FAKULTI KEJURUTERAAN PEMBUATAN

UNIVERSITI TEKNIKAL MALAYSIA MELAKA (UTeM)

MANUFACTURING MANAGEMENT

BMFP 4413 ASSIGNMENT SESSION 2019/2020

Question 1

For the project data in Table 1, answer the following questions:

a) Draw an AOA network of the project?


b) Perform forward path and backward path calculations?
c) What is the effect of delaying activity D by 3 days?

Untuk data projek dalam Jadual 1, jawab soalan berikut:

a) Lukis rangkaian AOA projek?


b) Menjalankan pengiraan jalan ke hadapan dan ke belakang?
c) Apakah kesan melambatkan aktiviti D oleh 3 hari?

Table 1: Data for Question 1

Immediate
Activity Duration
predecessor
A 2 -AA
B 6 BB
C 3 C, D
D 1 E, F
E 6
F 3
G 2
Question2

Perform PDM calculations for the small project below and determine activity times. Durations
are shown on the activities.

Lakukan pengiraan PDM untuk projek kecil di bawah dan tentukan masa aktiviti. Durasi
ditunjukkan pada aktiviti.

Question 3

For the activities listed in the table below, draw the time-scaled diagram and mark the critical
path. Determine the completion time for the project. Tabulate activities times and floats.

Untuk aktiviti-aktiviti yang disenaraikan dalam jadual di bawah, lukis gambarajah skala masa
dan tandakan laluan kritikal. Tentukan masa siap untuk projek. Tabulasi aktiviti masa dan
terapung.

Table 2: Data for Question 3

Activity Duration Predecessor


A 4 -
B 4 A
C 8 B
D 3 C
E 5 A
F 2 B, E
G 8 C, F
H 5 D, G
I 17 -
J 10 G, I
Question 4

Perform PDM calculations for the small AoN network shown here. Pay special attention to the
different relationships and the lag times shown on them.

Lakukan pengiraan PDM untuk rangkaian AoN kecil yang ditunjukkan di sini. Beri perhatian
khusus kepada hubungan yang berbeza dan masa lag yang ditunjukkan pada mereka.