Practitioner Exam Questions

® 8
PRINCE2 Practitioner Resource Book

Syllabus Area Question Number Part 2 Marks


Risk Theme 3 C 4

The project is now at the end of Stage 2. The project manager has heard about a hurricane
in America and the weather forecasters have suggested that this might cause a period of
torrential rain which will hit the UK soon. There is a threat that torrential rain may cause
localised flooding on the site during the excavation of the foundations which will cause
delays to the construction of up to 4 weeks.

PPL have an operational manager (Sandy) who watches the weather forecasts as weather
affects visitor numbers.

Column 1 contains a number of items from the risk assessment identified by the Project Manager
and team following an assessment of the risk. Column 2 contains a list of headings from the Risk
Register. For each item in Column 1, select from Column 2 the heading under which it should be
recorded. Each option in column 2 may be used once, more than once or not at all.
No Column 1 Column 2
1 Record the risk in the Risk Register and monitor the situation. A Risk category

2 Torrential rain is expected in November. B Probability

3 This is a risk to the schedule. C Proximity

4 This risk is active. D Risk response

E Risk status

F Risk Owner

Question Part

3 C A B C D E F

1
2
3
4

© 2009 ILX Group plc 108