You are on page 1of 4

HANKIN

27th WEDC Conference Lusaka, Zambia, 2001


PEOPLE AND SYSTEMS FOR WATER, SANITATION AND HEALTH
The afridev handpump – problems and solutions
Philip Hankin, Malawi

THIS PAPER DISCUSSES problems encountered with AFRIDEV removing the rising main. Pump Caretakers are trained to
handpumps during 6 years of implementing Rural Water remove the internal components and replace fast wearing
Supply and Sanitation (RWSS) programmes in Malawi, parts.
including 4 years of detailed monitoring of 375 water At times it is necessary for the rising main to be removed
points. Suggested solutions for each problem will also be e.g. when the rising main fails; when a pump rod breaks;
presented. when the rods are dropped; when the foot valve is jammed
in the cylinder; etc. The rising main is made of UPVC with
The programme permanently bonded joints using solvent cement. The
The implementation of RWSS in Malawi, with bilateral co- programme introduced a system of Area Mechanics whereby
operation between the governments of Malawi and Germany suitable individuals within the community are identified
funded through the German Bank for Reconstruction and trained to withdraw the rising main. This is done with
(KfW) commenced in mid-1995 with the Kalembo the help of the community who withdraw the rising main
Groundwater Project. A total of 375 boreholes with in one piece. The necessary repairs are carried out and the
AFRIDEV handpumps were installed. The project ended in cylinder and rising main replaced, again in one piece. There
mid-1998. is therefore a capacity within the community to repair the
The implementing agency for the programme is the entire pump without recourse to other, often centralised,
Ministry of Water Development who has employed GITEC organisations.
Consult of Düsseldorf in Germany to design and supervise
the projects. Spare parts supply and distribution
A second project in East Mangochi district has been Without a reliable supply and distribution of spare parts
designed, implementation started in early 1999 and is there can be no sustainability of the pump and hence the
ongoing. water point.
Monitoring of the Kalembo Groundwater project started Malawi is in the process of developing a sustainable
in the third quarter of 1997 and is ongoing. Each of the 375 supply and delivery of parts. The supply has been the most
water points is visited quarterly. problematical with the Ministry of Water Development
making the procurement utilising funds solicited from
The AFRIDEV handpump donors. A revolving fund was set up which, for a variety of
Development of the AFRIDEV handpump started in Malawi reasons, failed to provide sufficient funds to reorder
in the early 1980’s with the collaboration of the Malawi replacement stocks. General opinion is that the procurement
Government, UNICEF, UNDP and World Bank. A pump and supply of parts should be privatised and moves towards
called the Malawi Development Pump (MALDEV) was this end are under way.
developed. Research and development was moved to Kenya A distribution system was put in place through Chipiku,
in 1983 and the pump name was changed to the Africa a nation wide chain of wholesalers. The stocks have been
Development (AFRIDEV) pump after some modifications. supplied by the ministry and are sold on a commission
The Swiss Centre for Development Co-operation in basis.
Technology and Management (SKAT) issued the first
specifications and drawings for the AFRIDEV in 1989. AFRIDEV problems and solutions
There have been three revisions since then the latest being A number of problems were encountered with the pumps
in 1998. The AFRIDEV is a “Public Domain Pump” and during the implementation of the Kalembo Groundwater
has no copyright or patent, anybody can purchase the Project. All of the problems identified can be avoided with
specifications from SKAT and manufacture the pump. careful procurement procedures and close supervision of
The AFRIDEV has been adopted as the standard deep installation.
well handpump for Malawi. The problems identified have been categorised into:
• Design flaws;
Operation and maintenance • Manufacturing defects; and
The AFRIDEV is a true Village Level Operation and • Installation faults.
Maintenance (VLOM) pump. All the internal moving
components can be withdrawn without the necessity of Suggested solutions for each problem are included.

121
HANKIN

Afridev problems and solutions


Location Description Possible cause Suggested solution

Foot valve Initial fitting of foot valve. The foot valve oscillates in The length of the top rod
In some cases the foot valve the rising main as it descends can be easily calculated (even
has hung up (stuck) on the and can lodge on top of the roughly) to double check the
lip at the top of the cylinder. brass cylinder. setting depth.
The depth of plunger setting There is 508mm of brass
(Timing) is then set incor- cylinder liner above the top
rectly with the plunger oper- of the foot valve, the stroke
ating in the rising main. is only 225mm. (Installation fault.)

Foot valve bobbin Displaced bobbins are being 1) When the foot valve is Pre-shipment inspection.
found in the foot valves dropped into the rising
jamming the valve open. main it hits the water fast
which, when coupled
with possible oscillation,
could cause displace-
ment. (Manufacturing defect.)
2) Dimensional.

Cylinder Bent. Cylinders have been This occurs during the Pre-shipment inspection.
found to be bent, oval and assembly process especially
undersize. during the cooling of the
assembly after shrink fitting (Manufacturing defect.)
the plastic pipe and brass
liner.

“U” Seals Fast wearing (in some cases 1) Material consistency, Pre-shipment inspection.
within 1 month) & rolling some very soft ones have
out of location groove. Many been found.
“U” seals have a very short 2) Dimensional?
operating life and a number 3) Rolling out may be
have also been rolling out of caused during with-
their grooves. drawal against the inside
of rising main joints.
4) Siltation. (Manufacturing defect.)

“U” Seals Blocking of cylinder. When


“U” seals become dislodged
and remain inside the cylin-
der it is not possible to with-
draw the foot valve without
withdrawing the whole
pump.

Plunger Dimensional. The groove for Incorrect spin welding of the Pre-shipment inspection.
the “U” seal is asymmetric two parts of the plunger.
and dimensionally incorrect.
Could contribute to “U” seal
problems. (Manufacturing defect.)

Plunger Plunger legs breaking and Maybe caused during foot Cut off legs before in-
blocking the foot valve. valve installation or when stallation.
excessive force is applied. (Design flaw.)

122
HANKIN

Afridev problems and solutions


Location Description Possible cause Suggested solution

Rod centralisers Bad wear of rod centralisers 1) Heavy siltation of bore- If the first pipe installed
often causing heavy friction hole. above the cylinder is 1.0
during operation. 2) Coincidence of rod and metre long then the joints
rising main joints causing cannot coincide.
the centralisers to wear
excessively. (Installation fault.)

Rods Bent rod joints. Rod joints Pre-shipment inspection.


misaligned with the axis of
the rod causing excessive (Manufacturing defect.)
friction.

Rods Bent rods. 1) During transportation or Careful supervision.


storage.
2) During installation.
3) During subsequent re-
installations.

Fulcrum and hanger pins Cracks in the stainless steel Corrosion of inner mild steel Consider solid stainless steel
sleeves. pin. pins.
(Design flaw.)

Rising main Straightness of individual Poor transport and storage Careful supervision.
pipes. conditions.

Rising main Straightness of rising main Tension is being induced in Rope should be slack as
column. the rope causing the rising shown in the SKAT install-
main to bend. ation manual.
(Installation fault.)

Rising main Joint alignment. The socket Incorrect formation of sock- Improved socket formation
is not aligned with the axis et. at the manufacturers. An
of the pipe. extended mandrill should be
used to align the socket
former with the axis of the
pipe.
(Manufacturing defect.)

Rising Main Joint preparation. Sharp Both the inside and the
edges left inside and outside outside of the spigot must be
the spigot. Inside causes a bevelled.
problem with the plunger
and centralisers, outside
hinders jointing. (Installation fault.)

Rising main Jointing incorrect, not Depth mark not drawn on The marks should be made
pushed home far enough. spigot before jointing, in- at the workshop, not in the
(Must be 115mm.) sufficient effort to joint field.
correctly. (Installation fault.)

Rising main Double sockets are not long Use of short double sockets Double sockets should be
enough (should have the designed for jointing hori- parallel and at least 230mm
same socket dimensions zontal pipes which are long.

123
HANKIN

Location Description Possible cause Suggested solution

as the pipes) and also many readily available. These need to be made
are necked (smaller diameter available at spare part
in the middle as the pipe) outlets.
causing a re-striction to the
plunger and centralisers.

Operation Short pumping strokes 1) Foot valve not working. 1) Remedy technical
during operation are causing 2) Plunger timing wrong. problems.
excessive wear throughout 3) Children operating 2) Educate users.
the pump. pump.

Solvent Cement. Not readily available for Packaging quantity should


maintenance purposes. be reduced to enough solvent
for a double socket joint i.e.
2 joints, and sold with the
double socket.

Conclusions: Fulcrum and hanger Pins:


Pre-shipment inspection: Both the fulcrum and hanger pins are of similar design with
All consignments of pumps and/or spare parts must be a 2mm thick stainless steel sleeve glued onto a mild still pin
inspected in the country of manufacture before shipment using epoxy resin. Both these parts operate within a very
and payment. Control of pump imports must be put in humid atmosphere and moisture penetrates along capillaries
place, maybe by stipulating that all pumps installed must in the resin attacking the mild steel pin. The resultant
have an inspection certificate. corrosion causes the sleeve to split which in turn destroys
the bush bearings.
Design flaws: The programme has specified that both pins should be
SKAT have been notified of the problems encountered and manufactured from solid stainless steel.
some modifications have been offered as alternatives in
Revision 3 of the Specification.
PHILIP HANKIN, Team Leader, GITEC Consult, Private
Installation faults: Bag 55, Mangochi, Malawi. gitec@sdnp.org.mw
All pump installers should receive approved training and
be certified. Only certified pump installers should be al-
lowed to install pumps.

“U” Seals: Table 1. Spare Part consumption for


The “U” seal seems to present a disproportionate number 375 AFRIDEV handpumps from
of problems during the operation and maintenance of the October 1997 to March 2001.
pump. It is not just that it wears out but it also causes other
more serious problems often requiring the withdrawal of Bush bearings 48
the rising main. “U” Seals 186
The locating groove in the plunger body is formed at the “O” Rings 42
Bobbins 36
joint of the two components of the plunger body during Rod Centralisers 40
spin welding, which is often out of tolerance. This, coupled Rising Mains 21
Cones 1
with the widely varying quality of the material, often causes Covers 0
it to roll out of it’s location causing a blockage in the Cylinders 1
Plungers 9
cylinder. Foot valves 3
It has also been observed that silt settles out of the water Pump Rods 25
column overnight filling the inside of the seal and when full, Fulcrum Pins 12
Hanger Pins 6
overflows inwards into the groove, thus pushing the seal Rod Hangers 0
out causing it to wear irregularly. Handles 1
Pump Heads 1
After discussion with SKAT and other users the pro-
gramme has now specified the use of a brass plunger with
a more substantial cup seal as used in the India Mark III.

124

You might also like