Professional Documents
Culture Documents
Practitioner Exam Questions: Prince2 Practitioner Resource Book
Practitioner Exam Questions: Prince2 Practitioner Resource Book
® 8
PRINCE2 Practitioner Resource Book
The project is now at the end of Stage 2. The project manager has heard about a hurricane
in America and the weather forecasters have suggested that this might cause a period of
torrential rain which will hit the UK soon. There is a threat that torrential rain may cause
localised flooding on the site during the excavation of the foundations which will cause
delays to the construction of up to 4 weeks.
PPL have an operational manager (Sandy) who watches the weather forecasts as weather
affects visitor numbers.
Column 1 contains a number of items from the risk assessment identified by the Project Manager
and team following an assessment of the risk. Column 2 contains a list of headings from the Risk
Register. For each item in Column 1, select from Column 2 the heading under which it should be
recorded. Each option in column 2 may be used once, more than once or not at all.
No Column 1 Column 2
1 Record the risk in the Risk Register and monitor the situation. A Risk category
E Risk status
F Risk Owner
Question Part
3 C A B C D E F
1
2
3
4