30-Oct-19
No Description QTY Unit
1 Accomodation
2 Main Cable
2.1 Open Cable Trench Power House to Admin, 370 Meter
Canteen dan Accomodation
2.2 Pulling Cable 4C# 240mm Powerhouse to SDP-01 210 Meter
Admin
3 Lightning Protection
manpower electrical
13 orang
31-Oct-19 dule Plan
1-Nov-19
2-Nov-19
3-Nov-19
4-Nov-19
5-Nov-19
Schedule Plan
6-Nov-19
7-Nov-19
8-Nov-19
9-Nov-19
10-Nov-19
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec
III. STAFF MESS BUILDING 0.0% 1.0% 2.1% 3.1% 4.2% 8.2% 15.1% 42.2% 66.0% 92.8% 100.0% 100.0% 100.0%
a. PEKERJAAN ELEKTRIKAL 0% 4% 8% 13% 17% 25.0% 33.3% 62.5% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - 24 24 24 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 16.7% 33.3% 50.0% 66.7% 83.3% 100.0% 0% 0% 0% 0% 0% 0%
Quantity (Titik) - 24 24 24 24 24 24 - - - - - - 16.6667
Manpower (Orang) - 2 2 2 2 2 2 - - - - - -
3 Pemasangan Pipa Conduit 0% 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 17% 33% 50% 67% 83% 100% 0% 0% 0% 0% 0% 0%
Quantity (titik) - 24 24 24 24 24 24 - - - - - -
Manpower (Orang) - 2 2 2 2 2 2 - - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 280 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 26 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 16 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 72 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 2 2 2 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 8 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 4 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
d. Telecom (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 100 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 104 - - -
Manpower (Orang) - - - - - - - - - 4 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 8 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec
IV. STAFF MESS BUILDING 0.0% 0.0% 0.0% 0.0% 0.0% 3.8% 12.0% 41.5% 66.0% 92.8% 100.0% 100.0% 100.0%
a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0.0% 7.3% 20.8% 59.4% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - 24 24 24 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - 24 24 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 25% 25% 25% 25% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 25% 50% 75% 100% 0% 0% 0% 0%
Quantity (meter) - - - - - 280 280 280 280 - - - -
Manpower (Orang) - - - - - 2 2 2 2 - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 256 - - - - - 256
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 16 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 72 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 6 6 4 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 6 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 3 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
d. Telecom (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec
V. RECREATION ROOM 0.0% 0.0% 0.0% 0.0% 0.0% 1.9% 8.4% 40.7% 66.0% 92.9% 100.0% 100.0% 100.0%
a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0.0% 0.0% 6.3% 56.3% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 0% 0% 100.0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - 24 24 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 35 35 - - - -
Manpower (Orang) - - - - - - - 2 2 - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 15 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 8 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 8 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 16 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 72 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 6 6 4 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 6 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 3 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
d. Telecom (PAGA, Telephone, LAN) 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 7.1% 28.6% 42.9% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Schedule Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec
II. LEAD MESS BUILDING 0.0% 0.0% 0.0% 0.0% 0.0% 1.9% 13.1% 42.2% 66.0% 92.9% 100.0% 100.0% 100.0%
a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0% 0.0% 25.0% 62.5% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (M) - - - - - - - 12 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - - 24 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - 24 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 4 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
b. Penangkal Petir 0.0% 0.0% 0.0% 0.0% 0.0% 3.0% 10.6% 63.6% 90.9% 100.0% 100.0% 100.0% 100.0%
1 Pabrikasi Support Base Plate 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - 18 18 - - - - -
Manpower (Orang) - - - - - - 4 4 - - - - -
2 Pekerjaan Instalasi Support 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
3 Pekerjaan Pulling kabel BC 50 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 128 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
4 Pekerjaan Pulling kabel Down Conductor BC 70 mm2 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - 24 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Termination Box 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
6 Pekerjaan Instalasi Air Terminal 500 mm & Base 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 36 - - - - -
Manpower (Orang) - - - - - - - 4 - - - - -
7 Pekerjaan Pembuatan Ground Pit (Concrete) 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33% 67% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - 2 2 2 - - - - -
Manpower (Orang) - - - - - 3 3 3 - - - - -
8 Pekerjaan Instalasi Ground Rod 5/8" x 3000 mm 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 8 - - - - -
Manpower (Orang) - - - - - - - 3 - - - - -
9 Pekerjaan Instalasi Kabel BCC 70 mm2 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 20 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
10 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 4 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
11 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 4 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
c. Instrument (Fire Alarm) 0.0% 0.0% 0.0% 0.0% 0.0% 4.8% 9.5% 14.3% 42.8% 85.7% 100.0% 100.0% 100.0%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 3 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 33.3% 33.3% 33.3% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 33.3% 66.6% 99.9% 0% 0% 0% 0% 0% 42.8571
Quantity (Meter) - - - - - 15 15 15 - - - - -
Manpower (Orang) - - - - - 2 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi Device FA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JBFA 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
d. Telecom (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 8 7 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -
EPC-3A EIT Progress Plan
September-19 October-19 November-19 December-19
NO. DESCRIPTION
1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec
I. MANAGER MESS BUILDING 0.0% 0.0% 0.0% 0.0% 0.0% 8.5% 26.6% 52.6% 68.3% 92.9% 100.0% 100.0% 100.0%
a. PEKERJAAN ELEKTRIKAL 0% 0% 0% 0% 0% 25.0% 37.5% 62.5% 87.5% 100.0% 100.0% 100.0% 100.0%
1 Pekerjaan Pemasangan Pipe Sleeve 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0%
Quantity (M) - - - - - - 6 - - - - - -
Manpower (Orang) - - - - - - 2 - - - - - -
2 Pekerjaan Bobokan Dinding 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
Quantity (Titik) - - - - - 26 - - - - - - -
Manpower (Orang) - - - - - 2 - - - - - - -
3 Pemasangan Pipa Conduit 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - 26 - - - - - - -
Manpower (Orang) - - - - - 2 - - - - - - -
4 Pekerjaan Instalasi & Fabrikasi Tray Electrical 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (meter) - - - - - - - 10 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
5 Pekerjaan Instalasi Kabel Listrik 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (titik) - - - - - - - 26 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
6 Pekerjaan Instalasi Panel Listrik 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
7 Pekerjaan Glanding & Terminasi 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - - 2 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
8 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
d. TELECOM (PAGA, Telephone, LAN) 0% 0% 0% 0% 0% 0% 7% 29% 43% 86% 100% 100% 100%
1 Pekerjaan bobokan 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0% 0%
Quantity (Unit) - - - - - - - 3 - - - - -
Manpower (Orang) - - - - - - - 2 - - - - -
2 Pekerjaan Instalasi Tray 0% 0% 0% 0% 0% 0% 50% 50% 0% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 50% 100% 0% 0% 0% 0% 0%
Quantity (Meter) - - - - - - 0 0 - - - - -
Manpower (Orang) - - - - - - 2 2 - - - - -
3 Pekerjaan instalasi Kabel (Looping) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0% 0%
Quantity (Meter) - - - - - - - - 30 - - - -
Manpower (Orang) - - - - - - - - 2 - - - -
4 Pekerjaan Instalasi WLAN & Telephone 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 6 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
5 Pekerjaan Instalasi JB Telecom 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
6 Pekerjaan Terminasi & Glanding 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0% 0%
Quantity (Unit) - - - - - - - - - 2 - - -
Manpower (Orang) - - - - - - - - - 2 - - -
7 Commissioning 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Accumulative progress (%) 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 0% 0%
Quantity (Unit) - - - - - - - - - - 2 - -
Manpower (Orang) - - - - - - - - - - 2 - -