Professional Documents
Culture Documents
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
Mechanical and Process Design of the Flevo Power
Station Conversion Project
J. FEENSTRA, EPON, the Netherlands
P. KAMMINGA, Thomassen International, the Netherlands
This paper gives a description of the The original studies to repower steam
most important points of the mechanical, and power plants with gas turbines indicated a
process design of the combined cycle unit high potential for improved efficiency. How-
and the influence of the gas turbine on the ever, all plans for conversion were later
starting procedure. disregarded because they were not econo-
mically feasible. The main reason for this
was the large overcapacity in generating
INTRODUCTION power, which would be substantially in-
creased if a large amount of gas turbine
The production of electricity in the power were added.
Netherlands is mainly based on fossil fuel
fired power plants. For example, in 1980, the production
capacity installed was 15,500 MW, the
highest load demand being 9,500 MW with a
The predominant factor determining the
potential of 800 MW of gas turbine power.
price of electricity is fuel cost. Table I
shows the percentages of fuel used over the
A few years later in the Netherlands
last decade along with the anticipated use
another concept was studied which was to
in the near future.
keep the total station output constant by
reducing the steam turbine output by the
Table 1: Fuels For Power Generation In The
same amount as the output of the gas turbine
Netherlands
being installed.
1. 976 198 1 1985 1.990_
This concept proved to he very success-
Coal 5% 14% 27% 42%
ful and as a result several utility
Oil 8% 41% 1% 2%
companies installed gas turbines. A total
Gas 78% 37% 64% 48%
amount of 850 MW of gas turbine power was
Uranium 9% 8% 8% 8%
ordered for efficiency improvement of 10
different power generating plants having a
total generating capacity of 3,800 NW.
Presented at the Gas Turbine and Aeroengine Congress and Exposition—June 4-8, 1989—Toronto, Ontario, Canada
C
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
generating capacity in the Netherlands.
2
H
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
- fuel flow kg/s 9.1 8.9 7.4
- exhaust flow kg/s 408 420 372 the heating surface of the superheater and
- exhaust temp. K 808 809 775 reheater had to be enlarged. Enlarging of
- efficiency % 31.0 28.8 30.3 the heating surface lead to a unit
efficiency increase of 0.25 percentage
With these three gas turbines Stork point. A feasibility study concluded that it
Boilers made performance calculations using i_s more profitable to choose the lower
the cycle calculation program "cycle Ill" efficiency, i.e. by not increasing the
(1). The results are given in Figure 2. heating surface of superheater and reheater.
3
L
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
centage point of the units efficiency at the compressor inlet guide vanes,
60% load, because of the lower live steam resulting in an increase of airflow of 2%.
temperatures and reheat steam temperatures - The first stage bucket material was
in this range. changed to a General Electric developed
alloy GTD-111, which has increased
temperature capability compared to its
We can eliminate this disadvantage by predecessor IN738.
enlarging the heating surface of the super- - The first stage turbine nozzle was
heater and reheater but then we introduce equipped with an improved cooling design
another disadvantage, namely the which gives optimal performance.
investment of enlarging these. - Combustion liners of the latest design
have a thermal barrier coating.
- An improved exhaust diffuser design.
Based on this evaluation, EPON decided - A small increase in firing temperature of
to realize the repowering without a gas 10 ° C.
turbine evaporator.
Incorporating the new data in the
overall cycle calculation revealed an even
GAS TURBINE PG9161 (E) better performance, resulting in an improved
heat rate of the total power station of
During the evaluation phase of the 0.6%, and hence an improved economical
project an improved version of the PG9141 feasibility of the conversion program.
(E) gas turbine, the PG9161 (E), became
available and was used for the Flevo
Project. Based on good experience with the
60 Hz gas turbine MS7001E several design The gas turbine PG9161 (E) is shown in
improvements were made, giving an increase Figure 3.
in output of 4.4% and a decrease in heat
rate of 2.8%.
1612 0546 0801 1501 0703 0702 0705 0706 1503 1625
214 0701
0514 Ilil 502 1403 409
0513 1401
0811 0802 1302 0512
O2 /
A/// 1
1301 / 0803
1314
1319
131 3
II i.^
TJL:
IG-=— --1
1604 II 0901
H AIR
IN LET COMPRESSOR —a^s- COMBUSTION —TURBINE rls EXHAUST
4
IS A GAS TURBINE STACK NECESSARY? Based on an optimization study EPON
decided not to install a gas turbine stack.
In Figure 4, the simplified situation
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
before repowering and two alternative
repowering models with and without gas
turbine stack are shown:
STARTING PROCEDURE
SITUATION BEFORE REPOWERING WITH REPOWERING WITHOUT
REPOWERING GASTURBINE STACK GASTURBINE STACK The decision not to install a gas
150 kV 150 kV 150 kV turbine stack resulted in the need for an
integrated starting procedure for the total
plant: gas turbine, boiler and steam
EXTRA
TRANS- TRANS- TRANS- TRANS- turbine. A major concern was the capability
FORMER FORMER FORMER 01 FORMER of the boiler to accept the exhaust
conditions of the gas turbine during a
STEAM STEAM STEAM normal starting procedure. The fact that a
TURBINE TURBINE TURBINE gas turbine after firing accelerates to its
G G rated speed and exhaust flow in just 8
minutes, made modifications to the starting
sequence necessary.
GASTURBINE
STACK In order to obtain a slower and smooth
BOILER IBOIL BOILER
starting characteristic, several salient
features were added to the normal starting
® cycle:
FAN
G 1. Warming-up speed after firing is increased
CASTUR INE from the normal 20 - 30% to 50% speed in
order to increase the initial mass flow and
reduce boiler purge time. The length of this
phase is determined by the boiler.
Figure 4: The Simplified Situation Before
2. Turbine acceleration between 50% and 95% of
And After Repowering rated speed is fixed, because in this speed
range the compressor is moving through
regions with possible rotating stall which
Installing of a gas turbine stack has could lead to compressor blade damage if
several advantages: prolonged operation at such a condition
- we can instantly produce electrical power could take place.
to the grid, so the gas turbine can In order to limit compressor flow, the com-
operate instantly at its best efficiency; pressor inlet guide vanes remain in the
- the quantity of exhaust flow to the boiler closed position (34 ° ).
can be controlled, i.e. maximized;
- the above mentioned advantages result in A further possible measure to reduce
25% lower starting costs in comparison airflow, is to allow the inlet air heating
with the situation without using a gas system for anti-icing to preheat the inlet
turbine stack; air to the compressor and hence create a
- the availability of the unit can be lower density resulting in a reduced mass
increased because solo operation of the flow.
gas turbine is possible. The turbine remains at this condition until
the boiler and steam turbine are warmed-up.
A gas turbine stack has disadvantages 3. After synchronising, the turbine is loaded
too: to 2 MW, air preheating is shut down and the
- the investment of the gas turbine stack; compressor inlet guide vanes opened to the
- in the situation of using a gas turbine minimum position (57 0 ) for loading the gas
stack we cannot apply the electrical turbine, representing approximately 80% of
connection of the gas turbine alternator rated air flow.
like we planned in the situation without
a gas turbine stack. So when we decide on 4. Turbine is loaded to base load, representing
using turbine stack an extra transformer 100% air flow and a maximum position (84 ° )
is needed; of the compressor inlet guide vanes.
- flue gas leakages through the gas turbine
stack dampers; For details see Figure 5, depicting the
- vulnerability of the gas turbine stack main parameters during the starting
dampers. sequence.
GASTURBINE
MW K 7.
} } I EXHAUST TEMP (K)
EXHAUST FLOW (7.)
500 773 100
SUPER-
I.G.V.'S AT 57' I. G.V.'S AT 84'
HEATER
116 MW
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
400 673 80 379 MW
STEAM TURBINE LOAD (MW)
LOW PRESSURE
ECONIMISER
6
in
Nett. Unit
Efficientcy (%) (LHV) As there is some uncertainty between the
46
ng guaranteed and expected NOx levels, the
following solutions were studied in case the
expected levels are not met:
Downloaded from https://asmedigitalcollection.asme.org/GT/proceedings-pdf/GT1989/79160/V004T09A022/4457033/v004t09a022-89-gt-245.pdf by Korea Power Engrg Co Inc Library user on 23 October 2019
42
ring - steam injection into the gas turbine;
60
After completing several feasibility
studies on some systems of the combined
40 -------- t t
cycle unit, the repowering concept of Flevo
Power Station unit 3 has been optimized.
20 Gas Turbine Load:100% 100% 100% 1 After This combined cycle unit will be in
Boiler Load: 20% 60% 100% J Repowering operation in February 1989, after which the
0 actual efficiency will be determined. The
100 200 300 400 500 _i
calculated unit efficiency is given in
Nett.Unit Load (MW) Figure 7.
Figure 7B: NOx Emissions (gr NOx/GJ fuel) Before And After Repowering
r kg/h NOx
(natural gas) REFERENCES
1000
(1) Miedema, J.A.; Liefhebber, F. and Op den
900 ng Brouw, H. Computer Program Cycle III
Report EV-1158 (1980) and EV-1157 -2
800 (1986)
Delft University of Technology,
700 Laboratory for Thermal Power Engineering
600
500
, wering
400
300
200
100
0
100 200 300 400 500
MW
Figure 7C: NOx Emissions (kg/h NOx) Before And After Repowering