Electrical Schedule Plan

30-Oct-19
No Description QTY Unit

1 Accomodation

1.1 Staff Mess (8 Building)


Laying cable Building (3C# 2.5mm) 560 Mater
Laying cable Underground (3C# 4mm) 350 Mater
Connect cable building roundbox 88 ea
Install dan Connect Receptacle dan Switch 128 ea
Install dan Connect Lighting fixture 144 ea
Install LDB dan Termination 8 ea

1.2 Lead Mess (3 Building)


Laying cable Building (3C# 2.5mm) 210 Mater
Laying cable Underground (3C# 4mm) 300 Mater
Connect cable building roundbox 33 ea
Install dan Connect Receptacle dan Switch 48 ea
Install dan Connect Lighting fixture 54 ea
Install LDB dan Termination 3 ea

1.3 Manager Mess (3 Building)


Laying cable Building (3C# 2.5mm) 210 Mater
Laying cable Underground (3C# 4mm) 300 Mater
Connect cable building roundbox 33 ea
Install dan Connect Receptacle dan Switch 48 ea
Install dan Connect Lighting fixture 54 ea
Install LDB dan Termination 3 ea

1.4 Recreation (1 Building)


Laying cable Building (3C# 2.5mm) 210 Mater
Laying cable Underground (3C# 4mm) 300 Mater
Connect cable building roundbox 33 ea
Install dan Connect Receptacle dan Switch 48 ea
Install dan Connect Lighting fixture 14 ea
Install SDP-04 dan Termination 1 ea

2 Main Cable
2.1 Open Cable Trench Power House to Admin, 370 Meter
Canteen dan Accomodation
2.2 Pulling Cable 4C# 240mm Powerhouse to SDP-01 210 Meter
Admin

2.3 Pulling Cable 4C# 120mm Powerhouse to SDP-03 280 Meter


Canteen

2.4 Pulling Cable 4C# 70mm Canteen SDP-03 Building 90 Meter


to Accomodation SDP-04 Recreation Room
2.5 Install SDP-03 dan Termination 1 ea
2.6 Install SDP-04 dan Termination 1 ea

3 Lightning Protection

Fabrication support base plate


Intalltion Support
Pekerjaan Pulling kabel BC 50 mm2
Pekerjaan Pulling kabel Down Conductor BC 70 mm2
Pekerjaan Instalasi Termination Box
Pekerjaan Instalasi Air Terminal 500 mm & Base
Pekerjaan Pembuatan Ground Pit (Concrete)
Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm
Pekerjaan Instalasi Kabel BCC 70 mm2
Pekerjaan Terminasi & Glanding

manpower electrical
13 orang
31-Oct-19 dule Plan
1-Nov-19

2-Nov-19

3-Nov-19

4-Nov-19

5-Nov-19
Schedule Plan

6-Nov-19

7-Nov-19

8-Nov-19

9-Nov-19

10-Nov-19
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec

EPC-3A EIT Progress Plan (Constrution + Comm.)

III. STAFF MESS BUILDING 0.0% 1.0% 2.1% 3.1% 4.2% 8.2% 15.1% 42.2% 66.0% 92.8% 100.0% 100.0% 100.0%

a. PEKERJAAN ELEKTRIKAL 0% 4% 8% 13% 17% 25.0% 33.3% 62.5% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - 24 24 24 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 16.7% 33.3% 50.0% 66.7% 83.3% 100.0% 0% 0% 0% 0% 0% 0%
Quantity (Titik) - 24 24 24 24 24 24 - - - - - - 16.6667
Manpower (Orang) - 2 2 2 2 2 2 - - - - - -
3 Pemasangan Pipa Conduit 0% 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 17% 33% 50% 67% 83% 100% 0% 0% 0% 0% 0% 0%
Quantity (titik) - 24 24 24 24 24 24 - - - - - -
Manpower (Orang) - 2 2 2 2 2 2 - - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 280 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 26 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 16 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 72 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 2 2 2 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 8 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 4 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -

d. Telecom (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 100 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 104 - - -
Manpower (Orang) - - - - - - - - - 4 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 8 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec

EPC-3A EIT Progress Plan (Constrution + Comm.)

IV. STAFF MESS BUILDING 0.0% 0.0% 0.0% 0.0% 0.0% 3.8% 12.0% 41.5% 66.0% 92.8% 100.0% 100.0% 100.0%

a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0.0% 7.3% 20.8% 59.4% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - 24 24 24 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - 24 24 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 25% 25% 25% 25% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 25% 50% 75% 100% 0% 0% 0% 0%
Quantity (meter) - - - - - 280 280 280 280 - - - -
Manpower (Orang) - - - - - 2 2 2 2 - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 256 - - - - - 256
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 16 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 72 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 6 6 4 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 6 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 3 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -

d. Telecom (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec

EPC-3A EIT Progress Plan (Constrution + Comm.)

V. RECREATION ROOM 0.0% 0.0% 0.0% 0.0% 0.0% 1.9% 8.4% 40.7% 66.0% 92.9% 100.0% 100.0% 100.0%

a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0.0% 0.0% 6.3% 56.3% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 0% 0% 100.0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - 24 24 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 35 35 - - - -
Manpower (Orang) - - - - - - - 2 2 - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 15 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 16 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 72 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 6 6 4 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 6 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 3 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -

d. Telecom (PAGA, Telephone, LAN) 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 7.1% 28.6% 42.9% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec

EPC-3A EIT Progress Plan (Constrution + Comm.)

II. LEAD MESS BUILDING 0.0% 0.0% 0.0% 0.0% 0.0% 1.9% 13.1% 42.2% 66.0% 92.9% 100.0% 100.0% 100.0%

a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0% 0.0% 25.0% 62.5% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - - - 12 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - 24 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - 24 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 4 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 2 2 2 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 8 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 4 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -

d. Telecom (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Progress Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec

EPC-3A EIT Progress Plan (Constrution + Comm.)

I. MANAGER MESS BUILDING 0.0% 0.0% 0.0% 0.0% 0.0% 8.5% 26.6% 52.6% 68.3% 92.9% 100.0% 100.0% 100.0%

a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0% 25.0% 37.5% 62.5% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (M) - - - - - - 6 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - 26 - - - - - - -
Manpower (Orang) - - - - - 2 - - - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - 26 - - - - - - -
Manpower (Orang) - - - - - 2 - - - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 10 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 26 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -

b. Penangkal Petir 0% 0% 0% 0% 0% 9% 55% 91% 100% 100% 100% 100% 100%


1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0% 0%
Accumulative progress (%) - - - - - 50% 100% 0% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 9 9 - - - - - -
Manpower (Orang) 0% 0% 0% 0% 0% 2 2 - - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 64 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 6 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 4 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 2 2 - - - - - -
Manpower (Orang) - - - - - 3 3 - - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 4 - - - - - -
Manpower (Orang) - - - - - - 3 - - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 10 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 4 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -

c. Instrument (Fire Alarm) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%


1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - - 8 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 9 9 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -

d. TELECOM (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 0 0 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -