Professional Documents
Culture Documents
Time-Cost Tradeoff Task Durations Can Be Flexible: Task Direct Costs Project
Time-Cost Tradeoff Task Durations Can Be Flexible: Task Direct Costs Project
Direct
Cost
of the
task
1
18-07-2019
Linear Time-cost Tradeoff for Tasks Non-Linear Time-cost Tradeoff for Tasks (Convex)
i j
i j
Direct
Cost of Direct
the task Cost
of the
task
Non-Linear Time-cost Tradeoff for Tasks (Concave) Discontinuous Time-cost Tradeoff for Tasks
i j i j
Direct Direct
Cost of Cost of
the task the task
2
18-07-2019
Example 1 Example 1
2
Paths A B C D E F G H
A F
D
ADG 100 80 140
B G 5 AF 100 50 60
1 4
c E H
BG 120 140
3 CEG 50 140
*
Identify all the paths in the network and the
corresponding completion times CH 50 100
3
18-07-2019
Example 1 Example 1
Direct Cost
Increment
• Identify the critical path among all the paths 900
800
• On the critical path, which activity should be chosen for crashing?
700
600
500 Crash D
400 by 2 days
300 P2
200
100 P1
Project
11 12 13 14 15 16 Duration
Example 1 Example 1
Paths A B C D E F G H
Possible combinations of tasks that can be chosen for crashing
ADG 100 80 140 14
AF 100 50 60 14 • A, B
BG 120 140 14 • A, G
CEG 50 140 • F, G
* 12
CH 50 100
• D, F, B
5
1 2 1 0 2 2 1
Example 1 Example 1
Possible combinations of tasks that can be chosen for crashing Possible combinations of tasks that can be chosen for crashing
• A, B [Cost: 220, Maximum crash: 1]
• A, B [Cost: 220, Maximum crash: 1] • A, G [240, 1]
• A, G [240, 1] • F, G [200, 2]
• F, G [200, 2] • D, F, B [260,0]
• D, F, B [260,0] • Crash A & G; Relax D [160, 1]
4
18-07-2019
Example 1 Example 1
Direct Cost Paths A B C D E F G H
Increment
900
800
ADG 100 80 140 13
700
AF 100 50 60 13
600
500 Crash A & G;
P3 BG 120 140 13
400 320 Relax D
300 CEG 50 140
200
160 P2 * 11
100 P1
CH 50 100 5
Project
11 12 13 14 15 16 Duration 0 2 1 1 2 1 1
Project Management: Amit Kumar Bardhan, Faculty of
Management Studies, University of Delhi.
Example 1 Example 1
Direct Cost
Increment
Possible combinations of tasks that can be chosen for crashing 900
800
• A, B [Cost: 220, Maximum crash: 0] 700
P4
• A, G [240, 0] 600 520 Crash F & G
500
• F, G [200, 1] 400 320
P3
• D, F, B [260,1] 300
200
160 P2
• Crash A & G; Relax D [160, 0] 100 P1
Project
11 12 13 14 15 16 Duration
Project Management: Amit Kumar Project Management: Amit Kumar
Bardhan, Faculty of Management Bardhan, Faculty of Management
Studies, University of Delhi. Studies, University of Delhi.
Example 1 Example 1
Paths A B C D E F G H
Possible combinations of tasks that can be chosen for crashing
ADG 100 80 140 12
• A, B [Cost: 220, Maximum crash: 0]
AF 100 50 60 12
• A, G [240, 0]
BG 120 140 12 • F, G [200, 0]
CEG 50
* 140 10 • D, F, B [260,1]
CH 50 100 5
• Crash A & G; Relax D [160, 0]
0 2 1 1 1 0 1
5
18-07-2019
Example 1 Example 1
Direct Cost Paths A B C D E F G H
Increment
900 P5
800 780 ADG 100 80 140 11
Crash D, F & B
700
AF 100 50 60 11
600 520 P4
500
P3 BG 120 140 11
400 320
300 CEG 50 140
200
160 P2 * 10
100 P1
CH 50 100 5
Project
11 12 13 14 15 16 Duration 0 0 1 0 0 0 1
Project
11 12 13 14 15 16 Duration