33 0.52 1.36 0.30 32
Indicated
Inferred Mineral Resources
North Dam 0.87 5.5 2.03 0.33 1.33 0.25 37
South Dam 0.90 5.7 2.32 0.47 1.19 0.23 24
West Dam 0.48 6.3 1.83 0.61 1.47 0.38 34
Total Inferred 2.25 5.7 2.10 0.44 1.30 0.27 31
Notes to accompany Mineral Resource Table: 1) ZnEq% refers to a calculated Zn equivalent grade the formula for which is stated in section 14.6.3 and
these are different to the originally reported (May 2009) ZnEq grades which were based on a different formula; 2) Values are rounded to two significant
numbers and some rounded related discrepancies may occur in the totals; 3) The Mineral Resource is reported in a manner compliant with the JORC 2004
and NI 43-101 Codes. This information was prepared and first disclosed under the JORC Code (2004) in May 2009. It has not been updated since to
comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. 4) TriAusMin acquired more drill
hole data in 2008, subsequent to the Mineral Resource estimation. That data however does not materially alter the Mineral Resource estimate and due to
data collection problems it is not viable for use in a re-estimate. Nevertheless, statistics of the later assays confirm the reported estimated grades; 5) further
details of the Mineral Resources estimation can be found in the market release of 22nd April 2015 entitled “Preliminary Economic Assessment Delivers
Strong Business Case for the Woodlawn Zinc-Copper Project” (available from ASX or SEDAR) including the Competent Person Statement
Mineral Reserves for the WRP were calculated as part of the Feasibility Study in
2008 (Intermet, 2008). For the purposes of the PEA in and in accordance with NI
43-101 guidelines, the production schedule for the reprocessed tailings elements of
the PEA plant feed has been based on the WRP Mineral Resource. Hence, the
historical Mineral Reserves for the WRP do not form a part of this Report. It is
noted that this PEA does not replace the prior studies and the previously published
tailings Mineral Reserves remain unchanged.
1.7 Mining
Beck Engineering (Beck), an east coast Australia-based specialist consultancy,
was engaged to assist with the rock mechanics input to the proposed underground
operation. As a component of their work, the extensive historical mine records
have been reviewed to better understand the ground conditions previously
encountered at Woodlawn and previous ground control practices. In addition to this
historical knowledge base, inspection and geotechnical logging of Kate Lens
diamond drill core has led Beck to note that the hangingwall appears competent for
this new lens. This, together with the use of competent backfill, are important input
parameters for the selection of an appropriate mining method that provides for
maximum recovery and high productivity.
A number of changes to historic work practices will improve the future
management of the ground conditions. These include:
Full time geotechnical resources on site to provide timely day-to-day support to
mine operations.
Whole-of-mine structural modelling to improve the predictive capacity for mine
planning.
Adoption of alternative extraction techniques to minimise creation of isolated sill
pillars.
Implementation of cemented paste fill as a competent support medium that will
enable significantly higher resource recovery whilst providing local and regional
ground support to the mine excavations.
The deposit will be accessed with a box cut located on the western side of the
existing open-pit, which provides for early access to underground material.
Stoping areas will be accessed by rehabilitating some of the existing workings and
constructing additional underground declines and levels to access the new areas.
The mining methods have been selected to mine both areas of unmined and
remnant material around the previously mined areas of the deposit. The mining
method selection takes into consideration the location of the existing open pit
above the deposit which is being used as a bioreactor by Veolia. The mine design
has assumed that some stopes will be filled with paste fill, and multi-level
continuous fill method areas will be filled using rock fill.
Production will be transferred from stoping areas to loading bays and a haulage
fleet used to deliver plant feed to the run-of-mine (ROM) pad at the proposed
process plant.
The production schedule for the underground benefits from the inclusion of
significant material discovered from the recent drilling campaigns, with
approximately 2.8 million tonnes of Inferred Mineral Resources identified from this
work. Importantly, 80% of the total underground plant feed material is away from
former mining areas and is amenable to low cost, low risk mining methods. Figure
1.4 below shows the stope designs currently planned, with stopes coloured green
being material which is away from previously mined areas and hence amenable to
lower cost, lower risk mining methods, with areas in orange being adjacent to
previously mined areas for which more conservative mining methods have been
employed.
Figure 1.5: Plant Feed Sources and Grades Delivered to the Mil
Financial Year LOM 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
U/G Polymetallic Tonnes Mined kt 3,060 65 341 495 634 618 624 284 - - - -
Zn Grade (Equiv.) kt 15.72% 15.72% 15.42% 17.42% 19.30% 16.34% 12.89% 10.03% 0.00% 0.00% 0.00% 0.00%
Zn Grade % 7.01% 6.28% 5.51% 6.59% 9.54% 8.31% 5.96% 3.53% 0.00% 0.00% 0.00% 0.00%
Pb Grade % 2.66% 3.19% 2.90% 2.70% 3.48% 2.76% 2.09% 1.34% 0.00% 0.00% 0.00% 0.00%
Cu Grade % 1.38% 1.21% 1.27% 1.74% 1.47% 1.31% 1.19% 1.28% 0.00% 0.00% 0.00% 0.00%
Ag Grade g/t 57.1 76.9 95.7 81.7 58.6 44.9 37.6 29.8 - - - -
Au Grade g/t 0.63 0.89 0.86 0.89 0.70 0.40 0.45 0.61 - - - -
U/G Copper Tonnes Mined kt 715 - - 58 39 90 75 316 137 - - -
Zn Grade (Equiv.) kt 9.44% 0.00% 0.00% 12.00% 11.34% 9.07% 10.50% 8.97% 8.57% 0.00% 0.00% 0.00%
Zn Grade % 1.55% 0.00% 0.00% 4.70% 3.03% 1.57% 1.53% 1.05% 0.94% 0.00% 0.00% 0.00%
Pb Grade % 0.46% 0.00% 0.00% 2.48% 1.07% 0.35% 0.41% 0.19% 0.16% 0.00% 0.00% 0.00%
Cu Grade % 2.26% 0.00% 0.00% 1.08% 2.18% 2.20% 2.61% 2.38% 2.34% 0.00% 0.00% 0.00%
Ag Grade g/t 13.8 - - 48.7 20.4 11.3 14.5 10.4 6.4 - - -
Au Grade g/t 0.07 - - 0.52 0.05 0.02 0.05 0.04 0.02 - - -
Tailings Tonnes Mined kt 11,240 479 1,140 947 827 792 801 900 1,363 1,500 1,500 990
Zn Grade (Equiv.) kt 5.99% 5.71% 5.71% 5.71% 5.71% 5.71% 6.19% 6.26% 6.26% 6.18% 6.04% 6.04%
Zn Grade % 2.22% 2.43% 2.43% 2.43% 2.43% 2.43% 1.97% 1.90% 1.90% 2.06% 2.34% 2.34%
Pb Grade % 1.31% 1.15% 1.15% 1.15% 1.15% 1.15% 1.40% 1.44% 1.44% 1.42% 1.38% 1.38%
Cu Grade % 0.49% 0.47% 0.47% 0.47% 0.47% 0.47% 0.57% 0.59% 0.59% 0.52% 0.40% 0.40%
Ag Grade g/t 31.1 23.4 23.4 23.4 23.4 23.4 33.4 34.9 34.9 35.6 36.9 36.9
Au Grade g/t 0.28 0.21 0.21 0.21 0.21 0.21 0.34 0.36 0.36 0.32 0.26 0.26
Total Tonnes Mined kt 15,015 544 1,481 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 990
Zn Grade (Equiv.) kt 8.14% 6.46% 7.67% 9.66% 11.43% 10.46% 9.31% 7.77% 6.72% 6.18% 6.04% 6.04%
Zn Grade % 3.16% 2.71% 3.04% 3.82% 5.32% 4.89% 3.70% 2.18% 1.85% 2.06% 2.34% 2.34%
Pb Grade % 1.55% 1.30% 1.50% 1.70% 2.09% 1.81% 1.66% 1.22% 1.33% 1.42% 1.38% 1.38%
Cu Grade % 0.76% 0.53% 0.63% 0.89% 0.94% 0.92% 0.94% 1.09% 0.81% 0.52% 0.40% 0.40%
Ag Grade g/t 35.5 27.6 38.5 43.9 38.0 32.3 34.3 29.8 32.6 35.6 36.9 36.9
Au Grade g/t 0.34 0.27 0.35 0.44 0.41 0.30 0.36 0.36 0.33 0.32 0.26 0.26
The production schedule for the UG Starter Case contains 36% Measured, 35%
Indicated and 29% Inferred Resources, broken down into WUP: 32% Indicated
Resources, and 68% Inferred Mineral Resources, and WRP: 47% Measured, 37%
Indicated and 16% Inferred. Approximately 80% of the tonnes from underground
mining relate to areas which have not previously been mined. The breakdown
between remnant and new areas is illustrated in Figure 1.6 below:
The underground resources fall into two main types, a “Polymetallic” type which
refers to polymetallic massive sulphide mineralisation with high-grade Zn and Pb,
and a “Copper” type which refers to Cu dominated massive and stringer sulphide
mineralisation. The mining schedule preferentially feeds the Polymetallic material,
with the Copper material generally being skewed to the later stages of the
production profile as shown in Figure 1.7:
A one month stockpile on the ROM pad has been assumed for the underground
production, consistent with the previous operations. Reclaimed tailings are fed
directly into the mill after thickening.
Based on the mining schedules above, Table 1.4 presents the detailed life-of-mine
production schedule for the Woodlawn Project on an annual basis, showing
concentrate production on a dry tonne basis and gross metal content by
concentrate. Metals that are unlikely to be payable have been removed from the
table. Moisture in the shipped concentrates is expected to be around 10%.
Table 1.4: Annual Production by Product (combined WRP and WUP)
Production by Product LOM 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Zn Concentrate dry kt 779.7 21.0 73.7 96.2 136.6 125.5 94.5 54.0 42.5 46.9 53.4 35.3
Zn kt 352.7 9.5 33.2 43.3 61.5 56.5 42.5 24.4 19.6 21.6 24.6 16.2
Ag koz 2,306.1 58.2 261.1 304.3 263.5 223.7 234.7 196.4 194.3 209.3 217.2 143.4
Pb Concentrate dry kt 249.9 5.61 22.61 28.92 38.32 32.47 27.77 18.26 20.30 21.28 20.70 13.66
Pb kt 112.0 2.7 11.1 14.2 18.8 15.9 13.6 8.4 7.3 7.7 7.5 4.9
Cu kt 19.4 0.5 1.7 2.0 2.0 2.0 2.1 2.5 2.4 1.8 1.4 0.9
Ag koz 5,635.2 130.6 693.4 881.3 761.7 628.4 602.6 452.7 382.0 405.0 420.2 277.3
Au koz 37.4 0.8 4.5 7.2 6.7 4.5 4.5 3.9 1.6 1.5 1.2 0.8
Cu Concentrate dry kt 244.9 4.16 18.15 31.13 34.38 34.01 33.25 39.44 24.49 11.41 8.73 5.76
Cu kt 57.6 1.0 4.4 7.5 8.3 8.2 8.0 9.2 5.4 2.5 1.9 1.3
Ag koz 913.2 20.2 117.0 154.4 133.4 108.7 100.1 71.1 54.1 56.6 58.8 38.8
Au koz 10.9 0.2 1.3 2.1 1.9 1.3 1.3 1.1 0.5 0.5 0.4 0.2
Total Production dry kt 1,274.5 30.8 114.5 156.2 209.3 192.0 155.6 111.7 87.3 79.6 82.8 54.7
Zn kt 352.7 9.5 33.2 43.3 61.5 56.5 42.5 24.4 19.6 21.6 24.6 16.2
Pb kt 112.0 2.7 11.1 14.2 18.8 15.9 13.6 8.4 7.3 7.7 7.5 4.9
Cu kt 77.0 1.5 6.1 9.5 10.3 10.1 10.1 11.7 7.8 4.3 3.3 2.2
Ag koz 8,854.5 208.9 1,071.5 1,340.0 1,158.5 960.9 937.4 720.2 630.4 670.9 696.2 459.5
Au koz 48.3 1.1 5.8 9.3 8.7 5.8 5.9 5.0 2.1 2.0 1.6 1.1
Average annual Production Target figures are shown in Table 1.5 for the life-of-
mine (LOM) and for the four-year period where the underground is producing at
target production rates:
Table 1.5: Annual Commodity Gross Production (LOM & Steady State)
preliminary mine life and the mill feed blend ratio will be reviewed further in the
next stage of the project studies.
For underground production, a two stage crushing circuit has been incorporated
into the plant design, together with a primary grind ball mill. For tailings material, a
fine grind mill is planned that reduces the particle size down to 30 micron (µm), a
size which previous and current testwork confirms maximises recovery
performance from the flotation circuit. For the underground material, the initial float
(copper concentrate) is undertaken at a 75µm grind size, with a regrind of copper
tails to 30µm being employed subsequent to that stage to maximise the recoveries
from the lead and zinc flotation stages.
The flotation circuit comprises a talc, copper, lead and zinc differential flotation
sequence. The overall plant design is consistent with the design of the original
1978-1998 plant that was historically used to successfully treat Woodlawn ore.
Talc cleaner concentrate recovered from the talc flotation cleaner cell will be
discarded to final tails to remove some of the talcose gangue ahead of the
differential flotation circuit. A differential flotation circuit for copper, lead and zinc
will be utilised with concentrate regrind stages in the copper, lead and zinc circuits
to produce marketable copper, lead and zinc concentrates. The copper circuit will
also utilise a rougher and scavenger tailings regrind circuit prior to the lead flotation
stage. Tailings from the flotation plant will be thickened for recovery of process
water and underground paste fill, with slime tailings deposited into a new tailings
storage facility (TSF4).
The PEA metallurgical testwork program was undertaken by Australian Mineral
Metallurgical Laboratories Pty Ltd (“AMML”) in their Gosford testing facility with
input from GRES and focused on the underground massive sulphides at the
Woodlawn Project. This work represents the first full suite of metallurgical tests
undertaken on the underground mineralisation since the 1998 mine closure, and
also the first tests on a combination of the tailings and fresh zinc-copper
mineralisation. The overall results from this work have demonstrated better than
historical operational performance and reflect the advancements made in the field
of sulphide flotation, and in-particular fine grinding technology. The testwork
demonstrated the ability to produce three readily saleable concentrates.
Concentrates from the copper, lead and zinc flotation circuits will be thickened and
subsequently filtered for road transport. Copper and zinc concentrates will be
shipped via Port Kembla in bulk carriers. Transport of the concentrate from site will
be by road with concentrate loaded into half-height containers via front end loader
at site. The high precious metals lead concentrates will be loaded into “bulka”
bags via a bagging plant at the process plant. Loaded bags will then be
containerised for dispatch via Port Botany or Port Kembla.
Final flotation tailings will be de-slimed and used in the paste fill plant which will
generate a cemented paste that will be reticulated underground and used to
backfill completed stopes.
Outotec has completed an initial set of testwork on the paste fill, including rheology
and strength testing, using tailings samples from the recent metallurgical testing.
Whilst this is sufficient for the PEA, further work will be undertaken during the
proposed Feasibility Study (FS) including leachability tests, additional trial mix tests
to optimise binder type and mix to deliver adequate strength to mine fill, and longer
term strength and stability tests.
1.9 Infrastructure
The Woodlawn site is well supplied with infrastructure. Existing infrastructure
includes:
a sealed access road to the mine site;
shared (with Veolia) administration building and offices;
an existing site laboratory;
raw water tank;
evaporation ponds;
site water pipe systems and pumps, and
electrical supply sub-station.
A sealed road exists immediately adjacent to the mine site. Some 350 metres (m)
of new sealed road will be installed to cater for logistics and administrative needs.
Other roads internal to the mine site will be constructed from locally sourced
crushed aggregate.
Raw water will be pumped from the existing Willeroo Borefield and stored in the
10,000 cubic metre (m³) raw water dam at the plant site.
Water from the evaporation ponds will be re-used in the process plant as part of
the make-up water requirements. The water has high ion content and a low pH
and will be treated before usage.
Potable water will be generated onsite from a raw water supply to a reverse
osmosis plant.
The sewerage treatment system will be of packaged proprietary form and will
consist of a number of in-ground collection pits located adjacent to the plant
buildings where waste water is generated.
Dam South once this dam is empty. This strategy is identical to that outlined in the
previous WRP FEED Study (Sara, 2012).
As each older tailings dam is emptied for retreatment, rehabilitation of the dam will
be carried out to repair any damage created in the monitoring operation. Following
this, each dam will be recommissioned and ready to receive tailings from new
processing operations.
1.10.4 Closure
Peak Cash Draw is defined as initial capital working capital post commissioning
until the mine achieves a break-even cash position, and excludes financing costs.
Maintenance capital has been built into the operating cost estimates. No
allowance has been made for financing charges or interest, Goods and Services
Tax (GST) related cash flows, intra-period cash flows, or fluctuations in the
exchange rate (estimates were provided on the basis of a rate of 0.80 A$:US$).
The basis for the capital estimates includes:
Engineering, Procurement and Construction model for non-mining
infrastructure.
Owner operator processing facilities and workforce.
Owned fixed plant, mobile surface plant, and administration buildings.
Contract mining and leased underground mining equipment and maintenance
facilities
Contract concentrate road haulage, port storage and handling and ship loading.
Construction of the new tailings storage facility TSF4.
Ongoing capital of A$107.7 million is required for the underground decline and
lateral development, decline rehabilitation, ventilation raises, escapeways,
infrastructure and sustaining capital. The profile is driven by the production
schedule and is shown below starting in the second quarter post commissioning
(being the quarter immediately after Peak Cash Draw, with capital prior to that
period being shown in Table 1.6):
The Woodlawn project economics have been assessed using the discounted cash
flow method, based on a quarterly schedule of tonnes mined and processed from
both the WUP and the WRP. Capital and operating costs are applied to mining,
processing and overheads. The processed material has recovery factors applied,
together with flotation splits to the three concentrates which make up the project
production. Shipping and logistics, product payability, treatment and refining costs,
state royalties and taxes are adjusted for to derive a Net Present Value (NPV) for
the Project.
Refer to Section 22 for further detail.
The main inputs and outputs of the financial model for the UG Starter Case are
summarised in Table 1.10, which is based on the Forecast Commodity Price Deck.
The Project’s post-tax NPV at an 8.3% post-tax real discount rate (approximately
equivalent to a 10% post-tax nominal discount rate) is A$300 million and the IRR is
46%. Payback of start-up capital is achieved approximately two years from
commissioning.
Base Case
(Forecast Commodity Price Deck)
Post-tax NPV8.3 A$300 million
Post-tax IRR 46%
Initial Capital A$140M / US$112M
Payback Period 2 years from commissioning
Post-tax Cash Flow A$594M
1
C1 Cash Cost US$0.00/lb (zero) Zn
1
C3 Total Cost US$0.31/lb Zn
Plant Feed Rate 1.5mtpa
Total Underground Feed 3.8Mt
Total Tailings Feed 11.2Mt
Total U+T Feed 15.0Mt
Mine life 11 years
1
C1 and C3 (refer to Section 27 for definitions) presented in this table are based on Zn as primary product with all
other saleable commodities treated as by-product credits. Refer to Section 22.2.2 for further details.
Results are based on AUD / USD Foreign Exchange (FX) trending from 0.80 to
0.73 by 2021 (forward curve as at 31 March 2015). The Forecast Commodity Price
Deck is based on the average of a number of forecasts for each commodity
resulting in prices of US$1.09/lb Zn, US$0.95/lb Pb, US$3.00/lb Cu, US$18.5/oz
Ag and US$1,200/oz Au.
The project is subject to Australian corporate tax, which has been applied at 30%.
Tax calculations are impacted by depreciation deductions for capital items.
New South Wales levies mineral royalties for extractive operations within the state.
The royalties are based on an “ad valorem” value of minerals, being 4% of the ex-
mine value less allowable deductions.
Opening capitalised exploration expenditure of A$12 million has been depreciated
on a unit of production basis.
Heron’s opening tax losses of A$60 million have been fully netted against the
project tax calculations. In addition, A$44.3 million of the A$53 million in additional
losses subject to the available fraction rule have been netted against the project
tax calculations.
The cost of transportation to port, port handling and storage charges, and ocean
freight has been estimated. The payability and Treatment Costs / Refining Costs
(TC/RC) terms vary by concentrate and commodity depending on the concentrate
specifications and the levels of by-products in each concentrate. Independent
advice has been sought to provide estimates for these based on expected
concentrate characteristics. The assumptions are in line with normal market terms.
Capital Costs
Refer to Section 1.11.1 for details of the mining and plant capital costs, which
includes the costs associated with the underground mine access and rehabilitation.
Mine Production Schedule
An 18 month construction period has been assumed pre-production. A ramp-up in
capacity has been assumed, commencing at an annualised rate of 900ktpa in
quarter 1, rising to 1.43Mtpa in the third quarter, and reaching 1.5Mtpa by the
fourth quarter. The mine plan has been developed based on an underground
mining schedule, with the residual capacity then being applied to treatment of the
tailings.
The underground mine production schedules are based on a stope by stope
evaluation undertaken by SRK, taking into account the desired production profile,
tonnes and grade (with post-dilution zinc equivalent grade as the key driver), stope
access, and mining and capital development costs.
The tailings production profile is based on the FS production model, under which
the three tailings dams are treated sequentially: Tailings Dam South (TDS), then
Tailings Dam West (TDW) and finally Tailings Dam North (TDN), with a constant
grade profile assumed across each dam. For the purposes of the PEA the same
sequence has been assumed, with the plant feed tonnes being driven by the
difference between the underground feed deliveries and the capacity of the plant
(as modified by the ramp-up profile described above).
A one month stockpile on the ROM pad has been assumed for the underground
production, consistent with the previous operations. Reclaimed tailings are fed
directly into the mill after thickening.
The resulting production schedule is described in Section 1.7.
Operating Costs
Refer to section 0 for details of the mining and plant operating costs.
Closure Costs
An amount of A$9 million has been assumed for the net closure costs associated
with the end of mining at the Woodlawn site for the UG Starter Case. The
economic evaluation is not sensitive to changes in the closure costs.
Plant Recoveries
Design work for the PEA has been based on start-up of operations on retreatment
of tailings from previous production, and moving to processing a blend comprising
0.75Mtpa fresh underground material and 0.75Mtpa of tailings from the previous
operations.
Refer to Section 13.3 for details of the testwork results. Based on this testwork,
the recovery outcomes to concentrates are described in the tables below, firstly as
the constituent parts, and then as a blended outcome:
Table 1.11: Economic Model - Concentrate Recoveries - Underground
The concentrate specifications are based upon the metallurgical testwork carried
out during the PEA and earlier studies as described in Section 13.2 and 13.3. They
are considered representative, though concentrate grades and by product
streaming to the concentrates will be impacted by the mix of material entering the
plant as well as by the flotation conditions at that time. Although similar to the
previous operations over 20 years, the new plant will utillise energy efficient fine
grinding machines with inert media to aid in optimisation of recovery characteristics
to the different concentrates.
Table 1.14: Economic Model - Concentrate Specifications
The modelled economic case for the Project has been subject to sensitivity
analyses based on percentage movements in each driver. For the sensitivities,
only a single factor has been modified, with other factors being left unchanged
(noting that movements in some of these may in reality be correlated with
movements in the modified factor – for example, FX and commodity prices).
The factors on which sensitivities have been undertaken are:
1. commodity prices;
2. zinc price (without moving other commodity prices);
3. the exchange rate (FX);
4. pre-production capital;
5. mining costs;
6. production grade delivered to mill;
7. processing costs;
8. payability; and
9. recoveries.
NPV is most sensitive to the commodity price / FX environment on the revenue
side, and to grade (which in turn is driven by dilution considerations), and recovery.
Other significant factors influencing the project returns include the underground
development capital, and the plant operating costs. Refer to Section 22.6 for
further discussion of project sensitivities.
1.13 Conclusions
Based on the assumptions and methodology applied, to normal PEA levels of
confidence, the results of this Study demonstrate that the Woodlawn Project has
positive economics and hence should be advanced to the next stage of
development as outlined in Section 26. As such the PEA has successfully
achieved its objectives.
The key Study conclusions are:
Recent exploration has resulted in the successful generation of a new
underground Mineral Resource focused on:
o near surface extensional positions and Kate lens;
o identification of resources suitable for mining away from areas of
previous mining; and
o seeking to build an initial production schedule to support the PEA.
The underground Mineral Resource and resulting contribution to the Plant
Feed Estimate are sufficient to support a robust underground starter
operation with an initial life of 6-7 years.
The tailings Mineral Resource and resulting contribution to the Plant Feed
Estimate provides additional low-cost (mining), but lower recovery material
which extends the production schedule out to around 11 years.
Metallurgical testing for the PEA has confirmed that co-treatment of the
underground plant feed with the tailings plant feed is feasible and results in
acceptable recoveries to saleable concentrates.
Capital and operating costs have been detailed and are acceptable.
Current project approvals, infrastructure and local relations provide good
support for the commencement of operations at Woodlawn.
There is potential for the Project to be developed in two stages,
commencing with construction of the tailings plant based on updating the
previous FEED Study with changes from the PEA, and followed by the
development of the underground once the FS is completed.
In addition, the Study has demonstrated that there remains significant optionality in
the Project based on:
1. the additional underground Resource outside the current PEA production
schedule;
2. the number of areas prospective for further exploration; and
3. potential enhancements to a number of key drivers to the economics,
including optimisation of the underground mining (dilution, capital
development), and process engineering costs.
1.14 Recommendations
The Company has considered the outcomes of the PEA and has determined that it
will continue with the further study of the Woodlawn Project through undertaking a
Feasibility Study (FS) on the combined underground and tailings project. This has
been approved by the Board and the work program outlined below has
commenced. The Company considers that the FS will be able to be completed
within approximately 12 months from the publication of this Report.
It is the view of the Company that the higher level of confidence associated with
the design of the processing plant, which is central to the success of the Project,
together with the mining of the tailings material, will allow the Project to be
progressed directly from PEA to FS without first going through a Pre-feasibility
Study stage, and planning is being undertaken on that basis.
The Board has approved a FS budget of A$11.0 million through to June 2016.
Within the FS budget an allocation has been made for further exploration work to
test a number of targets identified in the PEA drilling program. Within this
exploration activity, there will be an emphasis on proving up additional Resources
that can contribute to the FS. Examples of high priority targets include:
1. the newly discovered Lisa Lens;
2. potential extensions to Kate and G Lenses;
3. the poorly defined off-hole EM conductor adjacent to C Lens; and
4. the EM target identified at the Currawang satellite deposit.
Regional exploration will continue with a focus on developing and testing near mine
targets, particularly those targets which have the potential to add to the life of the
Woodlawn mine, albeit that it is unlikely that any mineralisation identified though
this exploration program will be included in the FS.
2 Introduction
2.1 Terms of Reference
The Woodlawn Project is owned and operated by Heron Resources Limited
(Heron). Heron is a public company listed on the Australian Securities Exchange
(ASX) and Toronto Stock Exchange (TSX), and registered in Australia (ASX code:
HRR, TSX code: HER). The address of the corporate office is Level 1, 37 Ord
Street, West Perth, Perth 6005, Western Australia.
This technical report was prepared for the Woodlawn Project to the standard of the
Canadian National Instrument 43-101 “Standards of Disclosure for Mineral
Projects” to summarise the findings of a Preliminary Economic Assessment (PEA)
covering the Woodlawn Underground Project and the Woodlawn Tailings
Retreatment Project.
Item Title
2 Rankin, R (2009). Woodlawn Exploration Project Technical Report (NI 43-101) report
for Tri Origin Minerals Ltd, effective date 9 October 2009.
3 Rankin, R (2008). Woodlawn Retreatment Project (WRP) Mineral Resources report for
th
Tri Origin Minerals Ltd, effective date 29 May 2008
The site includes a number of existing features constructed during past mining
operations that will be utilised for the proposed development of the Woodlawn
Project including:
Hickory’s Paddock, which includes a previously cleared area for agricultural
uses and is located to the immediate south of Collector Road and east of
the former plant site.
Three tailings dams, TDN, TDS and TDW, located to the south of Hickory’s
Paddock, which are intended to be reprocessed.
Two evaporation dams, including Evaporation Dam 1 (ED1) and
Evaporation Dam 2 (ED2) located to the west of Hickory’s Paddock
immediately south of Collector Road.
Diamond drill core storage and processing facility.
A number of existing formal and informal site roadways.
Site reticulated power and pumping systems.
Woodlawn Mine Grid (WMG) Map Grid of Australia MGA (Zone 55)
8771.90mE 733518.60mE
19699.10mN 6117691.50mN
10497.31mE 735122.03mE
19226.63mN 6116898.23mN
The difference between True North and MGA Grid North is -1.48o (1o 28’ 38.60”) at
Woodlawn and is a constant. The MGA coordinate system is based on the GDA94
geodetic datum.
4.5 Tenure
4.5.1 Mining License – SML 20
The Woodlawn Site is currently subject to an existing Special Mining Lease (SML
20), see Figure 4.1. SML 20 has remained current since the closure of the
operations in 1998 and title was transferred into the name of Tarago Operations
Pty Ltd, a fully owned subsidiary of Heron, in March 2014. The Mining Lease has
recently been renewed for a period of 15 years with an expiry date of 16 November
2029. The conditions associated with the renewed license are standard in nature,
a summary is provided in Section 4.7.
A number of legal agreements between Heron and Veolia have been entered into
covering the Woodlawn Site. They are as follows:
Call Option: This gives Heron the option to purchase the land covered by
the proposed mining operations.
Deed of Assignment: This covers the details for assignment of SML 20 to
Heron (completed) along with the excision of the Veolia operations area
from SML 20 and interaction with the Windfarm.
Co-operation Agreement: Veolia and Heron have agreed to co-operate and
assist each other in opportunities of mutual benefit, including (but not
limited to):
- Joint use of facilities including power connections, weighbridge,
offices and loading facilities.
- Heron and Veolia accepting sole specific responsibility for certain
rehabilitation requirements.
- Heron’s use of waste derived compost for mine site rehabilitation
from Veolia’s AWT plant.
Figure 4.4 illustrates the nominal demarcation of Heron, Veolia and Windfarm
operations and liabilities. This is included in the above agreements.
Based on the agreements and subsequent deeds these agreements are valid until
31 December 2015 to put into effect the excision of Veolia’s Area of Operations.
4.6 Ownership
A significant portion of the landholdings covering, and adjacent to, the Woodlawn
Site are owned under freehold title by Veolia (refer to Section 4.2 for further
details). Heron has a Call Option Agreement with Veolia permitting Heron to
acquire certain areas of the site.
The land for purchase encompass the surface areas required to operate both the
tailings and underground projects and include Hickory’s Paddock (proposed site for
the new plant), tailings dams, existing waste rock dump, core storage area and the
evaporation dams, Evaporation Dam 1 (ED1) and Evaporation Dam 2 (ED2).
As at the effective date, surveying of the subdivision for the land purchase was well
underway. Following completion of the survey, local council approval will be
required to redefine the ‘lot’ boundaries followed by an independent valuation of
the land to be purchased. The amount of land required to be purchased will
depend on the final site design, but is expected to be a minimum of 630 hectares,
and potentially up to around 1,000 hectares.
4.7 Environmental
The Woodlawn Project site is not a pristine environment, being disturbed by the 20
years of previous mining operations. The Company has undertaken an extensive
amount of work to consider the legacy site issues along with the integration of the
proposed operational activities to provide, firstly, minimal new impacts and,
secondly, a plan to remediate the overall site. The proposed approach to the site
has been the subject of a formal State Government approval process that required
the submission of a detailed Environmental Assessment document and the
approval was provided on the basis of complying with a number of conditions.
On the 4 July 2013, Heron received State Government approvals for the
development of both the tailings and underground projects from the Department of
Planning and Infrastructure.
The conditions associated with the project approval include:
Administrative Conditions – covering the limits of the approval, protection
requirements, staging of submissions and community contributions.
Environmental Performance Conditions – covering tailings dams,
underground mining and rehabilitation objectives.
Environmental Management Conditions – specific aspect management
including water, noise, blasting, air quality, land management, transport,
heritage, visual, waste and bushfire management.
Additional Procedures – covering landowners and independent reviews.
Environmental Management, Reporting and Auditing – requirements to
report and review, access to information.
Additional environmental conditions exist under the mining license, SML 20. The
lease conditions include:
Rehabilitation Requirements – to be completed to satisfaction of the
Minister.
Mining Operations Plan (MOP) & Annual Environmental Management
Report (AEMR) – covering requirements to document and obtain approval
for a Mine Operations Plan (MOP), post mining land use, apply and amend
MOP, preparation of AEMR.
Compliance Report – annual preparation and content covering compliance
of license conditions.
Environmental Incident Report – requirement to notify and report any
breaches of conditions or relevant Act or Regulations.
Resource Recovery – an obligation to optimise mineral recovery (economic
constraints).
Security – lodgment timing and quantum of the security deposit (bond).
Cooperation Agreement – obligation to cooperate with holders of
overlapping title.
Exploration Reporting – standard reporting requirements for exploration
activities on mineral properties.
The transfer of SML 20 to Heron required the negotiation of a security deposit and
lodgment timing with the Division of Resources and Energy. A security deposit
amount of A$3.577M was agreed based on the area of disturbance over the first
five years of operations with the lodgment of the bond required “prior to
commencement of any on ground activity”.
The Sydney to Canberra rail line passes through Tarago approximately 10km to
the east of the site. The daily train services offer several options each day to
connect with Sydney (three hours) and Canberra (one hour). A rail siding exists in
Tarago and historically was used to rail concentrates to smelters in Newcastle and
Port Kembla and to a concentrate berth at Port Kembla. This siding presents an
option to recommence railing concentrates for the new operations however costing
estimates to date have suggested lower road haulage costs to deliver concentrate
directly to the Port Kembla concentrate berth.
The major form of out-bound haulage is the transportation of the three base metal
concentrates to be produced by the Project. The road transport route from the
Project Site to Port is via Tarago-Bungendore Road (referred to as Bungendore
Road), Braidwood Road, the Hume Highway, then one of the following options:
Picton Road, Mount Ousley Road and Southern Freeway to the Port
Kembla Terminal (preferred option).
M5 Motorway and Foreshore Road to the Port Botany Terminal.
M7, M2, F3 and John Renshaw Drive, New England Highway, Pacific
Highway and Industrial Drive to the Port Newcastle Terminal.
An alternative haulage route was considered for the section of the haulage route
between the Project Site and Goulburn via Collector Road, Federal Highway and
the Hume Highway. However, this option requires significant road upgrades on
Collector Road between the Project Site and the Federal Highway. This route was
also not considered due to safety concerns regarding the road surface type and
road width along the route. The Collector Road / Federal Highway intersection
was also considered unsafe due to a lack of adequate storage space for large
vehicles turning right out of Collector Road onto the Federal Highway.
Aside from the concentrate haulage, connections with other local centres will be
required for in-bound resources and distances to key centres from the Woodlawn
Site:
Tarago 10.7km
Bungendore 32km
Goulburn 48km
Canberra 71km
Port Kembla 211km
Sydney 247km
Canberra International Airport, located 64km to the south, is the closest well
serviced airport to the Project. Given Canberra’s position as the political centre for
Australia, flight times and destinations are numerous.
As was the case for the previous operations, a key operating philosophy will be to
source the operational labour force from within the local community. Within a
55km radius of the site (being the estimated realistic limit for a daily commute)
there are in excess of 430,000 people, with the most likely sources of local labour
being the communities of Tarago (population 351, 2011 census), Bungendore
(population 3,553, 2011 census) and Goulburn (population 21,484, 2011 census).
Anecdotally, Goulburn currently appears to be the preferred residential location, as
was the case during previous mining operations.
5.2 Climate
The Woodlawn region has a cool temperate climate, with seasonal climatic
variations ranging from hot summers to cool winters. The average daily maximum
temperature ranges from 27.5ºC in January to 11.5ºC in July.
The nearest Bureau of Meteorology (BoM) rainfall station with long-term
continuous rainfall data is Lake Bathurst (Station 70036 - Somerton), which is
approximately 10km to the north-east of the Woodlawn Site. The station has
recorded data since 1931 up to the present. Monthly average rainfall is distributed
unevenly throughout the year with the summer and autumn months receiving the
highest rainfall. The mean annual rainfall at Lake Bathurst is 685mm.
Rainfall data at the Woodlawn Site is currently measured by Veolia and is available
from 1986 to date. The mean annual rainfall at the Woodlawn Site is 635mm.
Evaporation data is available from the Goulburn TAFE station. The annual
average pan evaporation is nearly twice the annual average rainfall.
5.3 Vegetation
The following has been taken from the 2012 Environmental Assessment (EA)
document compiled by Parsons Brinckerhoff.
The Project lies within the central part of the South Eastern Highlands Bioregion
which covers approximately 749,155 hectares (Thackway & Cresswell 1995).
Overall, the lower slopes and valleys of the locality have been largely cleared of
eucalypt woodlands for grazing and agriculture, with larger remaining areas of
native vegetation restricted to the hilly ridge line areas, or as roadside vegetation.
The nearest conservation reserve in the region is Morton National Park located
approximately 30km to the east.
Vegetation within the Project Site is highly fragmented with large expanses of
cleared land surrounding predominantly isolated remnants along the rocky ridges
and roadsides. Although some of the highly degraded remnant vegetation patches
are of sufficient size to maintain viable populations of some small endemic
mammals, amphibians and reptiles, they are likely to be of only limited biodiversity
value within the wider landscapes.
Five vegetation communities were identified within the ecological survey area
based on assessment of the dominant species and structural form:
The Hickory Wattle Low Open Forest and Black She-oak Low Open Forest
communities each occupy two small stands within the ecological survey area
located on the eastern side of the central rise that is geologically associated with
the sedimentary shale and outcropping sandstone.
The Hickory Wattle Low Open Forest community is predominantly an Acacia
falciformis regrowth community with very few (<5% canopy cover) remnant
eucalypts. The community has generally been highly modified by a history of
agricultural activities including clearing, grazing and pasture improvement.
The central remnant of the Black She-oak Low Open Forest community has been
significantly modified by earth movement associated with the Project Site and a
A total of 276 species of plant, representing 39 families, were recorded within the
ecological survey area, of which 218 (79%) were native. The number of species
recorded in each community is summarised in Table 5.2.
No threatened species of plant listed under the Threatened Species Conservation
Act 1995 (TSC Act) or the Commonwealth Environment Protection and Biodiversity
Conservation Act 1999 (EPBC Act) was recorded in the ecological survey area.
No Rare or Threatened Australian Plants (ROTAP) species was recorded.
Table 5.2: Number of species of plant recorded in the ecological survey area
discussions with Veolia and with external providers with a view to improving both
fixed line and wireless services across the site.
Access – The site is accessed through a network of well-maintained heavy
haulage rated, sealed roads. Refer to Section 5.1.
Labour – Woodlawn will be a “drive in / drive out” operation. A number of small,
medium and large communities exist within daily travel distances to the site and
will form the basis for the operational labour residential requirements. Community
services and infrastructure are somewhat limited in the local village of Tarago;
however, the towns of Bungendore and Goulburn provide a wide range of services.
Supplies – The proximity to industrial centres at Wollongong (including Port
Kembla) and Sydney provide a ready access point to source major consumables,
spare parts, equipment and service providers.
5.5 Physiography
The Woodlawn Project is located within the Woodlawn Eco-precinct along with the
Veolia Bioreactor and power station and the Infigen Woodlawn Wind Farm. The Eco-
precinct is located in a valley within the Great Dividing Range (GDR) which runs from the
south in Victoria to the north in Queensland.
Regional elevations within SML 20 vary from 1,000mRL at the headwaters of
Allianoyonga Creek on the northern boundary to 750mRL on the eastern boundary.
The Bioreactor is located in the old Woodlawn open pit, the surface of which lies at an
elevation of approximately 800mRL. The open pit was developed on a ridgeline that
forms part of the GDR. The Woodlawn Windfarm is located on the ridgeline to the south
of the Bioreactor at an elevation of 850mRL.
The GDR splits the site into two water catchments, the.
Sydney Catchment to the east, and
the Hawkesbury Nepean Catchment to the west.
The main water stream is Allianoyonga Creek and this is split by the GDR and runs
both to the west and into Lake George and to the east into Crisps’s Creek and
ultimately to the Mulwaree River.
6 History
The Woodlawn deposit was discovered in 1970 and mined by open-pit and
underground methods between 1978 and 1998. TriAusMin then acquired the
project and completed further studies and drilling programs through to 2013.
Heron merged with TriAusMin in August 2014 and has been conducting further
drilling programs for estimation of a revised Mineral Resource and a PEA, the
subject of this Report. Further details of the project history are provided in Table
6.1 below:
Table 6.1: Woodlawn Site History
Date Details
1985 Title transferred to Australian Mining and Smelting Ltd (AMS), a CRA
subsidiary. Commencement of the underground feasibility.
1991- Denehurst retreated 1.9Mt of tailings from Tailings Dam North and
1996 Tailings Dam South from a stand-alone concentrator with no re-grind
in the flow-sheet. The retreatment focused solely on the production
of a zinc concentrate.
Denehurst was placed into administration and receivership and the
1998
underground mine ceased production in March 1998. The
Date Details
underground mine produced in total approximately 5.8Mt @ 10.1%
Zn, 1.6% Cu, 4.1% Pb, 0.5g/t Au and 90 g/t Ag.
Total production for the deposit to this point was approximately
13.8Mt @ 9.1% Zn, 1.6% Cu, 3.6% Pb, 0.5 g/t Au and 74 g/t Au.
1999 Mineral rights to SML 20 acquired from Denehurst Administrator by
Tri Origin Australia NL. Collex (now Veolia Environmental Services
(Australia) Pty Ltd) purchased the landfill rights to the open pit.
2004 Tri Origin Minerals listed on the ASX. Woodlawn Bioreactor began
operation.
2010 Tri Origin Minerals listed on the TSX. Name subsequently changed
to TriAusMin Ltd.
The Goulburn Basin, together with the Hill End Trough, represents one of the
marine rift basins that opened across the Lachlan Orogen in the middle to late
Silurian under an extensional tectonic regime (Thomas & Pogson 2012).
Figure 7.1: Regional Geological Setting of the Woodlawn Project, within the
Goulburn Basin.
As part of McPhie’s (2015) work, a short traverse was completed along the
southeastern side of the Woodlawn open cut and provided a good overview of
some of the key geological units. Key observations are:
beds dip to the west at a moderate angle;
close to the northeastern end of the traverse, younging to the west is
indicated by graded beds (refer Figure 7.3), and
it is assumed that the traverse obliquely crossed progressively younger
units. However, no younging indicators were observed in the remainder of
the section, and this assumption could be wrong.
McPhie’s (2015) report further went on to break the units down into facies. The
facies are briefly described below:
Facies 1
Facies 1 is identified as pale, thinly planar bedded volcanic mudstone interbedded
with thin to medium tabular beds of quartz-crystal-rich sandstone. Some
sandstone beds are graded from coarse to fine (refer Figure 7.3).
Facies 2
Facies 2 is a poorly sorted breccia composed of grey, phyllosilicate-altered,
coarsely quartz-phyric rhyolite clasts approximately 4cm to15cm (refer Figure 7.4).
On surfaces parallel to cleavage, the rhyolite clasts have equant shapes and curvi-
planar margins (refer Figure 7.5, Figure 7.6) and on surfaces perpendicular to
cleavage, they are strongly elongate. The pale matrix consists of finer (<2cm)
quartz-phyric rhyolite clasts and is more siliceous than the coarse clasts. The
breccia is (at least locally) thickly bedded and contains interbeds of graded quartz-
crystal-rich sandstone (refer Figure 7.6). Where strongly altered, the rhyolite clast
outlines are masked and this facies has a much finer apparent grainsize (“tuff”).
Figure 7.5: Equant rhyolite clast with curviplanar margins, in the monomictic quartz-
phyric rhyolite breccia; viewed on a surface parallel to cleavage
Facies 3
Facies 3 contains massive quartz-phyric rhyolite that has coarse, euhedral or
rounded quartz phenocrysts evenly distributed in a fine sericite-altered
groundmass (refer Figure 7.7). Coarse quartz phenocrysts dispersed in dark
green-grey chloritic groundmass is observed and because this facies is strongly
altered, the porphyritic texture could be false.
Facies 4
Facies 4 is described as green-grey massive basalt / dolerite containing dark
green chlorite filled amygdales that are up to approximately 1cm in size (Figure
7.8). The amygdales are ovoid and weakly aligned. The groundmass around the
amygdales is equi-granular and fine-medium grained.
Figure 7.8: Massive amygdaloidal basalt / dolerite (amygdales are filled by dark
green chlorite).
Figure 7.9: Schematic section based on the Woodlawn Pit traverse. The section was
not measured but the approximate thickness is in the range of several tens of metres
to possibly 150 m. The younging direction is not confidently known but is generally
considered to be younging up the section.
7.4 Mineralisation
The Woodlawn deposit occurs in Silurian felsic volcanic rocks, volcanogenic
sediments and carbonaceous shales intruded by doleritic sills. It is considered to
be part of suite of Volcanic-hosted Massive Sulphide (VMS) deposits formed along
the eastern coast of Australia in the Paleozoic (240 to 540 Ma) (Gemmell et al
1998). Other significant VMS deposits in this suite include Mt Lyell, Rosebery, and
Hellyer in Tasmania, Stockmans in eastern Victoria, Captains Flat in NSW and Mt
Morgan and Thalanga in Queensland.
These VMS deposits tend to form in back-arc and inter-arc volcanic basins in
proximity to rift faults and host rocks range in composition from rhyolite-andesite to
basalt. Rhyolitic rocks are the common on the footwall while sediments and/or
mafic volcanics are the most common hangingwall types.
The Woodlawn deposit was extensively studied during the twenty years from its
discovery in 1968, with these studies culminating and to a large extent being
synthesised in a PhD study by W.J. McKay in 1989, with the major findings
published in an Economic Geology paper by McKay and Hazeldene (1987). Since
this time there has been little published work completed apart from a paper by Glen
et al (1995) who describe the syn- and post-tectonic mineralisation styles at
Woodlawn.
McKay (1989) and those who came before him were largely focused on the
mineralisation exposed in the open-pit and they had limited or no access to the
underground mineralisation exposed from 1987 onwards. Nevertheless, the
studies undertaken up until 1989 provide a solid foundation for the ongoing
understanding of the deposit.
McKay and Hazeldene (1987) recognised two main styles of mineralisation:
poly-metallic “complex ore” (sphalerite, galena and chalcopyrite); and
footwall stockwork chalcopyrite-rich “copper stringer ore”.
They described the deposit as forming essentially on the sea floor as mounds of
chalcopyrite and pyrite capped by massive sphalerite-galena sulphides. The main
lenses of poly-metallic massive sulphides comprise pyrite with variable sphalerite,
galena and chalcopyrite with minor arsenopyrite, tetrahedrite-tennantite, pyrrhotite,
marcasite and electrum.
Beneath the mounds is a network of fossil feeder channels that comprise the
copper stringer ore. The copper stringer ore is a network of fracture filling
assemblages of pyrite and chalcopyrite with subordinate to minor sphalerite,
galena, pyrrhotite, quartz, calcite, chlorite and barite.
The depositional history of the main Woodlawn lens (C Lens) is divided by McKay
and Hazeldene (1987) into three stages:
1. Precipitation and deposition of pyrite-chalcopyrite from early, hot, silica-rich
metalliferous solutions mixing with seawater to form sulphide mounds
adjacent to exhalative vents.
2. Deposition of sphalerite and galena in basinal lows north of the mounds
from cooler, fractionated, negatively buoyant ore solutions.
3. On-lapping sedimentation of sulphides over mounds choking off venting ore
solutions followed by sub-surface hydrothermal and diffusion of solutions
through unconsolidated sulphides to form zinc-lead rich chimney structures
above and to the north of the chalcopyrite mounds.
However, the important paper by Glen et al (1995) showed there are some
significant flaws in the mineralisation model described by McKay and Hazeldene
(1987) and they demonstrate the importance of ore-types related to and probably
emplaced as part of the Devonian deformation events. Relationships of the ore in
parts of the A Lens show the ore is structurally controlled and that it overprints an
earlier layered sphalerite-chert rock. Glen et al (1995) concluded that the ore at
Woodlawn is a composite of pre-, syn- and post-deformational type.
Recent studies (for example, McPhie, 2015) have also shown the original
Woodlawn massive sulphides, at least in part, probably formed sub ocean floor
with broad zones of hydrothermal chlorite, sericite and pyrite alteration extending
from both the hangingwall and footwall sides of the sulphide lenses.
Figure 7.10: Copper stringer and polymetallic massive sulphide mineralisation from
WLTD015 Kate Lens “discovery hole”, 396 to 409m with assay results
8 Deposit Types
8.1 Volcanic Massive Sulphide Deposit Model
The Palaeozoic VMS deposits of Australia have been extensively studied and a
coherent geological model has been developed. The following is adapted from a
summary of the Australian Palaeozoic VMS systems by Gemmell et al 1998.
Figure 8.1 shows a highly schematic cross section through a Palaeozoic VMS
system.
Deposit Examples:
Eastern Australia: Hellyer, Rosebery, Que River, Hercules, Mt Lyell, Woodlawn,
Thalanga, Wilga, Currawong, Balcooma, Mt Chalmers.
Other major examples include deposits from the Japanese Green Tuff belt (Kuroko
deposits), Norwegian Caledonides and Canadian Bathurst Group, New Brunswick.
Typical Size and Metal Content:
Major deposit size: 15Mt to 90Mt.
Median deposit size: 1Mt to 5Mt.
Average grade for Cu / Pb / Zn deposits: 1.0% Cu, 12% Zn, 5% Pb.
High Ag and Au credits: average 120g/t Ag and 2.0g/t Au.
Mining and Treatment:
Massive sulphide style limits dilution effect with sharp cut-off between ore
and waste.
Stringer zones are only mined where they are high-grade or large tonnage
(e.g. Mt Lyell).
Polymetallic nature may cause recovery problems in fine grained ores.
Metamorphosed - recrystallised ores are easier to treat.
Fe content of sphalerite is moderate to high.
Pyrite content is generally high.
Regional Geological Criteria:
Back-arc and inter-arc rift volcanic basins.
Preferred ages: Cambro-Ordovician and Silurian.
Calc-alkaline submarine volcanics and sediments.
Compositional variation: rhyolite-andesite-basalt.
Proximity to syn-volcanic rift faults.
Located proximal to volcanic centres (Cu -rich ores) or in distal volcanic
facies (Pb / Zn-rich ores).
Syn-volcanic magnetite-series granites may be present.
Rhyolite is most common footwall composition.
Sediment and / or mafic volcanics are most common hanging-wall rock
types.
Regional sericite ± chlorite alteration in footwall volcanics.
Local Geological Criteria:
Mineralisation located in favorable horizon between volcanic units.
Favorable horizon may be iron-rich exhalite, sulphide bearing epiclastic,
shale or carbonate.
Figure 8.1: Cross section through typical Palaeozoic VMS system of Eastern
Australia (after Gemmell et al 1998).
9 Exploration
This section describes the history of exploration completed at Woodlawn since its
discovery in the late 1960s. The first section has been adapted from a report
written by M. Bouffler in 1998 which summarised the exploration on SML 20 to the
end of 1997.
Table 9.1: Details of significant drill intercepts from 2009 to 2013 TriAusMin
campaigns
Down Estimate
hole Lens True
Hole No From (m) To (m) Zn (%) Cu (%) Pb (%) Au (g/t) Ag (g/t)
Width Width
(m) (m)
WLTD004B 398.5 406.6 8.1 C 6.5 0.4 2.8 0.1 0.2 12.6
WLTD004B 438.9 446.2 7.3 C 5.8 12.3 1.7 4.9 2.3 171.0
WLTD005 353.0 371.0 18.0 A 14.4 11.5 0.7 4.7 0.6 87.7
WLTD005 417.0 432.0 15.0 B 12.0 7.6 1.7 3.5 0.2 89.2
WLTD011 517.8 520.0 2.2 I 1.8 4.7 0.2 2.5 1.4 31.5
WLTD011 542.2 552.1 9.9 I6 7.9 6.1 1.6 1.2 0.7 14.1
WLTD011 849.0 853.0 4.0 D1 3.2 0.1 3.3 0.0 0.0 12.8
WLTD011 869.0 881.1 12.1 D2 9.7 0.1 4.8 0.0 0.1 14.9
WLTD011W1 551.0 565.5 14.5 I6 11.6 11.7 3.7 3.7 1.9 120.8
WLTD011W1 630.2 638.5 8.3 D1 6.6 5.6 1.7 1.6 2.6 48.0
WLTD011W1 696.6 708.0 11.4 D2 9.1 7.8 1.2 2.7 0.6 49.3
WLTD011W2 564.0 573.0 9.0 I6 7.2 8.6 2.9 4.6 2.1 167.3
WLTD011W2 648.0 656.9 8.9 D1 7.1 6.3 2.7 3.0 1.2 71.1
WLTD012 804.0 808.0 4.0 JC 3.2 0.1 3.1 0.0 0.0 8.1
WLTD014W1 543.0 549.7 6.7 IC 5.4 0.1 3.4 0.0 0.2 6.2
WLTD014W1 674.9 686.0 11.1 D2 8.9 8.3 0.9 3.6 0.5 61.2
WLTD015 377.0 409.0 32.0 Kate 25.6 4.6 1.8 1.2 0.6 21.2
WLTD017W1 450.0 453.2 3.1 I 2.5 3.3 0.4 2.0 3.0 34.7
Notes: True width is an estimate of the actual thickness of the intercept based on interpreted lens orientation (approximately
80% of down hole width); grades are weighted average grades, weighted by length of samples intervals down hole, which
are nominally 1 metre. No weighting was applied for differences in specific gravity.
Down Estimate
hole True
Hole No From (m) To (m) Lens Zn(%) Cu(%) Pb(%) Au(g/t) Ag(g/t)
Width Width
(m) (m)
WNDD0001 373.6 388.0 14.4 Kate 11.5 4.6 4.1 0.8 1.0 56.8
WNDD0002 368.0 370.3 2.3 Kate 1.9 12.0 0.6 5.4 1.3 116.0
WNDD0002 374.0 382.7 8.7 Kate 7.2 12.6 1.6 7.5 2.3 152.0
WNDD0006 626.1 631.8 5.7 I 4.5 13.3 0.7 5.4 1.2 25.9
WNDD0006 679.0 683.0 4.0 I 3.2 4.8 0.5 0.2 0.0 14.5
WNDD0006 699.4 707.4 8.0 D 6.5 3.0 2.3 3.1 2.6 68.8
WNDD0006 759.0 769.0 10.0 D 8.0 1.6 1.7 0.2 0.2 15.3
WNDD0007 414.3 426.6 12.3 Kate 9.8 20.0 2.1 6.1 0.8 52.9
WNDD0007 434.7 437.1 2.4 Kate 1.9 20.1 1.6 4.2 2.1 39.7
WNDD0008 434.0 439.4 5.4 Kate 4.3 11.1 1.6 0.8 0.6 11.4
WNDD0009 198.0 214.8 16.8 G 8.9 5.4 2.7 2.0 1.2 48.5
WNDD0009 308.7 316.8 8.1 Kate 6.5 7.2 1.1 2.3 0.9 28.0
WNDD0010 206.0 210.4 4.4 G 3.5 4.1 3.2 0.9 2.6 39.0
WNDD0010 353.0 354.0 1.0 Kate (Cu) 0.8 0.0 1.6 0.0 0.0 1.1
WNDD0010 360.0 361.1 1.1 Kate (Cu) 0.8 0.1 1.6 0.0 0.2 4.5
WNDD0010 365.0 366.0 1.0 Kate (Cu) 0.8 0.1 1.6 0.0 0.0 3.5
WNDD0011 348.2 354.1 5.9 Kate 4.7 6.3 3.2 1.7 1.3 73.5
WNDD0012 74.0 79.8 5.8 G 4.6 3.6 0.7 1.5 1.0 60.4
WNDD0012 135.1 139.3 4.2 E 3.4 14.8 2.2 6.2 0.7 37.2
WNDD0013 76.2 85.6 9.4 G 5.6 6.4 3.2 2.8 2.4 150.0
WNDD0014 61.2 63.3 2.1 G 1.7 3.1 6.5 1.3 1.2 146.0
WNDD0015 241.9 246.2 4.3 Lisa 3.4 17.7 1.6 5.0 1.1 28.0
WNDD0016 429.0 446.0 7.0 Kate (Cu) 13.6 0.1 1.8 0.0 0.1 2.9
WNDD0017 254.1 263.6 9.5 D 7.6 3.8 1.6 0.3 0.8 16.9
WNRC0010 37.0 45.0 8.0 G 6.4 3.6 1.3 2.6 1.0 65.4
Notes: True width is an estimate of the actual thickness of the intercept based on interpreted lens orientation (approximately
80% of down hole width); grades are weighted average grades, weighted by length of samples intervals down hole, which
are nominally 1 metre. No weighting was applied for differences in specific gravity.
The focus of the Heron drilling has been to delineate the Kate Lens and better
define the lenses in shallow positions, to provide drilling input into a revised Mineral
Resource estimate. Of the 20 diamond holes drilled in this first phase program,
some 14 intersected significant massive sulphide mineralisation, often in multiple
lenses. A brief description of each of the targets is provided below.
Kate Lens
Ten of the Heron diamond holes targeted the Kate Lens to follow-up the discovery
hole WLTD015, drilled by TriAusMin in 2013. The drill pattern was designed on
nominal 40m by 40m spacing and is shown in Figures 9.1 and 9.2, which also
show the modelled EM plate that proved to be a reliable guide to the zone of
massive sulphides. The highest grade mineralisation is towards the centre of the
lens (holes WLTD015 and WNDD0007) and becomes more copper dominated and
semi-massive towards the south in holes WNDD0010 and WNDD0016. To the
north the mineralisation becomes off-set and wrapped into the 790 fault system
(WNDD0011), and then weakens to a minor zone of sulphides in WNDD0018
where it is closed off.
While the Kate Lens has been closed in certain directions through the current
drilling, a number of positions still provide extensional possibilities. For example,
the position above and to the north of WNDD0009 where Drill-hole Electro-
magnetic (DHEM) survey modelling suggests further extensions, and in the area
below WNDD0007 and WNDD0016 where the lens is not closed off. There is
potential to find further extensions of the Kate Lens in the down plunge area to the
north where little drilling has been undertaken.
I Lens
Three diamond drill holes were drilled into the I Lens position (refer to Figure 9.3),
with WNDD0004 and WNDD0005 drilled in the up-dip position and WNDD0006
drilled in the down-plunge position. WNDD0004 and WNDD0005 intersected only
minor sulphides in the expected position of the lens, however from DHEM
modelling it appears the main lens passes between the two holes, which suggests
only a modest size potential. WNDD0006 intersected the down plunge position of
the lens.
G Lens
Five drill holes intersected the G Lens position; one RC hole (WNRC0010) and the
four diamond drill holes (WNDD00009, WNDD0010, WNDD0013 and WNDD0014),
as shown in Figure 9.4. The results confirmed the high-grade nature of the lens
and the intercept in WNDD009 has shown the potential for thicker zones of
mineralisation in what is thought to be a keel shaped structure towards the centre
of the lens.
Lisa Lens
Two diamond drill holes (WNDD0015 and WNDD0017) were drilled to test along
strike from two historical holes which recorded copper-rich intercepts in the
stratigraphic plane of the I Lens (Figure 9.3). The historical holes recorded:
W089: 4.0m at 4.9% Zn, 2.8% Cu, 2.3% Pb, 0.8g/t Au and 25g/t Ag from
266m depth, and
W145: 4.0m at 2.0% Cu from 234m depth.
Drill hole WNDD0015 intersected a zone of high-grade poly-metallic mineralisation
to the north of these historic results and indicated the potential for new lens in this
position.
Drill hole WNDD0017 was drilled in the up-plunge position of this intercept,
however the lens had apparently been intruded by a large volume of late stage
dolerite and no massive sulphides were intersected.
The Lisa Lens, while relatively narrow, represents the discovery of a new high-
grade lens and further drilling will be planned to delineate it. DHEM surveys of
WNDD0017 have shown the presence of a strong conductor down-plunge and
slightly to the north of this drill hole, and this provides an immediate target for
future drilling to extend and delineate the Lens.
D Lens
The D Lens was intersected in holes WNDD0006 and WNDD0017 in the down-
plunge position of the lens.
The D Lens was not a high priority for the Heron drilling program, however the
holes that did intersect it were in line with previous drilling indicating generally
broad zones of lower grade, and relatively more copper-rich material.
E Lens
Like the D Lens, the E Lens was not a high priority for the Phase 1 drill program,
however, a strong off-hole conductor modelled from WNRC0010 provided a robust
target that was tested by WNDD0012, which returned a high grade polymetallic
result.
This result allowed a more solid interpretation and connection of the E Lens up-dip,
providing greater certainty to the interpretation and additional mineralised tonnages
in this position.
A Lens
The up-dip A Lens was targeted by the early round of RC drilling (WNRC0001 to
WNRC0005), but failed to intersect any significant massive sulphide positions.
With the lack of DHEM targets from these holes, it would appear the lens is mostly
pinching out in the up-dip position. Drill holes WNDD0007 and WNDD0009 were
extended into the footwall of the Kate Lens into the potential down-plunge position
of the A Lens; however, no significant sulphides were intersected. A weak off-hole
EM response was returned from WNDD0009 and may be indicative of minor
massive sulphide lens in the down-plunge of the A Lens, but is not at this stage a
priority target.
Other Lenses
The B, C, F and H Lenses were not targeted as part of this program. All of these
lenses have good potential for down plunge extensions; however, the deeper
targets, particularly on the B Lens, were not considered a target in the current
round of drilling, with focus being on expanding the resource base in the top 500m
of the system.
Figure 9.1 Woodlawn Oblique Cross-Section looking north (top) and Figure 9.2
Woodlawn Long-section looking east in the plane of the Kate Lens (bottom).
The Currawang East deposit, located some 10km north northwest of the Woodlawn
mine, was discovered directly to the east of the old Currawang copper mine. The
Currawang copper mine was first mined in the late 1800s and in 1973 Jododex
completed surface geochemical surveys. The deposit is made up of a discrete
“pod” of massive sulphides hosted within Currawang Basalt rocks (~80%) and
Woodlawn felsic volcanic rocks (20%) positioned some 100m below the surface. It
was accessed via a decline near the old Currawang workings and was mined
between 1991 and 1995 with some 553,000t being extracted at grades of
approximately 13% Zn, 2.2% Pb, 1.6% Cu and 33g/t Ag (Bouffler, 1998). The
extracted amount was roughly in line with original estimated mineable tonnage.
The Cowley Hills deposit, located some two kilometres directly north of the
Woodlawn mine was discovered by Jododex through shallow geochemical drilling
in 1982. Like Currawang East, the mineralisation at Cowley Hills consists of a
discrete “pod” of massive sulphides hosted mostly within Woodlawn volcanic rocks,
but in close proximity to Currawang basalt units (basalt and dolerite). A small
mineable deposit was outlined with mining being undertaken between 1989 and
1991 via a short underground decline, although it is reported only some 25,000t
were extracted (Bouffler 1998).
Like Currawang East, the Cowley Hills prospect provides an immediate exploration
target in close proximity to the Woodlawn mine. Again modern EM surveys will be
employed to fast track drill hole targeting.
The Cullarin JV Project (EL7954) is located 45km north of Woodlawn (Figure 4.1)
and covers the northern extent of the prospective Silurian felsic volcanic sequence.
Heron has earned a 78.9% interest in the project and Golden Cross Resources Ltd
(GCR) has 21.1% interest and is currently diluting its interest while Heron manages
and funds the exploration work.
The project area has demonstrated potential for VMS type deposits, intrusive
related porphyry deposits and associated skarns. Drilling by previous explorers
within the joint venture area has identified several high priority prospects where
potentially ore-grade intercepts have been reported. The tenement covers a 28km
long belt of well-mineralised north-south trending Silurian felsic sediments and
volcaniclastics fault bounded on the east by the Lake George Fault and the Cullarin
Fault on the west. EL7954 covers over 30 mineral occurrences that span an array
of mineral deposit styles, many of which were former producing mines. Prospects
include the Gurrundah barite (stratiform with VMS affinities) deposit, the Wet
10 Woodlawn Drilling
The Woodlawn deposit has, and continues to be, delineated and quantified through
drill hole information. This section describes the drilling that has been undertaken
to define the Woodlawn mineralisation, with particular focus on the more recent
drilling undertaken by Heron.
The following tabulation is of the drill holes at Woodlawn that are in or close to the
Woodlawn Underground Project area (refer Table 10.1). They include holes drilled
above, in, or through the open cut, but exclude holes drilled at the nearby satellite
Currawang and Cowley Hills deposits. Table 10.1 is approximately chronological,
and therefore commences with initial exploration drilling, proceeds through mine
operation (thus includes mine development drilling), and then covers the more
recent exploration drilling after the mine closed.
Table 10.1: Listing of drilling programs and drill hole numbers completed at
Woodlawn (recent drilling by Heron is included here for completeness).
Total Hole
Hole ID
metres Purpose Company Year Type
Woodlawn discovery
W001-W050
12,332 drilling Jododex 1969-71 DDH
W201-W286 11,655 Resource drilling Jododex 1971-72 DDH
Resource drilling
W051-W069
6,806 Underground potential Jododex 1971-79 DDH
Underground potential &
W070-089
10,632 Exploration Jododex 1980-81 DDH
W287-290 590 Resource drilling Jododex 1984 DDH
W090-W166 30,603 Woodlawn Underground AMS 1981-88 DDH
Woodlawn Underground
U001-U190
21,478 Feasibility AMS 1985-88 UDD
U194-U469 30,252 Woodlawn Underground Denehurst 1988-96 UDD
W167-W199 8,252 Woodlawn Underground Denehurst 1988-93 DDH
W300-314 4,264 Exploration Denehurst 1995-96 DDH
WLRC001-026 828 Exploration Tri Origin 2005 RC
WWTD001 232 Underground Hydrology Tri Origin 2007 DDH
Underground Met /
WLTD004-005
1,138 Geotech Tri Origin 2007-08 DDH
Underground Portal
EPBH001-005
222 Geotech Tri Origin 2007 DDH
Underground Decline
EDBH001-004
504 Geotech Tri Origin 2008 DDH
WLTD009-010 3,951 Exploration Tri Origin 2010 DDH
WLTD011-12 3,693 Exploration TriAusMin 2012 DDH
WLTD013-17 4,039 Exploration TriAusMin 2013 DDH
WNDD0001-0020 7,668 Resource / Met Heron 2014/201 DDH
Total Hole
Hole ID
metres Purpose Company Year Type
5
2014/201
WNGT0001-12
770 Geotech Heron 5 DDH
WNRC0001-11 1,147 Resource drilling Heron 2014 RC
Hole planning is undertaken by the Senior Geologists. The recent Heron program
has been designed to provide a reasonable coverage of specific lenses to provide
Inferred Mineral Resources for input into the PEA Study.
The holes are designed in standard 3D mining software. A handheld GPS is used
to site the collar positions and the collars are “picked up” by a licensed surveyor
after the holes had been completed.
The azimuth of the holes is determined by setting the rig up on magnetic
declination using a sighting compass. The sighting compass has an accuracy of
±1 degree. A north seeking gyroscopic tool was used to align the rigs in early part
of the program and had an accuracy of <0.05 degrees.
The holes are surveyed during drilling for dip and azimuth every 30m down hole
using a Pathfinder digital camera that records the dip and magnetic azimuth of the
hole. At the end of hole, an end of hole gyro survey was carried out using either:
1. a non-north seeking gyroscopic tool (IsGyro) operated inside the drill rods by
a suitably trained driller before moving the drill rig off the drill site; or
2. a north seeking gyroscopic tool (Keeper Gyro) operated inside 50mm PVC
casing inserted into the hole after removing the drill rods and drill rig from the
site, by a licenced operator (J. Buchannan from Gyro Australia Pty Ltd).
A comparison between the IsGyro down hole survey data to the Pathfinder survey
found predominately good correlation with minimum offset. Drill hole WNDD0007
was an exception, showing discrepancies between the two sets of data and a
decision was made to use Pathfinder results. A comparison between the Pathfinder
camera readings and the Keeper gyroscope readings showed very little to no
spatial offset of the drill hole trace. Figure 10.1 is an example of the correlation
between the two survey methods showing the spatial offset for drill hole
WNDD0018 (approximately 5m).
Figure 10.1: WNDD0018 comparison of Pathfinder vs Keeper Gyro down hole survey
readings
Each one metre sample is sieved and laid out in plastic chip-trays where they were
geologically logged on the drill site by the rig geologist. The geological logs were
entered directly into a spreadsheet at the drill site using Heron’s standard logging
template and codes.
All diamond core is stored in standard plastic core trays and the core trays are laid
out on trestles for logging by qualified geologist. The general logging procedure is
as follows:
The core is laid out in core trays on trestles and marked up with metre marks
and core orientation line (indicating the bottom of the hole from the known
orientation marks) and wetted down to get an overview of the lithology,
alteration and major features. The key observed changes are marked with a
yellow chinagraph pencil and the depth recorded. Significant mineralisation is
marked with a red chinagraph. After all marking out is completed, starting
from the top of the hole, the geologist will record the lithology and defining
characteristics into a set of standard excel templates using a laptop computer.
A handheld XRF Niton instrument is used to record titanium / zirconium ratios
and other elemental levels to assist the geologist with rock type identifications
(such as distinguishing siderite from low-iron sphalerite, tarnished pyrite from
chalcopyrite).
Alteration, recorded separately to lithology, records the effect of hydrothermal
alteration on the primary lithology. The alteration minerals are recorded in
descending order of alteration intensity, for example, strong and pervasive
alteration listed before weak and patchy. A “whole of rock” alteration is also
recorded to provide an alteration grouping and an estimation of the overall
destruction of primary features.
Sulphide minerals of hydrothermal origin are recorded with an estimate of
contained percentage over the whole logging interval. Generally only sulphide
bands greater than 5cm are recorded as a separate interval.
Veins that are larger than 10cm or encompass a significant percentage over
an interval (i.e. 50% quartz-carbonate veins within a section of mafic intrusive)
are recorded as a lithology type. All veins greater than 2cm are recorded in
the veins worksheet;
Point structures are recorded in a separate worksheet for geological features
that have a single point measurement, such as a foliation or geological
contact. Another worksheet, records geological features that extend over an
interval, such as a shear zone or fault gouge.
A kinometer is used to measure the angle of a point structure to the core axis
and these measurements (alpha and beta angles) are recorded.
All logging data is forwarded to Heron’s DBA on a daily basis for final
verification and then entry into the database.
differences being:
RC samples did not need to be crushed because the particle size was
small enough to go through the pulveriser.
RC sample drying time were generally longer (up to two to four hours).
RC samples larger than 3.2kg were riffle split. The riffle splitter was a
stainless steel unit with riffles set to 50:50 left / right tray splitting. For
large work orders, a preparation duplicate was collected at frequency of 1
in 50 samples. The preparation duplicates were assigned a PREP DUP
suffix and assayed along with the original samples. These values were
reported on the final Certificate of Analysis (COA).
Heron senior geological staff conducted three site visits to ALS Orange during the
course of the 2014-2015 drilling to review laboratory procedures and report on
outcomes. These reviews resulted in minor refinements to sample preparation
procedures, mainly in dealing with very high grade samples. In one instance, the
first diamond hole WNDD0001, QAQC assessment required re-sampling of the
entire batch due to smearing detected during sample preparation. All subsequent
sample preparation employed additional quartz flushes to eliminate this issue.
Blank material used for the TriAusMin programe consisted of builders’ cement
aggregate pre-mix (BLANK_AGG). The majority of the cement aggregate blank
samples assayed during the drilling campaign reported within acceptable limits.
Blank material used during the Heron QAQC procedure consisted of Sydney sands
(BLANK_SS). A total of 60 blank standards were submitted during the Heron 2014
to 2015 drilling program. The majority of the blank control standards assayed
during the drilling campaign reported within acceptable limits.
The first batch of Heron samples, relating to hole number WNDD0001, was re-
sampled and re-analysed as a result of contamination evident in the blind blanks
included with the mineralised samples (third sample in graph). A total of 17 blank
aggregate samples were submitted to the laboratory during TriAusMin drilling
program in 2013. Similar issues were identified with the TriAusMin QAQC blank
aggregate and a re-assay program was undertaken.
Figures 11.1 to 11.5 show the results for the Heron blank material for Zn, Cu, Pb,
Au, and Ag. The high levels displayed for the third sample are related to the issue
in WNDD0001. As can be seen from the plots this issue was largely controlled in
subsequent batches through the insertion of quartz flushes (not used in the first
batch) after massive sulphide samples. Weakly anomalous Au values for blanks in
fire assayed Au analysis are related to laboratory precision for the chosen assay
method. Heron specified a “mine grade” fire assay method to be used for all
samples, rather than a low level geochemical assay typical in greenfields
exploration projects.
GEOSTAT Cu/Zn
GBM907-14 HERON 2014 6 6 1 sulphide ore
GEOSTAT
Zn/Cu/Pb/Ag massive
GBM909-12 HERON 2014 9 9 0 sulphide ore
GEOSTAT
Zn/Cu/Pb/Ag sulphide
GBM911-11 HERON 2014 12 12 0 ore
Total 183 178 34
The accepted threshold set for the project was ±2 Standard Deviations from the
mean. Results for standards submitted by Heron were generally within acceptable
ranges. The highest discrepancy for copper being -1.97% and gold -5.26% outside
the two standard deviation range. Figures 11.6 to Figure 11.14 are examples of
standard results for 2014 to 2015 drilling campaign.
Figure 11.20: Correlation Plot for Zn Original vs Lab Duplicate Check Analysis
Figure 11.21: Correlation Plot for Cu Original vs Lab Duplicate Check Analysis
Figure 11.22: Correlation Plot for Pb Original vs Lab Duplicate Check Analysis
Figure 11.23: Correlation Plot for Ag Original vs Lab Duplicate Check Analysis
Field Duplicates
A total of 16 core field duplicate and 12 RC field duplicate samples were submitted
to the laboratory during the TriAusMin 2013 diamond drilling program and Heron
2014 RC program. A comparison of the RC field duplicates to original assay
results showed good repeatability for levels below 0.3% Zn. However, for the
higher levels, repeatability is considered to be poor for two of the three samples
recorded (Figure 11.24). Due to the limited number of samples involved it is not
possible to identify the source of the poor repeatability. As RC samples from these
programs currently make up substantially less than 1% of the assays used in the
resource model there is limited risk of any adverse effects in the resource estimate.
If further RC drilling is planned a more detailed duplicate program will be
developed.
On a regular basis, the logging geologist provides the DBA with completed field
data capture templates which are then imported into the Heronv3 database.
Collar survey pickups and down hole survey pickups are electronically supplied by
survey contractors in text file format. The files are imported into the Heronv3
database by the DBA.
Sample Information, including QAQC and density data, are captured in Excel
templates by field technicians. The Sample Submissions are electronically
completed by the field technician and checked by the Senior Geologist. The
Sample Submission is sent to the respective laboratories in both electronic and
hard copy form with the dispatched samples. Completed sample information and
sample submission files are electronically sent to the DBA to import into the
Heronv3 database.
Assay laboratory files are electronically supplied directly to the DBA and Project
Geologists in sif and text file format. For each laboratory a data entry import object
has been designed to capture all assay data information specific to that
laboratory’s format. The sif file format is used to import assay data into Heronv3
database by the DBA. During import, a QAQC summary report is generated and
forwarded to the Project Geologist who will decide whether to accept or reject the
file. On acceptance of the file, the data are used populate the batch, assay and
QAQC tables in the database.
The drill hole plod information is manually entered daily into the Heronv3 database.
The drill hole plods are electronically scanned and saved to the Perth server for
future reference.
Core tray and field photos are provided to the DBA electronically and saved to the
Perth Heron server for future reference.
showed an overall good correlation between the original results and duplicate
check assays.
Composites were prepared from underground core drilling to represent the two
main mineralised types (zinc-copper mineralisation with high precious metals and
copper rich mineralisation). These have been tested individually as well as in
50:50 blends with the tailings composite from TDS used the 2011-12 testwork.
The tailings composite had been in frozen storage since that work to minimise
potential oxidisation. Similarly, drill core was frozen as soon as practical after
logging and sawing. Half NQ core was used for the metallurgy testwork. In limited
cases, quarter core has been used where a second quarter of the drill core was
required for resources estimation QA/QC. Variability testing was also conducted
on separate drill hole intersection composites to ensure the developed flowsheet is
appropriate to process feed from different lenses and areas.
The head grades of the three main composites used in this testwork are set out in
Table 13.1.
Table 13.1: Summary of main testwork composites
Zinc-Copper
1.6 4.8 9.9 101
Mineralisation
Copper Rich
3.0 0.2 1.3 24
Mineralisation
Reclaimed
0.4 1.1 2.3 27
Tailings
13.3.2 Results
Results from the metallurgical tests were published in a Heron ASX announcement
on 11 February 2015 and are summarised in Table 13.2, Table 13.3, and Table
13.4.
Table 13.2: Preliminary flotation results for the zinc-copper mineralisation sample
(bracketed numbers represent typical recoveries achieved during previous
operations at Woodlawn, c. 1992).
Assays % Recoveries
%
Weight g/t
% Cu % Pb % Zn g/t Ag Cu Pb Zn Ag Au
Au
Copper 4.4 25.4 5.5 2.1 227 5.8 70.8 5.0 0.9 9.9 13
Concentrate
(5.4) (22.0) (4.1) (4.9) (260) (68.0) (5.5) (2.6) (16.3)
Lead 6.5 2.3 53.2 6.0 813 14.1 9.2 71.1 3.9 51.8 46
Concentrate
(5.9) (1.0) (36.9) (19.7) (387) (3.4) (53.5) (11.7) (26.8)
Zinc 14.2 0.5 2.8 45.0 99 0.8 4.4 8.1 79.5 13.9 6
Concentrate
(14.3) (0.5) (1.9) (50.8) (80) (4.2) (6.6) (73.0) (13.4)
%
Assays % Recoveries
Weight
% Cu % Pb % Zn g/t Ag Cu Pb Zn Ag
Rougher
12.4 19.8 0.7 1.2 71 81.7 43.5 12.1 26.5
Concentrate
Cu
9.8 24.0 0.7 1.1 69 71.8 34.1 8.5 28.2
Concentrate
Table 13.4: Preliminary flotation result for combined zinc-copper and tailings blend
Assays % Recoveries
%
Weight
% Cu % Pb % Zn g/t Ag g/t Au Cu Pb Zn Ag Au
Cu
2.9 23.6 3.7 1.6 180 3.4 66.1 3.6 0.7 7.6 10
Concentrate
Pb predicted
4.3 3.9 49.0 7.1 878 9.4 16.0 69.0 4.4 54.1 43
Concentrate
Zn predicted
10.4 0.5 1.5 45.0 99 0.7 5.4 5.3 73.9 15.2 7
Concentrate
The PEA design criteria has been based on the results set out in Table 13.4
above, taking into account that the circuit is adaptable to the processing of
reclaimed tailings only until production of feed from underground is achieved. The
required circuit changes will be achieved by the re-routing of piping.
Tailings only results generated in the FEED study are set out in Table 13.5.
Table 13.5: Flotation result for tailings
Assays % Recoveries
%
Weight
% Cu % Pb % Zn g/t Ag Cu Pb Zn Ag
13.3.3 Comminution
Comminution is used generally for the liberation of particular minerals from each
other and from gangue. During the 2014 testwork program it was confirmed that
some of the Woodlawn minerals had significantly higher flotation kinetics than
others. Supported by mineralogy this led to a change in comminution approach. A
relatively coarse grind ahead of the talc and copper rougher flotation enabled the
fast floating copper minerals to be recovered into a copper concentrate with little
gangue or other valuable minerals except those locked in composite particles.
Regrinding of the copper rougher concentrate to liberate the non-copper composite
particles resulted in higher grade copper concentrate at improved recoveries. This
change in comminution strategy was carried forward to the lead circuit where using
a similar approach increased lead concentrate grades significantly.
Similarly the talc cleaner concentrate tailing was shown to contain little copper
mineralisation allowing the talc cleaner tailings to go straight to the lead circuit.
The blending of reclaimed former tailings still applied the FEED study comminution
of regrinding this material (that was devoid of the fast floating mineralisation sent to
concentrates in previous operations) to 80% passing 30µm. Products from the two
separate grinding stages were blended ahead of flotation.
The plant design will therefore incorporate feeding crushed ROM material to a ball
mill grinding circuit operating in closed circuit with hydrocyclones to produce a
fresh underground feed sizing to flotation of P80 75µm.
Conventional Bond work indices and abrasion indices on the testwork composites
confirm the underground plant feed material to be relatively soft as shown in Table
13.6.
Table 13.6: Summary of comminution testwork
Tailings from the original Tailings Storage Facilities will be reclaimed by hydraulic
mining to a thickener. Thickened tailings will feed an IsaMill where they will be
ground to a P80 30µm and combined with the fresh ground underground material to
feed the flotation circuit.
As in the previous Woodlawn operation, gangue from the combined ground feed
will be floated in a rougher and cleaner “talc” circuit to produce a “talc concentrate”
that will be discarded straight to final tailings. This represents about 4% of the feed
mass with a minimal loss of valuable metals. Tailings from the talc cleaner flotation
will be depleted of copper and so may go straight to the lead circuit. Talc rougher
tailings contain the bulk of the valuable metals and will feed the copper flotation
circuit.
Tailings from the copper flotation will be reground in an IsaMill M5000 to a P80 of
30µm and fed to the lead flotation circuit.
A conventional lead rougher, cleaner and recleaner lead circuit will float the lead,
along with the bulk of the silver into a high precious metals lead concentrate. A
feature of this circuit is the bleeding of the lead cleaner tailings to the zinc
retreatment circuit when processing the reclaimed tailing. Zinc will be depressed in
the lead circuit and report to the zinc rougher flotation.
Zinc will be concentrated in a flotation circuit comprising rougher flotation with two
stages of cleaning. The rougher – scavenger concentrates will be reground to a
P80 of 15µm prior to cleaning. The zinc second cleaner concentrate will report as
the final zinc concentrate.
Cu Pb Zn Ag Au
% % % gpt gpt
Cu Concentrate 23.5 3.5 2.0 116 1.39
Pb Concentrate 7.8 44.8 8.6 701 4.65
Zn Concentrate 0.9 2.4 45.2 92 0.42
Table 13.8: Expected concentrate production profile and gross metal content from
mixed underground feed and reclaimed tailing (based on 1.5Mtpa treatment)
lenses, and the new Kate lens, with all new mineralisation modelled being a result
of TriAusMin and Heron exploration drilling from 2010 till March 2015.
Refer to Section 2.5 for details of the reconciliation between the resource
categories used and the CIM categories.
Figure 14.1: Denehurst lens model from 1997 looking south showing from left to right
C Lens (magenta, under pit) B5 Lens (dark blue, next to C), B1 Lens (green), A Lens
(red), F Lens (light green, under pit edge), E Lens (orange, below F), G Lens (green,
above E),
Lens boundary wireframes were constructed in three dimensions using the drill
hole intercepts and points derived principally from geological interpretations of the
backs mapping. Both sets of points were often recorded on the relevant backs
mapping sheets. Orthogonal blocks based on the width of wireframed lens
interpretation (X- east) by 20m (Y-North) by 5m (Z-RL) were estimated using a
combination of the nearest drill hole bulked grades and volumes derived from the
resource wireframe. This process was reviewed in 1988, and subsequent resource
models used the inverse distance squared weighting (ID2) for estimating block
grades as this interpolation appeared to best match mining performance (a number
of different algorithms were tested at this time).
Density was assigned to the modelled blocks using a density regression
determined from a calculation derived from density determinations and assays for
drill core taken from the underground resource area. The formula was:
SG = 2.2118+(0.0552*Fe%)+(0.0487*Pb%)+(0.0226*Zn%)
The density regression was applied to the estimated block grades to assign density
values to the model.
Historically, the resultant block model was then depleted manually by the mine
geologist for mine development, stoping, collapse zones and non-recoverable
pillars to arrive at the estimated remaining resource grade and tonnes.
Reserves are recoverable and include an allowance for 10% dilution at zero grade.
Reserves include 11,000 tonnes at 3.71%Cu, 2.39%Pb, 7.71%Zn, 42g/tAg, 0.3g/tAu in crown
pillars at the base of the open pit. These reserves may not be mined if the open pit is developed
as a waste management facility
Woodlawn Mine Mineral Resources 28th February 1997
Tonnes
%Cu %Pb %Zn Ag g/t Au g/t
(Million)
Complex and Copper Ore
Measured 0.10 1.30 2.10 6.50 33.00 0.50
Indicated 0.04 3.10 0.40 3.00 10.00 0.10
Inferred 0.12 3.40 1.00 3.50 29.00 0.70
Total 0.26 2.60 1.30 4.50 27.00 0.50
Resources quoted are in situ and undiluted
used. Lenses were constrained along strike up and down dip by a 10m boundary
from the last intersection point. Some 39 lenses in 10 major sets were interpreted
by this method to produce the Rankin (2006) resource model (Figure 14.2).
Figure 14.2: 2006 lens model with drilling, looking north, showing from left to right I
Lens (light green), D Lens (dark blue), F Lens (purple), A Lens (yellow), B Lens (red),
J Lens (light green), C Lens (middle green), and as intercepts only H Lens (orange),
G lens (yellow) and E lens (cyan).
All data flagged by lens was composited to 1m using length weighting, and
geostatistical studies were performed on Zn and Cu for all domains combined. The
block model used to model the volume within the lenses had parent cell
dimensions of 4m (X-East), 5m (Y-North) and 6m (Z-RL) with a minimum sub cell
of 1m in all directions.
A geostatistical study was carried out on Zn and Cu distributions within the deposit
(all lens domains combined). Interpolation of grades was carried using inverse
distance squared. Zn and Cu were interpolated using different parameters based
on the results of variography. All other elements were interpolated using the Zn
parameters.
Table 14.2: Table showing interpolation parameters used in the TriAusMin 2006
Mineral Resource model (from Rankin, 2006)
Density was determined for blocks within the model using the historical density
regression equation applied to the interpolated block grades. The use of the
equation was as recommended by Mr Robert Cotton (2006) for individual assays
where:
all of Fe, Pb and Zn have been assayed for a single sample: use
SG = 2.2118+(0.0552*Fe%)+(0.0487*Pb%)+(0.0226*Zn%);
Fe has not been assayed and Zn is less than 5%:% use the density 2.9,
and
Fe has not been assayed and Zn equals or exceeds 5%:% use the density
3.9.
Only a few default values of 3.9t/m3 were assigned as both iron and zinc values
were virtually always present in the model. The application of density was
effectively the same as for the previous Denehurst resource and reserve models.
A zinc equivalent grade was calculated for each block using a formula based on
the block Zn, Pb, Cu, Au and Ag values. The factors used were based on metals
prices current in October 2006. The zinc equivalent was used as a cut-off for the
Resource reporting. Classification of the resource model was based on the
interpolation parameters for individual blocks with:
Measured used a distance of < 30m and at least 4 points.
Indicated used a distance of < 45m and at least 2 points.
Inferred used a distance of < 60m and at least 1 point.
Figure 14.3: Block model 2006 E/W vertical cross section 19,500mN showing Zn
block grades. Note grey blocks indicate voids where previous mining has taken
place. Lenses from left to right A, B hangingwall Lenses, B1, B2 footwall Lens (Cu
rich).
The 2006 Mineral Resource estimate was reported as all unmined blocks above a
Zn equivalent (Zneq) cutoff grade of 7%. No dilution or pillar factors were applied.
Blocks within 50m radius of the historic open cut were not reported. No Ore
Reserves were calculated.
Table 14.3: Woodlawn 2006 Mineral Resource above 7.0% Zneq cutoff grade,
excluding all blocks within 50m of the open cut pit
All of the backs (roof) mapping plans were created during the development of and
mining of the deposit, by both Denehurst (mining operations) and Jodoex (pre-
feasibility development mapping). The vast majority of geological maps were
prepared by two mine geologists; Mr T Ho and Mr R Hollinger.
The scale of the mapping is a mix of 1:500 (all capital development headings and
some cut and fill stope plans) and 1:250 (later cut and fill stope plans). There is
very good constancy of legend and quality between all of the geological plans. The
mapping sheets are stored in a plan cabinet at the Woodlawn site. They comprise
a mix of A0 and A3 transparency mapping sheets, in the form of hand-drawn,
drawn drafted ink, and pencil plans, projected onto the WMG for spatial reference.
Features mapped include massive sulphide boundaries, stringer sulphide domains,
dolerite boundaries, host lithologies, faults, joints, shears, foliation, and rare
primary bedding features (typically only recognised in cherty units). The mapping
sheets contain many detailed sketches of key geological features and many
thousands of dip and strike measurements taken by geologists during the mapping.
There are also notes on the geotechnical conditions of drives, local areas of
collapse, mineralogy of material within significant fault planes (gouge), and many
comments and outlines in pencil pertaining to historical Denehurst resource
models.
It is quite clear that these are the original working geological plans that contain
both “fact data” from geological mapping and “interpretative data”. While the
interpretative data and plan overlay data were examined, only the fact data has
been digitised.
Figure 14.4: Typical underground level mapping – Denehurst mine mapping 1:500
scale geology backs map of B14 level (2390mRL) showing B Lens (B1 and BC) along
with the 750 fault. Massive sulphides are coloured in Red, stringer sulphide chert in
light pink, shale in brown, dolerite in yellow and rhyolite in magenta. Note the
additional observations with reference locations and resource model data in outlines
and pencil lines. (Note the WMG used at the time of mapping omitted the 10,000m
addition to northings used in the current work by Heron)
Some 33,327 points were digitised by Heron as a part of this process into 2,767
individual strings. The geological contacts were digitised for the massive and
stringer sulphides, dolerite intrusive rocks, and faults.
Figure 14.5: Digitised underground mapping method. I Lens, oblique view looking
north, showing TriAusMin/Denehurst void model, backs mapping plan I20-2 level
(2470mRL) with the mapping strings of the hangingwall (red) and footwall (pink)
massive sulphide contacts digitised and then projected onto the corresponding void
backs plan for each level. Note also drilling with massive sulphide shown in red, and
intersection selections in green (HW and FW) at the geological contact
Digitising was completed by geologists into Micromine using the plan grid for X and
Y co-ordinates, and the historical void model to provide the RL (or Z plane).
The digitising process identified a number of wireframe and projection issues in the
historical void model. These issues were addressed by the creation of a new void
model (detailed under Section 14.3.6) from the survey plans. From a comparison
of the two void models, it was concluded that the RL control on the digitised
geological mapping data is of sufficient accuracy for resource modeling, being +/-
2m in RL.
The drilling data was extracted from the DataShed WUP project database
Heronv3, as built and maintained by Heron. The vast majority of drilling data used
in the resource model are historical. This included 113,105m of surface diamond
drilling, 51,811m of underground drilling and 2,029m of underground face
sampling. The source of these datasets, and the validation performed on them, is
described in Section 10.1.2.
While every effort has been made by Heron to verify the historical data against
source data, to date original source data has only been located for drill hole collar,
down hole survey, and down hole geology logging data. The absence of source
sample and assay data is partially offset by the correlation of the historical
Techbase and more recent TriAusMin Excel and Micromine databases. Further
details on validation undertaken can be found in Section 12.1.1.
There has been no QAQC data located for the historical portion of the database.
However, the mine did operate successfully and profitably as both an open cut and
underground operation based on the historical Techbase drill hole database. While,
no QAQC data have been located, the quality of historical assays is considered to
be reasonable given mine to mill production reconciliation grades and tonnes were
considered to be sufficiently accurate as to support the producing underground
operations up until mine closure. Furthermore, the sample database appears to
spatially match closely with the backs mapping data, previous resource models,
plans, sections and production records.
Recent drilling by TriAusMin between 2006 and 2012, and later by Heron in 2014
has been included in the resource model. A full description of the drilling methods,
logging and sampling procedures, assay methods, QAQC and database
management is presented in Section 12 of the Report.
The cutoff date for assay results used in the resource model was 20th March 2015.
All drilling data was sourced from the Heronv3 database. It included assay results
from all of the drilling conducted in 2014 and the first quarter of 2015 by Heron at
Woodlawn.
During underground mining operations all surveys were carried out by Mine
Surveyor Mr M Fantin using conventional survey techniques during day to day
mining operations. Mr G Michl, a mining engineer with surveying experience, also
contributed to the survey of the “west wall” decline and the later stages of mine
development with the D and E Lenses subsequent to 1993. After the resignation of
Mr Fantin, Mr C Ablett, a contract surveyor oversaw the last five months of mine
life survey.
The survey was completed from each portal, by use of backs mounted survey
stations, with bearings and distances between the surveys carried out using a
Leica theodolite. Some closure surveys were completed using vent shafts, and
levels were routinely back calculated during operations. During Denehurst mining
operations, all surface exploration survey work was also carried out by Mr Fantin.
All survey work was carried out in the Woodlawn Mine Grid (WMG). The origins of
the grid and its orientation are described in Section 4.3. All surveys of
underground development were documented on hand drafted A0 and A3
transparent film plans in a mix of 1:250 and 1:500 scales. The plans are located at
the Woodlawn site office, and have been scanned and digitised to and used to
create a new void model of the underground workings.
All underground and surface drill hole collars drilled during the life of the
underground mine (as operated by Denehurst) were picked up by the underground
surveyors (personal comments Mr M Bouffler,M Fantin and G Michl 2015).
Records of the survey control and pickup of the original Jododex and AMC drilling
have not been located, but there is a reasonable down hole correlation between
these, and later drill holes in the resource area.
Subsequent to the closure of the mine, TriAusMin added 10,000m to the northings
of the WMG. All historical data has been converted to the new coordinate system.
Heron has used the new WMG in all of its resource modelling data.
Figure 14.6: Oblique view from south showing historic drilling in black, Heron and
TriAusMin drilling in magenta.
14.3.5 Topography
The topographic digital terrain model of Woodlawn, used in the resource model is
of unknown origin. It appears to be adequate for resource modeling because no
potentially recoverable resource exists within less than 30m of the modelled
surface, and thus the topographic model does not directly impact on the modelled
resources.
The topographic model is of sufficient accuracy for the planning of drill holes, and
correlates well with the surveyed pickups of completed collars. It also correlates
well with man-made features such as road cuttings, ramps, pit crests, dam
causeways, and the final mined pit outline.
While the surface model is of sufficient accuracy for the purpose of PEA studies
and drill planning, it is proposed to update the model for future feasibility studies.
A new underground void model was constructed to capture known areas of mining
voids missing from the previous void model, and to include the shanty back profiles
that had not been modelled in the previous void model.
All of the original survey plans were scanned and all data points on the plans
digitised. A series of scripts were developed to connect the survey string, backs
and floors measurements together to form the new void model. The resulting void
model was checked against the plans, and available production data, as well the
recollections of staff onsite at the time of mining.
The new void model was checked against historical extraction figures for the
stoped areas of the mine (ore production only).
Table 14.4 : Historic extraction of ore vs void models
Tonnes
Void Model
(Million)
Historic Extraction
(milled) 6.1
SGCM 2006 Void
Model 4.5
2015 Void Model 6.1
Figure 14.7: Previous void model (grey) against resource wireframe outline (red)
showing sections of unmined resources between levels
Figure 14.8: New Void Model (grey) against resource wireframe (red) showing shanty
back profile and mining of the resource between levels. Note the area at top right
was noted on the geology plan as hangingwall unmined (due to mineralisation being
wider than the maximum permitted span of the drive. This area is captured in the
new resource model as an unrecoverable skin
Down hole surveying was carried out on all drill holes in the database. Historical
down hole surveys were by single shot camera, generally at 30m intervals. Some
underground collar surveys were done by the mine surveyor using a theodolite in
the mine local grid.
Recent drilling by Heron has been surveyed by a multi-shot electronic camera, and
upon hole completion, by MEMS gyro surveys (IsGyro) with an Azimuth aligner
used to collect the collar survey. Selected holes were further checked with a north
seeking gyro.
The majority of surveys in the database rely on magnetic surveys. These readings
have all been adjusted within the database to reflect the change in magnetic pole
declination over the life of the mine.
Although it is not possible to directly test the validity of the down hole survey
readings of historical holes, there is close correlation between intercept locations in
both the surface and underground drilling, the underground backs mapping and
recent surface drilling by Heron.
Limited bulk density determinations were available for the model. No measured
density data was available for historical drilling. Heron routinely conducts a density
determination on all samples sent to the laboratory using the industry accepted /
water immersion density determination method for each sample (see Section 10.5).
The historical regression equation was checked against recent drilling density
determinations and was found to be reasonable for most material types tested. An
adjustment has been made for lower grade material after examining density and
assay results for drilling performed by Heron in late 2014 and early 2015.
Figure 14.9: Graph showing the measured versus the calculated density
measurements. Note the underestimation of lower grade samples by the density
regression equation.
It is important to note that the density data from drilling available at the time of the
resource model data cutoff date came from two principal areas of the mine, the
Kate Lens area and the I/D Lens deeps area, rather than across all of the lenses
modelled. Heron is currently performing density tests on appropriate core sample
from historical drill programs samples to provide coverage in all areas relevant to
further feasibility studies.
While the density regression calculation shows a reasonable correlation of 0.91
with measured density, there is some subtle bias if the data are split into ranges.
The regression equation underestimates density of low zinc and iron
samples. No sample in the data set (which includes waste material
either side of the mineralisation) has a measured density below 2.65.
Regressed densities for these samples are as low as 2.40 using the
historical grade regression equation. In the resource model a lower cut
off of 2.65 was applied to all calculated block densities to reflect that no
material of a density below this value is present in the areas tested.
There is considerable scatter in the calculated versus. measured
density for stringer material types. The scatter is thought to be partially
a result of the variability in material types in actual samples (typically
these samples are stringer sulphide material, containing both silicate
and sulphide in the sample). Another likely effect is that copper grade is
not been included in the regression. Many of these samples, but not all,
are chalcopyrite + pyrite + silicate mineralogy, and no allowance is
made for chalcopyrite in the historical regression function. The scatter
does not appear to be biased overall, with samples being as likely to be
Lens I6 Fe IC Fe D1 Fe D2 Fe BC JC KC
Defaults Defaults Defaults Defaults Defaults Defaults Defaults
Fe Value 22.6 25.1 24.9 22.7 9.7 14.0 28.7
Number of
holes 3 2 3 3 1 1 1
affected
Number of
samples 25 14 8 27 33 4 23
affected
geometric relationships along strike and down dip. The geological logging of the
drill holes was used to build constrained domains for:
massive polymetallic mineralisation (pyrite, sphalerite, chalcopyrite,
galena);
copper mineralisation (pyrite, chalcopyrite);
massive sulphide pyrite dominant (pyrite only) – not modelled, and
mixed domains (where polymetallic and copper domains could not be
separated from the available data).
Domain boundaries were defined using mapping data, and where mining has
previously not taken place, drill hole lithology logging. All domain boundaries were
built up from string and point files into three dimensional wireframes.
The deposit has been domained into 11 individual lenses and 33 sub domains
within those lenses. The F Lens was not modelled for the PEA. Pyrite only
material has not been modelled for the PEA. Lisa Lens, although modelled, has
not been classified due to limited drilling to date and is not currently part of the
resource statement. Portions of the AC, BC, and G1 Lens where insufficient
drilling is currently available have not been classified.
A nominal cutoff grade was not used to interpret the domain boundaries, as there
is usually a clear natural break in grade between the sulphide dominant material
(both massive and stringer) and adjacent host rocks. However, in some areas,
usually along strike, the domain boundary of stringer material is gradational or
feathery and an assay cutoff of 0.5% Cu has been used to help define the domain
limits. The assay cutoff is substantially below the expected economic cutoff grade.
There are parts of D, E and Kate Lenses that appear to only contain massive pyrite
material. The cutoff between complex sulphide and pyrite only mineralisation was
found to be relatively sharp in previous mining of D and E Lenses. As a result, the
boundary between complex and pyrite only mineralisation is modelled as a sharp
domain boundary for all three lenses (note the pyrite only mineralisation was not
included in the block model).
Table 14.6: Summary of domain constraints
Sub
Lens Characteristics Data Used Contacts
Domain
A A1 Massive Polymetallic Type Mapping>Drilling AC,B7,790F,750F
AC Stringer Sulphide Copper Type Mapping>Drilling A1,790F,750F
B B1 Massive Polymetallic Type Mapping>Drilling BC,B7,750F
B5 Massive Polymetallic Type Mapping>Drilling B1,BC,B7,750F,790F
B7 Massive Polymetallic Type Mapping>Drilling A1,B1,BC,750F,790F
B8 Massive Polymetallic Type Drilling>Mapping B1,750F
BC Stringer Sulphide Copper Type Mapping>Drilling B1,B7,750F,790F
C C1 Massive Polymetallic Type Mapping>Drilling C2,C4,CC
C2 Massive Polymetallic Type Drilling>Mapping C1,CC
C4 Massive Polymetallic Type Mapping>Drilling C1,CC
C5 Stringer Sulphide Copper Type Drilling >Mapping 790F
CC Stringer Sulphide Copper Type Mapping> Drilling C1,C2,C4
D D1 Massive Sulphide Mixed Type Mapping>Drilling D2,D3
D2 Massive Sulphide Mixed Type Drilling D1
D3 Stringer Sulphide Copper Type Mapping>Drilling D1
Sub
Lens Characteristics Data Used Contacts
Domain
E E1 Massive Polymetallic Type Mapping>Drilling KC,K1,790F
E2 Stringer Sulphide Copper Type Drilling>Mapping KC,K1,790F
F Not Modelled
G G1 Massive Sulphide Mixed Type Drilling>Mapping H1,790F
G2 Stringer Sulphide Mixed Type Drilling>Mapping
H H1 Massive Sulphide Mixed Type Mapping>Drilling G1,790F
I I1 Massive Polymetallic Type Mapping>Drilling 123F
I2 Massive Polymetallic Type Mapping>Drilling 123F
I3 Stringer Sulphide Copper Type Mapping>Drilling 123F
I4 Stringer Sulphide Copper Type Drilling IC,LC
I5 Massive Sulphide Mixed Type Drilling 123F
I6 Massive Polymetallic Type Drilling IC
IC Stringer Sulphide Copper Type Drilling I4,I6
J J1 Massive Polymetallic Type Mapping>Drilling 790F
J2 Stringer Sulphide Copper Type Drilling>Mapping 790F
JC Stringer Sulphide Copper Type Drilling>Mapping 790F
Kate K1 Massive Polymetallic Type Drilling 790F,K2,E1,E2
KC Stringer Sulphide Copper Type Drilling E1,E2
K2 Not Modelled (pyrite only type) Drilling K1,KC
Lisa LC Not Classified (insufficient drilling) Drilling I4
The domain boundaries were built from wireframe plane models of:
hangingwall contact;
footwall contact;
principal constraining fault planes, and
wireframe “cookie cutters” between pyrite and complex domains where
required.
The planes were developed in three dimensions from the digitised mapping data
and drill hole intersections using the Leapfrog implicit modelling algorithm. Drill
hole intersections were used principally where mapping data were not available,
usually in areas where mining has not taken place. In areas where both mapping
and drill hole data were available, the mapping data were used in preference to
drilling data to define bounding wireframes as it was considered to be spatially
more representative of both dip and strike than the drilling pierce points. In most
cases, the two data sets were coincident and both were used.
The implicit modelling algorithm was adjusted for each domain modelled. Most
mineralisation domain boundary wireframes honored the data best by interpolating
with a 4:2:1 aspect ratio aligned along the plunge of the intersection lineation
between the principal foliation direction (and plane of lenses) and the 790 level
fault plane. This lineation has a strike of 170°, dip of -60°, and plunge of 110° to
the north. A two metre minimum triangle size was used for all wireframes to
provide a reasonably accurate representation of each lens volume and location for
the purpose of economic evaluation. All boundary wireframes were checked
against the primary mapping data to ensure the resultant wireframes were within
the two metre tolerance.
Figure 14.10: Domain boundary from mapping strings, for the I1 massive sulphide
domain. Same view as for figure 14.5 showing drilling, mapping strings and the
resulting wireframe domain boundary
The resulting wireframe models were used to domain the deposit into the
mineralised lenses and non-mineralised domains by intersecting the footwall and
hangingwall mineralised domains with bounding structures as appropriate for each
domain. This was completed using Boolean intersections in Micromine.
The non-mineralised domain was not subdivided into different lithologies and
alteration types for the PEA model.
For most lenses, sufficient data were available to further discriminate the lenses
between “polymetallic” (dominantly pyrite + sphalerite + galena + chalcopyrite),
“copper” (chalcopyrite + pyrite) and “barren” (pyrite only) mineralisation styles.
This was considered to be an important step as most historical mining was
concentrated in the polymetallic domains, leaving adjacent copper domains
unmined. Without separating the domains within a lens there was a risk that high
grade zinc and lead values could be smeared into copper and barren domains
during the interpolation of grades (refer Figure 14.11).
Figure 14.11: Showing grade changes in B Lens on the 2250mRL from polymetallic
to copper rich across a single sample interval. Note previous mining centered on the
polymetallic mineralisation. Drill hole traces showing lithology (massive sulphide
red, dolerite dark)
While the effect of not domaining polymetallic from copper and pyrite only material
would be slight on the overall deposit grades, the combining of material types into
single domains using mining cutoff grade parameters can significantly skew local
grades of remnant material that have been used as part of the PEA plant feed.
The new domain rationale reflects the large increase in the amount of data
(principally digitised backs mapping) used in the current resource model compared
to previous models. The new model also seeks to estimate both the recently
discovered lenses, and deeper portions of the deposit previously drilled but not
modelled. The additional domaining was considered to be important as the
resource model’s principal purpose was to allow the designing of stope outlines for
the PEA. This required that reliable grades be assigned to the domains based on
relatively wide spaced drilling over a significant portion of the model.
Samples were selected for the domains by way of lode coding of the database.
Selected drill hole interval samples were composited to one metre lengths, with the
remainder of the interval retained in the composite file. Assays were both length
and density weighted. Density weighting, where density measurements were not
available, was applied to assays using the historical regression equation as
discussed in Section 14.3.8.
A number of drill holes had samples which crossed geological domains, as logged.
These holes were principally from drilling between the end of the Jododex
feasibility study, and about half way through the grade control and exploration
drilling carried out by Denehurst, where one metre sampling was used without
consideration of geological contacts. For these holes, intersection selection was
based on the assay results in combination with the geological log, with samples
with discernibly lower grades than the adjacent mineralised domain samples being
removed from the intersection selection for that domain. Some issues were
experienced in finding sufficient samples for the copper rich domain AC. For this
domain there was an area mapped (and partially mined) as being copper stringer
material without any drill hole assays present. While the area was modelled for the
PEA the area without adequate sample support was not classified and has not
been reported as part of the resource.
Not all samples within the mineralised domains were assayed for gold. Gold
assays on historical samples were carried out at the discretion of the geologist,
generally only where significant gold mineralisation was thought to occur (personal
comment from Mr M Bouffler). Some 35% of samples within the domains do not
contain gold assays. For the purposes of the model, samples without gold assays
were assigned the grade of 0.01g/t, this being the minimum detection limit for gold
assays from the site laboratory. This conservative approach was taken to ensure
that gold was under, rather than over estimated in incompletely sampled domains.
Top cuts have not been previously used for resource models of the Woodlawn
deposit. Examination of data from all domains indicated that top cuts were not
required for zinc, copper or lead.
There is limited data for domains where top cuts may be considered for gold, and
infill sampling will be required for the I6, H1 and G1 domains to resolve this issue.
Part of the problem likely relates to historical issues with selective sampling of gold
as outlined in Section 14.4.2. No gold assays were cut in this model.
Silver distribution throughout the deposit varies from lens to lens. The G1 domain
is notably high in silver compared to other lenses. For the G1 domain a top cut of
850ppm Ag was applied to the composites of two adjacent drill holes where the
silver values were an order of magnitude greater than for the other holes in the
domain. Four composites are affected in total. No other grade cuts were applied
to silver assays in this model.
Table 14.7: Summary Statistics for all uncut assays used in the resource estimate
Field No of Coeff. of
Name Min Max Points Mean Variance Std Dev Variation Skewness
Strong Positive Skew
Au_g/t 0.01 19 7450 0.59 0.97 0.98 1.68 (7.03)
Strong Positive Skew
Ag_g/t 0.01 2877 9368 69.7 11162.12 105.65 1.52 (8.56)
Strong Positive Skew
Cu_% 0.0001 26.3 9570 1.81 5.23 2.29 1.27 (3.03)
Fe_% 0.01 46 9413 18.27 102.00 10.10 0.55 Symmetric Skew (0.22)
Strong Positive Skew
Pb_% 0.0001 27.81 9568 3.23 15.27 3.91 1.21 (1.55)
Moderate Positive
Zn_% 0.0001 44.3 9570 8.21 71.42 8.45 1.03 Skew (0.91)
The statistics for each lens were calculated from the one metre density and length
weighted composites. As can be seen from the following tables the different lenses
have similar overall composite populations, with more skew evident for Ag and Au
values in some of the lenses. Some distributions are clearly bimodal (e.g. A Lens).
Cu is very well structured, with a very low nugget effect. The major direction of
continuity, with a range of 90m is N170° (along strike). The semi-major direction is
down dip (N260°, dip -60°). The minor direction is across lenses with a maximum
range of 23m.
Pb is very well structured, with a very low nugget effect. The major direction of
continuity, with a range of 130m is down dip (N260°, dip -60°). The semi-major
direction is N170° (along strike). The minor direction is across lenses with a
maximum range of 38m.
Zn is very well structured, with a low nugget effect. The major direction of
continuity, with a range of 100m is down dip (N260°, dip -60°). The semi-major
direction is N170° (along strike). The minor direction is across lenses with a
maximum range of 35m.
ZnEq is very similar to Zn, which is not surprising as both variables are highly
correlated. ZnEq is very well structured, with a low nugget effect. The major
direction of continuity, with a range of 180m is down dip (N260°, dip -60°). The
semi-major direction is N170° (along strike). The minor direction is across lenses
with a maximum range of 35m.
Au, after back-transformation from the Gaussian variable, is well structured, with a
very low nugget effect. The major direction of continuity, with a large (somewhat
arbitrary) range of 900m is N300°, dip -53°. The semi-major direction is N182°, dip
-19°. The minor direction is across lenses with a maximum range of 160m. Note
that this variogram was calculated prior to setting the missing values to 0.01g/t as
used in the interpolation for gold.
Ag, after back-transformation from the Gaussian variable, is well structured, with a
low nugget effect. The major direction of continuity, with a range of 270m is down
dip (N260°, dip -60°). The semi-major direction is N170° (along strike). The minor
direction is across lenses with a maximum range of 50m.
Fe is well structured, with a low nugget effect. Within the lodes plane, the
variograms are fairly isotropic (similar ranges of the order of 150m). The minor
direction is across lenses with a maximum range of 35m.
The block model is defined in the Woodlawn Mine Grid as outlined in Table 14.8.
The block model was intersected with the surface topography wireframe to produce
a parent waste model. As all modelling included in the PEA occurs below the base
of oxidation, a base of oxidation model was not included in the block model,
although a wireframe has been constructed to assist with drill hole planning.
Table 14.8: Model Limits for resource block model
Minimum
Minimum Maximum Maximum
Block Size Sub-cell
Coordinate Coordinate No of
(m) Dimension
(WMG) (WMG) Sub-cells
(m)
East 8700 10320 10 10 1
North 18635 20085 20 10 2
RL 1750 2870 20 10 2
Ordinary Kriging was chosen for the interpolation of grades into the model. A total
of six elements were interpolated for each domain. Grade interpolation parameters
were developed from the results of the variography study for each element and
these parameters were applied to every domain. Each domain used a separate
composite file for the domain being modelled. All domain boundaries were treated
as hard boundaries for the purposes of interpolation.
Table 14.9: Variogram model simplified parameters
Variogram Parameters
Directions Structures Ranges
Element Range Range
Azimuth Plunge Nugget Partial Sill 1 Partial Sill 2 1 2
170 0 12 70
Zn % 260 60 3 35 29 12 100
80 30 5 35
170 0 7 75
Pb % 260 60 1 5 7.6 7 130
80 30 5 38
170 0 8 90
Cu % 260 60 0.3 1.5 2.6 10 30
80 30 5 23
182 19 20 170
Au g/t 245 -53 0.03 0.3 0.45 20 900
284 30 10 160
170 0 50 270
Ag g/t 260 60 2500 5000 2500 120 200
80 30 200 40
170 0 12 70
Fe % 260 60 30 35 29 12 100
80 30 5 35
A three pass elliptical search was used to interpolate grade. The search ellipse
was based on the variography. The first pass interpolated the majority of blocks,
and only sparsely drilled areas were informed by the second and third search
passes.
Factors in the above Table 14.10 are expansion factors applied to the original
search ellipse in a multi-pass search to locate sufficient samples with which to
compute block grades.
ZnEq was not interpolated, but was instead calculated for each block from the
estimated block grades. The ZnEq calculation takes into account, mining costs,
milling costs, recoveries, playability (including transport and refining charges) and
metal prices in generating a zinc equivalent value for each block grade for Au, Ag,
Cu, Pb and Zn.
ZnEq = Zn%+Cu%*3.12 +Pb%*0.81+*Au g/t*0.86+Ag g/t*0.03
Specific gravity was assigned to individual blocks in the block model using the
adjusted historical density grade regression as discussed in Section 14.3.7 applied
to the interpolated block grades. This is principally the same approach as for
previous models with the exception of the application of a lower cut applied to
material falling below the minimum measured densities from recent drilling (2.65).
SG = 2.2118+(0.0552*Fe%)+(0.0487*Pb%)+(0.0226*Zn%)
Waste material outside of the mineralised domains was assigned the same
minimum density as the mineralised domains.
Upon the completion of interpolation each domain was individually assessed for
interpolation performance of all six elements. Grades were examined:
visually in three dimensions for comparison between original assay grades
(pre compositing) and interpolated block grades;
the slope of regression and Kriging error were also checked against the drill
hole intercept spacing, and
swath plots were generated for composite grades and block grades on a
20m RL level spacing (i.e. in the long axis of the mineralisation) for each
domain.
The visual comparison of the grades between the model and the original drill hole
assay data was found to be acceptable. There is inherent in the use of Kriging,
some smoothing of high and low grades. The effect was negligible in the well
drilled areas of the model (usually classified as Indicated), and moderate in areas
of broader spaced drilling, which have been classified as Inferred. Because of the
tight geological domaining employed in the modelling there was no significant
smearing between mineralisation types.
With the search parameters employed, the slope of regression and Kriging errors
for almost all of the modelled domains was well within acceptable limits. Only on
the edges of domains, or domains with limited sample information were there some
issues with interpolation confidence. This has been reflected in the classification of
resources.
The main domain where this was an issue was the Lens AC domain, where, while
there is extensive geological mapping information to define the domain, there is
limited drilling and assay data available to estimate grades. The domain was
downgraded to Not Classified in areas of poor sampling information, and resources
have not been reported for this portion of the domain.
Mineral Resource classification took into account the geological confidence of the
interpretation, the results of the interpolation performance and the engineering
assessment of recoverability of resources.
Material was classified on a domain by domain basis according to the results of the
assessment as being:
MN – Mined: mineralisation inside the revised and updated void model.
SK – Skin: mineralisation outside of the void model which is either
considered to be unrecoverable prior to future mine re-entry validation
(such as pillars or skins to waste rock filled historic openings), or within a
zone of known ground failure.
ID – Indicated: mineralisation with geological mapping supporting
interpretation and sufficient assay data to be considered to be ± 15%
overall accuracy. This corresponds to areas of the deposit with a drill
spacing of 30m or less and good geological confidence of geometry
between intersections, including most remnant areas of the previous
operations. All of the blocks in the domain were interpolated in the first
pass of the interpolation.
14.7.2 Estimate
The resources are reported insitu, without dilution, but depleted for previous
mining. A lower cutoff grade of 7% ZnEq has been applied.
14.7.4 Discussion
A number of refinements of the resource model are recommended for future economic
studies, up to and including feasibility studies. These include:
Fault model wireframes have been constructed from mapping data for the
major fault planes in the mine. A more detailed fault model should be
created from the available mapping and drilling data, both to improve the
domaining of mineralisation, and to assist with the development of the
geotechnical model as a part of future feasibility studies.
Waste domains, alteration domains and geotechnical domains have not
been modelled as part of the PEA study. However it is recommended for
further economic assessments, including feasibility studies that a full
geological model of the deposit and surrounding rock mass be developed.
A structured drill out of resources to Indicated classification based on the
required production schedule to support operation construction and ensure
profitability. The recent drilling and modelling has highlighted the presence
of a number of economically significant, near surface, unmined resources
accessible from new underground development. Drilling of these shallow
resources from surface to indicated status should, combined with remnant
material, provide sufficient resource inventory to justify redevelopment of
the underground mine.
The resource is not currently considered to be geologically closed off at
depth, or along strike to the north and south. Further exploration drilling
may locate other mineralised lenses within the immediate mine area,
consistent with VMS mining camp resource distributions.
Grades
Resource Category Quantity ZnEq (%) Zn Cu Pb Au Ag
(Mt) (%) (%) (%) (g/t) (g/t)
Measured + Indicated Mineral Resources
North Dam
Measured 0.83 6.2 2.35 0.43 1.43 0.29 35
Indicated 1.38 6.7 2.68 0.45 1.44 0.29 40
Sub-Total 2.21 6.5 2.56 0.44 1.44 0.29 38
South Dam
Measured 2.43 6.0 2.60 0.48 1.19 0.22 25
Indicated 1.17 5.8 2.44 0.48 1.19 0.22 23
Sub-Total 3.60 5.9 2.55 0.48 1.19 0.22 24
West Dam
Measured 2.05 6.5 2.00 0.60 1.46 0.39 36
Indicated 1.54 6.5 1.93 0.60 1.51 0.39 37
Sub-Total 3.59 6.5 1.97 0.60 1.48 0.39 36
All Dams
Measured 5.31 6.2 2.33 0.52 1.33 0.30 31
Indicated 4.09 6.4 2.33 0.52 1.40 0.31 34
Total Measured + 9.40 6.3 2.33 0.52 1.36 0.30 32
Indicated
Inferred Mineral Resources
North Dam 0.87 5.5 2.03 0.33 1.33 0.25 37
South Dam 0.90 5.7 2.32 0.47 1.19 0.23 24
West Dam 0.48 6.3 1.83 0.61 1.47 0.38 34
Total Inferred 2.25 5.7 2.10 0.44 1.30 0.27 31
Notes to accompany Mineral Resource Table: 1) ZnEq% refers to a calculated Zn equivalent grade the formula for which is stated in section 14.6.3 and
these are different to the originally reported (May 2009) ZnEq grades which were based on a different formula; 2) Values are rounded to two significant
numbers and some rounded related discrepancies may occur in the totals; 3) The Mineral Resource is reported in a manner compliant with the JORC 2004
and NI 43-101 Codes. This information was prepared and first disclosed under the JORC Code (2004) in May 2009. It has not been updated since to
comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. 4) TriAusMin acquired more drill
hole data in 2008, subsequent to the Mineral Resource estimation. That data however does not materially alter the Mineral Resource estimate and due to
data collection problems it is not viable for use in a re-estimate. Nevertheless, statistics of the later assays confirm the reported estimated grades. 5)
Further details of the Mineral Resources estimation, including Competent Person statements can be found in the market release of 22nd April 2015 entitled
“Preliminary Economic Assessment Delivers Strong Business Case for the Woodlawn Zinc-Copper Project” (available from ASX or SEDAR) including the
Competent Person Statement.
16 Mining Methods
16.1 Introduction
The Woodlawn Retreatment Project (WRP) will treat reclaimed tailings material
from the tailings dams deposited during the previous operations of the Woodlawn
mine prior to closing down in 1998. These tailings will initially be reclaimed in
sequence at a rate of up to 1.5 million tonnes per annum (Mtpa) by hydraulic
monitoring from the Tailings Dam South (TDS), Tailings Dam West (TDW) and
Tailings Dam North (TDN).
The tailings reclamation strategy will be by “top down” hydraulic monitoring system
(Figure 16.1). The slurry collected will be screened to remove trash prior to
thickening and pumping to the feed stock tanks. The water for monitoring will be
provided from the mining thickener overflow with makeup from the process water.
Hydraulic mining operations will operate on a 24 hour per day basis.
The Woodlawn Underground Project (WUP) will be accessed by a new portal and
decline. Currently two locations for the portal are being considered:
One adjacent to the treatment plant located in Hickory’s Paddock.
The other on the western side of the open pit and just to the north of the up
dip E and G Lenses.
The WUP is scheduled to produce at a maximum of 690 kilotonnes per annum
(ktpa) using three different mining methods:
Drift and half uppers;
Underhand Longitudinal and Transverse Open Stoping; and
Multi-level continuous fill.
Two main mining studies were undertaken on the tailings reclaim process by
TriOrigin in 2007-8. An initial study was undertaken by an independent consultant,
which provided technical and economic assessments for project scoping,
technology applications and broad production rationale. This work was then
followed up with more detailed assessment, including the involvement of Fraser
Alexander Tailings, which is the world’s largest tailings recovery contractor. Under
a monitor-based hydraulic mining scenario the principal drivers for determination of
the optimum throughput are the overall project economic parameters. The low
capital intensity of this mining method, and the relative flexibility in throughputs,
allows relatively linear scalability in determination of production scale alternatives.
There is also no shortage of potential working faces around the dams and
production rates of up to 2.0 million tonnes per annum (Mtpa) are considered easily
achievable with overall hydraulic mining costs on a per tonne basis remaining
similar across the range of throughputs.
A 2008 study was carried out into the appropriate factors (dilution and ore loss) for
converting the resource into a practical mining plan.
Dilution and recovery assumptions adopted are based on an average vertical loss
of 200mm tailings material on the extremities of the dams in the course of
recovering the material by the monitors. Of the remaining material, the assumed
amount of dilution is equivalent to 100mm average vertical gain of the original
block, at no grade. Effectively this material is added back to the product stream
delivered to the sump. In some areas, material with grade will be lost and in other
areas, material with no grade will be added to the product stream. Applying these
criteria, the overall mining loss has been calculated at 3.5%, and the dilution factor
at 3.1%.
The nature of the tailings dam resources and the significant body of historical
information available from earlier operations suggest that the Inferred component
of the resource estimate will be converted to Measured or Indicated resource
category as further drilling and metallurgical test work is conducted. Drilling access
has been restricted in some parts of the dams due to standing water, which varies
depending on local rainfall patterns. The final mining schedule, however, includes
all resource categories of tailings and is presented in Table 16.1.
Financial Year LOM 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
South Dam Tonnes Mined kt 4,290 479 1,140 947 827 792 104 - - - - -
Zn Grade (Equiv.) kt 5.71% 5.71% 5.71% 5.71% 5.71% 5.71% 5.71% 0.00% 0.00% 0.00% 0.00% 0.00%
Zn Grade % 2.43% 2.43% 2.43% 2.43% 2.43% 2.43% 2.43% 0.00% 0.00% 0.00% 0.00% 0.00%
Pb Grade % 1.15% 1.15% 1.15% 1.15% 1.15% 1.15% 1.15% 0.00% 0.00% 0.00% 0.00% 0.00%
Cu Grade % 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.00% 0.00% 0.00% 0.00% 0.00%
Ag Grade g/t 23.4 23.4 23.4 23.4 23.4 23.4 23.4 - - - - -
Au Grade g/t 0.21 0.21 0.21 0.21 0.21 0.21 0.21 - - - - -
West Dam Tonnes Mined kt 3,930 - - - - - 697 900 1,363 970 - -
Zn Grade (Equiv.) kt 6.26% 0.00% 0.00% 0.00% 0.00% 0.00% 6.26% 6.26% 6.26% 6.26% 0.00% 0.00%
Zn Grade % 1.90% 0.00% 0.00% 0.00% 0.00% 0.00% 1.90% 1.90% 1.90% 1.90% 0.00% 0.00%
Pb Grade % 1.44% 0.00% 0.00% 0.00% 0.00% 0.00% 1.44% 1.44% 1.44% 1.44% 0.00% 0.00%
Cu Grade % 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.59% 0.59% 0.59% 0.59% 0.00% 0.00%
Ag Grade g/t 34.9 - - - - - 34.9 34.9 34.9 34.9 - -
Au Grade g/t 0.36 - - - - - 0.36 0.36 0.36 0.36 - -
North Dam Tonnes Mined kt 3,020 - - - - - - - - 530 1,500 990
Zn Grade (Equiv.) kt 6.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.04% 6.04% 6.04%
Zn Grade % 2.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.34% 2.34% 2.34%
Pb Grade % 1.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.38% 1.38% 1.38%
Cu Grade % 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.40% 0.40% 0.40%
Ag Grade g/t 36.9 - - - - - - - - 36.9 36.9 36.9
Au Grade g/t 0.26 - - - - - - - - 0.26 0.26 0.26
Tailings Tonnes Mined kt 11,240 479 1,140 947 827 792 801 900 1,363 1,500 1,500 990
Zn Grade (Equiv.) kt 5.99% 5.71% 5.71% 5.71% 5.71% 5.71% 6.19% 6.26% 6.26% 6.18% 6.04% 6.04%
Zn Grade % 2.22% 2.43% 2.43% 2.43% 2.43% 2.43% 1.97% 1.90% 1.90% 2.06% 2.34% 2.34%
Pb Grade % 1.31% 1.15% 1.15% 1.15% 1.15% 1.15% 1.40% 1.44% 1.44% 1.42% 1.38% 1.38%
Cu Grade % 0.49% 0.47% 0.47% 0.47% 0.47% 0.47% 0.57% 0.59% 0.59% 0.52% 0.40% 0.40%
Ag Grade g/t 31.1 23.4 23.4 23.4 23.4 23.4 33.4 34.9 34.9 35.6 36.9 36.9
Au Grade g/t 0.28 0.21 0.21 0.21 0.21 0.21 0.34 0.36 0.36 0.32 0.26 0.26
A “top down” hydraulic mining approach (Figures 16.1 and 16.2) has been
designed and will use multiple monitors on two faces, with possibly a third unit on
standby backup.
Tailings Dam South is the first dam to be mined, followed by TDW and then TDN.
This selection is based on a Net Smelter Return (NSR) analysis undertaken, which
involved assessing the different dams value on a comparative basis. This aided in
understanding the NSR of each dam, relative to one another. The assumptions
adopted for the NSR calculation were based on the Project’s economic evaluation
model data at that time. Another advantage of mining TDS first is that it liberates a
larger storage capacity for returned tailings, than either TDW or TDN.
The mining method for TDS is based on taking two lifts. The first lift being a full
width extraction to a single mid-dam located channel and sump arrangement at a
low point in the southwest corner of the dam wall.
Tailings will be monitored back to the channel, flowing to the sump and pump
arrangement. The location of the channel has also been placed to maximise the
use of an existing drainage channel on the surface of the dam.
A second lift involving three cells and associated channels has been designed to
maximise recovery and use floor contours to benefit material flow. Bench cleanup
of the floor is planned to progress behind extraction of each cell in the bottom lift.
A floating pontoon, fitted with two submersible pumps, will be installed in the
southern end of the TDS in the standing water on the dam surface. A dual
containment pipeline corridor will be installed on an easement corridor to the
planned plant location and then onto Evaporation Dam 1 (ED1). Standing water
and drain-down water will be transferred to ED1.
Mining of TDW will involve taking 5m high benches, subdivided into two cells with
an associated channel for each cell. The final lift will involve final floor clean up to
the base of the dam.
Mining of TDN will involve five cells based on sections delineated by existing
internal walls constructed during placement of original tailings.
Although the resource model work identified two horizontal domains in TDN, a
mining method that selectively mines these sections has not been designed and
scheduled. It is assumed that the two parts will be bulk mined together.
As the original portals and declines were located within the open pit which Veolia is
using as a bioreactor to generate gas to fire a power station, the Woodlawn
Underground Project (WUP) will be accessed by a new portal and decline from the
surface and outside the open pit.
Two potential areas to locate the decline portal were considered (Figure 16.3)
however geotechnical drilling and testing of Option 1 indicated relatively poor
ground conditions to the east of the open pit which would require considerable
support in the decline.
Option 1 was abandoned in favour of a site located on the eastern side of the
open-pit where ground conditions are known to be more favourable.
Option 2 is immediately to the west of the open-pit. There are a number of sub-
options at this location. Each sub-option will be considered in light of infrastructure
that Veolia require within the defined Veolia Area of Operations for development of
Veolia’s Mechanical Biological Treatment (MBT) facility which is to be constructed
further to the west of the proposed portal location.
These sub-options require a much shorter decline to access the upper sections of
E and G Lens stopes and the mine in general. However, they do require material
to be hauled on surface across or around Veolia’s area of operation. During the
next stage of study Heron plans to investigate the options for hauling material from
the portal location to the processing facility in Hickory’s Paddock, or if relocation of
the processing facilities to the north of the open pit in the area bounded by
Collector Road, the existing Veolia Administration Building, Evaporation Dam 1 and
Veolia’s access road to the MBT Plant is warranted.
Option 2 portal sites west of the open pit not been evaluated in a geotechnical
study but will be included in future work for the FS.
Apart from offering a shorter decline length into the upper reaches of E and G
Lenses, past drilling indicates that there is significant dolerite in this area which
would offer better ground conditions for the development of the portal and decline.
Development of the portal boxcut will be by earthworks contractor whilst
development of the decline will be by mining contractor.
A preliminary design for the western decline spirals on the north side of G Lens
and places the decline as close as practical to both E and G Lenses.
With the portal located closer to the top of E Lens, access to the upper levels of E
and G Lenses can be achieved without any additional incline development.
Figure 16.4 shows the preliminary decline design to access the upper orebodies
west of the open-pit.
The following temporary facilities will be provided by the mining contractor as part
of the decline development contract.
Site offices including temporary connection to water, power and
communications.
Muster and crib room.
Cap lamp room.
First aid & emergency response room.
Ablution block and change rooms.
Workshop & store.
Refuelling and lubrication bay.
Power supply including backup emergency generator.
Surface fans.
Mine pumping system.
Underground communications (leaky feeder).
Compressor.
Water main.
Shotcrete system.
The WUP involves the re-opening of the Woodlawn underground mine that was
closed in 1998 for predominantly economic factors with other mines held by
Denehurst. The Woodlawn mine, under administration at the time, was unable to
provide sufficient guarantee to the administrator on the immediate production
future. During final operations by Denehurst a number of the accessible remnant
ore pillars were systematically extracted whilst other blocks were left untouched.
Figure 16.5: Underground Mine Showing New Stopes and Existing Workings
Proposed
Resource Zinc Lead Copper Gold Silver
Domain % plant
classification (%) (%) (%) (g/t) (g/t)
feed (Mt)
Polymetallic Indicated 26% 0.98 16.1 7.9 2.9 1.3 0.3
Inferred 55% 2.10 2.10 15.5 2.6 1.4 0.8
Copper Indicated 6% 0.24 0.24 10.2 0.8 2.1 1000.1
Inferred 13% 0.48 9.1 9.1 0.3 2.4 0.1
Total 100% 3.80 14.5 6.0 2.2 1.5 0.5
These figures include dilution and ore losses as discussed in Sections 16.4.9 and
16.4.10.
The existing workings (Figure 16.6) for the Woodlawn mine primarily access A, B
and C Lenses. The original mine was accessed by two declines from within the
open pit. These accesses have been plugged and Veolia have commenced
constructing a methane bioreactor within the pit. Consequently an alternative mine
access is required. In the latter stages of the mine operation there are limited
records of what was mined and this has been pieced together from drill designs
and interviews with employees employed at the site during that period. Where
there is any uncertainty to whether the ore block has been mined, the block has
been excluded from the proposed mill feed.
The historic operation generally placed unconsolidated waste to backfill stopes.
The surface ventilation shafts have been backfilled from the surface. No records
regarding the quantities placed in the shafts have been sourced and it is known
that the ladder ways were not removed from the shafts prior to backfilling.
The PEA design, where possible, aims to rehabilitate the mine development where
appropriate to access the remaining Woodlawn deposit.
The mining method has been selected to mine both areas of previous unmined
material and remnant material around the previous mined areas of the deposit.
The mining method selection takes into consideration the location of the existing
open pit above the deposit which is being used a as bioreactor by Veolia.
The mining methods that have been considered are:
Drift and Half-uppers (Figure 16.7).
Underhand Longitudinal and Transverse Open Stoping (Figure 16.8).
Multi-level Continuous Fill (Figure 16.9).
The drift and fill half uppers mining method is planned to be mined in the remnant
areas of the A Lens, B Lens, D Lens, G Lens, H Lens and J Lens.
The stopes are typically 10m to 20m along strike with the shorter strike lengths in
the vicinity of the major faults and between 3m and 20m wide.
The production cycle for the drift and fill half uppers includes the following:
Tight fill old workings below.
Develop footwall drive along the top of the old workings using probe holes in
the face, floor and backs with every cut.
Probe backs along drive to determine old workings location and proposed sill
pillar stability.
Drill and blast backs to required height leaving the new sill pillar.
Construct bulk head and paste fill drive / stope.
Mine next drive adjacent to the paste filled drive / stope and repeat process
across the width of the orebody.
The Multi-level Continuous Fill method has been selectively applied in the B Lens
where there are production areas over multiple levels within the existing mined
area.
The sublevel spacing is governed by the existing development and any new
sublevels are mined at 20m spacings.
The production cycle for the underhand open stoping is as follows:
Tight fill old workings below.
Develop a drive along the top of the old workings using probe holes in the
face, floor and backs with every cut.
Probe backs along drive to determine old working location.
Begin to mine drive on top of old workings.
Drill and blast the lower level stope to the bottom of the old workings.
Retrieve the stope for feeding to the plant while filling with waste rock form the
above drive.
Continue to fill with waste rock to the floor level of the upper drive.
Advance the upper drive and place waste fill as lower level stope is retreated.
The fill drive is used to extract the next crown, becoming the drill drive.
Plant feed will be transferred from production areas to loading bays with
underground loaders and then loaded onto articulated trucks to be hauled to the
surface via the decline and from there on surface to the run-of-mine pad (ROM) at
the processing plant.
The underground mine design has been completed based on the Mineral Resource
Model (BMFinal Classified 20150412 Mined.csv).
Table 16.4 summarises the design parameters applied for the underground mine
design.
Table 16.4: Mine Design Parameters
HW hydr
Vert Typical HW HW
Typical Strike rad. @ HW FW
Location Method height HW dip [rH] dip
N’ length spec. ELOS ELOS
(m) (deg) crit extent
dimensions
Overhand 25 60 0.83 3.5 28.9 10 3.7 1.5 1.0
Around major faults
Underhand 20 60 23.1 10 3.5
Remnant areas Underhand 15 65 4.0 16.6 15 3.9 1.5 1.0
Other lenses above Overhand 25 65 4.0 6.0 27.6 20 5.8 1.0 0.5
2300mRL (exc faults) Underhand 20 65 22.1 20 5.2
Other lenses below Overhand 25 53 2.6 5.2 31.3 15 5.1 1.5 0.5
2300mRL (exc faults) Underhand 20 53 25.0 15 4.7
16.4.9 Dilution
Description Value
Minimum 0%
Maximum 50%
Average 7%
Kate Lens 9%
Lower D& I 16%
Other Lenses 12%
Around Major Faults 20%
Multi-level Continuous Fill 20%
Mining recovery has been calculated based on the shape of stopes and the
mineralisation that is not expected to be recovered. An angle of repose of 45° was
assumed in the calculations. The multi-level continuous fill recovery is based on
the mining recovery typical in a sub-level cave.
Table 16.8: Mining Recovery Assumptions
Mining Recovery
Stope Type
(%)
Stope width < 10m 97.5%
Stope width > 10m 95%
Multi-level Continuous Fill 85%
Table 16.9 presents the cutoff grades used by SRK for each of the mining
methods.
Table 16.9: Cut-off Grade by Mining Method
Total primary airflow requirement has been estimated based on 0.06 m3/s for every
kilowatt power of mobile equipment according to Section 71.3 of the Work Health
and Safety (Mines) Regulation 2014 (NSW). Table 16.10 shows the estimated
peak production required airflow.
In the first year of production only the South Ventilation Rise will be required.
Production from A and B Lens commence after approximately 18 months; at this
stage the North Ventilation Rise will be required. The ventilation requirement will
be evenly distributed between the rises during years 3 to 5 and after the fifth year
the majority of the ventilation requirement will be from the North Ventilation Rise.
Table 16.10: Required Ventilation
3
Equipment Power rating (kW) Units Total power (kW) Total airflow required (m /s)
Primary Ventilation
The primary ventilation system consists of the decline portal as the main air intake
coupled with the northern and southern egress systems. Mine air is exhausted
through two rises connecting to the surface. There are three ventilation circuits;
the South, the Upper North and the Lower North. The maximum capacity of the
designed ventilation circuit is 183m3/s.
The South ventilation system utilises fresh air from the decline and southern
escape way to service primary air to E, G, H and Kate Lenses. The air is returned
through the South ventilation rise as shown in Figure 16.10.
The Upper North ventilation system utilises fresh air from the decline and northern
escape way to provide primary ventilation to A and B Lenses above 2400mRL. Air
from the North Decline is returned though a series of crosscuts to a ventilation rise
system that links back to the Northern ventilation rise. The ventilation circuit ends
at 2400mRL, where the Lower North ventilation system continues.
The Lower North ventilation system provides primary ventilation to the D, I and J
Lenses and the A and B Lenses below 2400mRL. Air from the North Decline is
returned through the Northern ventilation rise. Figure 16.11 shows the interactions
between the North Decline and the two northern ventilation systems.
Secondary Ventilation
Secondary ventilation will be supplied from fans located in the decline via ducting
to the working areas.
16.5.2 Backfill
The mine design has assumed that stopes will be filled with paste fill and the multi-
level continuous fill method using rock fill.
Waste rock and mineralised waste will be identified in the stopes and, where
possible directed to an existing open stope requiring filling.
Preliminary test work undertaken by Outotec has indicated that suitable paste fill
will be able to be made from the Project tailings when combined with lime and low
heat cement.
The paste will be manufactured at the process plant, pumped to and piped down
the decline or delivery holes into the mine for reticulation to the stopes to be filled.
See Section 17.3.10 for further details.
16.5.3 Water
Mine water will be supplied underground via the decline and service holes.
Dewatering of the underground mine will consist of a series of pump stations linked
via service holes, utilising the decline where required.
Compressed air will be supplied underground from a surface compressor via the
decline to each sublevel.
16.5.5 Power
The underground mine will require a 1,000V power supply. The power will be
distributed underground via the decline and service holes where required. The
installation of underground substation has been allowed for in the design.
An emergency egress ladder way system is included in the mine design. Coupled
with the decline, personnel will have a second means of egress from all sublevels
within the mine.
During initial development it is recommended that refuge chambers be advanced
along with the decline development face. Decline stockpiles can be converted to
fixed refuge chambers as necessary to enable all personnel to be within close
proximity of a refuge chamber or fresh air source.
There are two secondary ladder way rises that connect to the surface. The
northern ladder way provides secondary egress to the A and B Lenses above
2400mRL. The southern ladder way provided secondary egress to all other areas
of the mine.
E, G, H and Kate Lenses production areas connect directly in to the southern
ladder way. D, I and J Lenses and A and B Lenses below 2400mRL connect to
the southern ladder way via a rehabilitated drive at 2440mRL that crosses between
A and Kate Lenses and connects to the Kate Lens decline and ladder way.
Figure 16.12 show the two surface connection ladder ways and the escape way
path from below 2400mRL.
SRK have applied typical development rates base on previous experiences. Table
16.11 presents the lateral and vertical development rates including the overall
monthly lateral development capacity.
Table 16.12 summarises the productivities for each mining method. The
underhand stoping longitudinal mining method has separate productivities based
on the strike length and across strike width of the mining panels. The productivities
are the maximum production per year per location and include ore development
tonnes.
Rate
Development
(m/mth)
Single Heading
Decline 120
Rehabilitation 300
Rise 3
General development 60
Multiple headings
Lateral development capacity 720
Rehabilitation capacity 300
Rate
Mining Method
(kt/yr)
Drift and half-upper/longhole 44
Drift and half-upper/transverse 45
Multi-level continuous fill 159
Paste fill beam 39
Underhand stoping/transverse 109
Drift and fill 105
Jumbo mining 5m (W) x 5m (H) 194
Jumbo mining 4m (W) x 4m (H) 124
Jumbo mining 3.5m (W) x 3.5m (H 95
Figure 16.13 shows the annual development profile for the WUP. Ore
development within the stopes is not included in the development schedule
because the ore development is included in the stope production rates and costs.
The lateral development peaks at 5,000m per year excluding rehabilitation in the
second and third year of mining operation.
The mine equipment requirements for the WUP are presented in Table 16.13.
Table 16.13: Mine Equipment Requirements
Equipment No of Units
Truck AD 55 3
LHD R1700 2
LHD R2900l 2
Jumbos 3
Production Drills 3
Service vehicles 1
Light vehicles 3
16.7.3 Personnel
Shift Schedule
The mining costs have been estimated using a continuous mining operation, 24
hours a day, 365 days per year. All employees will be residential in the
communities surrounding the operation.
The WUP is planned to have a 4 days on and 4 days off, 12 hour shifts, roster for
operators and maintenance personnel and a 5 days on and 2 day off, 8 hour shifts,
roster for staff personnel
Personnel Levels
The personnel requirements for WUP are summarised in Table 16.14. All on-costs
for annual / sick leave and training have been estimated in the operating costs. All
equipment has been assigned with one operator per crew per machine.
Table 16.14: Personnel Requirements
Staff Number
Mine Manager 1
Underground Supervisors 4
Mine Technical Services Personnel 7
Jumbo Operators 12
Loader Operators 16
Truck Drivers 12
Longhole Drillers 8
Blasting Personnel 4
Services Crew 12
Grader Operators 2
Maintenance Planner 1
Leading Hand Fitter 1
Fitters 8
Leading Hand Electrician 1
Electricians 4
17 Recovery Methods
17.1 Introduction
The selected process recovery method has been based on co-treatment of the
underground resource and the retreatment of process tailings from the existing
tailings storage dams (TDs). A Front End Engineering Design (FEED) study was
completed on the Woodlawn Tailings Retreatment Project in 2012 (Sara, 2012)
and the metallurgical testing regime conducted as part of the FEED has laid the
basis for the co-treatment flowsheet design. The process plant will consist of both
conventional and fine grinding circuits then utilise differential flotation for the
extraction of copper, lead and zinc concentrates. The concentrates will be filtered
on-site for export via either Port Kembla or Port Botany. The proposed flowsheet
allows for the operation commencing with the plant feed of 100% tailings
reclamation as the underground mining operation ramps up to full production.
A simplified process flow diagram is shown in Figure 17.1 and Figure 17.2 for the
co-treatment plant design. Based on flotation test results achieved, as outlined in
Section 13.0, minimal changes to the original flowsheet design were needed and
this thereby provides for flexibility within the plant to treat a blend of 50% fresh
underground feed with 50% reclaimed tailings.
Feed Grades
- Copper % 1.21
- Lead % 2.34
- Zinc % 5.50
- Silver g/t 49
- Gold g/t 0.56
Copper Concentrate
- Copper Grade % 22
- Copper Recovery % 68
- Recovery of Silver to Concentrate % 10
Lead Concentrate
- Lead Grade % 45
- Lead Recovery % 65
- Recovery of Silver to Concentrate % 5
Zinc Concentrate
- Zinc Grade % 45
- Zinc Recovery % 70
- Recovery of Silver to Concentrate % 5
Operating Hours
- Crushing Circuit - Underground Feed h 6,132
- Milling Circuit - Underground Feed h 7,998
- TSF Regrind Circuit h 7,998
Treatment Rate
- Crushing - Underground Feed t/h 150
- Milling Circuit - Underground Feed t/h 95
- TSF Regrind Circuit t/h 95
- Combined Flotation Feed t/h 190
Feed to the new treatment plant will consist of both fresh sulphide underground
material and reclaimed tailings on a nominal 1:1 blend ratio. Following completion
of the PEA, the blend ratio may be refined during future studies.
TSF Reclamation
The tailings will be reclaimed from the three existing tailings storage dams, Tailings
Dam South (TDS), Tailings Dam West (TDW) and Tailings Dam North (TDN) via a
hydraulic mining method with the material then being screened and pumped to the
process plant. The reclaimed tailings will be thickened and ground to a P80 of
30µm prior to the co-treatment flotation circuit.
The co-treatment flotation circuit employed will utilise a talc, copper, lead and zinc
differential flotation sequence. Talc cleaner concentrate recovered from the talc
flotation cleaner cell will be discarded to final tails to remove some of the talcose
gangue ahead of the differential flotation circuit. A differential flotation circuit for
copper, lead and zinc will be utilised with concentrate regrind stages in the copper,
lead and zinc circuits to produce sales grade copper, lead and zinc concentrates.
The copper circuit will also utilise a rougher and scavenger tailings regrind circuit
prior to the lead flotation stage. Tailings from the flotation plant will be thickened
for recovery of process water and to provide underground paste fill material, with
slime tailings deposited into a new tailings dam, Tailings Storage Facility No 4
(TSF4).
Flotation concentrates from the copper, lead and zinc differential flotation circuit will
be thickened and subsequently filtered for road transport. Copper and zinc
concentrate will be shipped via Port Kembla in bulk carriers. Transport of the
concentrate from site will be by road with concentrate loaded into half height
containers via Front End Loader (FEL) at site. The high precious metals lead
concentrates will be loaded into bulka-bags via a bagging plant at the process
plant. Loaded bags will then be containerised for dispatch via the Port Botany
container port or via the container port at Port Kembla.
Raw water will be supplied to the process plant from the Willeroo borefield. No
water will be discharged from site with excess process water collected in
evaporation dams. The process water circuit will incorporate a water treatment
system for recovery of evaporation dam waters.
A two stage crushing circuit has been selected based on similar applications and
on the historical data from Woodlawn operations. Fresh underground material will
be reclaimed by a FEL to a ROM bin. Feed will be reclaimed by a vibratory grizzly
pan feeder which will screen out undersize material and feed to the primary jaw
crusher. Underground feed will be reduced in size to a P80 of 105mm at the
primary crushing stage, based on a close side setting of 100mm on the jaw
crusher.
Primary crushed feed will be conveyed to a product screen with oversize directed
to a secondary cone crusher. The secondary crusher will provide for the additional
size reduction with a close side setting of 22mm.
The secondary crushing stage will be closed circuited with the product screen. The
final product size will be controlled by the product screen bottom deck to generate
a ball mill feed sized material with a P80 of 10.5mm.
Product sized material will be conveyed to a fine ore bin (FOB) for subsequent
reclaim to the primary ball mill.
Reclaimed tailings, hydraulically mined from the existing tailings dams will be
screened and pumped to the processing plant, where it will be thickened in an 18m
diameter high rate feed preparation thickener to achieve an underflow density of
between 60% and 70% solids (w/w). Thickener overflow will gravitate to the
process water dam for reuse in the hydraulic mining process and process plant.
Thickener underflow will be pumped to the IsaMill feed surge tank by one of two
thickener underflow pumps in a duty / standby configuration. The IsaMill feed
surge tank will provide a 2,200m3 storage capacity, prior to the milling circuit.
Thickened slurry from the surge tank will be diluted to approximately 50% solids
within the mill feed sump and then be pumped by centrifugal slurry pump to the
horizontal type grinding mill. The grinding mill selected is an IsaMill M10000 unit
that will have a volume of 10m³ and will be equipped with a 3.0MW drive. Mill feed
slurry will be ground from an average feed size F80 of 106µm to a product size P80
of 30µm using ceramic grinding media. The grinding mill will be configured in open
circuit. Lime is added to the mill feed to maintain a pH of 5.5 to 6.0.
Product discharged from both the underground grinding stage and tailings reclaim
grinding stage will be transferred to the talc flotation circuit consisting of a
conditioning stage, roughing stage and one stage of cleaning. The final talc
concentrate will be pumped to the flotation tailings sump for disposal. Talc flotation
rougher tails will feed the copper flotation circuit.
The cyclone overflow from the fresh underground milling stage and the tailings
IsaMill will discharge into a 35m³ agitated talc flotation feed conditioning tank. The
tank volume will provide a three minute conditioning residence time at the design
processing conditions.
Reagent additions in the talc flotation circuit include:
Sodium Meta-bisulphite (SMBS) and lime will be added to the talc
conditioning tank.
Frother added to the feed box of the talc rougher flotation stage.
Slurry will gravitate from the talc conditioning tank to the feed box of the first talc
rougher flotation cell. Flotation will take place in forced aspiration flotation cells.
The talc flotation circuit will comprise:
five 10m³ talc rougher tank cells,and
one 10m³ talc cleaner tank cell.
The recovered talc rougher concentrate will be pumped to the talc cleaner flotation
cell and the talc rougher tailings will discharge into the copper feed sump and then
be pumped to the copper flotation circuit.
Talc cleaner concentrate will be pumped to the final tails sump and the talc cleaner
tailings will gravitate from a tails box fitted with dart plugs to either the head of the
talc rougher flotation circuit or to the talc cleaner tail sump for transfer to the copper
conditioning tank.
The talc rougher tailings collected in the copper feed sump will be pumped to the
copper conditioning tank. The copper flotation circuit will comprise a conditioning
stage, roughing and scavenger stages followed by a regrind and two stages of
cleaning on the concentrate and a regrind stage on the circuit tail stream. The final
copper concentrate will be pumped to the copper concentrate dewatering circuit
and the copper flotation tailings will be pumped to a tail regrind circuit ahead of
lead flotation.
The copper feed pump located at the tail section of the talc rougher circuit will
discharge pulp into a 35m³ agitated copper rougher conditioning tank. The tank
volume will provide a three minute conditioning residence time at the design pulp
flow.
Reagent additions in the copper flotation circuit include:
SMBS and lime will be added to the copper feed sump;
copper collector will be added to the copper conditioning tank and the head
of the copper rougher and the copper cleaner cells;
frother added to the feed of the copper rougher cells and the head of the
copper cleaners; SMBS and lime will also be added to the head of the
copper cleaner flotation cells; and
CMC dispersant / depressant will be used as required.
Slurry will gravitate from the copper conditioning tank to the feed box of the first
copper rougher flotation cell. Flotation will take place in forced aspiration type
flotation cells. The copper flotation circuit will comprise the following:
one 10m³ copper tank cell;
two 10m³ copper rougher tank cells;
four 10m³ copper scavenger tank cells;
one SMD Detritor 355kW copper regrind mill;
five 1.5m³ conventional copper cleaner cells;
three 1.5m³ conventional copper recleaner cells, and
one IsaMill M5000 copper tail regrind mill fitted with a 1,500kW motor.
The copper rougher concentrate will be pumped to a regrind mill circuit closed with
hydrocyclones for concentrate size reduction to a P80 of 20µm. Cyclone underflow
will be reground in the Detritor mill while, overflow will gravitate to the copper
cleaner cells. The discharge from the Detritor mill will report back to the cyclone
feed pump, closing the regrind circuit.
Copper scavenger tailings and copper cleaner tailings will discharge into the
copper scavenger tails sump and thence to the secondary cyclone cluster for
classification to produce an overflow P80 of 30µm. Underflow from the cyclone will
be treated by the secondary regrind mill (IsaMill) and will discharge ground product
to the copper tails sump, prior to being pumped to the lead flotation circuit.
The copper cleaner concentrate will be pumped to the copper recleaner flotation
cells and the copper cleaner tails will be open circuited and pumped to the copper
scavenger tails sump combining with tails prior to regrinding ahead of lead
flotation. The copper recleaner concentrate will be pumped to the copper
concentrate thickener and the copper recleaner tailings will gravitate to the copper
cleaner feed box. The recleaner flotation circuit has been designed as a closed
circuit with the first stage cleaning circuit.
Classified and reground tails from the copper scavenger and copper cleaner will be
pumped to the lead conditioning tank. The lead flotation circuit will comprise a
conditioning stage, roughing/scavenger stage followed by lead regrind and two
stages of cleaning. The final lead concentrate will be pumped to the lead
concentrate dewatering circuit and the lead rougher / scavenger flotation tailings
and lead cleaner tailings will be pumped to the zinc flotation circuit.
The copper tail regrind product will discharge into a 35m³ capacity agitated lead
rougher conditioning tank. The tank volume will provide a four minute conditioning
residence time at the design pulp flow rate.
Reagent additions in the lead flotation circuit include:
lead collector, Sodium Isobutyl Xanthate (SIBX), added to the lead
conditioning tank, the lead rougher / scavenger circuit and the lead cleaner
flotation cells;
frother added to the feed of the lead roughers and at the head of the lead
cleaners;
lime added to the lead conditioning tank and lead cleaner feed;
zinc sulphate (zinc depressant) added to the lead cleaner circuit;
SMBS (zinc and pyrite depressant) added to the lead cleaner circuit; and
CMC dispersant will be used as required.
Slurry will gravitate from the lead conditioning tank to the feed box of the lead
rougher. Flotation will take place in forced aspiration type flotation cells. The lead
flotation circuit will comprise the following:
two 20m³ lead rougher tank cells;
five 20m³ lead scavenger tank cells;
one SMD Detritor lead regrind mill (355kW model fitted with a 500kW motor);
one 5m³ lead cleaner agitated conditioning tank;
six 4.25m³ conventional lead cleaner cells, and
five 1.5m³ conventional lead recleaner cells.
The recovered lead rougher concentrate will be pumped to the lead regrind mill
and the lead rougher/scavenger tailings will discharge into the lead scavenger
tailings sump along with the lead cleaner tailings which are then pumped to the
zinc flotation circuit. The lead rougher concentrate size will be reduced to a P80 of
20µm in the lead regrind mill in closed circuit with classifying cyclones. The lead
regrind cyclone overflow will gravitate to the lead cleaner conditioning tank.
Lead cleaner concentrate will be pumped to the lead recleaner cells and the lead
cleaner tails will report to the lead rougher / scavenger tailings sump. Lead
recleaner concentrate will be pumped to the lead concentrate thickener and the
lead recleaner tailings will gravitate to the feed box of the lead cleaners.
The lead rougher / scavenger tailings and lead cleaner tailings from the lead
flotation circuit will be pumped to the zinc flotation circuit. The zinc flotation circuit
will consist of a zinc roughing and scavenger circuit, a cleaner circuit and a cleaner
scavenger circuit. The zinc concentrate will be pumped to the zinc concentrate
thickener and the final tailings will be pumped to the tailings thickener circuit.
Lead rougher / scavenger tailings and lead cleaner tailings from the lead flotation
circuit will discharge into the first of two 35m³ agitated zinc rougher conditioning
tanks. The tank volume will provide 3.5 minutes of conditioning residence time
each, with a total of 7 minutes for the circuit.
Reagent additions in the zinc flotation circuit include:
lime pH modifier added to the first zinc conditioning tank, the zinc
rougher/scavenger circuit, zinc cleaner conditioning tank and as stage
additions to the zinc cleaner circuit;
copper sulphate activator added to the second zinc conditioning tank;
SIBX collector added to the second zinc conditioning tank; and
frother added to the head of the first zinc rougher, and the zinc cleaner
circuit as stage additions.
Slurry will gravitate from the second zinc conditioning tank to the head of the zinc
roughers. Flotation will take place in forced aspiration type flotation cells. The zinc
flotation circuit will comprise the following:
Zinc Rougher Scavenger Circuit:
three 20m³ zinc rougher tank cells;
five 20m³ zinc scavenger tank cells;
five 10m³ zinc scavenger (2) tank cells, and
an 1100 kW SMD zinc regrind mill.
Zinc Cleaner and Cleaner Scavenger Circuit:
one 5.0m³ zinc cleaner agitated conditioner tank;
seven 4.25m³ zinc 1st cleaner conventional cells;
six 4.25m³ zinc 2nd cleaner conventional cells, and
nine 1.5m³ zinc 1st cleaner scavenger conventional cells.
Slurry from the zinc conditioning tanks will report to the zinc rougher and extended
scavenger circuit. The circuit will use the zinc scavenger 2 cells as zinc retreat
rougher cells when treating only tailings feed. Concentrate from each stage is
combined for regrind, whist the tails are treated in sequence down the bank. Zinc
scavenger 2 tail then forms the bulk of the flow of the final tail.
The zinc rougher and scavenger concentrate will be reground by a SMD mill to
produce a product size P80 of 20µm prior to the zinc cleaner circuit. The mill will be
closed circuited with a cluster of cyclones.
Classified concentrate from the regrind will then be pumped to the zinc 1 st cleaner
and the tailings from the first cleaner will be pumped the zinc 1st cleaner
scavenger. The zinc 1st cleaner concentrate will be pumped to the zinc 2nd cleaner.
The zinc 2nd cleaner concentrate will be pumped to the zinc thickener as final zinc
concentrate. Tails from the second cleaner stage will be recycled in closed circuit
back to the first zinc cleaner in combination with the zinc 1st cleaner scavenger
concentrate.
The zinc 1st cleaner cells may be used as zinc retreat cleaners allowing the circuit
to be reverted to the original tailings feed only flotation circuit ahead of
underground feed being available for processing. Concentrate from each
scavenging bank is combined with the zinc 2nd cleaner tail stream and pumped
back to the zinc 1st cleaner in closed circuit. Tails from the first bank of zinc 1st
cleaner scavengers will report to the next bank with the final zinc 1 st cleaner
scavenger tail being combined with the zinc scavenger 2 tails as final tails.
Concentrate Thickening
Final copper, lead and zinc concentrates from the flotation circuits will be pumped
to 6, 7 and 10m diameter high rate concentrate thickeners respectively. Flocculant
will be added to increase the settling rate and underflow density to 60% solids.
Underflow will then be pumped to the associated copper, lead and zinc agitated
concentrate storage tanks by thickener underflow peristaltic pumps. To protect the
copper, lead and zinc filters, in-line strainers will be installed on the discharge lines
from the thickener underflow pumps to remove trash. Overflow from the each of
the concentrate thickeners will gravitate to the retreatment water rapid mix tank.
The control systems for all thickeners will include bed level indication to control the
flocculant addition rates and bed mass pressure indication to control the thickener
underflow pump speed. Rake torque will be measured and the system will be able
to automatically raise or lower the rakes as required.
Concentrate Filtering
The filtration section will be similar for copper, lead and zinc concentrates and will
comprise concentrate storage tanks, filter feed pumps and three pressure filters.
The concentrate storage tanks will be 100m³ agitated tanks for the copper and lead
duties and 200m3 for the zinc concentrate duty. The copper concentrate storage
tank will provide an operational surge time of 15 hours while the lead will provide
17.5 hours and the zinc 13 hours capacity prior to the filtration stage.
Thickened concentrate slurries will be pumped in batches from the respective
concentrate storage tanks for dewatering in the pressure filters. Provision will be
made for the slurry to be recycled to the concentrate storage tank whilst the filter is
in a dewatering cycle or off-line for routine maintenance. The respective filtration
area requirements will be:
28m² expanded to 32m2 for the copper concentrate filter;
16m² expanded to 25m2 for the lead concentrate filter, and
48m² expanded to 60m2 for the zinc concentrate filter.
The pressure filter will dewater the slurry to produce a filter cake containing
nominally 9 to 10% (w/w) moisture and a filtrate. The filtrate will be pumped to its
respective concentrate thickener to reclaim the water. The copper and zinc filter
cakes will be discharged automatically from each filter press into the respective
sections of the concentrate storage shed with lead concentrate discharging to a
lead storage bin.
The copper and zinc filter cakes will be stored on separate stockpiles inside the
concentrate storage shed. The lead concentrate will be stored in a lead storage
bin. The concentrate storage structure will be sized to accommodate inventory for
both the copper and zinc filter cakes with provision to move the stockpiles within
the enclosed building to extend the storage inventory or to provide a drying
mitigation area, should the concentrates not meet Transportable Moisture Limit
(TML) specifications and require further drying.
The concentrate load-out facility will comprise of a direct load-out truck
weighbridge for the copper and zinc concentrates. Both copper and zinc
concentrate will be loaded into half height containers equipped with tarpaulins for
road transport to the bulk freight terminal at Port Kembla.
Lead concentrate from the lead filter will gravitate via a chute to the lead
concentrate bin. The bin will be of a mass flow design with 50m3 of storage
capacity. Concentrate stored in the storage bin will be reclaimed via a feeder to the
lead bagging facility. The lead bagging facility will bag the lead concentrate into
one tonne bulka-bags for transfer to a sea container. Containerised bulka-bagged
lead concentrate will be dispatched either through the container port at Port Botany
or Port Kembla.
Final flotation tailings from the zinc circuit will be pumped to a cluster of de-sliming
cyclones. Cyclone underflow will gravitate to a paste filter feed tank. Cyclone
overflow will report to the tailings thickener.
The underflow from the de-sliming cyclones will be transferred to a 500m3 capacity
paste filter feed tank. A variable speed paste filter feed pump will transfer the
material to a single horizontal belt vacuum filter at a feed density of 60% solids.
Filtrate recovered as part of the filtering process will be pumped to the tailings
thickener for process water recovery. Cake generated by the filter will discharge to
a paste mixer feed conveyor.
Dry mass flow of material fed to the paste mixer will be estimated in the plant
control system by using the calculated mass flow to the filter (from a nucleonic
density gauge and magnetic flowmeter) and the weightometer reading along with
an assumed moisture content of the “dry” material. This dry mass flow will be used
for the ratio control of cement addition.
Filter cake will be discharged into the feed chute of the dual shaft continuous paste
mixer along with binder dosed at a proportion of the measured dry weight of the
feed.
Mixed paste will gravitate from the paste mixer to a conical discharge paste
hopper. The paste hopper is to be mounted on load scales and discharged via a
level control valve to the underground reticulation system.
A 30m3 paste plant flush water tank and a 15m3 air receiver are located near the
paste hopper to aid in flushing the borehole and delivery pipe system.
Binder will be transported to site via bulk tankers and pneumatically conveyed
using a truck mounted compressor and pneumatic conveyor to a 300t capacity
binder silo. The storage silo will be installed on an independent support structure.
A set of high rate screw feeders will be used to transfer and lift binder from the
storage silo to a loss in weight hopper installed above the paste mixer feed
conveyor head chute. Load scales on the hopper and a variable speed screw
feeder will be used to accurately dose binder to the paste mixer based on a ratio of
the calculated dry mass of solids being conveyed to the mixer.
The final tailings, consisting of the talc cleaner concentrate and the de-sliming
cyclone overflow will be transferred to an 18m diameter high rate final tailings
thickener. Additional streams from the water treatment rapid mix tank, the paste
thickener filtrate and tailings dam return water will also feed the thickener with
evaporation dams ED1 and ED2 treated water to a pH of 4-5 against the high pH of
the zinc circuit tail. This will allow for the thickener overflow to reach a more
neutral pH prior to reporting to overflow water. Flocculant will be added to increase
the settling rate and underflow density to between 45 and 55% solids (w/w).
Underflow will then be pumped to the TSF4. Thickener overflow will gravitate to
the process water dam.
17.4 Reagents
Treatment of the sulphide material from undeground by the differential flotation
process will require a specific suite of flotation reagents to ensure activation and
depression of mineral species as well as frothers for froth stability and collectors for
mineral recovery. A summary of the reagents usage is listed in Table 17.2.
Table 17.2: Annual Reagent Consumption
Flotation Reagents
CMC 0.00 0
Antiscalant 0.01 9
Grinding Media
The copper collector will be a dithiophosphate with the trade name Aero® 3894.
The collector is an organic compound that changes the surface chemistry of
sulphide particles thereby making them hydrophobic (water repellent) and
promoting the attachment of the mineral particles to air bubbles via the flotation
cell. The copper collector will be supplied as a 100% concentrated solution in
1,000 litre bulk boxes.
Copper collector will be pumped undiluted to a head tank for distribution to the
copper flotation circuit. Flow control will be provided using variable speed dosing
pumps. Flow rates will be manually measured.
17.4.2 MIBC
The frother will be Methyl Isobutyl Carbinol (MIBC). Frothers are organic
compounds that promote the formation of a stable froth when mixed with air and
water in a flotation cell. The frother will be supplied as a 100% concentrated
solution in 1,000 litre bulk boxes.
Frother will be pumped undiluted to a head tank for distribution through the flotation
circuits. Flow control will be provided using variable speed dosing pumps. Flow
rates will be manually measured.
SMBS is a pyrite and sphalerite depressant. The surfaces of pyrite and sphalerite
can absorb sulphite ions, which prevent collector adsorption, and the reducing
action of the sulphite ions can prevent oxidation and dissolution of copper, hence
preventing activation of zinc and iron minerals. SMBS will be supplied in 1,100kg
bulk bags.
Bulk bags will be lifted by the reagents hoist, split and stored in a SMBS silo.
SMBS will be automatically mixed with raw water on a batch basis to generate a
20% (w/v) solution. A dust collector will be fitted to the SMBS silo. The mixed
SMBS solution will be automatically transferred from the mixing tank to the storage
tank.
The SMBS solution will be automatically transferred from the storage tank to a
head tank for distribution to the talc, copper and lead cleaner flotation circuits.
SMBS solution will be distributed via variable speed dosing pumps. Flow rates will
be manually measured.
Lime will be used to increase the pH of process streams and neutralise the acidic
condition of the stream and to form hydroxides of particular metals. The lime will
be supplied as hydrated lime (Ca(OH)2) in bulk as a powder. Upon receipt at site,
it will be pneumatically transferred into a 200t capacity silo. The hydrated lime will
then be added with water into a lime mixing tank to produce hydrated lime slurry.
Lime will be automatically mixed with raw water on a batch basis to generate a
20% (w/v) slurry of hydrated lime. The hydrated lime slurry will be automatically
transferred from the mixing tank to the storage tank. Both the mixing and storage
tanks will be agitated. Hydrated lime slurry will be pumped via a ring main for
distribution throughout the plant. Individual addition points will be controlled by an
automatic valve and timer.
automatically transferred from the mixing tank to a stainless steel head tank for
distribution to the zinc flotation circuits. The copper sulphate transfer pump
normally draws from the agitated section of the tank but when a low level is
reached, the draw point will be changed to the storage section of the tank. Excess
solution overflows to the storage section of the dual purpose tank.
The mixed copper sulphate solution will be distributed to the plant via a variable
speed dosing pumps. Flow rates will be manually measured.
17.4.7 Anti-Scalant
Anti-scalant will be added to the discharge of both the process water pumps and
mining slurry water pump to inhibit the formation of gypsum (CaS04). The anti-
scalant will be supplied as a solution in 1,000 litre bulk boxes.
Anti-scalant will be distributed undiluted to the discharge of process water pumps
and mining slurry water pump via variable speed dosing pumps. Flow rates will be
manually measured.
Zinc sulphate is a depressant for zinc sulphide minerals. Depressants change the
surface chemistry of selected minerals to depress the action of collectors in
flotation. Zinc sulphate will be supplied in granular form in 1,000kg bulk bags.
Zinc sulphate mixing will be completed manually by the operator. The bulk bags
will be lifted by the reagents hoist, split and then mixed with raw water to generate
a 15% (w/v) solution. The hood over the mixing tank will be fitted with an
extraction fan.
Zinc sulphate will be pumped to a head tank for distribution. Flow control will be
provided using variable speed dosing pumps. Flow rates will be manually
measured.
17.4.9 Flocculant
The flocculant will be an anionic flocculant with a trade name Magnafloc 342.
Flocculants are long chain molecules that aid solids settling by causing individual
particles to stick together thereby forming larger, heavier particles. Flocculant will
be supplied as a powder in 800kg bulk bags.
The flocculant mixing system will be a proprietary packaged plant comprising a dry
flocculant hopper, powder feed and wetting system, mixing tank, transfer pump and
storage tank. Flocculant will be mixed automatically with raw water on a batch
basis to generate a 0.25% (w/v) solution. The flocculant solution will be
automatically transferred from the mixing tank to the storage tank.
Flocculant solution will be pumped by individual progressive cavity dosing pumps
for distribution to the thickeners. Additional dilution water is injected into a mixing
device located in the dosing pump discharge lines near the flocculant dose point.
Flow rates will be manually measured.
CMC is not required for the co-treatment process; however it will be required for
the full tailings retreatment process for the depression of talc.
CMC is a water soluble polymer that is used as a depressant for talc (silicate) type
minerals. CMC is naturally hydrophobic (water repellent). The addition will be
controlled at a slow and steady rate to permit wetting of individual particles and
minimise viscosity build up and prevent agglomeration during the mixing stage.
The CMC will be supplied in bulk bags and mixed in a proprietary packaged plant
comprising a dry CMC powder hopper, powder feed and wetting system, mixing
tank, transfer pump and storage tank. CMC will be mixed automatically with raw
water in batches to generate a 0.2% (w/v) solution. The mixed CMC solution will
be automatically transferred from the mixing tank to the storage tank. CMC
solution will be pumped by dedicated variable speed progressive cavity dosing
pumps to the copper flotation feed conditioning tank, copper cleaner flotation cells
and lead regrind mill. Flow rates will be manually measured.
17.4.11 Binder
Boral stabilment binder (ground granulated blast furnace slag (GGBFS) and
hydrated lime 85:15) will be used in the paste plant as the binder for the de-slimed
sands returned to the underground stopes. The binder will be added at a ratio to
dry tonnes of mine backfill and will be mixed in a paste mixer prior to being
pumped back down to the required backfill stope.
17.5 Services
17.5.1 Control Systems
A multiplexer will be fitted to the OSA to provide for metallurgical samples on each
stream analysis for shift composite samples for metallurgical accounting. The
sample cut timing will be adjusted from the dedicated OSA PC and the sampling
will occur automatically. There will be provision to manually operate the cutter to
obtain samples for calibration.
Plant and instrument air are a combined compressed air system. Plant and
instrument air to the processing facility will be supplied by two screw compressors
arranged as one duty and, one standby machine and via a dedicated air dryer and
plant air receiver.
An additional dedicated air compressor will provide air services to the filter presses
as high pressure air for drying purposes and a separate receiver will be housed at
the filter building for this duty.
Flotation air to the flotation circuits will be supplied by two dedicated blowers
arranged in a duty-standby configuration.
Raw water will be sourced from the Willeroo Borefield and stored in the existing
10,000m³ raw water dam at the plant site. Raw water will then pumped to the raw
water tank at the process plant or process water dam as required. Raw water will
be used for:
process water make up;
reagent mixing;
flocculant dilution;
cloth washing in filtration;
gland water
IsaMill flushing;
regrind milling cooling water;
potable water treatment plant feed, and
fire water.
Raw water will be pumped to the raw water tank and process water dam via the
raw water submersible pumps and the raw water booster pump.
Two raw water distribution pumps arranged in a duty-standby configuration will be
located at the raw water tank. These pumps will distribute the raw water
throughout the entire processing facility. In addition, there will be two dedicated
pumps, arranged in a duty-standby configuration, for gland water.
The lower portion of the raw water tank will provide a dedicated fire water reservoir
for the fire water system. The fire water system will include two pumps, an electric
fire water pump and a diesel driven fire water pump to ensure a continuous supply
of water to the fire system in the event of a power failure.
Raw water will also provide feed supply for a potable water treatment plant.
Potable water will be provided by a reverse osmosis plant designed for 1.5m³/hr
consumption rate and will provide for the potable water services to amenities and
toilets.
Metallurgy
Manager
The processing team will be made up of a three panel roster working on a four
days on and four days off basis. The roster will be a split nightshift to dayshift
rotation based on 12 hour shift cycles which allows for the four panel alignment
and continuous coverage.
18 Project Infrastructure
18.1 Existing Infrastructure and Services
Woodlawn will operate as a shared site with Veolia operations, while maintaining a
separation of the two operations. There will be no shared personnel between
Heron and Veolia; however, there will be site interaction (including invitee to daily
mine meeting) between the two parties for access to pipelines, and the provision of
raw water to the existing Veolia site operations. Woodlawn Project labour
requirements are based on direct personnel only with no allowance for a liaison
officer role with Veolia operations.
Existing infrastructure includes:
a sealed access road to the mine site;
shared administration building and offices;
an existing site laboratory;
raw water tank;
evaporation ponds;
site water pipe systems and pumps, and
an electrical supply sub-station.
18.3 Buildings
New site buildings will be required to support the operation and will include:
administration office including plant and mining offices;
underground support and geology offices;
plant workshop and store;
plant maintenance and stores offices;
laboratory;
training facility;
plant control room;
plant switchrooms;
crib room facilities;
shower house / ablution facilities, and
a new car park facility.
All of the buildings apart from the workshop / stores sheds will be transportable
style sandwich panel buildings constructed on a steel sub frame. The buildings will
be pre-wired for telephone, data, light and 240V power. The location of these
buildings is shown on the site plan.
The plant workshop and stores sheds will be of steel framed and clad construction.
Electrical power for the operation, estimated to be an average load of 12MW for
the processing plant and associated services, and excludes the underground
mining requirement.
415V (3 phase supply) for the plant equipment and to 240V for single phase supply
as required.
Power factor correction equipment will be installed as part of the new works to
ensure a minimum power factor of 0.95 lagging.
Raw water will be sourced from the Willeroo Borefield and stored in the existing
10,000m³ raw water dam at the plant site.
Borefield raw water transfer pumps will be located at the Willeroo Borefield. The
pumps will be dedicated to supplying water to the raw water dam.
Water from the evaporation ponds will be re-used in the process plant as part of
the make-up water requirements. The water has high ion content and a low pH
and will be mixed and treated in a water treatment rapid mix tank using lime from
the process plant system to neutralise the pH and drop out ion species. The water
is then pumped from the rapid mix tank to the tailings thickener for clarification and
recovery as thickener overflow water to the process water dam.
Potable water will be generated onsite from a raw water supply to a reverse
osmosis plant.
18.5.4 Sewage
produced by the plant will be discharged to the new TSF4. Ongoing operation of
the system will require only general maintenance of the pumps, agitators and air
blower.
18.7 Communications
Telecommunication land lines are currently available adjacent to the site. It is
proposed to connect the plant offices PABX to the existing Telstra cable to
establish reliable voice communications.
There are a number of wireless providers, for mobile telephone coverage in the
area. During the site visit it was observed that mobile coverage was sporadic and
only particular carriers provided a service that takes in the plant site. To ensure
reliable mobile wireless coverage of the site for broadband internet connectivity it is
proposed to install a radio repeater at the site.
For internal communications on site it is proposed that mobile radios be used to
supplement the copper wire telephone systems.
18.8 Accommodation
No accommodation will be provided; all employees will reside in local townships or
will commute from the regional cities of Goulburn or Canberra.
18.9 Security
New security fencing will be erected around the process plant, administration and
mine office areas. No allowance has been made for front gate access security
boom gates.
18.10 Roads
18.10.1 Site Access Road
A new access road approximately 350m in length will be required to access the
plant site from Collector Road. This new road will enable two B-double trucks to
pass and will also cater for the operations’ light vehicle traffic. A tee junction
intersection will be provided on Collector Road in accordance with the
requirements of the local authority. This is a public road and it is currently used by
the trucks and light vehicles accessing the adjacent Veolia waste treatment site.
Due to the lifespan of the mining operation, maintenance cost considerations and
the issue of fugitive dust from an unsealed road; it is proposed to pave the full
length of the new road and the main traffic loop within the plant site.
Internal roads will not be sealed, but will be made from crushed aggregate locally
sourced.
The Project provides greatest exposure to zinc, followed by copper then lead.
Based on an internal review of forecast prices for the payable commodities, Heron
has selected price series for the economic analysis which align with consensus
expectations of metals prices during the modelled period during which the mine will
operate. These assumptions are detailed in Section 22.4.2.
Heron commissioned an independent report on Marketing and Logistics which was
prepared by BPDT & Co Pty Ltd (2015). The report examined the movement of
product from site to port, storage, ocean freight, expected TC/RCs for the three
concentrates, and marketability.
Based on indicative product specifications, all three products are considered
readily marketable. There is potential for a penalty charge to be applied to lead in
the copper concentrate. Otherwise, it is expected that concentrates will be sold to
smelters or traders on normal industry terms.
The author has reviewed the concentrate treatment charges, payabilities and
commodity prices projected by Heron and the results support the assumptions
used in this technical report.
19.2 Contracts
There are no contracts in place for the Woodlawn Project at this stage.
As is normal for such approvals, the DPE imposed a number of conditions on the
approval including to:
prevent, minimise, and / or offset adverse environmental impacts;
As is normal for such approvals, the DPE imposed a number of planning and
reporting requirements, including development, submission to DPE for approval,
and maintenance of its Environmental Management Plan.
In June 2014 the Company submitted its Environmental Management Strategy
(EMS) required under the Project Approval. The EMS:
provides the strategic framework for the environmental management of the
project;
identifies the statutory approvals that apply to the project;
describes the role, responsibility, authority and accountability of all key
personnel involved in the environmental management of the project;
describes the procedures that would be implemented to:
- keep the local community and relevant agencies informed about the
operation and environmental performance of the project;
- receive, handle, respond to, and record complaints;
- resolve any disputes that may arise during the course of the project;
- respond to any non-compliance, and
- respond to emergencies,
and includes:
- copies of any strategies, plans and programs approved under the
conditions of this approval, and
- a clear plan depicting all the monitoring required to be carried out
under the conditions of this approval.
Under the EMS, the main plan relevant at this stage of the development of the
Project is the Construction Environmental Management Plan and the Construction
Mining Operations Plan. It is noted that the EMS will be updated as required to
incorporate the provisions of operational management plans and ultimately provide
and overarching framework for the management of the Woodlawn Mine.
The subsidiary plans which will fall under this EMS are, as required by the Project
Approval:
Construction Environmental Management Plan.
Tailings Rehabilitation Strategy.
Extraction Plan (for underground mining).
Subsidence Monitoring Program (included in Extraction Plan).
Water Management Plan, including: Surface Water Management Plan,
Groundwater Management Plan, Surface and Groundwater Response Plan.
Noise Management Plan.
Blast Management Plan.
Air Quality Management Plan.
Waste Rock Management Plan, with particular emphasis on the
management of potential acid forming material.
Vegetation Management Plan.
Rehabilitation Management Plan.
Road Transport Protocol.
Heritage Management Plan.
The subsidiary timing of the management plans are at an advanced stage and
relate to the stage of development, with 11 of the plans fully drafted and the
remainder being works in progress. The operational plans are required prior to
construction commencing while the Extraction Plan and Subsidence Monitoring
Program are required prior to the commencement of the Woodlawn Underground
Project.
Feature Objective
Mine Site (as a whole) Safe, stable and non-polluting with no final voids on
the surface. Integrated with the rehabilitation of the
Woodlawn Landfill. Re-vegetated with plant
species characteristic of Western Tablelands Dry
Forest vegetation community.
Waste rock dumps Any seepage from the waste rock dumps to be
contained and treated on the site.
Feature Objective
surrounding rehabilitated areas.
An amount of A$4.5 million was estimated as the net cost of closure and
rehabilitation during the BFS for the WRP (Intermet, 2008). The inclusion of the
underground does not materially affect the surface disturbance for the Project. For
the purposes of this study, an amount of A$9 million has been allowed at project
closure for closure and rehabilitation.
On 19 March 2014 the Company was notified that the Division of Resources and
Energy, NSW Trade and Investment, had approved the transfer of title in SML 20
into the name of Tarago Operations Pty Ltd, a 100%-owned subsidiary of Heron.
The approval includes the lease terms and conditions including a security bond of
A$3.577 million that will need to be provided prior to operations commencing.
SRK prepared the estimates for the mine operating and associated administration
costs. GRES prepared estimates for the processing plant, maintenance and
infrastructure costs, together with their associated overheads. Heron provided
estimates for owner’s costs. These estimates are described below.
Operating costs for the co-treatment plant have been estimated to an accuracy of
±25%. The costs are presented in Australian dollars (A$) and are based on prices
obtained during the first quarter of 2015 (1Q15) and exclude the GST cost
component.
The costs cover the reclamation mining process but exclude the underground
mining costs. Both the tailings retreatment and the additional underground
crushing and milling requirement costs have been captured as part of the main
processing plant. This also includes all the flotation, dewatering, materials
handling and service and administration costs.
21.1.2 Summary
Operating costs have been developed using the parameters specified in the
process design criteria. Annual operating costs and costs per tonne of co-
treatment (50/50 basis) have been developed and are summarised in Table 21.1.
The operating cost estimate has been developed on the basis of a process plant
feed tonnage of 1.5Mtpa.
The operating cost estimate is A$35.11 million per annum or A$23.41 per tonne of
feed.
The reagent component of the operating cost is subject to exchange rate
fluctuation and was based on 0.80 A$:US$.
Processing Costs
Processing Costs
The operating costs presented have been calculated from first principles and
budget quotations for supply of chemicals, materials and services. Process plant
operating costs are considered to have an accuracy of ±20%. The following items
have been excluded from the operating cost estimate:
Royalties – included in financial analysis.
All head office costs and corporate overheads.
Exchange rate variations.
Escalations.
Project financing costs.
Interest charges.
Political Risk Insurance.
The Australian Goods and Services Tax (GST) will not be a cost to the Project as
an income generated by the Project in the form of product sales is GST free (as the
products are considered export commodities) and will not attract output credits.
However, the GST has cash flow implications for the Project, as GST will be
applied to most inputs, including consumable costs. Any GST payable on the
following inputs can be claimed back from the Australian Taxation Office (ATO):
Land compensation / land owners costs.
Subsidies to the local community.
Rehabilitation costs.
Amortisation and depreciation charges.
Tailings Reclamation
Tailings reclamation costs are split into direct tails mining costs (sluicing and
screening) as part of HMS supply and processing related tails reclamation costs
associated with the tailings feed preparation thickener.
TSF4 construction costs are described in the capital cost estimate.
Product
Product transport from site by truck in proprietary lined sea containers has been
excluded from operating cost estimates.
Product marketing costs have been excluded.
Treatment and refining of the concentrate smelters by have been excluded.
Tailings Storage
Future wall lifts on TSF4 have not been included within the operating cost.
Environmental
Plant site rehabilitation costs have been excluded from the operating cost estimate.
Tailings rehabilitation costs have been excluded from the operating cost estimate.
Environmental sampling and monitoring costs have been estimated as an
incremental allowance to the existing environmental costs and include additional
assay costs, additional contracts/ consultants costs and general consumables.
Labour
Consumables
The consumption of reagents and other consumables are based on rates from the
metallurgical testwork and GRES experience.
All reagent and consumable costs have been sourced from suppliers and are
calculated as free-in-store at the Project site.
Utilities
The power schedule is based on the equipment list prepared by GRES. GRES has
calculated the power draw based on utilisation factors.
The power cost is based on grid power at a unit rate of A$0.113/kWh.
Laboratory
An allowance has been made for metallurgical laboratory facility only with an offsite
lab to conduct daily assay and environmental work. No onsite allowance has been
made for a chemist or wet laboratory staff.
General and administration costs have been estimated from other similar
operations.
SRK developed the operating costs by mining method. The unit costs for each
mining method include the lateral development, drill and blast, bogging, haulage
cost to the ROM pad, rock backfill and paste fill. Table 21.3 presents the unit cost
for each mining method.
Table 21.3: Unit Costs by Mining Method
Tailings mining operating costs are based on the mining cost estimates for the
WRP FEED Study (Sara, S. 2012), amended to allow for the change in scale of the
mining. For the purposes of the PEA, it a mining cost of A$1.67 per tonne of
tailings plant feed is assumed when the plant is being fed on tailings alone (i.e. at a
maximum rate of 1.5Mtpa), and this has been increased to A$2.15/t of tailings plant
feed when the tailings material is being co-treated with underground material.
Labour
The workforce will reside locally and drive in and out to the operations on a daily /
shift roster basis. Working cycles have been established to provide to the
minimum number of total employees by using current Australian shift cycles.
Woodlawn reclamation personnel will work the following proposed rosters:
Table 21.4: Proposed Work Rosters
The labour rates and personnel numbers used for the salary cost estimate are
summarised in Table 21.5.
Table 21.5: Personnel Numbers and Labour Rates
Production
Maintenance
Shared Resources
Power
The power demand has been calculated to be 11.8MW, with an annual usage of
86,000MWh for the processing plant. A figure of A$11.3 cents per kWh has been
generated from the current agreed tariffs, but is not a final contract price for power.
The calculated total power cost for the Woodlawn Project is A$9.7 million per year.
Consumables
Reagents and media consumption make up the largest part of the operating cost
estimates and have been based on the previous testwork regime for the WRP and
current flotation results for the 50/50 blend of fresh underground feed to reclaim
tailings.
All reagent costs have been based on dry powder bulk delivery to site with onsite
mixing required. Some of the reagents such as MIBC and A3984 will be supplied
in liquid form in 1,000 litre liquid bulk containers.
The grinding media consumption and cost have been based on similar applications
and advised by the vendor in the case of IsaMill ceramic media and the Metso
SMD ceramic media costs. The grinding media steel consumption is based on
similar operations and previous abrasion index figures and equates to 0.8kg/t.
The unit costs and consumptions used for the reagent cost estimate are
summarised in Table 21.6.
Grinding Media (3.5mm MTX Ceramic 5.50 0.15* 230* 1,267,905 0.85
Beads)
Plant Maintenance
Plant maintenance has been based on an estimated spares and consumables cost
for each section of the plant and equates to 5.05% of the operation cost at A$2.15
million.
Laboratory
An allowance has been made for a metallurgical laboratory facility only with an
offsite lab to conduct daily assay and environmental work. Contract wet assaying
costs have been estimated at A$552,000 per annum and are included within the
Processing Administration costs.
A capital cost estimate has been prepared as part of the scope of works and
covers the areas of design, supply, fabrication, transport, construction and
commissioning of the processing plant and support infrastructure facilities
proposed for the development of the Woodlawn Process Plant
Allowances have been made in the estimate where necessary for the upgrade of
existing infrastructure required to support the new processing plant. These items
of existing infrastructure include the high voltage power reticulation network, raw
water harvest and storage system and waste water evaporation / storage facilities.
Estimates have been based upon commodity quantity estimates developed from
preliminary engineering design, budget price quotations for major process
equipment and current market costs for site labour, construction equipment and
construction materials. Unit rates developed from tenders recently received from
the market place were applied to develop costs for the various construction and off-
site fabrication activities.
The quantity of man hours and therefore costs for engineering design,
procurement, construction management and commissioning were all estimated
from first principles using in-house data and experience gained from similar
projects.
The capital cost estimates presented in this document are considered to have an
overall accuracy of ± 25%. All estimates are presented in Australian dollars (A$)
and have been based on pricing obtained during the first quarter of 2015 (1Q15).
21.2.2 Summary
Table 21.8 details a summary by processing area of the capital cost estimate for
the design, construction and commissioning of the new processing facilities.
Table 21.8: Capital Cost Estimate Summary
Further, to allow the assessment of potential staged development scenarios for the
processing plant, commencing with the tailings plant and adding additional
components to support the underground at a later date, the capital estimate has
been broken down in Table 21.9 into:
1. elements required to support a tailings only operation, together with those
other elements required to support the underground operation whose
installation cannot practically be deferred; and
2. additional elements over and above those in item 1 above required to
support the underground operations.
Table 21.9: Plant Capital Breakdown to WRP and WUP Components
SRK derived the mining capital costs from benchmarking of similar sized
operations and first principle calculations.
Item Total
(A$M)
Boxcut & Portal 1.0
Development 78.51
Rehabilitation 8.85
Vertical Development 10.23
Mine Infrastructure 6.29
Mine Sustaining Capital 6.10
Total 110.98
Refer to Section 21.2.11 for details of additional capital items which have been
detailed in the owners’ costs.
The capital cost estimate presented in this study relate to capital works required to
construct a new processing plant and support infrastructure facilities. Design
criteria and flowsheets for the process plant and infrastructure were developed
using historical data, metallurgical testwork data and in-house experience.
From the developed processing route, plant equipment selections were made and
plant layouts were developed. Sufficient preliminary engineering design was
undertaken to ensure the functionality of the proposed layouts, suitability of
equipment specifications and to enable construction material quantities to be
estimated.
The following qualifications and exclusions apply to the capital cost estimate
presented in this Study:
No allowance has been made for interest charges or capital financing costs.
No allowance has been made in the estimate for exchange rate fluctuations
with respect to equipment sourced from outside Australia.
No allowance has been made for Goods and Services Tax or sales tax.
The estimate assumes power supplied to the incoming terminals of the new
66kV/11kV substation transformer from the Essential Energy local grid
supply.
All equipment pricing included in the estimate assumes the purchase of
new equipment.
All freight costs included in the estimate are Free on Transport (FOT) site.
Messing and accommodation costs for the construction workforce have
been included at A$125 per man day. The estimates assume that the
workforce will be accommodated in local towns.
The estimate assumes that plant assays will be undertaken by a contracted
(off site) analytical facility.
An allowance of A$1M has been made for surface works associated with
establishing the box cut and portal for the commencement of the underground
decline.
Lateral Development
Vertical Development
Mine Infrastructure
The allowance for the underground mine infrastructure for the WUP is detailed in
Table 21.13.
Table 21.13: Underground Mine Infrastructure - Capital Estimates
Underground mining sustaining capital has been allowed for in the mining
operating costs.
The capital cost estimate presented in this study relates to capital works required
to construct a new processing plant as defined by the process design criteria,
process flowsheets and plant layout. This estimate has been compiled on the basis
that the design and construction of the processing plant is executed under a lump
sum, turnkey (EPC) style of contract.
Preliminary equipment sizing for the selected duties was undertaken and has been
used in the plant layout and for vendor supplied capital equipment costs.
Estimates for structural steel requirements and allowances for plant process and
service piping have been based on similar sized plants and the proposed layout.
Plant sustaining capital costs have been allowed for in the plant operating costs.
21.2.8 Infrastructure
The capital cost estimate compiled for the plant services components of the Project
were based on requirements dictated by the preliminary process plant design, the
level of existing infrastructure available to the Project and investigations carried out
to determine the most suitable and economic solutions for the Project.
No allowance has been made in the estimate for supply of the power line from the
Essential Energy local grid to site. All new power to site will be provided by the
Essential Energy local grid. The major plant services included in the capital cost
estimate were:
Site process water reticulation system (excluding bore field).
Tailings thickening and slurry disposal pumping system (TSF4 design and
construction cost estimate to be completed by others).
Site wide 11kV power reticulation system within the Project site.
Potable water reticulation system (shared with the existing development).
Plant internal access roads and local site drainage system.
Tailings return water pumping system.
Site communications.
An allowance has been made in the capital estimate for the purchase of mobile
equipment required to operate the processing plant.
21.2.9 Contingency
The contingency allowances adopted for the estimate were based on the Project
scope outlined in this study document and do not include for changes to the
process flowsheet, process plant design or major equipment selections.
Contingencies in this regard are defined as an allowance for errors and omissions
based upon data assumed and equipment detailed as the basis for this study.
The estimate for EPCM services was developed from first principles for the
personnel required to perform all activities associated with the Project, for the
planned duration of the Project. The involvement of each team member was
individually estimated based on the complexity of the task and benchmarked
against the EPCM costs incurred on recent similar projects. The design,
procurement and management aspects of this work will be undertaken off site in
the offices of the EPC engineer.
The capital cost estimate contains an allowance for a site based construction
management team and site supervisors to be engaged for the duration of the site
works. Travel, site vehicles and site accommodation costs for these people have
been included in the study estimate.
Commissioning
Applicable engineering labour rates have been adopted for the commissioning
team. The team will consist of engineers from various disciplines, the relevant
vendor commissioning representatives and a team of tradesman selected form the
construction workforce. A travel allowance has been made to transport the
dedicated commissioning team to and from the site.
Certain items of major equipment such as the IsaMill, regrind mills, flotation cells,
filters and the thickeners will require vendor representation on site during final
commissioning. A vendor commissioning hire cost and travel allowance have been
included in the estimate for this purpose. This expenditure will ensure that
equipment warranties are preserved and any early operating issues are resolved
ahead of hand over. The vendor commissioning rates used in the capital estimate
were supplied to GRES with the equipment tenders.
An allowance has been made for the hire, establishment, operation and removal of
temporary construction offices, crib rooms and ablutions for the construction
workforce.
An allowance has also been made for site vehicles for the construction
management team and construction trades personnel.
Estimates of the mobilisation and demobilisation costs for each of the construction
contractors have been included in the capital cost estimates. These costs have
been based on data sourced from recent projects and make allowance for
materials, equipment and personnel.
22 Economic Analysis
The economic evaluation for the Woodlawn Project has been prepared based on
the mining schedules and mining costs estimates prepared by SRK and described
in Section 21, the process and infrastructure costs for a 1.5 million tonne per
annum plant prepared by GRES and described in Section 21, from information
contained within the WRP BFS (Intermet, 2008) and FEED Studies (Sara, S.
2012), from an independently prepared market study (BPDT & Co, 2015), and from
management estimates.
References to the relevant sections of this report or to other reports published by
Heron are provided in the subsections below.
Base Case
(Forecast Commodity Price Deck)
For the Base Case and in particular noting the expected metals prices described in
Section 22.4.2, the chart below shows the estimated breakdown of revenues by
commodity across all concentrates on a post-payability basis, but pre-TC/RCs.
Refer to Section 27 for definitions of the C1, C2 and C3 costs described herein.
The costs for the project in the Base Case, expressed in relation to Zinc in
concentrate shipped, are estimated to be:
Table 22.2: Economic Model - C1, C2 and C3 Costs - Zn Only Basis
C1 -7 0.00
C2 574 0.26
C3 693 0.31
The negative C1 cost is driven by the significant cost credits associated with the
by-product streams (Cu, Pb, Ag and Au). If the two major by-products Cu and Pb
are expressed in zinc equivalent tonnes and treated as primary product (with the
by-products then being Ag and Au only), the resulting costs are estimated to be:
Table 22.3: Economic Model - C1, C2 and C3 Costs - Zn, Cu, Pb Basis
C1 1,076 0.49
C2 1,395 0.63
C3 1,460 0.66
Figure 22.2 shows the marginal cost of production for zinc since 1981 to the
present, with a forecast to 2018, referenced from Morgan Stanley’s Commodity
Manual (Longson et al, 2015). Based on the 2017 forecast data, it can be seen
that the Woodlawn Project’s expected costs are expected to place the Project in an
attractive position on the cost curve.
The calculations above are based on an adjusted methodology and hence differ
from the numbers released to the market on 22nd April 2015.
Table 22.4 by category of expense, expressed per tonne of plant feed. These costs
are presented as the average across both the underground and tailings
components of the 15Mt of plant feed.
Table 22.4: Economic Model - Cost Breakdown Expressed as US$/t Plant Feed
Mining 10.9
Processing 17.4
G&A 2.3
Royalties 2.4
Realisation 22.5
Capital 11.6
All-in-Costs 67.2
Category % Contribution
Measured 0%
Indicated 32%
Inferred 68%
Total 100%
A total of 11.2Mt of tailings material has been included in the production schedule
for the PEA, broken down by resource category in Table 22.6:
Table 22.6: Economic Model - Tailings Resource Categorisation of Plant Feed
Category % Contribution
Measured 47%
Indicated 37%
Inferred 16%
Total 100%
This PEA includes only the tailings material previously classified as a Mineral
Reserve under the WRP BFS (Intermet, 2008); however, it is included here on a
Mineral Resource basis as described below. Additional Inferred material
comprising approximately 400,000 tonnes of Resource has not been included in
the Plant Feed Estimate for this PEA (but was included in the WRP BFS).
As a general rule, forward looking economic assumptions have been chosen using
fixed values considered representative rather than using time varying forward
assumptions.
Much of the cost base associated with the Woodlawn operation will be based in
Australian dollars, whilst the revenues will be principally earned in US dollars
(US$). Hence the exchange rate between the US$ and the A$ has a material
impact on the project cash flows.
A stepped exchange rate has been assumed by Heron based on the forward curve
as at 31 March 2015 according to Table 22.7:
Table 22.7: Economic Model - Exchange Rate Assumptions
Year A$:US$
2016 0.76
2017 0.75
2018 0.75
2019 0.75
2020 0.74
Lower exchange rates generally benefit the project economics; higher ones have
an adverse impact. Naturally, the project NPV sensitivity to the exchange rate is
approximately equivalent to the sensitivity to changes in commodity prices (though
in the opposite direction). As at 29 May 2015 the exchange rate was
approximately 0.77 A$:US$.
For the purposes of the model, no inflation has been applied either to costs or to
revenues. As a result, a real, post-tax discount rate has been applied to the
Project.
The selected discount rate of 8.3% is approximately equivalent to a post-tax
nominal discount rate of 10%, based on an inflation rate of 2.5% p.a.
No terminal value has been associated with the Project.
The metals prices assumed by Heron in the modelling are shown in Table 22.8.
These prices have been based on analysis of forecast commodity price data from a
number of different sources, with the selected prices being in the middle of the
range of expected outcomes. Nominal prices have been deflated for inflation at
2.5%, are expressed below in 2015 dollar terms, and have been held constant for
the duration of the model.
The project is subject to Australian corporate tax, which has been applied at 30%.
Tax calculations are impacted by depreciation deductions for capital items.
New South Wales levies mineral royalties for extractive operations within the state.
The royalties are based on an “ad valorem” value of minerals, being 4% of the ex-
mine value less allowable deductions.
Allowable deductions are confined to the direct costs incurred in upgrading the
mineral, after the first stockpile, and bringing it to market, and include crushing and
milling, concentration, assaying and analysis, realisation costs, and a depreciation
allowance. When applied to the project costs, the equivalent royalty expressed as
a percentage of net smelter revenue averages approximately 3.0% over the life of
mine.
Opening capitalised exploration expenditure of A$12 million has been depreciated
on a unit of production basis.
Heron’s opening tax losses of A$60 million have been fully netted against the
project tax calculations. In addition, A$44.3 million of the A$53 million in additional
losses subject to the available fraction rule have been netted against the project
tax calculations. These losses reflect accumulated losses for the group companies
and are based on preliminary independent advice received following the merger
between Heron and TriAusMin.
Goods and Services Tax (GST) cash inflows and outflows have been excluded
from this analysis.
The cost of transportation to port, port handling and storage charges, and ocean
freight has been estimated assuming that the concentrates will be shipped with a
moisture content of 10%.
The payability and TC/RC terms vary by concentrate and commodity depending on
the concentrate specifications and the levels of by-products in each concentrate
Independent advice has been sought to provide estimates for these based on
expected concentrate characteristics. The assumptions are in line with normal
market terms, and are equivalent to the values shown in Table 22.9:
Table 22.9: Economic Model - Selling Expense Assumptions
Transportation 6.1
Treatment 15.3
Refining 1.2
The underground Resources falls into two main types, a “Polymetallic” type which
refers to polymetallic massive sulphide mineralisation with high-grade Zn and Pb,
and a “Copper” type which refers to Cu dominated massive and stringer sulphide
mineralisation. The mining schedule preferentially feeds the Polymetallic material,
with the Copper material generally being skewed to the later stages of the
production profile as shown in Figure 22.4.
The mining from underground is split between areas away from previous mining
(“New Areas”) and areas around previous mining (“Remnant”). Approximately 80%
of the underground production schedule is based upon the mining of the New
Areas, with the breakdown over time as shown in Figure 22.5 below.
A one month stockpile on the ROM pad has been assumed for the underground
production, consistent with the previous operations. Reclaimed tailings are fed
directly into the mill after thickening.
The UG Starter Case will produce three concentrates, being a 45% zinc
concentrate with potentially payable silver credits, a 45% lead concentrate with
payable copper, silver and gold credits, and a 24% copper concentrate with
payable silver and gold credits. Details of the concentrate specifications, based on
the inputs described in this Section are shown in Table 13.7 and Table 13.8 in
Section 13.3.10.
The concentrate specifications are based upon the metallurgical testwork carried
out during the PEA and the previous WRP BFS (Intermet, 2008) as described in
Section 13. They are considered representative, though concentrate grades and by
product streaming to the concentrates will be impacted by the mix of feed entering
the plant as well as by the flotation conditions at that time. Although similar to the
previous operations over 20 years, the new plant will utillise modern energy
efficient fine grinding machines with inert media to aid in optimisation of recovery
characteristics to the different concentrates.
Further testwork will be undertaken during the FS to improve recoveries and refine
product specifications.
Design work for the PEA has been based on start-up of operations on retreatment
of tailings from previous production, and moving to processing a blend comprising
0.75Mtpa fresh underground material and 0.75Mtpa of tailings from the previous
operations. Refer to Heron’s announcement of 11 February 2015 titled “Successful
Metallurgical Testwork” for details of the flotation results from the PEA testwork
programme for the polymetallic and the blended underground & tailings samples.
Based on the testwork, the recovery outcomes to concentrates are described in
Table 22.11, and Table 22.13, firstly as the constituent parts, and then as a
blended outcome, all summarised over the life of the mine.
Table 22.11: Economic Model - Concentrate Recoveries - Underground
Refer to Section 21.1 for details of the mining and plant operating costs.
Underground Mining
Underground mining costs have been developed by SRK from first principles
based on the mining method, vertical development, horizontal access, stoping and
back fill costs, and vary according to the physical location and characteristics of the
mined material within the underground. The capital cost profile is shown in Table
22.16. The operating costs generally range between A$49/t and A$54/t on a mill
feed basis based on contract mining (and leased equipment) and including
maintenance costs, with variations based on the mining style chosen and individual
stope characteristics.
Tailings Mining
Tailings materials will be recovered from the three tailings dams in sequence,
utilising the proven technique of high pressure water jet monitoring. The pulped
material will then be pumped to the concentrator, thickened, and processed. The
mining rate is tied to the mill feed ramp-up rate, described below, and the resulting
schedule is provided above. The cost assumption for mining the tailings material is
A$2.14/t whilst blended feed is processed, reducing to A$1.67/t mill feed when the
plant is running on tailings alone.
Operating Costs
The operating cost estimate has been developed on the basis of a process plant
feed tonnage of 1,500,000 tonnes per annum. The operating cost estimate is
A$23.41 per tonne of feed and is shown in Table 22.14.
Table 22.14: Economic Model - Plant Operating Costs
Refer to Section 21.2 for details of the mining and plant capital costs, which
includes the costs associated with the underground mine access and rehabilitation.
Capital costs have been modelled in Australian dollar terms, with no allowance
made for movements in exchange rates for items supplied from overseas.
Pre-production capital is recognised for tax and accounting purposes at
commissioning, and depreciated according to normal protocols. For major plant
items, depreciation has been based on a 15 year equipment life, and for all other
capital items depreciation is recognised based on a unit of production measure.
A summary of the initial capital cost estimates (±25%) and inclusive of a 7.7%
contingency is provided in Table 22.15.
Table 22.15: Economic Model – Initial Capital Costs Summary (to Peak Cash Draw)
Financial statements are shown post-tax but pre-financing. They are for the Project only and do not include corporate overheads
or income / expenditure from other projects held by the Company. The financial statements are based on management’s
preliminary assessment of the Australian accounting treatment for each item.
Profit and Loss
Table 22.17: Economic Model – Project Pre-Finance Profit and Loss Summary
P&L Total 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Zinc Concentrate Revenue A$m 987.7 - - 25.8 91.3 119.4 170.3 157.9 119.5 69.1 56.1 61.9 70.1 46.2
Lead Concentrate Revenue A$m 550.6 - - 13.1 57.4 75.4 84.9 70.9 64.9 46.8 38.3 38.3 36.4 24.0
Copper Concentrate Revenue A$m 538.6 - - 9.3 41.8 70.7 77.4 75.8 74.4 84.6 49.3 24.1 18.8 12.4
Gross Payable Revenue Net Credits
A$m 2,076.9 - - 48.2 190.5 265.5 332.6 304.6 258.9 200.6 143.8 124.2 125.3 82.7
O/S Transport etc. costs A$m (125.2) - - (3.0) (11.0) (15.2) (20.3) (18.7) (15.4) (11.4) (8.9) (7.9) (8.1) (5.4)
Treatment costs A$m (313.2) - - (7.7) (28.2) (37.8) (52.3) (48.1) (38.2) (24.9) (20.2) (20.1) (21.5) (14.2)
Refining costs A$m (24.1) - - (0.5) (2.0) (3.1) (3.2) (3.1) (3.1) (3.4) (2.3) (1.4) (1.2) (0.8)
Net Smelter Revenue A$m 1,614.3 - - 37.0 149.2 209.4 256.8 234.8 202.3 160.9 112.4 94.7 94.5 62.3
Mining costs A$m (224.2) - - (4.2) (19.7) (31.3) (38.0) (40.2) (39.1) (33.8) (11.2) (2.5) (2.5) (1.7)
Benefication costs A$m - - - - - - - - - - - - - -
Processing costs A$m (357.7) - - (17.9) (35.9) (36.1) (36.0) (36.1) (35.0) (34.9) (35.2) (34.1) (34.1) (22.5)
Marketing costs A$m - - - - - - - - - - - - - -
Other Realisation costs A$m - - - - - - - - - - - - - -
Royalties paid A$m (48.9) - - (0.7) (4.3) (6.8) (8.7) (7.8) (6.6) (4.9) (3.0) (2.3) (2.3) (1.5)
Variable overhead costs A$m - - - - - - - - - - - - - -
Fixed and Closure costs A$m (47.7) - - (2.6) (5.3) (5.3) (5.3) (5.3) (5.3) (4.3) (1.4) (1.4) (1.4) (10.4)
Total costs A$m (678.4) - - (25.4) (65.2) (79.4) (88.0) (89.4) (85.9) (77.9) (50.7) (40.3) (40.3) (36.0)
EBITDA A$m 935.9 - - 11.6 84.0 130.1 168.9 145.4 116.4 83.0 61.6 54.5 54.2 26.3
EBITDA margin A$m n/a 0% 0% 24% 44% 49% 51% 48% 45% 41% 43% 44% 43% 32%
Depreciation Expense A$m (238.5) - - (3.5) (15.4) (21.4) (32.2) (34.6) (29.9) (22.2) (20.0) (21.1) (22.6) (15.8)
Amortization of Exploration Expense
A$m (12.0) - - (0.3) (1.1) (1.5) (2.1) (1.9) (1.4) (0.8) (0.7) (0.7) (0.8) (0.6)
EBIT A$m 685.4 - - 7.8 67.5 107.2 134.6 108.9 85.1 60.0 41.0 32.7 30.8 9.9
Interest & Borrowing Expense A$m - - - - - - - - - - - - - -
Interest Income A$m - - - - - - - - - - - - - -
Profit Before Tax A$m 685.4 - - 7.8 67.5 107.2 134.6 108.9 85.1 60.0 41.0 32.7 30.8 9.9
Income Tax A$m (205.6) - - (2.1) (19.8) (32.0) (40.3) (32.7) (25.5) (18.3) (12.9) (9.8) (9.2) (3.0)
Profit After Tax A$m 479.8 - - 5.7 47.7 75.2 94.3 76.2 59.5 41.7 28.0 22.9 21.5 6.9
Balance Sheet
Table 22.19: Economic Model – Project Pre-Finance Balance Sheet Summary
Balance Sheet Opening 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Current Assets
Cash A$m - - - 77.0 - 137.0 - 88.2 8.3 134.2 241.8 339.9 415.4 465.2 517.9 561.2 594.8
Accounts Receivable A$m - - 12.2 17.6 24.6 29.7 23.6 23.2 14.5 9.4 12.1 8.4 2.8
Inventory A$m - - 2.7 3.7 0.1 0.3 7.4 2.1 1.6 8.0 0.1 8.2 -
Total Current Assets A$m - - 77.0 - 122.0 - 66.8 33.0 164.2 272.8 365.3 431.4 482.6 530.1 577.8 597.6
Non Current Assets
Property, Plant and Equipment A$m - - - 134.6 148.5 158.0 149.0 125.4 99.7 79.2 59.4 38.3 15.8 - 0.1
Mining / Pre-Prodn Costs Capitalised
A$m - 77.0 0.9 2.4 2.8 3.1 3.2 3.1 2.2 - - - -
Tax assets A$m 114.7 114.7 114.7 112.6 92.8 60.8 43.5 33.7 26.0 20.5 16.6 13.7 10.9 12.0
Capitalised Exploration A$m 12.0 12.0 11.7 10.5 9.1 7.0 5.1 3.7 2.8 2.1 1.4 0.6 -
Total Non Current Assets A$m 126.7 126.7 203.7 259.8 254.2 230.7 202.6 167.3 132.5 104.7 78.2 53.4 27.3 11.9
Total Assets A$m 126.7 126.7 126.7 137.7 187.4 263.6 366.7 440.2 497.8 536.2 560.8 583.6 605.1 609.5
Current Liabilities
Accounts Payable A$m - - - 5.3 - 7.3 - 8.4 - 9.2 - 8.8 - 8.2 - 6.4 - 4.0 - 4.0 - 4.0 - 3.1
Deferred Tax Liability A$m - - - - - - 7.9 - 5.5 - 4.2 - 2.7 - 1.8 - 1.6 - 1.6 -
Total Current Liabilities A$m - - - 5.3 - 7.3 - 8.4 - 17.1 - 14.4 - 12.4 - 9.1 - 5.7 - 5.6 - 5.6 - 3.1
Total Liabilities A$m - - - 5.3 - 7.3 - 8.4 - 17.1 - 14.4 - 12.4 - 9.1 - 5.7 - 5.6 - 5.6 - 3.1
Net Assets A$m 126.7 126.7 126.7 132.4 180.1 255.3 349.6 425.8 485.4 527.1 555.1 578.0 599.5 606.4
Table 22.20: Economic Model - Key Sensitivities to NPV and IRR Outcomes
common occurrence and therefore probably represent a relatively low risk to the
project. In terms of the impact of exchange rate and metal prices on the Project’s
economics, the Company does have the option to mitigate against adverse
movements in currency or metal pricing by entering into hedging contracts with
appropriate counterparties.
Project operating costs and in particular the costs of consumables, labour, power
and materials handling logistics have a material impact on economics. An across
the board rise in costs would have a significantly negative impact on project
economics. While not all of the individual components of operating costs are
expected to move in unison, it is possibly that one or more of the cost centres
could fluctuate more sharply than others.
The cost of consumables represents a significant proportion of operating costs and
to the extent that they are imported, could be subject to price movements driven by
foreign exchange fluctuations. FX hedging could be employed to mitigate against
the downside risk of movements to this component of operating costs.
Similarly, whilst having a lower overall impact on the project economics, increases
or reductions in capital costs, including both the plant costs and the underground
capital, have the potential to impact on economics. Further work is warranted to
improve the confidence associated with the estimates, as well as to optimise
through commercial negotiation with vendors as the project advances towards
production.
Given the steepness of the sensitivity curves for metal prices, exchange rates and
operating costs, small movements in a combination of variables could have the
same impact as a large movement of any single variable. Similarly, strong
movements in one variable could also trigger an equally strong movement of other
variables in an opposite direction.
23 Adjacent Properties
23.1 Introduction
The Silurian felsic volcanic rocks of the Woodlawn area and the broader Goulburn
Basin (see Section 7) are prospective for VMS with a number of significant
prospects and deposits present. This Section briefly describes the relevant
mineral properties that are adjacent to the Woodlawn Project area, as shown on
Figure 23.1.
Figure 23.1: Map showing the relevant mineral prospects adjacent to the Woodlawn
Project
23.2 Captains Flat Deposit (Ironbark Zinc Ltd 50%, Glencore plc 50%)
The Captains Flat Deposit is located some 100km south of Woodlawn towards the
southern extent of the Goulburn Basin. It is owned via a 50:50 joint venture
between Ironbark Zinc Ltd (Ironbark) and Glencore plc, with Rutila Resources Ltd
retaining a small production royalty.
The deposit was first mined as the Lake George Mine from 1882 to 1889 and then
between 1937 to 1962 and is believed to have produced approximately four million
tonnes of ore at grades of 10% Zn, 6% Pb, 0.7% Cu and 55g/t Ag. The main
deposit is hosted in a north-south trending sequence of Silurian felsic volcanic
rocks enclosed within a broader sequence of Ordovician shales, sandstones and
siltstones. Mineralisation is considered by Ironbark to open at depth beneath the
old mine working, where there may be repeats of the existing mineralisation.
The project covers some 39 kilometres strike of prospective volcanic rocks which
contain several base-metal occurrences. Apart from the Captains Flat mine itself,
several other prospects are noted.
Vanderbilt Hill Prospect
The Vanderbilt Hill Prospect is located to the east of the Lake George Mine and
drilling has returned results such as 3.9m @ 10% zinc, 5.3% lead. The prospect is
considered to be highly prospective with open ended historic high grade drill results
yet to be followed up.
Jerangle Prospect
The Jerangle Prospect is located some 30 kilometres south of Captains Flat and
has returned some significant results including:
43.3m @ 1.9% Zn, 0.3% Pb, 0.14% Cu and 3.8g/t Ag from 355.5m down
hole, and high grade zones including, 2.2m @ 8.0% Zn and 4.4m @ 5.0%
Zn 378.0 and 386.8m down hole respectively.
Source: Ironbark website, 2015.
Dunsheas, Big Hill, Rise & Shine and Camages, all which have verified historic
head grades ranging from 0.25 to 4.0oz/t.
Mineralisation occurs in quartz veins in the form of free gold, or associated with
altered quartz-sericite-calcite-pyrite felsic and phyllic lodes and occasional
quartz/calcite veining. Gold is frequently associated with pyrite and chalcopyrite
with higher grade mineralisation often restricted to discrete ore shoots, true widths
range between 5 and 15 metres, surrounded by a large medium grade mineralised
envelope. Drilled intercepts include contained sectional grades of up to 25g/t Au
over the widths of up to 3m. Interpretation of the geological data indicates an
extensive multi-lode ore system ranging from 3m to 20m in width comprising high-
grade gold bearing ore shoots that remain open at depth (+500m).
Gold mineralisation at Dargue’s Reef occurs in the footwall and the hangingwall as
a steeply dipping, fracture controlled lode systems within zones of intense
alteration in the host Braidwood Granodiorite. The lodes follow a well-developed
fracture system adjacent to an intrusive dolerite dyke. At Dargue’s Reef, the two
main lodes thicken where they intersect creating a broad steep easterly plunging
ore shoot.
Mining at Dargue’s Reef is reported to target 50,000 ounces per year with an initial
5 year mine life. Mine development was stalled at the end of 2013 with much of
the mine infrastructure including the boxcut, ROM Pad and access roads having
been completed. The site is on care and maintenance whilst further technical
studies on processing onsite are finalised.
Source: Unity website, 2015 and from DIGS GSNSW.
25.2 Opportunities
The following opportunities may improve the project economics and warrant further
investigation during the next phases of study:
1. Resource inclusion: Inclusion of additional underground Resource outside
the PEA production schedule.
2. In-mine exploration potential: Following up a number of areas
prospective for further near surface exploration and which have the
potential to be included in the future production schedule.
3. Near-mine exploration potential: Following up exploration targets within
the local area (within 10km) of the Woodlawn Project area.
4. Staged development: the development of the Woodlawn Project may
benefit from staged development, particularly with regards staging the
tailings treatment plant construction in advance of underground mining and
the process plant additions required to treat the underground material.
5. Mining optimisation: Potential enhancements to mining design
parameters, particularly considering mining methods, dilution control,
smoothing the production profile and grade delivered to the mill, and capital
development optimisation.
6. Stope Design: Further stope design optimisation will lead to reduced
internal dilution and increased plant feed head grades.
7. Mine Planning: Further detailed mining planning work has the potential to
increase the extraction factor by bringing more mineralised material into the
mine plan.
8. Capital cost optimisation: Optimisation of capital costs associated with
the process plant, which have not yet been through a competitive tender
process.
9. Process Plant Performance: The plant design is considered to be of
conservative nature and there is the potential to operate at a higher
throughput once the plant is optimised and the latent capacity can be
exploited.
25.3 Risks
The following elements summarise the main areas of risk identified for the Project.
These risks are described more fully in Appendix 1.
1. General economic factors.
2. Resource estimates and exploration.
3. Mining performance and plant feed characteristics.
4. Capital costs.
5. Operating costs.
6. Metallurgical performance.
7. Veolia interactions.
8. Working capital requirements.
9. Permitting modifications.
10. Paste fill generation.
11. Environmental management.
26 Recommendations
26.1 Development Timetable
The Company has considered the outcomes of the PEA and has determined that it
will continue with the further study of the Woodlawn Project through undertaking a
Feasibility Study (FS) on the combined underground and tailings project. This has
been approved by the Board and the work program outlined below has
commenced.
The Company considers that the FS will be able to be completed within
approximately 12 months from the publication of this Report. Further stages of
development post completion of the FS will be contingent upon positive results
from this stage of work.
26.3 Exploration
Within the FS budget an allocation has been made for further exploration work to
test a number of targets identified in the PEA drilling program. Within this
exploration drilling program comprising approximately 1,900m of diamond drilling,
there will be an emphasis on proving up additional Resources that can contribute
to the FS. Examples of high priority targets include:
1. the newly discovered Lisa Lens;
2. potential extensions to Kate and G Lenses;
3. the poorly defined off-hole EM conductor adjacent to C Lens; and
4. the EM target identified at the Currawang satellite deposit.
Regional exploration will continue with a focus on developing and testing other
near mine targets, particularly those targets which have the potential to add to the
life of the Woodlawn mine, albeit that it is unlikely that any mineralisation identified
though this exploration program will be included in the FS.
FS Feasibility Study
FW Footwall
g Gram
g/t Grams per tonne, same as ppm
GDR Great Dividing Range
GeoRes GeoRes Consulting
GEOSTATS Geostats Pty Ltd
GPS Global Positioning System
GRES GR Engineering Services Limited
GSNSW Geological Survey of New South Wales
GST Australian Goods and Services Tax
h Hour
Ha Hectare
Heron, HER, HRR Heron Resources Limited
HW Hangingwall
ICPAES Inductively Coupled Plasma Atomic Emission Spectroscopy
ID Identifier
IGRF International Geomagnetic Reference Field
IP Induced Polarisation
IRR Internal Rate of Return
IsGyro Inertial Sensing Down hole Gyroscope
Jododex Jododex Australia Pty Ltd
JV Joint Venture
k Kilo or 1,000
km Kilometre
2
km Square kilometre (unit of area)
ktpa Kilotonnes per annum
L Litre
LFB Lachlan Fold Belt
LIMS Laboratory Information Management System
LLD Lower detection limit
LOM Life of Mine
m Metre
M Million
mm Millimetres
Mtpa Million metric tonnes per annum
ME-ICP61 Multi element by 4 acid digest with ICPAES finish
ME-OG62 Multi element ore grade by four acid digest with ICPAES finish
Mg Magnesium
MGA Map Grid of Australia
NATA National Association of Testing Authorities (Australia)
NI 43-101 Canadian National Instrument 43-101 Standards of Disclosure for
Mineral Projects
NPV Net Present Value
NSR Net Smelter Return
NSW New South Wales
OG62 Ore grade by four acid digest with ICPAES finish
OREAS Ore Research & Exploration Pty Ltd
Pb Lead
PEA A Preliminary Economic Assessment (PEA) is a formal study in
standard form prescribed by NI 43-101 which includes an economic
analysis of the potential viability of Mineral Resources, but which is
not a pre-feasibility study or feasibility study
ppb Parts per billion (by weight)
ppm Parts per million (by weight)
PVC Polyvinyl Chloride (plastic generally used for piping)
QAQC Quality Assurance and Quality Control
QC Quality Control
QLD Queensland
28 References
1. Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves (the ‘JORC code’), 2004 Edition, JORC (of AusIMM, AIG and MC),
December 2004
2. Australian Government Bureau of Meteorology. Monthly statistics on the national
web site.
3. Ayres, D.E. (1979). The mineralogy and chemical composition of the Woodlawn
massive sulphide orebody at Woodlawn, New South Wales. Geological Society of
Australia Journal, v. 26, p. 155-168.
4. Best J.G., D'Addario G.W., Walpole B.P. and Rose G., 1964, Canberra 1:250 000
Geological Sheet SI/55-16, 2nd edition, Geological Survey of New South Wales,
Sydney.
5. BPDT & Co Pty Ltd (2015). Marketing & Logistics. Unpublished confidential report
for Heron Resources Limited, March 2015.
6. Bouffler, M. (1998). Summary Report on Exploration of SML 20 Woodlawn, NSW for
the period from June, 1987 to December, 1997. Denehurst Ltd. 33p.
7. Capital (2009), Capital Mining Ltd ASX Announcement dated 29 April 2009 and
published on the Capital website: http://www.capitalmining.com.au/.
8. Capital website (2015): http://www.capitalmining.com.au/ sourced February 2015.
9. Centrex (2014), Centrex Metals Ltd Annual Report 2014, as published on the
Centrex website: www.centrexmetals.com.au.
10. Centrex 2015, Centrex Metals Ltd Quarterly Activities Report for the Period Ending
31st December 2014.
11. CIM Definition Standards - For Mineral Resources and Mineral Reserves (the ‘CIM
Definition Standards’), adopted by CIM Council on 11th December 2005.
12. Cotton, R. E. (1986). Assessment of Geological Model and Method Used to
Establish Underground in Situ Ore Resources, Woodlawn Mine, NSW. Prepared for
Woodlawn Minesby Robertson Research (Australia) Pty Limited.
13. Deyssing L. & Fitzherbert J.A. (2014). Controls on the mineralisation and
architecture of the southern Goulburn Basin. Geological Survey File GS2014/0941.
Geological Survey of New South Wales.
14. Deyssing L. & Fitzherbert J.A. (2014). Architecture of the Goulburn Basin: insights
from recent geological mapping of the Captains Flat Special sheet. Geological
Survey File GS GS2015/0140. Geological Survey of New South Wales.
15. Fitzgerald D J and Singer R P (1990). Ore Reserves at Woodlawn Mine, NSW. Ore
Reserves Estimates presentation, Melbourne March 1990.
16. Fitzherbert J.F., Thomas O.D., Deyssing L., Bewert-Vassallo K. E., Simpson C.J.
and Sherwin L. (2011). Braidwood 1:100,000 Geological Sheet 8827, Second
Edition, Geological Survey of New South Wales, Orange.
17. Gemmell, B.J., Large, R.R. and Zaw, K., (1998) Palaeozoic volcanic hosted massive
sulphide deposits. In AGSO Journal of Australian Geology and Geophysics, 17(4),
129-137.
18. Gillian, L.B., Felton, E.E., and Olgers, F. (1979).The regional setting of the
29 Certificates of Authors
PO Box 943
West Perth WA 6872, Australia
www.srk.com.au
CERTIFICATE OF AUTHOR
Daniel R. Guibal
Corporate Consultant (Geostatistics & Resources)
SRK Consulting (Australasia) Pty Ltd.
Email: dguibal@srk.com.au
HRN007_Certificate_NI 43 101.docx
SRK Consulting Page 2
company files on their websites accessible by the public, of the Technical Report.
(“signed”)
Daniel Guibal, Min Eng, FAusIMM (CP), MMICA, MGAA
Corporate Consultant (Geostatistics & Resources)
1) I am a Principal Geologist with the firm of SRK Consulting (Australasia) Inc., with an office at Level 1,
10 Richardson Street, West Perth, Western Australia;
2) I graduated from the Ballarat University College, Victoria with a Bachelor of Science (Geology) in 1989,
and have practiced my profession continuously since 1989. This includes nine years in mining
operations and over 16 years in consulting on a range of commodities including, base metals, gold, iron
ore, manganese, nickel, bauxite, mineral sands, and industrial minerals;
3) I am a professional Geoscientist, registered with the Australian Institute of Geoscientists, membership
number 5483;
4) I have personally inspected the subject project site on 11 March 2015.
5) I have read the definition of Qualified Person set out in National Instrument 43-101 and certify that by
virtue of my education, affiliation to a professional association, and past relevant work experience, I fulfill
the requirements to be a Qualified Person for the purposes of National Instrument 43-101 and this
technical report has been prepared in compliance with National Instrument 43-101 and Form 43-101F1;
6) I, as a Qualified Person, I am independent of the issuer as defined in Section 1.5 of National Instrument
43-101;
7) I am the co-author of this report and responsible for Sections 7 to 12 and accept professional
responsibility for those sections of this technical report;
8) I have had no prior involvement with the subject property.
9) I have read National Instrument 43-101 and confirm that this technical report has been prepared in
compliance therewith;
10) SRK Consulting (Australasia) Pty Ltd was retained by Heron Resources Limited to prepare a technical
report of the Woodlawn Project in accordance with National Instrument 43-101 and Form 43-101F1
guidelines;
11) I have not received, nor do I expect to receive, any interest, directly or indirectly, in the Woodlawn Project
or securities of Heron Resource Limited; and
12) That, as of the effective date of this technical report, to the best of my knowledge, information and belief,
this technical report contains all scientific and technical information that is required to be disclosed to
make the technical report not misleading.
30 Appendices
30.1 Appendix 1: Summary of Risks
The following is a non-exhaustive list of some of the risks which will need to be
managed for the Project as it moves into production.
The Woodlawn assets are subject to certain inherent risks and opportunities, which
apply to some degree to all participants of the base metals mining industry. These
risks, including fluctuations in base metal prices, silver price, exchange rates,
inflation rates and supply input prices are largely outside the direct control of
Heron; however, they can be reduced by having suitable mitigating plans in place.
As with any resource estimate, there are risk associated with the geological
interpretation and grade / geological continuity based on generating resources from
limited data. These risks and technical factors are reflected in the JORC (2012)
and NI 43-101 Inferred and Indicated Resource classifications which have been
applied to the Mineral Resource estimate in this report.
As noted in Section14, the Mineral Resource estimation methods have been
reviewed by SRK. They concluded that the model and resource estimates are
sound, based on a thorough analysis of the geology and the data. If anything, the
results are conservative, as a number of zones are eliminated from the resources
based on fairly strict criteria of confidence in the geology, data density and
mineability.
There is a risk that external dilution may be increased beyond that which is
planned and the mining recovery reduced as a result of mining practices employed
or due to factors including geotechnical conditions associated with the
underground deposit. This would have an adverse effect on mill head grade and a
negative impact on revenue.
For the tailings mining operation, the mining has been carefully designed to
minimize fluctuations in grade and particle size received at the plant entry point.
However, poor control in the mining operations could impact upon the tailings plant
feed, which could impact upon the plant head grade and/or recovery performance.
More generally, the availability of suitable mining equipment can impact on mining
rates and mining unit costs. Careful attention to equipment specifications and
equipment maintenance, as well as contractor management, will be key to
managing this risk, which is inherent to all mining operations.
Capital Costs
The capital cost estimate has been developed to a ±25% accuracy level and
contingency allowances have been calculated and are included within the estimate
total. Project risks that have an impact on the potential of capital cost overrun
include:
Schedule slippage (which often causes capital overrun and delays revenue
generation).
Incorrect trade contractor selection or contracting strategy.
Poor or poorly implemented project management and project controls
systems.
Inadequately understood environmental risks that require reactive design.
Health and safety risks.
Weather.
Soil / geotechnical / hydrogeological anomalies.
Permit issues.
Risk of project team integration problems / project management and site
control issues.
Input quality issues.
Social impact of construction workforces.
Import risks and unforeseen taxes.
Timely award of equipment supply contracts for certified vendor information
being available for detailed design to commence and proceed on schedule.
Ensuring consistent and timely payment of domestic and international
invoices for services and equipment to avoid interest claims or withholding
of supply.
Operating Costs
The operating cost estimate has been developed to a ±20% accuracy level and
contingency allowances have been calculated and are included within the estimate
total.
As with any ore processing operation, risks that manifest in increased unit cost boil
down to adequate and appropriate manning, poor control of reagents and poor
maintenance practices. Additional reagent demand may occur which will drive up
operating costs, but the impact is expected to be relatively minor. Latent
conditions that may drive up operating costs may also relate to harder or more
abrasive ores than anticipated; these characteristics have been tested but are
subject to experimental error and sample representivity issues.
Metallurgical Performance
outcome. By design the crushing system has significant in-built latent capacity (as
equipment selection has been driven by physical characteristics) but the overall
result will be dependent on grinding mill maintenance.
The process design criterion was developed from testwork and benchmarked data
from similar projects. Plant equipment selection is based on well proven
technology and equipment has been sized to allow for variable mass flows dictated
by variable plant feeds.
In order to facilitate this, the following issues will need to be monitored by
operations management:
Good industrial relations are maintained.
A strong safety and training culture is employed on site.
Maintenance is programmed and well managed to ensure plant availability.
The mining contractor(s) keep up with plant demand consistently.
Plant control systems remain calibrated.
Recoveries have been calculated from the flotation tests conducted as part of the
co-treatment option and referred to under Section 17.2 Process Design Basis.
All material types that have been included in the proposed production schedule
have been subject of at least some preliminary metallurgical testwork. Flotation
results for both fresh copper and zinc-copper mineralisation have been examined
with and without tailings retreatment and have shown good metallurgical recoveries
in line with expected historical values.
It should be noted that none of the current flotation tests have used site water. The
risk associated with metal ions within the site water has been ameliorated by the
inclusion of a water treatment plant. This should alleviate the possibility of lower
than expected concentrate grades due to unwanted activation of mineral species or
the increased requirement for depression reagents to counter the activation of
sulphide minerals outside of the required differential floatation process.
Given the conservative design that has been developed, there should be sufficient
latent capacity within the flotation circuit and concentrate regrind circuits to handle
variations in feed grade. As with any flotation operation, good material blending
practices will be key to maximising operational efficiency and recovery.
Other than risks associated with a change in responsiveness (hence recovery) due
to unidentified variability, risks associated with other aspects of plant performance
outcomes will remain until either further metallurgical and physical characterisation
testwork is complete or assumptions tested in the plant as constructed. Risks that
have been identified to date include:
1. As lime is being used as the primary pH modifier, calcium may reach
concentrations high enough to cause scale issues within the plant.
2. Limited Bond Mill Rod and Ball Mill Work Index tests have been conducted
on the fresh zinc-copper sulphide material. These results generated a
lower value for both index figures as opposed to the values generated for
finer grinding in the tailings retreat project. The higher values for work
index as detailed in Section 17.2 were used for sizing the ball mill
component. In the unlikely event that the unit proves to be undersized, this
would be relieved by a slightly higher grind size target which may realise
slightly reduced recovery, or throughput could be wound down.
3. Although vendor testing of the IsaMill™ and the Metso SMDDetritor on
fresh underground mineralisation has not been possible due to sample
constraint, the units selected have used previous specific energy test
results generated as part of the tailings retreat study. In the unlikely event
that the unit proves to be undersized, this would be relieved by a slightly
higher grind target which could realise slightly reduced recovery, or
throughput could be wound down. If the latter was selected the net
reduction of output could possibly be negated by further optimisation of the
flotation circuit.
4. Site surface waters from the evaporation pond and tailings dams presently
have extremely low pH values (in the range of 2 to 3). These will be used
as part of the initial plant make up water requirements. Although the pH in
these dams will rise with time a water retreatment circuit and the
introduction of a bleed stream into the tailings thickener has been proposed
to neutralise the water and return the process water to a pH value of 7.
Therefore, there is a risk that operational performance of the process plant in terms
of throughput and metallurgical recoveries to the three concentrate streams may
not meet planned levels. For high levels of contamination, penalties may be
applied by purchasers of the concentrate according to standard benchmarks. In an
extreme case this could result in one or more of the product streams being
rendered unsaleable for a period of time.
Veolia Interactions
The mine site is shared with Veolia, who use the old open pit for storage of waste.
Heron has an excellent working relationship with Veolia. The Veolia relationship is
a long term one and is governed by a number of cooperation agreements between
the parties. The interests of the two parties are aligned on a number of levels, and
the two parties continue to work together under agreed protocols to ensure that site
operations are effectively managed.
Veolia operates under a zero discharge policy in relation to their in-pit operations.
Both in-pit portals have been sealed using engineered plugs, and the pit itself is
fully lined, including a large plastic lined sump at the base of the pit. To the extent
that gaseous or aqueous discharge occurs into the underground workings, Veolia
is responsible for its clean-up and / or management. Nevertheless, such discharge
has the potential to impact significantly upon the underground operations, and
Heron will, during the FS stage, consider what additional safeguards will be put into
place to manage this risk, as well as to quantify whether there is a material
discharge issue.
Working capital requirements are affected by factors including the production and
processing schedule, shipping and payment timing and cost assumptions, and
mining and operating factors including plant feed grade, throughput and recoveries.
Careful attention will need to be given to these factors, particularly as the plant
moves through the commissioning stage to a position where it is cash flow
breakeven. Adverse impacts in the areas above could delay peak cash drawn and
result in a need for the company to find additional working capital. This risk will be
taken into account in the planned funding for the project as well as in the
commissioning management plan.
Permitting Modifications
The plant tailings characteristics comprise fine particles. Whilst the testwork
undertaken to date demonstrates that a portion of the tailings can be used to
generate paste fill with adequate strength characteristics for the underground
mining, further testwork is required during the FS stage to confirm the chemical
composition of the proposed paste. If adequate strength paste cannot be
generated from the tailings, additional costs may be incurred in sourcing a
replacement source of paste fill feed.
Environmental Management
The Woodlawn site environment has been managed effectively over the past 20+
years without material issue. Nevertheless, environmental issues will need to be
continually monitored and addressed in the future, with key areas including:
1. Site water balance and storage: the site is a zero discharge site. However,
failure to adhere to discharge requirements could result in sanctions
including fines and, in extreme circumstances, a loss of licence to operate.
The site has operated successfully under these requirements since 1978.
The site water balance is managed using extensive existing evaporation
ponds. Additionally, Heron notes that despite the tight nature of the country
rock, there is a high probability that the existing underground workings
contain significant quantities of water, which will need to be extracted and
managed on surface, using the existing water management infrastructure.
2. Spillage and acid drainage management: Waste stored on site, including in
particular the rehabilitated waste dumps and the tailings dams, have the
potential to discharge water containing high levels of acid. Management of
these issues has been ongoing for many years, and is well understood.
Runoff capture, storage and evaporation are currently used mitigants. For
the processing plant, the site will drain into the process water pond, and the
plant itself will be fully bunded.
3. Water supply quality and availability: The process plant requires significant
quantities of high quality water to operate. Processing throughput or plant
flotation performance could be adversely impacted, with a consequent
impact on costs and / or the quality of concentrates produced, if sufficient
water is not available. To address this issue, recycling of water within the
site will be maximised. The existing borefield will be utilised. Other sources
of water may be utilised if required. Finally, a water treatment plant has
been costed to ensure suitable quality water is available for the process
plant.
4. Site rehabilitation: rehabilitation requirements are noted in section 20.3.
Whilst the project economics are not sensitive to closure costs,
nevertheless the ongoing remediation requirements and closure
requirements will need to be adequately planned for and monitored in the
long term. The initial disturbance area for the tailings retreatment is