Professional Documents
Culture Documents
Prasad2011 PDF
Prasad2011 PDF
M. Prasad N. Theivarajan
Jawaharlal Nehru Technological University Power Plant Control Division
JNTUK, Kakinada Indira Gandhi Centre for Atomic Research (IGCAR)
Andhra Pradesh, India. Kalpakkam, Tamil Nadu, India.
ramprasadmajji@gmail.com theiva@igcar.gov.in
Abstract— Nuclear power plants have Normal and Normally an automatic fast transfer scheme is in service
Emergency power supply systems. Both the power supply during normal operation and if it fails the mode changes over
systems are to be reliable for safe operation of the plant. to slow transfer. For fast transfers, the electrical
Prototype Fast Breeder Reactor (PFBR) coming up at characteristics of the specific bus loads are determined by
Kalpakkam is a single unit 500MWe project. The normal calculation or test, in conjunction with the relay and breaker
power supply system consists of two Station Buses and two operating time, to ensure that the voltage and phase-angle
Unit Buses. The station buses are fed from grid through a displacement of the bus residual voltage will not cause
Station Transformer (ST). The Unit buses are fed through equipment damage.
Unit Auxiliary Transformers(UATs) either from plant A fast transfer incorporates the use of fast-acting, stored-
generator or grid .The UATs are normally fed by generator energy breakers (such as 5 cycles or less opening time)
while plant is in operation .When plant generator is not That disconnects the normal source and reconnects the
available the UATs are fed from grid through generator alternative source before phase-angle displacement of the bus
transformer. and residual voltage can change appreciably. A fast transfer
Normally unit buses and station buses supply the has no intentional time delay. The transfer is based on the
loads connected to them. In the event of a need on supply conditions that the two sources are in synchronism.
interruption to one unit bus, the loads supplied from this bus
can be transferred to a designated station bus and vice-versa This paper covers the modeling of the PFBR normal power
for continuity of power supply to the loads. The ST and UAT system having the provision of auto transfer, simulation of the
are adequately sized for this. This paper covers the modeling of system and assessment of bus electrical profiles with the
turbine generator, ST, UAT and the loads connected to the realistic loads .This will be helpful during site commissioning
station and unit buses of this system to analyze the bus transfer tests since transfer performance expected is available
of loads from a unit bus to station bus and vice-versa which beforehand to correlate with test results.
keeps the plant loads running on fast transfer mode.
2.0 PLANT DATA AND SYSTEM ARRANGEMENT
Keywords: Bus Transfer ,Turbo-Generator, Induction Motors, Class IV normal AC power supply scheme for PFBR is
ETAP. shown in Figure1.0. This power system derives its power
from different sources of supply as mentioned below:
1.0 INTRODUCTION 1) From the grid through 220 kV/6.9 kV/6.9 kV station
transformer.
The objective of a bus transfer scheme is to transfer the station 2) From the grid through a 235 kV/21 kV generator
loads between power sources safely while maintaining support transformer and two numbers of 21kV/6.9 kV unit
to the nuclear steam supply system, the turbine generator, and auxiliary transformers with the generator circuit breaker
plant auxiliary loads ensuring either continued unit operation or kept in open position.
safe shutdown. 3) From the terminals of the Turbo-Generator through the
two numbers of 21 kV/6.9 kV unit auxiliary transformers
In PFBR Normally 6.6kV unit buses and station buses supply when the Generator circuit breaker is closed during
the loads connected to them. In the event of a need on supply power generation.
interruption to one unit bus, the loads supplied from this bus The UATs are rated for 35MVA each. The ST is rated for
can be transferred to a designated station bus and vice-versa for 70MVA with each secondary winding rated for 35MVA .The
continuity of power supply to the loads estimated station auxiliary load is around 55MVA. Total
station auxiliary loads can be supplied either by the UATs or
Bus transfer scheme provided permits fast transfer, slow by the ST.
transfer and parallel transfer modes. They will be adopted to the
plant operating conditions suitably.
978-1-61284-379-7/11$26.00 2011
c IEEE 294
Normal class IV power supply to station loads at 6.6 kV are
supplied by two numbers unit buses and two numbers station Table.2: Individual Motor load details
buses. Two separate unit auxiliary transformers supply the Equivalent Inertia
two unit buses. One three winding station transformer with Constant
MOTOR KW KV
H
two secondaries supply the station buses. Similarly between (MW-sec/MVA)
the Unit bus-2 and Station bus-2 another tie circuit breaker is CEP-2 800 6.6 1.5
provided. The tie breaker one unit bus and a station bus NSWP-2 400 6.6 2
facilitates bus transfer one transformer to the other. The bus CWP-2 3600 6.6 1.5
CEP-1 800 6.6 1.5
transfer modes provided are:
NSWP-1 400 6.6 2
a. Auto bus transfer (fast and slow changeover) ASWP-2 550 6.6 1.5
Changeover in this takes place in auto mode through CWP-1 3600 6.6 1.5
auto transfer scheme. ASWP-1 550 6.6 1.5
b. Manual bus transfer (parallel transfer) NSWP-3 400 6.6 2
CEP-3 800 6.6 1.5
Changeover in this mode is made manually done after LML 1000 6.6 1.5
ensuring synchronism of the sources from MCR LML-1 1000 6.6 1.5
c. Manual bus transfer (fast and slow changeover) LML-2 10000 6.6 2
Changeover in this mode is made manually initiated LML-3 10000 6.6 2
through the auto transfer scheme from MCR/ Auto
transfer panel. The most important parameter in conventional fast - transfer
There are two separate auto bus transfer techniques is drive inertia. In general, the higher-inertia
panels one associated with the bus transfers between drives have a much better chance of success than do the
Unit Bus 1 and Station Bus 1 and the other associated lower - inertia drives. Also, in many instances, the high -
with the transfers between Unit Bus 2 and Station Bus 2 inertia drives act as generators to support the low - inertia
respectively. Auto Fast Transfer is planned to be drives as motors through the open-circuit transfer period.
operational during normal operation. Thus, not only are the individual drive inertias important but
so is the aggregate or equivalent inertia for all drives on the
transferred bus. In this paper an inertia constant, H used for
the motors and driven equipment combination are based on
the preliminary data sheets of the suppliers and estimation.
They will be fine tuned on the as manufactured equipment
supply.
3.0 SYSTEM MODELLING
Presently, advanced modeling and digital simulation
techniques can be used to analyze the dynamic behavior of
electrical systems. Digital simulations can accurately
represent the dynamics Turbine -generator unit, including the
governor and exciter/voltage regulators, grid, as well as the
load dynamics. The digital simulation is done using ETAP.
ETAP is a commercial Power System
analysis package. The transient stability module is used for
modeling and simulation for simulation of electrical transient
phenomena of the system. ETAP has several built-in models
of controller for generator excitation system and speed
governing control systems based from IEEE standard. Table:
Figure.1: System Arrangement.
4 shows the modeling basis used in the analysis.
Case Studies:
Figure.5: Induction Motor Equivalent Circuit Model. (Typical to Four study cases were simulated for fast transfer. The
all motors) command to trip the normal breaker and close the alternate
incoming breaker on proper logic is issued simultaneously.
4.0 FAST TRANSFER REQUIREMETS , CASE STUDIES & With the ordered breakers this results in approximately 3
SIMULATION cycle dead bus time for fast transfer. One advantage is that
Requirements of Fast Transfer: transfer time is too brief to allow residual bus voltage to slip
significantly out of phase with the source voltage
The broad requirements of fast transfer are given below [1]
The cases analyzed with the plant loads are:
A fast transfer is defined in ANSI C50.41 [B2] as one that
occurs within 10 cycles where the phase angle between the (1) Bus Transfer from Station bus-1 to Unit bus-1.
motor residual volts and the system equivalent volts does not
Exceed 90° and the resultant volts per hertz between the (2) Bus Transfer from Unit bus-1 to Station bus-1.
motor supply bus volts per hertz and the alternate. A source
volt per hertz, at transfer, does not exceed 1.33 p.u. volts per (3) Bus Transfer from Station bus-2 to Unit bus-2.
hertz.
For a 3 cycle delay, studies show the angular (4) Bus Transfer from Unit bus-2 to Station bus-2.
displacement to be 22° to 30°. Under this condition, the
resultant voltage is less than rated motor voltage. For a 6 Case 1: Bus Transfer from Station Bus-1 to Unit Bus-1:
cycle delay, the displacement is 40° to 60°. Under this During normal operation, when station transformer supply to
condition, the resultant voltage will be equal to or exceed station bus1 is interrupted by the incoming CB tripping on
motor rated voltage. Although the resultant voltage may ensuring no bus fault, bus tie breaker will close and enable
unit bus1 to supply the station bus 1with a break time of about
exceed the rated voltage, it is not expected to exceed the
3 cycles (60ms). The voltage, frequency and phase angles are
recommended value of 1.33 p.u. It should be noted that the
given in Fig.7 & Fig. 8
above values of angular displacement are approximate.
6.0 CONCLUSION
Presently, advanced modeling and digital simulation tools
help in modeling and simulation of complex auto fast transfer
scheme .They are used to analyze whether the conditions are
met to adopt fast transfer with the realistic loads.
The preliminary assessment assures successful fast transfer
for the estimated transfer time and the inertia constants based
on the preliminary data sheets from the vendors and the
generic modeling of turbine generator excitation and
governing system. The analysis will be updated models of the
generator AVR, governor, and load inertias.
8.0 REFERENCES