Standard Form Number: SF-INFR-50

Revised on: August 11, 2004

NAME OF CONTRACT: Repair/Maintenance of OP Building National Commission on Muslim Filipinos Regional Office Building Upper Calarian, Zamboanga City
LOCATION: Upper Calarian, Zamboanga City
NAME OF PROCURING ENTITY: DPWH Regional Office IXcal
EQUIPMENT UTILIZATION SCHEDULE
95 CALENDAR DAYS
CATEGORY/EQUIPMENT
6 DAYS 12 18 24 30 36 42 48 54 60 66 72 78 84 90
DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS DAYS

JACK HAMMER

CONCRETE
VIBRATOR

BAR CUTTER

BAGGER MIXER

BAR BENDER

WELDING M ACHINE

TILE CUTTER

Submitted by:

MALLI M. KADIL
AMO/OWNER
MMK CONSTRUCTION & ENTERPRISES

One of the requirements from the bidder to be included in its Technical Envelope is its equipment utilization schedule, referring to the weekly or monthly scheduling of the
minimum equipment required for the project.