MANUFACTURING MANAGEMENT
Question 1
Immediate
Activity Duration
predecessor
A 2 -AA
B 6 BB
C 3 C, D
D 1 E, F
E 6
F 3
G 2
Question2
Perform PDM calculations for the small project below and determine activity times. Durations
are shown on the activities.
Lakukan pengiraan PDM untuk projek kecil di bawah dan tentukan masa aktiviti. Durasi
ditunjukkan pada aktiviti.
Question 3
For the activities listed in the table below, draw the time-scaled diagram and mark the critical
path. Determine the completion time for the project. Tabulate activities times and floats.
Untuk aktiviti-aktiviti yang disenaraikan dalam jadual di bawah, lukis gambarajah skala masa
dan tandakan laluan kritikal. Tentukan masa siap untuk projek. Tabulasi aktiviti masa dan
terapung.
Perform PDM calculations for the small AoN network shown here. Pay special attention to the
different relationships and the lag times shown on them.
Lakukan pengiraan PDM untuk rangkaian AoN kecil yang ditunjukkan di sini. Beri perhatian
khusus kepada hubungan yang berbeza dan masa lag yang ditunjukkan pada mereka.