Professional Documents
Culture Documents
Because many of the recent dam sites in Japan are Au Japon, les sites sur lesquels sont construits de nom-
composed of soft rocks with low strength, the injection breux barrages sont composeÂs de roche tendre aÁ faible
pressure should be carefully controlled when performing reÂsistance, et la pression d'injection doit eÃtre, depuis peu,
the Lugeon water test (LWT). Particularly, where the controÃleÂe de treÁs preÁs lorsque l'on proceÁde au test de
groundwater level is low, the minimum injection pressure surcharge hydrique Lugeon (LWT; Lugeon water test). En
for the LWT generated by pressure control at the ground particulier lorsque le niveau d'eau en sous-sol est bas, la
surface is extremely high in deep parts of the foundation. pression d'injection minimum pour le LWT geÂneÂreÂe par la
Consequently, there is a possibility of overestimating the commande de la pression aÁ la surface du sol est extreÃme-
permeability because of fracturing of the rock mass ment eÂleveÂe aux endroits profonds de la fondation. Par
surrounding the test section. Under these circumstances, conseÂquent, il peut y avoir surestimation de la permeÂabi-
injection pressure should be applied by adjusting the lite due aux ®ssures dans le bloc rocheux entourant la zone
water level inside the borehole to begin the test at a low de test. Dans ces conditions, une pression d'injection doit
effective injection pressure. eÃtre appliqueÂe en reÂglant le niveau de l'eau aÁ l'inteÂrieur du
trou de sonde a®n de commencer le test aÁ une faible
Keywords : ®eld testing & monitoring; soft rock pression d'injection effective.
B-1-22 B-1-21
El. 152.20 m El. 152.20 m
L 5 80 m L 5 80 m
B-62-23 B-34
B-62-24 B-22
El. 150.20 m El. 151.78 m
L 5 100 m L 5 80 m El. 148.80 m El. 140.89 m
Elevation L 5 80 m L 5 75 m
0 0
150 0 B-21
10 10 0
10 El. 131.00 m
20 0 L 5 70 m
20 Ms 10 Tb Grouting tunnel
Ms 20
30 30 20 10
30
40 Tb Tf 20
40 30
40
50 50 Tf 40 30 TOD El. 100.50 m
100
50 SWL El. 96.0 m
60 60 50 40 Tb
Tb 60 1
70 70 Tb 50 Tf
1 60 Spillway
Tf 70
80 80 Tf 60
70
Tb m 80 75
90 m m 70
Tb m
50 100
m
0 20 40 m
Elevation
110
Grouting tunnel
100
m
45
90 5
,L
m
-1
7-P
45
5-P-1, L 5 65 m
4-P-1, L 5 65 m
3-P-1, L 5 60 m
2-P-1, L 5 60 m
1-P-1, L 5 60 m
L5
80
Spillway
-1,
6-P
70
60
50
40
0 10 20 m
30
Ms Mudstone
Tf Tuff
Tb Tuff breccia
Tb1Tf Alternating beds of Tb and Tf
TOD Top of dam
SWL Surcharge water level
Fig. 1. Geological pro®le of test site and locations of permeability test holes
of the foundation and to determine suitable grouting was increased varied for each borehole, while a pump was
speci®cations prior to the main grouting work. used to inject the water in each case. Figure 2 presents a
summary of the Lugeon values, water level in the borehole,
critical pressure and minimum injection pressure in the
Previous permeability investigation pressure-increase stage at various depths. The Lugeon
values obtained were generally high. Figure 3 shows
The results of LWTs conducted in the four boreholes B-21, representative p±q (injection pressure±¯ow rate) curves
B-22, B-34 and B-62-23 are summarized below. obtained at boreholes B-34 and B-62-23. These test results
The injection pressure was controlled at the ground indicate that from shallow depths from the ground surface
surface. The number of steps by which the injection pressure to 60 or 70 m in depth, the permeability is high: 20 Lu or
112
Downloaded by [ UNIVERSITY OF MINNESOTA] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Permeability of soft-rock foundations
Lugeon value: Lu Pressure: 1021 MPa Lugeon value: Lu Pressure: 1021 MPa
0 5 10 15 20 25 0 2 4 6 8 10 0 5 10 15 20 25 0 2 4 6 8 10
0 0
(27.4)
Min. injection pressure
10 Lugeon value (30.4) 10 Lugeon value Min. injection pressure
Critical pressure
(27.5) BBH (57.4)
01
BBH
. d
(43.7) 20 WLBH (40.0)
20 WLBH
0
. 2d
(30.5) (26.0)
0
. 2d
Depth d : m
(38.3) 30 (23.2)
30
Depth d : m
(28.6)
40 40
0. 05d
(27.0)
0. 05d
50 50
60 60 (25.7)
01
. d
(11.8)
70 70
0 20 40 60 80 100
BBH, WLBH: m
80
0 20 40 60 80 100
(a) BBH, WLBH: m
(b)
0 5 10 15 20 25 0 2 4 6 8 10 WLBH
0 20
30
0
Lugeon value
. 2d
10 Min. injection pressure
BBH
WLBH 40
Depth d : m
20
(26.1)
30 50
Depth d : m
0
. 2d
01
. d
60
0. 1
40
0. 05d
0. 05d
50 70
60 80
70 90
80 100
0 20 40 60 80 100 0 20 40 60 80 100
BBH, WLBH: m BBH, WLBH: m
(c) (d)
Fig. 2. Results of previous LWTs: (a) B-21, (b) B-22, (c) B-34, (d) B-62-23; BBH, bottom of borehole; WLBH, water level in borehole
greater. Figure 4 shows the distribution of permeability in However, in the deeper foundation, there were test
the ground, based on the test results. sections with a critical pressure ranging from 0´6 to 1´3 MPa,
The lateral extension of foundation grouting is deter- and the critical pressure tended to rise as the depth
mined in accordance with the sideways rise of the ground- increased, as shown in Fig. 2. The critical pressure is de®ned
water level as well as the distribution of permeability. The as the injection pressure at the point where the ¯ow rate
scope usually extends to those points where the surcharge rises rapidly in the p±q curve. On the other hand, in the
water level (SWL), that is, the maximum water storage level shallower foundation, even when the injection pressure was
during a ¯ood, intersects the groundwater table (River raised to about 1 MPa, a critical pressure was not found, as
Bureau, Ministry of Construction, 1983). The SWL at the shown in Fig. 3. The higher critical pressure predicted in the
dam site is at an elevation of 96´0 m. The ®nal stable water shallower foundation is inconsistent with the critical pres-
levels in the four test holes, which can be considered to sure in the deeper foundation. Additionally, as stated earlier,
have equilibrated with the surrounding groundwater level, because the groundwater level at the site is low, the
were extremely deep, ranging from 45 to 65 m below the minimum injection pressure was extremely high in the test,
ground surface. Because the water level in boreholes B-21 which was conducted by controlling the injection pressure at
and B-22 was below the SWL and the estimated permeabil- the ground surface. Consequently, at many stages where
ity of the ground was extremely high overall, there was high permeability was indicated, it is supposed that the test
some concern that the grouting range would expand was done using a pressure greater than the critical pressure,
substantially. and that the permeability was overestimated.
113
Downloaded by [ UNIVERSITY OF MINNESOTA] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Yamaguchi and Matsumoto
12
10
10
8 8
6 6
4 4
Lu 5 16.0
2
2 Lu 5 21.8
0 0
0 5 10 15 20 25 0 5 10 15 20 25
Flow rate q : l/min per metre Flow rate q : l/min per metre
(a) (b)
Fig. 3. Examples of p±q curves obtained from previous permeability investigation: (a) B-34, 75±80 m section; (b) B-62-23, 60±65 m section
B-62-23
B-34 B-22
Elevation B-21
150
20 # Lu
20 # Lu 20 # Lu TOD El. 100.50 m
100 SWL El. 96.00 m
Lu , 2
10 # Lu
, 20 Spillway
2 # Lu
,5 10 # Lu , 20
20 # Lu 2
Lu , 2 ,
2# , 10 Lu
Lu
,5 5 # Lu
Lu
50 ,
2
Lu Lugeon value
SWL Surcharge water level
0 20 40 m
Re-evaluation of permeability
deep, water was injected inside the test hole as the water
In the re-evaluation of the permeability, LWTs were level inside the borehole was adjusted, to start the test from
conducted in three newly excavated boreholes B-62-64, B-1- a low effective injection pressure. The minimum injection
21 and B-1-22. Boreholes B-1-21 and B-1-22 were excavated pressure was altered appropriately for each test, but in the
close to B-34 and B-62-23, respectively, in order to simplify lower injection pressure range, in principle, it was increased
comparison of the new and previous results. Because the in steps of 50 or 100 kPa.
groundwater level at the site was known to be extremely Figure 5 summarizes the results of these LWTs. Figure 6
114
Downloaded by [ UNIVERSITY OF MINNESOTA] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Permeability of soft-rock foundations
0
30
. 2d
6
Depth d : m
01
. d
40
0. 05d
50 4
60
70 2
Lu 5 0.5
80 pcr 5 0.34 MPa
0 20 40 60 80 100
BBH, WLBH: m 0
0 5 10 15 20 25
(a) Flow rate q : l/min per metre
(a)
10
21
Lugeon value: Lu Pressure: 10 MPa
0 5 10 15 20 25 0 2 4 6 8 10
Effective injection pressure p : 1021 MPa
0 8
. d
30
0
. 2d
Depth d : m
40 4
50
60 2
Lu 5 0.3
pcr 5 0.44 MPa
70
0
80 0 5 10 15 20 25
0 20 40 60 80 100
BBH, WLBH: m Flow rate q : l/min per metre
(b) (b)
0
. 2d
following.
01
. d
40
(a) Lugeon values of 10 Lu or greater were obtained in the
50
35 to 40 m deep section of B-62-24 and the 45 to 50 m
60 deep section of B-1-22, but Lugeon values obtained in
the other sections were extremely small. Because these
70 two sections are higher than the SWL at the site, there
will be no problem with grouting design.
80
0 20 40 60 80 100 (b) The p±q curves obtained for all sections are, as shown
BBH, WLBH: m in Fig. 6, shaped in a manner that permits a clear
(c)
assessment of the critical pressure.
(c) The ®nal stable borehole water level was found to be
Fig. 5. Results of re-evaluation of permeability: (a) B-62-24, (b) B-1-21, (c) between 45 and 60 m below the ground surface, just as
B-1-22 it was in the case of the previous study, which
115
Downloaded by [ UNIVERSITY OF MINNESOTA] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Yamaguchi and Matsumoto
20 40
Depth d : m
30 50
40 60
50 70
60 80
70 90
80 100
ELMBH: B–34 151.78 m ELMBH: B–62–23 150.20 m
B–1–21 152.20 m B–1–22 152.20 m
(a) (b)
Fig. 7. Minimum injection pressure in previous tests and critical pressure in re-evaluation tests: (a) B-34 and B-1-21; (b) B-62-23 and B-1-22; ELMBH,
elevation of mouth of borehole
B–1–22
B–1–21 B–62–24
Elevation
150
5 # Lu
, 10
2 # Lu
,5
10 # Lu , 20
Lu , 2 2 # Lu , 5
-I
Lu , 2
6-P
5 # Lu , 10
50 2 # Lu , 5
0 20 40 m 20 , Lu
3-P-I
2-P-I
1-P-I
5-P-I
4-P-I
116
Downloaded by [ UNIVERSITY OF MINNESOTA] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Permeability of soft-rock foundations
117
Downloaded by [ UNIVERSITY OF MINNESOTA] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.