1. Assess the Service Level Gap
The first step is to assess the existing situation and service levels gaps for Water Supply
(AMRUT Guidelines; para 3 & 6). This will also include existing institutional framework for
the sector. AMRUT is focused on improvement in service levels. The zone wise data shall be
used in identifying the gaps. These zone-wise gaps will be added to arrive at city level
service gaps. While assessing service level gap reply following questions not more than
word indicated against each question.
Question: What kind of baseline information is available for water supply system of the city?
Detail out the data, information, plans, reports etc related to sector. Is zone wise
information available? (75 words)
Baseline information on geography in house information regarding of the city sources of
Water Supply and details of Feeder mains, Storage Reservoirs, Distribution Network, Age &
Type of Pipeline, No. of Tap Connections, Reports of the Schemes already executed and
Zoning of distribution Network are available. The Plans relating to schematic flow diagram,
showing feeder mains and distribution networks is also available. Tumkur City is the district
headquarters of the Tumkur district in Karnataka. It is located at a distance of 70 km to the
North-West of Bangalore. The city is well known for the Siddhaganga Mutt and education
facilities. Tumkur is located at 13020’N longitude and 77006’E latitude. It has an average
elevation of 822 meters (2696 feet). The normal rainfall in Tumkur district is 780mm and it
varies from 918 mm at Tumkur to 620mm at Pavagada. The temperatures start rising from
January to a peak of around 34o C in April, the hottest month in the district. The city has a
population of 3,05,821 as per 2011 census. The City Municipal Council jurisdiction extends
up to an area of 75.4 Sq km, with 35 administrative wards. Two National Highways namely,
NH-4 and NH-206 passes through Tumkur city. The city is bounded by Anantapur district in
the northeast, Chitradurga in the north, Hassan in the west, Mandya in the south and Kolar
in southeast. The annual rainfall is about 700mm. Railways have said to have proposed
commuter train connecting the city with Bangalore. Master Plan of 2031 as Horizon year is
available. Water supply Base map (Rising main) & Schematic diagram of Tumkur city is
available. The detailed project report of continuous pressurized water supply scheme under
UIDSSMT is available. All ward wise details of distribution network of entire city with
location of service reservoir is available.
Question: Have you collected census 2011 data? Are you aware of baseline survey data of
MoUD? Have you correlated data from these and other sources? (75 words)
The census 2011 data is available with Tumakuru City Corporation. The consumer data is
collected duly conducting door to door survey. MoUD Baseline data is not available, Street
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 1/19
01/10/2015 Amrut Slip Generator
Lengths, Households data & HSC data is are correlated with ULB and CDP and 24x7 water
supply scheme DPR data.
What are existing service levels for water supply in the city? What is the coverage of water
supply Connections? What is per capita supply of water? How much is the extent of
metering? How much is non-revenue water? Provide information in table
Question: What is the gap in these service levels with regard to benchmarks prescribed by
MoUD? (75 words)
1) Coverage on water supply connections: There are 88,525 households in the city as per
the book of records of Corporation and out of which 41447 houses are provided with water
supply house service connections. Therefore, there is a gap of about 47078. As observed in
the city there are different nature of HSC’s ie., with PVC pipe, GI pipe etc., and found
enormous leakages and there is no uniformity in the methodology of HSC’s. To reduce the
NRW it is found necessary for remodeling the distribution network in the entire city with
new HSC’s. 2) Per capita supply of water The per capita water supply is calculated with total
quantity of water supplied to distribution system and the present population, the percapita
supply of water works out to 86 LPCD. Therefore there is a gap of 49 LPCD in the supply
rate. The total quantity of water pumped at source = 48 MLD By considering the
transmission losses, WTP losses and distribution system losses, the total losses would be
40%. Therefore net losses =19.2 MLD Net quantity of water supplied = 28.8 MLD
Population served = 325000 Therefore per capita supply = 86 LPCD 3) Extension of
metering There are 88,525 house holds in the city and there is no metering system in
households. Hence there is a gap of 88,525 metering for water connections. The gap
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 2/19
01/10/2015 Amrut Slip Generator
Please provide information in 150 words on the above responding to (however not limited
to) following questions.
Question: What is the existing source of water? Is it surface water source or under ground
water source? What is the capacity of these sources?
Question: Is there any treatment provided to water from these sources? How much water is
required to be treated daily? What is the treatment capacity installed in the city?
Question: What per capita water supply in LPCD (liter per capita per day) comes out, if you
divide total water supply by the total population.?
1.The source of existing water supply scheme is Hemavathy canal which is surface source.
The Hemavathy canal is running from Gorur reservoir built across river Hemavathy. The
water drawn from Hemavathy canal is being stored in impounding reservoir at
Bugudanahally and Hebaka. to cater the need of water during canal closure period. The
existing 1st stage WSS with Hemavathy canal is having capacity of 30 MLD which was
commissioned during 1997-98. There is an allocation of water to an extent of 1.135 TMC
from Hemavathy canal from GoK for drinking water purpose. The 2nd stage water supply
scheme to Tumakuru city with Hemavathy canal was commissioned during December-2011
and output of 2nd stage WSS is 50 MLD. 2.The source of existing water supply scheme is
Hemavathy canal which is surface source. The Hemavathy canal is running from Gorur
reservoir built across river Hemavathy. The water drawn from Hemavathy canal is being
stored in impounding reservoir at Bugudanahally and Hebaka. to cater the need of water
during canal closure period. The existing 1st stage WSS with Hemavathy canal is having
capacity of 30 MLD which was commissioned during 1997-98. There is an allocation of
water to an extent of 1.135 TMC from Hemavathy canal from GoK for drinking water
purpose. The 2nd stage water supply scheme to Tumakuru city with Hemavathy canal was
commissioned during December-2011 and output of 2nd stage WSS is 50 MLD. 3.The per
capita supply works out to 86 LPCD with 40% losses in the transmission mains and
distribution mains. The present population is about 3,25,000 and the net treated water
being supplied to Public after losses will be about 28.20 MLD.
DISTRIBUTION ZONES
Please provide information in 150 words on the above responding to (however not limited
to) following questions.
Question: City is divided in how many zones for water supply ?
Depending upon the Topography of Tumakuru city and to full fill the criteria of minimum
residual pressures at HSC’s – 7 Mtrs, City is divided into 37 zones.
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 3/19
01/10/2015 Amrut Slip Generator
Zone Total No. of Households with Water tap Households without Water
No. Households Connection tap Connection
STORAGE OF WATER
Please provide information in 150 words on the above responding to (however not limited
to) following questions.
Question: What is the total water storage capacity in the city ? What is capacity of elevated
and ground water reservoirs?
• The total storage capacity of Elevated service reservoir is 245 LL as detailed below. There
are three ground level service reservoirs of 54 LL storage capacity at pumping stations as
follows. 1) CMC park – 22 Lakh Ltr. 2) Santhemaidana - 22 Lakh Ltr. 3) Water works – 10
lakh ltr DMA Reservoir Name Cap.LL 1 Linga/Rangapura 5 2 Antharasanahally 5 3
Sathyamangala 2.5 4 Dibbur 5 5 D.C.Bungalow 10 6 Hanumanthapura 5 7 Aralimarada
Palya 5 8 Drivers Colony 5 9 Water Works 10 10 Devarayapatna 5 11 NR Colony 7.5 12
Court Compound 7.5 13 Santhemaidana 5 14 Shishuvihar 10 15 Bheemasandra 5 16 Azad
park 5 17 Bar Lane 7.5 18 SS Puram 10 19 Gangothri Nagar 10 20 Mahalaxmi extn 5 21
Sreenagara 5 22 SS Temple 5 23 Gandhinagara 10 24 CMC Premises 10 25 Ashok Nagar 5
26 Shettihally road 7.5 27 Siddarameshwara 5 28 Veerasagar 5 29 Alashettykerpalya 5 30
Upparahally 10 31 Saraswathipuram 10 32 Geddalahally 2.5 33 Kyatsandra School 5 34
Sapthagiri 5 35 Jayanagar 10 36 Gokula 10 37 Kyatsandra (terml.) 5 Total 245LL
Question: In case of surface water, does city need to have ground level reservoirs to store
raw treated water?
The city is having 3 GLSR at pumping station to meet the requirement. The water flow in
Hemavathy canal is only for a period of 4 to 5 months in a year. And has such it is required to
store at canal water to cater the need during canal closure period. Therefore 2 irrigations
tanks. ie. Bugudanahally tank and Hebbakka tank is converted has impounding reservoir.
The capacity of impounding reservoirs is as follows. 1) Bugudanahally reservoir- 4830 ML
(net capacity after considering losses ) 2) Hebbakka reservoir- 3830 ML (net capacity after
considering losses )
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 4/19
01/10/2015 Amrut Slip Generator
DISTRIBUTION NETWORK
Please provide information in 150 words on the above responding to (however not limited
to) following questions.
Question: What is the total length of water supply distribution pipe line laid in the city?
There is no exact records available in the ULB as the distribution lines were laid as and when
required to fulfill the demand. However it is estimated approximately that the existing
distribution pipeline in the city is about 400 Km.
Question: What is the total road length in the city? Is the pipe lines are laid in all streets? Is
the objective of universal coverage of water supply pipe line is achieved?
The total road length in the city is about 575 Km. At present some of the streets are not
covered with pipeline. The objective of Universal coverage of water supply pipeline is not
yet achieved in the city.
Question: What are the kind of pipe materials used in distribution lines?
The existing distribution network consists of different nature of materials ie., PVC, DI,
HDPE, CI and GI with different class of pipe varying from 4 Kg/ cm2 to 6 Kg /Cm2
Question: Provide zone wise details of street length with and without water distribution
lines in the Table?
Zone Total Street Street length with water Street length without water
No. Length distribution pipe line distribution pipe line
INSTITUTIONAL FRAMEWORK
Please provide information in 150 words on the above responding to (however not limited
to) following questions.
Question: Define role and responsibilities in terms of O&M, policy planning, funding, service
provision in table
Planning Construction/
and Design Implementation O&M
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 5/19
01/10/2015 Amrut Slip Generator
Status (as
Name of Scheme on dd mm
S.No. Project Name Cost Month of Compilation 2015)
Question: How much the existing system will able to address the existing gap in water
supply system? Will completion of above will improve the coverage of network and
collection efficiency? If yes, how much. (100 words)
The existing system of both 1st stage and 2nd stage WSS is not able to address the existing
gaps found in water supply system as the improvement to distribution system and 100%
house connections are not executed in the scheme. Only the bulk improvement was
priotorised in the commissioned / existing schemes. The proposed scheme of continuous
pressurized water supply scheme to Tumakuru city under UIDSSMT provides remodeling of
entire distribution network to an extent of 650 Km, since the existing distribution network
consisting of PVC network which is of different classes do not sustainable for continuous
pressurized water supply system and also in order to reduce the NRW. Details of existing
water supply scheme: Tumkur branch Hemavathy canal is considered as the source for 2nd
stage water supply scheme to Tumkur city. The Hemavathy canal authorities have allotted
1.135 TMC of water to Tumkur city for drinking purpose. The 2nd stage WSS to Tumkur city
is commissioned during Dec 2011. • To impound the required quantity of water for the
projected population of for the year 2036, Hebbaka Minor Irrigation tank which is located
U/s of Bugudanahally tank is developed as additional impounding reservoir. The net of
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 6/19
01/10/2015 Amrut Slip Generator
Question: Does the city require additional infrastructure to improve the services? What
kind of services will be required to fulfill the gap?
Yes. The city requires the following additional infrastructure to improve the services and to
full fill the gap and are listed below: Sl. No. Components 1 Replacement of existing pumping
machineries Provided during 1st stage water supply at water works pumping station 2
Construction of 15.00 lakh liter capacity of RCC GLSR at water works pumping station
including construction of pump house 3 Repairs to existing 0.5 MG capacity of RCC GLSR at
Sante Maidana and CMC park 4 Providing Additional House service connections of water
supply 5 Construction of 5.00 lakh liter capacity of RCC OHT at Melekote including Feeder
mains and connecting mains to distribution system 6 Dismantling of deteriorated condition
of 10 lakh ltr. Capacity OHT's at DC Bunglow and shishu vihara compound and
reconstruction. 7 Providing fencing alround Bugudanahalli and Hebbaka Impounding
Reservoirs (8000 + 4000 mtrs = 12000 Mtrs) 8 Purchasing of vehicles for Operation and
Maintenance of existing water supply scheme. 9 Providing, errection, commissioning and
trail run of Scada sytem for proposed water supply distribution network with BFM -
universal metering 10 Operation and maintenance of water supply scheme. 11 Providing
approach road with drains to Kuppur and Naraspura housing chamber 12 Providing contour
bound with waste weirs around Hebbakka and CD works with gates.
Question: How does the city visualize to take the challenge to rejuvenate the projects by
changing their orientation, away from expensive asset replacement programs, to focusing
on optimum use of existing assets?
It is proposed to utilize the existing treatment plant of 30 MLD capacity with rejuvenation
work to augment the total output upto 80 MLD to meet the feature demand. The existing
infrastructure such as 50 MLD conventional WTP, head works at Bugudanahally, 914 mm
dia raw water rising main, 914 mm dia pure water rising main, 35 Nos of service reservoirs
and its feeder mains network upto length of about 55 Kms will be proposed to utilize in
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 7/19
01/10/2015 Amrut Slip Generator
Question: Has city conducted assessment of Non Revenue Water ? if yes, what is the NRW
level? Is city planning to reduce NRW ?
a) There is no specific assessment of NRW in the city right now.
OBJECTIVES
PBased on above, objectives will be developed to bridge the gaps to achieve universal
coverage. While developing objectives following question shall be responded so as to arrive
at appropriate objective.
Please provide List out objectives to meet the gap in not more than 100 words.
Question: Does each identified objectives will be evolved from the outcome of assessment?
Yes.
Question: Does each objective meet the opportunity to bridge the gap?
Yes.
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 8/19
01/10/2015 Amrut Slip Generator
The objective will lead to explore and examine viable alternatives options available to
address these gaps.. These will include out of box approaches. (AMRUT Guidelines; Para 6.4
& 6.8 & 6.9). This will also include review of smart solutions. The cost estimate with broad
source of funding will be explored for each. While identifying the possible activities, also
examine the ongoing scheme and its solutions including status of completion, coverage and
improvement in O&M. Please provide information on the above responding to (however not
limited to) following questions.
Question: What are the possible activities and source of funding for meeting out the
objectives? (75 words)
• The source of funding for meeting out the objectives to achieve Universal coverage and to
reduce NRW, and improve cost recovery, is expected from AMRUT GoI assistance. The rest
of fund is proposed to obtain from GoK, ULB and assistance from financial institutions.
Question: How can the activities be converged with other programme like JICA/ ADB
funded projects in the city etc? (100 words)
There are no other programme like JICA / ADB / others in the city, other than UIDSSMT
programme as mentioned above. Need to provide other infrastructure under AMRUT to
meet the objectives.
Question: What are the options of completing the ongoing activities? (75 words)
The project of continuous pressurized water supply scheme to Tumakuru city under
UIDSSMT is proposed to taken up for implementation and for which tenders have already
been invited. The work will be commence after observing all the formalities of tender
process as per KTTP act and intended to complete by 36 months.
Question: How to address the bottlenecks in the existing project and lessons learnt during
implementation of these projects? (75 words)
There was no scope in the earlier commissioned scheme for remodeling of distribution
system and providing of HSC’s in uniform manner. Hence there was less scope of reduction
of NRW / UFW. Therefore needed to makes sufficient provision in proposed project to
connect all the households with unique type of HSC’s with 100% metering with provision of
SCADA / Automation system to improve the management efficiency.
Question: What measures may be adopted to recover the O&M costs? (100 words)
The 100% billing will be assured after implementation of project and collection of water
charges will be made on volumetric basis on monthly basis. As metering system will be
adopted the efficiency monitoring of each connection by customer will be monitor closely.
Customer service centre will be established for easy access ability for the customer and to
improve the collections against the demand created.
Question: Whether reduction in O&M cost by addressing NRW levels be applied? (75
words)
By addressing NRW level, about 20 to 25% of quantum of water will be saved. And there by
there will be reduction in O&M cost also. By addressing NRW levels there will be saving in
power charges, wear and tear of pumping machineries due to reduction in quantum of water
supplied.
Question: Does each objective meet the opportunity to bridge the gap?
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 9/19
01/10/2015 Amrut Slip Generator
Sr. Financing
No. Objective Activities Source
4. Citizen Engagement
ULBs will organize and conduct city level citizen consultation and receive feedback on the
suggested alternatives and innovations. Each alternative will be discussed with citizens and
activities to be taken up will be prioritized to meet the service level gaps. ULB will prioritize
these activities and their scaling up based on the available resources. (AMRUT Guidelines;
Para 6.6, 6.7 & 7.2). Please explain following questions in not more than 200 words detailing
out the needs, aspirations and wishes of the local people.
Question: Has all stakeholders involved in the consultation?
Yes.
Question: Has alternative taken up for discussions are prioritized on the basis of
consultations?
Yes.
5. Prioritize Projects
Based on the citizen engagement, ULB will prioritize these activities and their scaling up
based on the available resources to meet the respective objectives. While prioritizing
projects, please reply following questions in not more than 200 words.
Question: What are sources of funds?
For implementation of committed project of continues pressurized water supply scheme to
Tumakuru city under UIDSSMT the following funding pattern is adopted. GoI share (80%) –
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 10/19
01/10/2015 Amrut Slip Generator
15918.40 Lakhs / GoK share (10%) – Rs.1989.80 Lakhs / ULB share (10%) - Rs.1989.80
Lakhs.
Question: Has projects been converged with other program and schemes?
It is convergent with the other programme of UIDSSMT as stated above.
Question: Has projects been prioritized based on “more with less” approach?
Yes.
Question: Has the universal coverage approach indiated in AMRUT guidelines followed for
prioritization of activities?
Yes.
6. Conditionalities
Describe in not more than 300 words the Conditionalities of each project in terms of
availability of land, environmental obligation and clearances, required NOC, financial
commitment, approval and permission needed to implement the project.
a) The land required for the project is already in position with ULB. b) No environmental
obligations in the project. c) The prior permission required for road crossing and railway
crossing will be obtained immediately after finalization of DPR. d) Resolution from
Municipal council obtained for implementation of project from AMRUT
7. Resilience
Required approvals will be sought from ULBs and competent authority and resilience factor
would be built in to ensure environmentally sustainable water supply scheme. Describe in
not more than 300 words regarding resilience built in the proposals.
The resilience factors would be built into ensure environmental sustainability, safety,
serviceability aspects of all components in the water supply system. With due care about
hard geological strata in some areas for the proposals made regarding the location of the
service reservoirs and alignments of rising mains and transmission mains, location of service
reservoirs to improve water supply efficiency. Complete coverage of water supply to each
Household through continues and good quality of water which is environmentally
sustainable. The resilience is done to optimize the technologies and systems which helps in
improvement of the performance of the water supply system. It helps in identifying the
critical elements in the system such as pipe material, locations, pumping machinery etc
without any disruptions which leads to the proper performance of the system. Adaptive and
resilient water system proposals have been made which is fundamental to human health
and wellbeing with respect to inter-linked infrastructure.
8. Financial Plan
Once the activities are finalized and prioritized after consultations, investments both in
terms of capital cost and O&M cost has to be estimated. (AMRUT Guidelines; para 6.5)
Based on the investment requirements, different sources of finance have to be identified.
Financial Plan for the complete life cycle of the prioritized development will be prepared.
(AMRUT Guidelines; para 4, 6.6, 6.12, 6.13 & 6.14). The financial plan will include
percentage share of different stakeholders (Centre, State and City) including financial
convergence with various ongoing projects. While preparing finance plan please reply
following questions in not more than 250 words
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 11/19
01/10/2015 Amrut Slip Generator
Question: How the proposed finance plan is structured for transforming and creating
infrastructure projects?
Based on the financial status and the prioritized investment requirements different sources
of finance will be identified and a financial plan is yet to be prepare.
Question: Has financial plan prepared for identified projects based on financial convergence
and consultation with funding partners?
After finalization of projects and discussion with the Financing Agency, a financial plan can
be prepared for identified projects.
Question: Is the proposed financial structure is sustainable? If so then whether project has
been categorized based on financial considerations ?
After finalization of projects and discussion with the Financing Agency. Hence cannot be
furnished at this stage.
Question: Does financial plan for the complete life cycle of the prioritized development?
Yes.
Question: does financial plan include percentage share of different stakeholders (Centre,
State, ULBs)
Yes. GoI Share – 50 % / GoK share - 40% / ULB share – 10%
Year in
Year in which to
Priority which to be be Estimated
S.No. Project Name number implemented completed Cost
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 12/19
01/10/2015 Amrut Slip Generator
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 13/19
01/10/2015 Amrut Slip Generator
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 14/19
01/10/2015 Amrut Slip Generator
condition of 10 water
lakh ltr.
Capacity
OHT's at DC
Bunglow and
shishu vihara
and sharda
devi nagar,
shetty halli
compound and
reconstruction.
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 15/19
01/10/2015 Amrut Slip Generator
Impounding
Reservoirs
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 16/19
01/10/2015 Amrut Slip Generator
No.
FY 2016 FY FY FY FY
2017 2018 2019 2020
H1 H2
Replacement 2.00 Per capita 135 86LPCD 86LPCD 90LPCD 120LPCD 135LPCD 135LPCD
of existing Cr supply of LPCD
pumping water
machineries
Provided
during 1st
stage water
supply at water
works pumping
station
Providing 30.Cr Coverage of 100% 47% 47% 60% 80% 90% 100%
Additional water
House service supply
connections of connections
water supply
Repairs to 1.5 Cr Per capita 135 86LPCD 86LPCD 90LPCD 120LPCD 135LPCD 135PCD
existing 0.5 supply of LPCD
MG capacity of water
RCC GLSR at
Sante Maidana
and CMC park
Construction 1.5 Cr Per capita 135 86LPCD 86LPCD 90LPCD 120LPCD 135LPCD 135LPCD
of 15.00 lakh supply of LPCD
liter capacity water
of RCC GLSR
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 17/19
01/10/2015 Amrut Slip Generator
of RCC GLSR
at water works
pumping
station
including
construction of
pump house
Dismantling of 6.00 Per capita 135 86LPCD 86LPCD 90LPCD 120 135 135LPCD
deteriorated Cr supply of LPCD LPCD LPCD
condition of 10 water
lakh ltr.
Capacity
OHT's at DC
Bunglow and
shishu vihara
and sharda
devi nagar,
shetty halli
compound and
reconstruction.
Construction 1.75 Per capita 135 86 86LPCD 90LPCD 120LPCD 135LPCD 135LPCD
of 5.00 lakh Cr supply of LPCD LPCD
liter capacity water
of RCC OHT at
Melekote
including
Feeder mains
and connecting
mains to
distribution
system
Providing, 10.00 Efficiency in 90% 61% 61% 70% 80% 90% 90%
errection, Cr collection
commissioning and quality
and trail run of of water
Scada sytem
for proposed
water supply
distribution
network with
BFM -
universal
metering
Purchasing of 0.40 Cost 100% 42% 42% 50% 60% 80% 100%
vehicles for Cr recovery
Operation and
Maintenance
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 18/19
01/10/2015 Amrut Slip Generator
Maintenance
of existing
water supply
scheme.
Providing 3.60 Quality of 100% 88% 88% 90% 100% 100% 100%
fencing Cr water and
alround per capita
Bugudanahally
and Hebbaka
Impounding
Reservoirs
Providing 0.75 Quality of 100% 88% 88% 90% 100% 100% 100%
approach road Cr water and
with drains to per capita
Kuppur and
Naraspura
housing
chamber
Providing 13.88 Quality of 100% 88% 88% 90% 100% 100% 100%
contour bound Cr water and
with waste per capita
weirs around
Hebbakka and
CD works with
gates.
O&M of head 48.75 NRW and 20% 40% 40% 40% 35% 30% 20%
work and Cr Quality of
Distribution water
networks for 5
years
http://54.255.235.66/amrut/watersupplyresult.php?id=12528 19/19