Professional Documents
Culture Documents
on PC-09
1
(286th Session)
SENATE SECRETARIAT
—————
DEFERRED QUESTIONS
(Questions Nos. 47, 18, 19, 20, 21, 25, 32, 2, 3, 4, 5, 6, 11, 13, 16, 17,
18, 20, 22, 24, 25, 27, 30, 35, 41, 44, 45, 46, and 50 deferred on
14th December, 2018,
(285th Session)
Mr. Omar Ayub Khan: Yes, it is a fact that the voltage level at 132
KV grid station, Swabi drops down during summer season due to over
loading of the transmission network. But at present the voltage level of the
said grid station is ranging from 127 KV to 130 KV which is normal.
Mr. Omar Ayub Khan: Swabi area is currently being fed from
132 kV Grid Station Swabi which is presently getting supply from 220 kV
Burhan Grid Station via IESCO’s 132 kV grid station new Wah.
(a) the names and locations of wind and solar power plants in
the country indicating also the expenditure incurred on the
establishment of the same in each case;
(b) the per unit and per kilowatt price of electricity being
produced by the said plants and its comparison with the
cost of electricity produced by the recently installed plants
in neighbouring countries; and
The details of wind and solar power projects installed and in operation
are at Annex-1
(b) The per unit tariff for wind and solar power projects along with
per MW cost of these, as determined by NEPRA, is also shown at Annex-1.
The solar and wind power tariff comparisons with different countries
is at Annex-2
(b) the number of posts lying vacant in the said company with
grade wise and province wise break up and the time by
which the same will be filled in?
Mr. Omar Ayub Khan: (a) The number of persons working in’
PESCO with grade-wise and province-wise breakup is at Annex-A.
Annex-C
22
23
Annex-D
24
(Def.) *Question No. 2 Senator Mohsin Aziz:
(Notice Received on 5/09/2018 at 2:42 PM) QID: 34651
Will the Minister for Energy (Power Division) be pleased to state:
(a) the original estimated cost of Nandipur Power Project and
the actual cost incurred on the same so far; and
(b) the quantum of electricity being produced from the said
project at present indicating also the per unit cost of
production of the same?
Mr. Omar Ayub Khan: (a) The estimated cost of the project as per
Original PC-I (2007) was PKR 22,334.75 Million, whereas, the estimated
cost as per approved revised PC-I (2013) is PKR 58,416.20 Million. The
actual cost incurred so far is PKR 57, 655.00 million.
(b) Currently, the power plant is capable to generate around
460-480 MW of electricity on gas fuel. However, the Load (MW) varies
with ambient conditions.
NEPRA has determined levelized tariff of Nandipur Power plant on
gas fuel as Rs.10.3157/KWh
(Def.) *Question No. 3 Senator Mohsin Aziz:
(Notice Received on 6/09/2018 at 12:30 PM) QID: 34631
Will the Minister for Energy (Power Division) be pleased to state:
(a) the outstanding amount of circular debt at present in respect of
the IPPs, Government enterprises and other separately; and
(b) the time by which the debt in respect of each IPP will be
cleared separately?
Mr. Omar Ayub Khan: (a) The outstanding amount of circular debt
at present is Rs. 807,887 Million (as on 31-12-2018) and details of payable
to power producers/fuel suppliers are placed as (Annex-A).
Breakup of circular debt amounts is given as under:
Payable to Power Producers (as on 31-12-2018) = 683,484 Mln. Rs.
Will the Minister for Religious Affairs and Inter Faith Harmony
be pleased to state:
(a) the number of pilgrims who performed Hajj during the last
year with province wise break up;
(b) whether any quota for Hajj is reserved for Provinces, if so,
the details thereof;
(c) the criteria and procedure laid down for selection of persons
for Hajj in place of those who after selection cannot perform
Hajj due to some reasons; and
(d) the details of persons who after selection could not go for
Hajj during the last year indicating also the details of those
persons who replaced them with province wise break up?
(c) As per Hajj Policy & Plan-2018, if a person selected for Hajj
could not travel due to some medical reason or death, his blood relative
27
(specified in prescribed Performa) was considered for performing hajj in
lieu as a substitution case.
Mr. Ghulam Sarwar Khan: During the last five years three licenses
were issued to foreign petroleum companies for exploration of oil and gas in
the country. The application fee for grant of a Petroleum Exploration License
is Rs.100,000.00, thus the total amount received from them under the head
of license fee is Rs.300,000.00. The details of the aforesaid three licenses
are attached at Annexure-I.
29
30
(Def.) *Question No. 6 Senator Muhammad Talha Mahmood:
(Notice Received on 17/09/2018 at 9:30 AM) QID: 34843
(d) the authority which granted permission for the said visits?
(Annexures have been placed on the Table of the House as well as Library.)
(d) the authority which granted permission for the said visits?
Mr. Omar Ayub Khan: (a) & (b) On the basis of information received
from DISCOs, GENCOs & NTDC, the consolidated reply is given below:
(d) Foreign visits are usually for inspection and testing of material
as procurements are related to extra high voltage engineering and special
design of equipment. As per provision of relevant contract agreements,
inspection/testing is carried out at manufacturer’s works or independent labs
as per international practices and in accordance with international standards
for quality conformance.
(Annexures have been placed on the Table of the House as well as Library.)
Country
(1) Belgium
(2) Kuwait
(3) Malaysia
(4) Netherland
(5) Norway
(6) Poland
(7) Saudi Arabia
(8) Singapore
(9) UAE
(10) Vietnam
Will the Minister for Religious Affairs and Inter Faith Harmony
be pleased with refer to Senate Starred *Question No. 34, replied
on 5th October, 2018 and state:
(a) the date of approval of the existing Hajj Policy by the Cabinet;
(d) whether the said authority has powers to relax that policy,
if so, the details thereof; and
Mr. Noor-ul-Haq Qadri: (a) The Hajj Policy 2018 was approved
by the Cabinet on 26-12-2017.
(a) the criteria laid down for provision of gas to the areas
nearby gas fields in Taluka and District Mitiari, Sindh;
(b) the names of villages of the said Taluka and District nearby
gas fields which have been supplied gas; and
Mr. Ghulam Sarwar Khan: (a) SSGCL has reported that the
Company undertakes the gas development schemes for provision of gas to
new towns / villages on the recommendations of the Federal / Provincial
Government, Parliamentarians, Notables etc. after receipt of over and above
cost criteria share from the Government whereas SSGCL also invests within
cost criteria share as per the prevailing approved policy. The said approved
per customer cost criteria is Rs 54,000 for Sindh Province and Rs 270,000
for Balochistan Province.
(b) The Company has reported that there is one gas producing
field in District Matiari i.e Kausar Gas Field. Following nearby villages of the
said gas field have been supplied gas:
(c) The names of nearby villages of the said gas field which have
not been provided the facility of gas so far are as under:
47
Total project cost of the above villages has been worked out to Rs 178.767
million. The schemes for provision of gas to above villages exceed
per customer cost criteria of Rs 54000 approved by the Government of
Pakistan for Sindh province and the schemes are unfeasible. However, SSGCL
would undertake the schemes of the above villages after receipt of over and
above cost criteria share of Rs 135.027 million from the Government forum
and SSGCL would also invest within cost criteria share of Rs 43.740 million.
48
After receipt of required funds from the Government forum, the timeline for
supply of gas to the above villages can be provided accordingly.
Mr. Omar Ayub Khan: (a) New Matiari Grid Station (Switching
Station) is not operational and as such supplying no power to any part of
country. ± 600 kV Matiari-Lahore Transmission Line is a CPEC project for
evacuation of 4000 MW power from various IPPs (Coal Fired Power Plants)
in the southern region. Power will be collected at Matiari Convertor Station
for transmission to upcountry convertor station located at head Balloki, District
Nankana Sahib. The power transmitted through HVDC system will be
dispatched by NPCC throughout the country. Presently, only land has been
acquired for the construction of 500 kV Switching Station in Matiari and
COD of the project is expected in March, 2021.
(b) The works on the 500 KV Switching Station in Matiari are yet
to be started, which is the responsibility of the Chinese contractor for the
project, i.e. M/s Pak Matiari Lahore Transmission Line Co. Ltd. therefore,
recruitment will be made accordingly by them once work on ground is started.
(Annexures has been placed on the Table of the House as well as Library.)
(b) the estimated cost of the said projects indicating also the
share of each member country in the same?
Mr. Ghulam Sarwar Khan: (a) The ground breaking for the
Turkmenistan and Afghanistan portions of the gas pipeline was held in February
2018. The ground breaking for Pakistan portion is expected to be held in
December 2018. The expected completion of the first phase of the Project
is expected by December 2020.
Mr. Omar Ayub Khan: (a) Yes, it is a fact that three (03) students
and one (01) School teacher met with fatal accident on18-09-2018 inside
Al-Khidmat Foundation Public School, Kiwai, Tehsil Balakot due to touching
of 23 foot long metallic flag rod during flag ceremony in the said school, at
about 07:40 AM. The reasons of this accident are:-
(iii) Since this is a hilly and slopy area, therefore the management of
school made horizontal surface for school building by earthen
filling. In this way the school management itself decreased the
distance / clearance between ground and line up to 25 foot
(Approx.).
53
(iv) The above point No. (i), (ii) and (iii) were admitted by the
principal of said school in his written statement recorded in the
Court of law (Annexed).
(ix) The rod used for the flag was 22 feet long and its weight was
16 kg. So the management was required not to engage the
school children in such a manner which is the responsibility of
administration, the little children including school teacher could
not control the heavy weight of the lengthy rod.
(x) Lastly, the Principal of the School very clearly accepted the
responsibility of above accident.
(b) The policy already exists to remove the electricity wires passing
over the lawns, roofs of houses and buildings as below.
The above situation falls under category-1, hence notices have been
issued to all such premises to apply for shifting of line. After application by
the consumer, demand notice will be issued. After payment by the owner of
the premises, the line/wires will be shifted accordingly.
55
56
57
(Def.) *Question No. 37 Senator Muhammad Usman Khan Kakar:
(Notice Received on 2/11/2018 at 10:20 AM) QID: 35219
(b) whether it is a fact that work has not been started on the
Kan Metarzai grid station and Muslim Bagh city Feeder-III
so far, if so, the reasons thereof and the time by which work
will be started on the same?
Mr. Omar Ayub Khan: (a) Electricity supply from Passenzai grid
station has since been made on 5-01-2019.
(b) The PC-I cost of Kan Metarzai grid station is Rs. 263 Million
under Federal PSDP. Project cost has been proposed as 50:50
ratio by the Government of Pakistan and Government of
Balochistan Revised PC-I has been submitted on 15, January 2019
to the Ministry of Planning Development Reform for its
consideration to CDWP. Once project is approved work will
be started accordingly.
Will the Minister for Religious Affairs and Inter faith Harmony
be pleased to state:
(a) the number of Hajj tour operators who are enrolled with
the Ministry of Religious Affairs and Inter Faith Harmony
at present indicating also the number of the same who are
awarded Hajj quota;
58
(b) the procedure laid down for awarding Hajj quota to the
said operators; and
(c) the names and merit position of the new Hajj tour operators
who were awarded Hajj quota during the last five years
indicating also the number of quota awarded to each one
of them?
(b) The procedure laid down for awarding Hajj Quota to the said
companies is at Annex-A.
(c) The list of 60 companies who were awarded Hajj Quota in last
five years i.e. 2017 & 2018 is at Annex-B & C. No Hajj quota has been
allocated to the companies in the years 2014, 2015 and 2016 onwards.
59
60
Annex-B
61
62
63
Shoaib.M 0000(18) Senate. on PC-09
64
(Def.) *Question No. 40 Senator Molvi Faiz Muhammad:
(Notice Received on 8/11/2018 at 10:15 AM) QID: 35250
Mr. Ghulam Sarwar Khan: (a) The detail of tax paid by SNGPL
and SSGCL during the last five years is tabulated as under:
(a) the number of oil and gas wells in Balochistan with location
wise break up; and
(b) Six (06) E&P companies namely Oil & Gas Development
Company Limited (OGDCL), Pakistan Petroleum Limited (PPL), Mari
Petroleum Company Limited (MPCL), OMV (Pakistan) Exploration
Gesellschaft m.b.H, Orient Petroleum Pty Limited and China Zhenhua Oil
Co. Ltd have Exploration Blocks in Balochistan. Recently, PPL announced
a gas discovery over Hub X-1 well, which is located in district Lasbela,
Balochistan. Another, heavy oil discovery over Bolan East-1(which is located
in district Kachhi, Balochistan)has been announced by MPCL on 13th
September, 2018. The details of aforesaid discoveries are attached at
Annexure-II.
66
67
68
69
70
71
(b) whether it is also a fact that the price of the said meter is
Rs. 4000/- but the farmers are charged Rs. 18000/- for repair /
replacement of the same in case of any fault, if so, the steps
being taken by the Government to stop that overcharging?
Mr. Omar Ayub Khan: (a) The electricity meters under question
are Automatic Meter Reading (AMR) meters that were installed at MEPCO
under a project funded by USAID in September-2015 and are under
warranty. The warranty of meters is valid till February-2019.
Mr. Ghulam Sarwar Khan: (a) SNGPL has reported that 128,909
new domestic gas connections were provided during the last five years w.e.f.
July-2013 to June-2018.
Mr. Noor-ul- Haq Qadri: (a) Yes, National Ulema and Mashaikh
Council was constituted on April 21, 2016 in the Ministry of Religious Affairs
and Interfaith Harmony
(b) To give legal cover to the said Council a draft Bill has been
prepared. The Bill after due consultation with all the stakeholders including
the Law Division will be placed before the Parliament for consideration/
approval.
Mr. Omar Ayub Khan: (a) The outstanding amount of circular debt
at present is Rs. 807,887 Million (as on 31-12-2018) and details of payable
to power producers/fuel suppliers are placed as (Annex-A).
M/O Housing & Works moved a summary to the Prime Minister for
lifting of ban on new construction of residential accommodation for Federal
Government Servants as would be the only visable solution to cater the housing
needs of Federal Government employees in Islamabad as well as elsewhere.
(Annexure has been placed on the Table of the House as well as Library.)
83
*Question No. 31 Senator Syed Muhammad Ali Shah Jamot:
(Notice Received on 15/10/2018 at 11:40 AM) QID: 35108
(a) the number of oil and gas fields explored in the country so
far with district wise break up;
(b) the criteria laid down for provision of jobs to local people
and carry out development schemes works in surrounding
areas by the Oil and Gas Exploration and Production
companies operating in the said fields; and
Mr. Ghulam Sarwar Khan: (a) There are total 183 oil / gas fields
in the country. District-wise break-up is placed at Annexure-A.
(b) Criteria for provision of jobs to local people and guidelines for
utilization of social welfare obligations at present are placed at Annexure-B
& C respectively.
(Annexures have been placed on the Table of the House as well as Library.)
(b) No.
(d) SNGPL has reported that a new gas pipeline of 16" dia. has
been laid along Kashmir Highway and a new SMS is near completion at
Nilore, Islamabad. Further, various strategies are being adopted by the
Company, including diversion of system gas presently being supplied as blend
to industrial sector and RLNG to the high priority domestic sector. Resultantly
gas availability improving compared to previous years.
(a) whether it is a fact that the supply of Natural gas has not
been provided to the residents of Chak No. 82 JB,
Norangabad district Faisalabad despite the fact that the
pipelines for the provision of natural gas were laid there
one year ago, if so, the reasons thereof; and
(b) The Company further reported that work for laying of a gas
distribution network has been completed. However, the network would be
commissioned after installation of TBS for which work is in progress and will
be completed on or before 31-12-2018 subject to unforeseen circumstances.
Mr. Omar Ayub Khan: Power Division through AEDB, with the
support of National Renewable Energy Laboratory (NREL) of USA had
conducted a study in 2007 as a result of which the first mesoscale wind map
of Pakistan was developed showing potential of wind energy in different
parts of the country. Subsequently, several wind measuring masts were installed
by donor agencies and private sector investors in the potential area identified
through the wind map in Sindh province. The data gathered from these masts
formed the basis of development of wind power projects in the Gharo wind
corridor. As of now, 23 wind power projects of 1185 MW cumulative capacity
have been developed through private sector on IPP mode in the Gharo wind
corridor of Sindh.
(a) the details of Thar coal Power Project indicating also the
estimated cost, capacity and expected date of completion
of the same;
(b) The details of occupants who got stay orders from the court
are placed at Annex-II.
Annex-I
100
Annex-II
101
102
103
104
105
106
107
108
*Question No. 46 Senator Kalsoom Perveen:
(Notice Received on 26/12/2018 at 12:50 PM) QID: 35392
Mr. Omar Ayub Khan: (a) The requisite detail of areas in Balochistan
to be electrified during current fiscal year (FY 2018-19) alongwith the amount
allocated is attached as Annex-A.
Mr. Ghulam Sarwar Khan: (a) No. OGDCL and MOL Pakistan
are operators engaged in exploration and production activities in Districts
Kohat and Karak, Status of unskilled labor employed by M/s. OGDCL and
MOL Pakistan is as under:
(b) the decrease made in the prices of the said products in the
country on the basis of that decrease in International
Market; and
Mr. Ghulam Sarwar Khan: (a) the decrease registered in the prices
of petroleum products in international Market during the month of December
2018 is as under:-
Will the Minister for Religious Affairs and Inter Faith Harmony
be pleased to state:
1
(286th Session)
SENATE SECRETARIAT
—————
“UN-STARRED QUESTION AND ITS REPLY”
For Wednesday, the 23rd January, 2019
DEFERRED QUESTION